Project Accounting

We are looking at implementing PA for 11.0 or 11i; Looking through the documentation I have been unable to locate how sales tax is handled in PA and if you can still use Vertex to calculate tax rates and exceptions??
Is there anybody who has dealt with this issue that can help shed some light on this for me?
Thanks
null

<BLOCKQUOTE><font size="1" face="Verdana, Arial">quote:</font><HR>Originally posted by Joseph Mathew ([email protected]):
I am developing/assisting in the development of three interfaces from an external system (MFG/PRO) to Oracle.
ALL OLTP will take place on MFG/PRO and this will be the repository for all information. However, Oracle Projects is being used (in the absence of a suitable project module in MFG/PRO to enable Project managers to monitor progress on their respective projects.
There are three parts to this.
All Projects information wil be transferred to the MFG/PRO project table.
All AP (Voucher and Payment information being entered on the MFG/PRO side) information needs to be transferred to Oracle AP. There is no problem here - a data copy from the MFG/PRO instance (Oracle 8i) into the AP open interface tables will accomplish this with the help of Invoice import.
I am having problems with data transfer between the MFG/PRO PO module and the Oracle PO module and then into the Projects module.
Should I load PO data into the PO_REQUISITIONS_INTERFACE table and then use transaction import or try and load data directly into the PO tables per the Open Interface manual to achieve PO matching.
Anyone's help is appreciated.
Thanks
Joe Mathew<HR></BLOCKQUOTE>
Joe:
I am unsure if this is what you're looking for but to load actuals into PA on one project we utilized the XXX_PA_COMMITMENTS_OUTSIDE_SYS table to import contract (external commitments) into OPC. From there they were visible in the PSI and Expenditure online inquiry screens. Matching was done to the paper contract (that was the client's perferred business process).
The solution doesn't import into PO, and if you're working in 10.7 NCA I suspect this will be difficult. If you're using 11i workflow may be useful in having PO's entered through an external system and then routed into PO. Again I don't know if I fully understand the problem -- how this helps.
Robert
null

Similar Messages

  • How to use WEB ADI in R12 project accounting- Need urget

    Hi Friends,
    How to use WEB ADI in R12 for project accounting, right now iam working in a client place, i need to show demo on WEB ADI functionality in project accounting.
    Iam trying in different ways, it is showing error msgs, if any body have WEB ADI R12 exp, please guide me.
    I need to upload manual transactions through WEB ADI..
    What are the setups need to do, i have user guide but unable to solve my probelm..
    It is very urgent to me, please reply..
    Thanks,
    Srini
    Message was edited by:
    user620419

    Ravichandran wrote:
    Hi,
    Set the DQM Synchronization Method to "Batch" and it should solve your issue(Please note that this depends on whether you are using TCA)
    Regards,
    RaviHi Ravi,
    Thanks for replying this post. I had almost lost hope.
    As you suggested above, I tried to set the DQM Synchronization Method Profile Option to Batch using System Administrator responsibility but could not as the Profile Option is read only at all levels- Site, Application, Responsibility,User,etc. Please what am I doing wrong ? Thanks
    -Ibrahim

  • Project Accounting Month end Closing Process

    Dear Experts,
    Any one can help me by explaining Project Accounting Month End Closing Process
    Thanks & Regards
    Bharath

    Bharath
    1. Clear all the transactions from Interface tables
    2. Import them
    3. Run all the Expenditures (PRC, Interface processes) make sure none of the expenditures are not accounted
    4. Run Borrow and Lent process if any, Transfer to GL
    5. Run Revenue Process, make sure revenue is generated, accounted
    6. Review the revenue draft versions created, make sure all revenue draft versions are released
    7. INterface revenue to GL, then later Tie back process
    8. Run the Invoicing process
    9. Make sure to Approve, release all the Invoices in draft version
    10. Interface to AR ( ensure that none of the records are in error)
    11. Auto Invoice Import in AR
    12. Tieback process in PA
    13. run Exc: Transaction Exception details by GL Period/ PA period , Exc: Transaction Exception summary by GL Period/ PA Period
    14. Make sure the report output on step 13 are blank, if yes try to clear all the transactions and re run the reports
    15. Now try closing the period
    Thanks
    Krishna

  • Project Accounting Funtional Certification

    Hi
    Need help on Project Accounting Funtional certificaiton. Am entered in this module just 4 month. Planned to do some certification on this module.
    But I dnt know exact things abt this. Kindly provide the details on this.
    Thanks in Advance
    Senthur

    I deal much more in the server & development certifications.  The Oracle Applications side is a big grey blur to me.  That said, I don't see any that are specific to Project Accounting and Costing.  I would guess one of the 'Fusion Financials' certifications would best fit your needs.  You would have to make the decidion on which one -- I can't do that for you.
    The following page lists all of the certifications Oracle offers.  From the links on this page, you can access details pages with more data, including the cost and topic covered.
    Oracle Certification All Exam | Certifications | Oracle

  • Project Accounting Systems Module

    Can anyone explain the differences between project accounting system and project sytems module.  Are they both the same module?  Also, where can I find all the financial data against the project including revenue, profit etc.

