I have created a number or Excel 2013 reports which use OlapPortfolioAnalyser data connection. Typically creating a pivot table. I can select any dimensions and measures and excel works as expected.  However if I include the Project list or Resource
list it does not.  I have tried this in two separate instances but do not have a separate environmnent availabale but would appreciate confirmation or othrewise of the misbehaviour.
Steps are: (Assuming cube is built and permissions set correctly and using Excel 2013 client)
In PWA\Bi\Data connections navigate to cube folder
Double click on OlapPortfolioAnalyser – opens in Excel 2013 (warning about data connections being blocked)
Click Enable
In pivot select project list from pivottable fields
Save file (locally or to sharepoint)
Close file
Now re-open file
Excel displays warning - "We found a problem with some content in "xxx.xslx". Do you want us to try and recover as much as we can? If you trust the source of the workbook, click Yes.
Click Yes
Another warning is displayed (Repairs to xxxx.xslx)
Removed Part: /xl/pivotCache/pivotCacheDefinition1.xml part with XML error.  (PivotTable cache) Load error. Line 2, column 0.
Removed Feature: PivotTable report from /xl/pivotTables/pivotTable1.xml part (PivotTable view)
Click Close - you now see data but pivottable functionality is gone.
Note: this also happens with Resource list data.
How do I resolve this?
Thx
Mike
Mike Mahoney

More research and KB 2817339 appears to have the fix - see
http://blogs.technet.com/b/projectsupport/archive/2013/07/30/excel-2013-error-opening-saved-pivottable-reports-from-pwa-bi-center.aspx 
As I mention in the blog - the fix will not recover a broken xlsx as the break appeared to be on save rather than open.
Best regards,
Brian
Blog |
Facebook | Twitter | Posting is provided "AS IS" with no warranties, and confers no rights.
Project Server TechCenter |
Project Developer Center |
Project Server Help | Project Product Page
Unfortunately the blog post you linked is in error - it reports that the issue is fixed in build
15.0.4517.1001. However I am running 15.0.4517.1504 and still hit the problem. The only workaround is the one post by
adrian_rho, above, which solved my problem. Thanks Adrian for the workaround, and to Brian for the great job tracking and assisting people on this issue, even though it is Excel and not Project - much appreciated!
Mike

Similar Messages

  • Project Server 2013 - OLAP Cube Build Issues

    Hi,
    I have a Project Server 2013 environment with SQL Server 2012 SP1. My cube built successfully and Report Authors group (including me) were accessing the templates and Data Connections from BI centre successfully.
    I re-built the cube and suddenly we all cannot access templates or data connection as it says 'Access denied'!
    Went to server hosting Analysis Services and checked the role ProjectServerViewOlapDataRole and didn't see any of the check box ticked for database permissions like it was when I initially built the cube and added Report Authors group and account
    that is used by Secure Store app. Membership has both account and group.
    Has anyone come across this issue?
    Thank you,
    SJ

    SJ,
    The access of the BI Center, templates and data connections are handled by SharePoint permissions and are usually inherited from PWA.
    The ProjectServerViewOlapDataRole simply provides the ability to view the data from the OLAP database. It sounds like the issue isn't with the OLAP but rather with PWA itself. An OLAP error would have only precluded you from retrieving data.
    Did someone modify the BI Center site permissions recently such as breaking inheritance?
    Treb Gatte, Project MVP |
    @tgatte | http://AboutMSProject.com

  • Project Server 2013 - External Data Refresh Failed

    Hi, 
    I have built  new Project Server 2013 in a 3 tier farm, with OWA, configured PWA site everything working fine except, Reports in BI Center, where i am getting - External Data Refresh Failed error
    http://Sp2013/PWA/ProjectBICenter/Sample%20Reports/Forms/AllItems.aspx
    i have stopped using Excel Web also to use Excel Services, get below error
    External Data Refresh Failed
    An error occurred while accessing application id ProjectServerApplication from Secure Store Service. The following connections failed to refresh:
    Project Server - Issue Data
    Project Server - Risk Data
    Learn
    more about data refresh
    Steps Tried:
    1.deleted Excel Services - recreated
    2.Deleted Secure store - recreated
    Built  test box without OWA still have the same issue
    Any suggestions/ Solutions greatly appreciated.
    Thanks 
    Aleem
    Alim

