Project Server 2013 restore site from content database

My Project server was moved from one domain to other so i had to recreate everything since distributed cache was nt happy. I recreated everything. Now i have contet database from porject server that i need to restore to brand new environment. How to do that? 
Simply doing rmount content database is not working? How to reprovision it in Project server service application?
Adit

You mention that you mounted the content database.    Did you do this with PowerShell?  Have you tried adding the content databases, using the menus under Application management?
If that fails, I would just rebuild by doing the following. There probably is an easier way to do this, but here is what I would do
1) Delete the web application used for Project server
2) Create a new web application and point to the content database. 
3) Then you can provision project server
Michael Wharton, MVP, MBA, PMP, MCT, MCTS, MCSD, MCSE+I, MCDBA
Website http://www.WhartonComputer.com
Blog http://MyProjectExpert.com contains my field notes and SQL queries

Similar Messages

  • Project Server 2013 - Remove user from resource pool via sync

    Hello everyone,
    has anyone managed to configure their Project Server 2013 box with a resource pool sync that will actually remove user from the resource pool (disable "User can be assigned as resource" or deactivate users) when the user is removed from the AD
    group(s)?
    Setup: Single box, SQL 2012 SP1, SharePoint/Project Server 2013 + PU March + CU April. 2 PWA instances, 1 in SharePoint and 1 in Project permission mode. Tried on 2 different machines (different setup, accounts, domains).
    Proceedings:
    Create AD user U, AD group G. Add U to G.
    Go to PWA, setup resource pool sync with G, sync.
    U is now in the resource pool, has no PWA permissions.
    Remove U from G. Resync resoure pool.
    U is still in resource pool, still a resource, still active, can still be assigned as resource.
    Adding U back to G an repeating the whole spiel with a resource pool and a PWA group sync of G will result in U being added and removed from the user list (as expected), and U being added but not removed from the resource pool.
    Having read
    http://technet.microsoft.com/en-us/library/gg982985.aspx and
    http://technet.microsoft.com/en-us/library/gg750243.aspx, there does not seem to be an omission on my part.
    The first article states:
    Note:
    The corresponding Project Server User Account is not deactivated based on this synchronization. If the same Active Directory user is configured to synchronize with a Project Server security group, the Project Server user account will be inactivated when
    that synchronization occurs. For more information, see
    Best practices to configure Active Directory groups for Enterprise Resource Pool synchronization in Project Server 2013.
    Unfortunately, this deactivation either does not seem to occur even with a PWA group sync or I misunderstood the article.
    So, did anyone manage to setup their resource pool sync in a way, that new resource will be added, but also be removed from the resource pool?
    Kind regards,
    Adrian

    Hi Adrian,
    you tried to sync the same AD group that you used for the resource pool sync also with a Project Server permission group?
    And on removal of the user of the AD group the project user/resource is not deactivated? Only removed from the group
    Regards
    Christoph
    Hi  Christoph,
    even though I might have tried that before, I tried it again in several constellations. It didn't change anything. The the user will be properly added to and removed from the PWA group whenever I remove them from the AD group, the use will also stay active
    (but cannot logon without permissions). However, the user will always remain in the resource pool, i.e. the "User can be assigned as resource." checkbox will remain unless it is cleared manually.
    Having re-read the technet articles, none of the scenarios actually seem to descibe or address the process that I require, or maybe I'm just misunderstanding. Let me just try to outline the core issue:
    Add user to AD group. Sync AD group with resource pool. User is now a PWA resource and PWA user.
    Remove user from AD group, but do not deactivate/delete user from AD.
    (Magic happens!)
    User cannot be assigned as ressource in PWA.
    So, is there anything to make this step 3 happen, or is it just not possible to sync users out of the resource pool anymore unless they are deleted/deactivated in AD?
    Kind regards,
    Adrian

  • Project Server 2013 reporting database change in Schema from Project Server 2010

    I have a current Project Server 2010 implementation, I am planning to migrate to Project Online.
    We have Customized Reports that consume from the PS 2010 Reporting DB.
    Are there differences in the Reporting DB schema  between PS 2010 and Project Online?
    My Question is: if we migrated to Project Online, will the reports crash?
    Another question is that, is PS 2013 Reporting DB schema the same as Project Online?