    Hi Catherine,
    It is the same module abbreviated as PS.  Accounting "submodule" is mostly about integrating with financial modules such as FI, CO, AA, IM, while logistics part is about PS integration with modules like MM, SD, PP, PM.
    If you are familiar with Controlling (CO) module, the concept is very much the same.  PS provides a number of objects that can be used as cost account assignment objects, for which you can report similar to Cost Centers or Internal orders.
    There are a lot of other specifics, but since your question is quite general, the answer is also of a general nature.
    Regards,
    Paulo

  • Oracle PROJECT ACCOUNTING BASICS...

    Hi i need some materials or e-books or some links to know about the details of PROJECT ACCOUNTING module in oracle apps.Please help me out with this ASAP.

    unless you can get to some oracle classes, I would recommend their online education tools.

  • Oracle project  accounting material

    Hi
    can any body please provide me complete material for oracle project accounting at my mail id [email protected]?
    Thanks
    Roopali
    [email protected]

    Dear Hussain,
    Thanks a lot for your mail but more of that I am looking for oracle project accounting configuration material. How I can do the set up under oracle project management module. Could you please send that material to my mail id [email protected] or else you can provide link to me.
    Many thanks for your help!
    Thanks
    Roopali
    [email protected]

  • OBAW Schema / ETL Mappings for Project Accounting

    Hello - We have done our Oracle Financial Analytics deployment using OBAW / Oracle Apps 7.9.5 and wanted to see how i can get more information about the Project Accounting module.
    Anyone can share information about PA (Project Accounting)? It will help tremendeously if someone will share the spreadsheet "BI Apps 7.9.5 - ETL Data Lineage" specifically for Project Accounting module. Or, schema or ETL information.
    Regards,

    Project accounting was released in 7.9.6 and is not present in 7.9.5.x
    The Data lineage document for 7.9.6 is available in Metalink3

  • Integration of PO with Project Accounting

    Hi ,
    we have a requirement of linking project number with existing open Purchase Order,
    Requisition from Purchasing.
    Recently our client implemented Oracle project costing.
    my question is
    1. How project number enabled/display during creation of purchase order (any profile option
    we need to enabled)
    2. How cost coming from PO to PA (if any request to run)
    (Any direct interfacing between PA and PO)
    3. want to understanding the PA-PO relationships as per expenditure is concern
    Any reply is appreciated.
    Thanks in advance.

    Hi
    On the Purchasing system setup you should define the accounting rule - to accrue on receipt or accrual at period end. If you accrue on period end the receiving transactions are not charging the expense account nor interface to Projects. Only when supplier invoice is matched to the PO and validated, you could Interface the invoice to Projects. However, if you enable the Accrue on receipt, then system generate accounting to expense account on the receipt transaction, and the PO receipt can be interfaced also to Projects. In that case the supplier invoice matched to the PO will not be interfaced to Projects, unless there are variances between the receipts amounts and the invoice value.
    In both cases, you need to run the same process - PRC: Interface Supplier Costs to Projects.
    Note the parameters - If you enabled Accrue on receipt run that process always with the parameter PO Receipts as YES.
    Dina

  • Error in c project accounting

    Dear plm consultant,
    I am facing problem in c project costing . when i go for calulate the cost, i get following error.
    <b>Error occurred in accounting - see controlling cockpit (cProjects)
    Message no. DPR_FIN_GECCO024</b>
    Diagnosis
    Errors occurred when transferring to accounting.
    System Response
    DPR_FIN_GECCO 024
    Procedure
    Choose the link on the Accounting tab page. In the cockpit, you can create a variant with your cProjects project under Selection Variant Orders cProjects . The errors that occurred are then displayed. If no messages are displayed in the controlling cockpit, they have already been processed or deleted. If this is the case, trigger the transfer again.
    No more messages are displayed once the transfer has been carried out successfully (that is, no errors occurred).
    i am unable to trace the problem,help me for same
    point will be reward for answer
    thanx
    sunil jawalkar
    [email protected]

    hi shivshankar,
    there is option on accounting tab page controlling cocpit you click on them. 
    then thruogh ITS it go to your r/3 system there you make nessary settings
    thnax
    sunil jawalkar