    Hi,
    If you are still facing the same issue follow the below steps:
    1) Access PWA from your server
    2) Download any built in report from Reports section (in your case
    Project Server - Issue Data Project
    Server - Risk Data) to your server.
    3) Open report in excel, go to Data->Connections in Workbook Connection dialog open "Project Server - Issue Data" go to properties.
    4) Here select tab 'Definition' under connection file remove tick for 'Always use connection file'
    5) Tweak your connection string & tick save password option 
    6) Excel Services: Authentication Settings (suit yourself)
    Now, save & publish on PWA, hope it works :)

  • Project Server 2013 OLAP cube build error

    When I try to build the OLAP cube I receive the below error:
    [2/26/2014 12:36 PM] Failed to build the OLAP cubes. Error: The attempt to build the OLAP database on server SQL_Server_Name failed, the SQL Server Analysis Services Analysis Management Objects (AMO) client software may not be installed on this server, please
    install/update the client on this server and retry. The underlying exception was: Could not load file or assembly 'Microsoft.AnalysisServices, Version=10.0.0.0, Culture=neutral, PublicKeyToken=89845dcd8080cc91' or one of its dependencies. The system cannot
    find the file specified.
    I did some search and found that Analysis Management Objects (AMO) client software is not installed on my servers, I downloaded and installed the AMO client software , restarted the Project Server Service application to the 4 Servers. I rebooted the
    4 servers, tried to build the cube, but I got the same error. I checked the assembly on the 4 servers and they contain the dll Microsoft.AnalysisServices.
    Any help?
    I read that AMO client software tools must be installed during the farm setup, after installing the SharePoint Prerequisites and before installing SharePoint. Is that correct?

    Hello,
    Even with SQL 2012, the 2008 SQL AMO component is required on the Project Server servers. See the post from Brian for more details:
    http://blogs.msdn.com/b/brismith/archive/2012/11/12/project-server-2013-requirements-to-build-an-olap-cube.aspx
    Paul
    Paul Mather | Twitter |
    http://pwmather.wordpress.com | CPS

  • Project server 2013 olap database remains in processing state

    Hi,
    In an attempt to restore the Reporting Database in Project Server 2013, I did an archive and restore of Custom fields. Both of these events were successful, however, the Reporting database refresh kept on hanging in "Waiting to be processed status".
    Before this was noticed, the OLAP Database was configured and a build was initiated. Now the status of the PWAOLAPDatabase build just remains in the "Processing..." status.  What am I to do here? Thanks!

    Hi Jaco,
    It seems like your reporting database refresh has failed, so the OLAP DB cannot be generated either. It could be due to a large resource pool.
    See reference below:
    http://social.technet.microsoft.com/Forums/projectserver/en-US/7ac3bb1b-6621-46f0-a6c5-d9a04f770418/reporting-database-refresh-project-server-2010?forum=projectserver2010general
    http://blogs.msdn.com/b/brismith/archive/2011/07/14/project-server-2010-reporting-database-refresh-failing-with-large-resource-pools.aspx
    Note also that you can click on "processing" (as per your screenshot) to have the OLAP DB creation log in order to have more information on the status.
    Hope this helps,
    Guillaume Rouyre, MBA, MCP, MCTS |

  • Failed to build the OLAP cubes (Project Server 2013)