  • C Project Accounting integration

    Hi all,
    Pls help me come out of this accounitng integration problem in cprojects.
    The object type 0FIN_INT_ERP_PS  is not appearing in Define Object types Node. Instead I have one object type as 0FIN_INT_PROJ , but his is not helping. and also this is greyed out.
    I wish to create WBS automatically from C projects.
    0FIN_INT_ERP_PS object type is what is specified in settings as Single-Obj. Controlling on WBS Elements as object links for accounting integration with Destination as NONE and proxy class as CL_DPR_OLR3_WBSELEMENT.
    Thanks
    Rajeev
    In case of any documentation pls send me to [email protected]

    Hi Rajeev ,
    Where you chek this object type link,
    -->0FIN_INT_ERP_PS
    -->0FIN_INT_SOC_R3
    both are come defult
    Please check the path and revert back
    SPRO ---> Collrabration Project
                             --->Conection to Exteranl System
    > Acoounting Integration
                                                --> Define object link to Accounting Integration
    Here you find the
    -->0FIN_INT_ERP_PS
         proxy class:CL_R3_OLR3_PROJECTDEFINITION
    -->0FIN_INT_SOC_R3
          proxy class:CL_R3_OLR3_INTERNAL_ORDER
    Give the destinaion from which client your are getting the values of PS data or internal order.
    thanks
    sunil jawalkar
    null

  • Project Accounting Data Conversion

    Dear Friends,
    Can any one tell me what data we have to Migrate from Legacy to Oracle PA @ the time of Implementation
    Thanks
    Bharath

    Hi
    For any project type you will need to convert -
    - Projects and Tasks
    - Project Budgets, financial plans and work plans
    - Actual cost incurred on existing projects.
    If you have billing installed, look at converting also -
    - Agreement and fundings
    - Actual revenue generated
    - Actual invoices billed to customers
    If you implement capital projects you will need to take care of the following -
    - Assets linked to projects
    - Actual capitalized asset lines
    Dina

  • Project Accounting Expenditure status is Pending

    Hello all,
    I have created Expenditure in PA. (Expenditure > Pre Approved Batches > Enter) and I did Submit and Release.
    After that i ran Distribute Labor Cost and Distribute Usage and Miscellaneous Costs concurrent program.
    Both has completed successfully.
    I am facing issue While opening Item menu > Cost Distribution Line (Expenditures > Expenditure Inquiry > All ). In Cost Distribution Line form status as Pending.
    Actually it should be Accepted.
    What i need to do to change the status.
    Please help to resolve this issue.
    Thanks and Regards,
    Muthu

    Hi Samba,
    Thanks for your input, After running PRC: Submit Interface Streamline Processes program the status has been changed as Accepted.
    But Default Account and Descriptions field Debit only having Account code not in Credit.
    What would be the issue.
    Please guide me to resolve the issue.
    Thanks and Regards,
    Muthu
    Edited by: Muthu on Feb 27, 2012 3:22 PM

  • Required Project Accounting Information

    I want to know the Budget Approval Hierarchy,
    I'm struck with an Issue.
    Once the Budget gets approved it sends a Notification to concerned Approver.
    I want to know that where its defined and also the Hierarchy of this
    Approval Process.
    Thanks,
    Kumar.

    Hi Mohan,
    Link: http://help.sap.com/
    Path: SAP Best Practices --> Baseline Packages --> Based on SAP ECC 5.00 --> Select Country: for eg, Localized for India --> Technical Information --> Building Blocks --> Select Country for eg, India -->
    Topic: J12 - Project System
    Here you will get both Configuration guide & Development master list
    Also kindly visit following link
    http://www.sapprojectsystem.com/
    You will get all relevant stuff.
    Hope this helps.
    Regards
    Tushar
    PS : Reward points if you find answer useful.

  • Report on Funding Sources Affiliated with Projects in Grants Accounting

    We are trying to create a report that shows a listing of all of our funding sources and the Projects affiliated with them. A Funding Source can have 0 or more Projects. We are not sure where these links are made
    In the report we would like to see:
    Funding Source ID
    Funding Source Name
    Project ID
    Project Name

    Hi Chris,
    We need help implementing Grants Accounting and Projects Accounting Modules for a university client. Can you help? or refer us to a functional and a technical colleague(s) with good experiences implementing Grants Accounting? Much appreciate your help. Thanks in advance.
    Roger, (646) 736-6083 zx7013 and [email protected]