    We are receiving errors when attempting to build our OLAP cubes.  We've attempted to install the 2008 version of the SQL server native client 2008 but still the error appears.  Please advise.
    Configuration:
    Project Server 2013
    SharePoint 2012
    SQL Server 2012
    Error Message:
    ===== Initiating OLAP database build process =====
    [1/7/2014 2:00 AM] Cube build request message has been added to the Project Server queue ===== Verifying and running pre-build server event handler =====
    [1/7/2014 2:00 AM] Verifying and running pre-build server event handler ===== Determining database and OLAP database structure =====
    [1/7/2014 2:00 AM] Cube build initialization started ===== Building database and cubes =====
    [1/7/2014 2:00 AM] Cube build session started ===== Verifying and running post-build server event handler =====
    [1/7/2014 2:00 AM] Verifying and running post-build server event handler ===== Processing OLAP database =====
    [1/7/2014 2:00 AM] Process OLAP database session started ===== Process Completed =====
    [1/7/2014 2:00 AM] Failed to build the OLAP cubes. Error: Failed to process the Analysis Services database OLAP_FTF on the XYZ server. Error: Errors in the back-end database access module. The provider 'SQLNCLI10' is not registered.
    The following system error occurred:  Class not registered Errors in the high-level relational engine. A connection could not be made to the data source with the DataSourceID of 'Project Reporting data source', Name of 'Project Reporting
    data source'.
    Errors in the OLAP storage engine: An error occurred while the dimension, with the ID of 'Project List', Name of 'Project List' was being processed.
    Errors in the OLAP storage engine: An error occurred while the 'Start Date' attribute of the 'Project List' dimension from the 'OLAP_FTF' database was being processed.
    Internal error: The operation terminated unsuccessfully.
    Server: The current operation was cancelled because another operation in the transaction failed.

    Hi Importek,
    Please have a look to a similar threads that has been answered.
    http://social.msdn.microsoft.com/Forums/en-US/a2696e29-e68e-45a8-8dae-fa8fa5640575/receive-the-following-error-when-trying-to-build-cube-errors-in-the-highlevel-relational-engine?forum=sqlanalysisservices
    http://social.technet.microsoft.com/Forums/projectserver/en-US/420958bd-4613-451c-ac06-a1f149f64da9/problem-when-trying-to-build-the-cube?forum=projectserver2010general
    Finally an article by Brian Smith:
    http://blogs.msdn.com/b/brismith/archive/2007/07/16/yet-another-olap-error-message-the-longest-yet.aspx
    This might be an issue of the SQL instance alias.
    Hope this helps.
    Guillaume Rouyre - MBA, MCP, MCTS

  • Baseline timephased data disappeared in MS Project 2013 with Project Server 2013!!!

    Hi,
    I am facing a very strange problem within a custom "task usage" view that I' 
    ve created. In the right pane I have three timephased fields (work, baseline 
    work and actual work). When I first add resources to tasks and save baseline 
    everything works great and the baseline work data are distributed normally in 
    the respective line next to the resource name and also in the summary tasks 
    lines. A few days after saving and publishing the project to the Project 
    Server 2013, I opened the project from the PrjProfessional and the timephased 
    baseline data had disappeared. However, the total values of baseline work 
    (shown in the respective column at the left pane) were all still there. In 
    other words, I cannot see the distribution of baseline work into the timephased 
    schedule. When I check the database the data is also gone (MSP_EpmAssignmentBaselineByDay table).
    This has a huge impact for the customer!
    If found a similar issue reported with Project 2007 --> http://www.44342.com/Microsoft-Project-f1227-t2482-p1.htm
    Regards,
    Philip
    Verlinden Philip

    Hi Philip,
    Please refer to thjis thread: 
    https://social.technet.microsoft.com/Forums/projectserver/en-US/5f721eaf-6424-4b32-9c96-fed646e94f88/cumulative-timephased-data-in-ps-2013-db-wrong-or-just-misunderstood?forum=projserv2010setup
    I think it is a known bug that Elli identified a few weeks ago. I don't know if there is a fix planned soon by MS.
    Hope this helps,
    Guillaume Rouyre, MBA, MVP, MCP |

  • Default ODC connection in Project Server 2013

    Hello every one.
    Anyone know where the default ODC connector used in the BI reports is stored within Project server 2013. I need to create a custom default ODC connection so that the fully qualified domain name is used instead of the alias currently used.
    Thx
    mt

    Default location is
    /PWA/ProjectBICenter/Data%20Connections%20for%20PerformancePoint/English%20(United%20States)
    Hrishi Deshpande Senior Consultant

  • Project Server 2013 not saving custom field data

    Hello all,
    I have a Project Server 2013 deployment with several Project-level custom fields.
    One of them, never saves the info typed in. All others work just fine but this one does not like to save anything. There's no error in queues or the ULS.
    I'm so lost with it. Any thoughts?
    Rene Alvarez

    An update on this issue.
    I could isolate it to the project plan template. If I use my custom fields with an EPT without a plan template, I have no problem.
    So the problem is the template right? Well, I did the following:
    Create a blank template and attach it to the EPT. Result: all Ok.
    Create a template with 10 tasks (task name only) and attach it to the EPT. Result: all Ok.
    Create a template with my full 135 tasks (task name only) and attach it to the EPT. Result: all Ok.
    Create a template with the 135 tasks (task name and WBS) and attach it to the EPT. Result: all Ok.
    Create a template with the 135 tasks (task name, WBS and milestones) and attach it to the EPT. Result: FAIL. Cannot save custom fields again.
    A user noticed something. If he opens a problematic project in Project Pro, and publish it again (no changes) then the project accepts data in the custom fields.
    Rene Alvarez

  • How to make the 'Finish Date' field Editable in Project server 2013

    Hi All,
    In Project server 2013 on premises deployment, When I try to create a new enterprise project [Also in case of new custom project type], Only the 'Start Date' field is available. The 'Finish Date' field is by default taking the value of the 'start Date' itself.
    I am unable to make this 'Finish Date' field editable.
    Any pointers on this would be very helpful,
    Thanks
    Shanky

    Shanky --
    When you create a new project in either Microsoft Project Professional or Project Online, the system does not allow you to enter both a Start date and a Finish date for the project.  Here is how the software works:
    You enter the Start date of the project.
    You completely plan the project with tasks, task dependencies, task Durations, and assigning resources to tasks.
    Based on the Start date you provide, plus all of the task information, the software calculates the Finish date of the project for you.  So, you cannot provide both the Start date and the Finish date, nor is they any way to force the system to allow
    you to do this.  Hope this helps.
    Dale A. Howard [MVP]

  • Pull large amounts of data using odata, client API and so takes a long time in project server 2013

    We are trying to pull large amounts of data in project server 2013 using both client API and odata calls, but it seem to take a long time. How is this done
    In project server 2010 we did this creating SQL views in both the reporting database and for list creating a view in the content database. Our IT dept is saying we can't do this anymore. How does a view in Project database or content database create issues?
    As long as we don't add a field in the table. So how's one to do this with creating a view?

    Hello,
    If you are using Project Server 2013 on premise I would recommend using T-SQL against the dbo. schema in the Project Web Database for your reports, this will be far quicker that the APIs. You can create custom objects in the dbo. schema, see the link below:
    https://msdn.microsoft.com/en-us/library/office/ee767687.aspx#pj15_Architecture_DAL
    It is not supported to query the SharePoint content database directly with T-SQL or add any custom objects to the content database.
    Paul
    Paul Mather | Twitter |
    http://pwmather.wordpress.com | CPS |
    MVP | Downloads

  • Unable to Change Project Start Date in Project Server 2013

    Dear All,
    I have created new EPT in Project Server 2013. After that, when i am creating any new project in PWA 2013 by using newly created EPT, then i am not able to change Date as per my requirement. 
    Basically, EPT created on 02/18/2015 & even though i am changing Project start date then its again showing same date (02/18/2015)
    Kindly suggest what i can do.

    Hello,
    Does this new EPT have a project plan template associated? What happens if you set the EPT not to have a plan template then create a new project from this EPT? Does that let you update the start date? The start date should default to today (date the project
    plan was created). If that works as expected, add the plan template back to the EPT (if you had one to start with) and test creating another project to see if that then works or you then get the same behaviour. This will point us to the cause hopefully.
    Do other EPTs work as expected?
    Paul
    Paul Mather | Twitter |
    http://pwmather.wordpress.com | CPS |
    MVP | Downloads

  • Problem after installation Project Server 2013 CU September 9, 2014

    Dear All,
    I have some problems after installation
    Project Server 2013 CU September 9, 2014 (Hotfix 2883072) on 3 level farm
    Before installing CU, I have installed
    SP1 for Project Server 2013, installation and configuration was successful.
    Then I have installed CU and I have not get any errors during installation process. Then I have restarted servers and in SharePoint health analyzer got an error about patch/installation status
    on WFE server.
    I checked in Windows installed updates and hotfix is installed. I checked in SharePoint Update and Upgrade history and there were no errors during installation. But when I checked in Manage
    Patch Status list I found an information:
    Language Pack for SharePoint and Project Server 2013 - Russian
    Microsoft Project Server Russian Language Pack 15.0.4420.1017 Installed
    Hotfix for Microsoft Project Server 2013 (KB2883072) 64-Bit Edition
    15.0.4649.1001 Missing/Required
    Microsoft Project Server 2013
    Microsoft Project Server English Language Pack 15.0.4571.1502 Installed
    Hotfix for Microsoft Project Server 2013 (KB2883072) 64-Bit Edition
    15.0.4649.1001 Missing/Required
    Service Pack 1 for Microsoft Project Server 2013 (KB2880553) 64-Bit Edition
    15.0.4571.1502 Installed
                Microsoft Project Server Web Front End Server
    15.0.4571.1502 Installed
    Hotfix for Microsoft Project Server 2013 (KB2883072) 64-Bit Edition
    15.0.4649.1001 Missing/Required
    Service Pack 1 for Microsoft Project Server 2013 (KB2880553) 64-Bit Edition
    15.0.4571.1502 Installed
    If I run installation again I get message that nothing will be updated - no update needed.
    Please help, how I can install missed packages?

    The problem was solved !
    I solve it using two ways:
    1. I have installed the hotfix for Project Server -  Hotfix for Project Server 2013 October 14, 2014 KB 2889959 (Projectserverwfe-x-none.msp, Projectservermui-Language-Code.msp)
    2. using command
    Psconfig -cmd upgrade -inplace b2b -force -cmd applicationcontent -install -cmd installfeatures -cmd installcheck -noinstallcheck
    After two actions I was able to run SharePoint Configuration Wizard and upgrade database. Configuration completed successful.

  • Resource time phased data in project server 2013/project 2013

    Hi all,
    I am using project server 2013 .
    one resource availability percentage is set as 80% ie 6.4 hrs per day. But when we are doin task assignment, only 5.6 is taken for a day and rest is pushed to next day ( i have noticed this in the timephased data in the task usage screen).
    for eg. if 6.4 work is assigned to the resources for a task with start date 1/1/2014 and end date 1/1/2014.  5.6hrs is taken for first day and 0.8 hr is moved to next day. Also the duration still shows as 1 eventhough task finish date is changed to 1/2/2014.
    Please help to understand is there any settings where 5.6 is taken for a day though the resource capacity is set as 80% ie, 6.4hrs.
    Thanks, Rose

    Hi Rose,
    is there any chance you have auto leveling turned on?  Menu Resource > Leveling Options > Automatic.

  • Connecting "ms project pro 2007" to "project server 2013"?

    Hello, Is there a way to connect "ms project pro 2007" to "project server 2013"? Do we have a "backward compatibility mode" in this context? Thankx

    If I understood correctly, you are asking for whether the MS Project Professional 2007 is supported in Project Server 2013. The answer is
    no. 
    Project Server 2013 supports only Project Professional 2013 version.