    Hi Atia,
    IN project server 2013 we have only one database instead of 4, it means draft, archive, published and reporting with in one database.Project Server 2013 reporting database schema tool that can be downloaded.
    http://blogs.msdn.com/b/project_programmability/archive/2013/01/28/project-server-2013-reporting-database-rdb-schema-reference.aspx
    There are differences in reporting of on-premises vs. Project Online
    The Project Server 2013 reporting schema includes three new tables, 27 new views, and a total of 33 tables and views that include new fields.
    Answer-1 : Yes there are some differences between PS 2010 and project Online.
    Answer-2 : Reports will crash as In Project Online you have to use ODATA to create report. You can not query project online data for reporting directly you have to have use ODATA. 
    http://msdn.microsoft.com/en-us/library/jj163015.aspx
    Answer-3 : NO, PS 2013 Schema and Project online Schema is different. 
    kirtesh

  • Site Collection Content Database 250GB Limit

    Hi All,
    i recently read that the supported maximum size of a content Database is 250GB. is this true ? if we want to exceed this limit, is there any way to do that ? if we want to store more than that (1TB+) what can we do?
    Thank you!

    Hello ,
    #Copied
    Content databases of up to 4 TB are supported when the following requirements are met:
    Disk sub-system performance of 0.25 IOPs per GB. 2 IOPs per GB is recommended for optimal performance.
    You must have developed plans for high availability, disaster recovery, future capacity, and performance testing.
    You should also carefully consider the following factors:
    Requirements for backup and restore may not be met by the native SharePoint Server 2013 backup for content databases larger than 200 GB. It is recommended to evaluate and test SharePoint Server 2013 backup and
    alternative backup solutions to determine the best solution for your specific environment.
    It is strongly recommended to have proactive skilled administrator management of the SharePoint Server 2013 and SQL Server installations.
    The complexity of customizations and configurations on SharePoint Server 2013 may necessitate refactoring (or splitting) of data into multiple content databases. Seek advice from a skilled professional architect
    and perform testing to determine the optimum content database size for your implementation. Examples of complexity may include custom code deployments, use of more than 20 columns in property promotion, or features listed as not to be used in the over 4 TB
    section below.
    Refactoring of site collections allows for scale out of a SharePoint Server 2013 implementation across multiple content databases. This permits SharePoint Server 2013 implementations to scale indefinitely. This
    refactoring will be easier and faster when content databases are less than 200 GB.
    It is suggested that for ease of backup and restore that individual site collections within a content database be limited to 100 GB. For more information, see Site
    collection limits.
    Please refer below articles:
    http://blogs.technet.com/b/stefan_gossner/archive/2011/07/08/paul-andrew-talks-about-new-larger-sharepoint-content-database-size-limits-and-rbs-clarifications.aspx
    http://blogs.msdn.com/b/pandrew/archive/2011/07/08/announcing-new-larger-content-database-size-limits-and-rbs-clarifications.aspx
    http://technet.microsoft.com/en-us/library/cc262787(v=office.15).aspx#ContentDB
    Best Regards Kuldeep Verma
    Please remember to click "Mark As Answer"
    if a post solves your problem or "Vote As Helpful" if it was useful.

  • No PDP found after restoration of Project Server 2013 !!

    Hi All,
    I have an issue while performing database restoration of project server 2013. I have followed below mentioned two links for backup and restore procedure
    http://technet.microsoft.com/en-us/library/dd207307.aspx
    http://technet.microsoft.com/en-us/library/dd207305.aspx
    Everything works great ! restored successfully all projects, custom tables, group settings etc. But while opening the projects it prompts error that unable to find PDP etc something like that.
    Can anyone please help in such situation as how can we get the PDP pages in database restoration and what is the reason behind that ? Is there anything that I am missing?
    REGARDS DANISH DANIE

    Hello,
    Sounds like a new PWA site collection was created as part of the restoration? The PDPs are stored in the content database. If you are rolling over between environments (prod to test for example), see the post below:
    http://pwmather.wordpress.com/2013/05/02/projectserver-2013-environment-migration-rollover-steps-powershell-ps2013-msproject-sp2013/
    Paul
    Paul Mather | Twitter |
    http://pwmather.wordpress.com | CPS

  • Publication of the big-sized Enterprise projects from Project Professional 2013 to Project Server 2013 takes about 60+ minutes.

    Dear Sirs,
    I need your support over the following MS EPM 2013 issue:
    Publication of the big-sized Enterprise projects from Project Professional 2013 to Project Server 2013 takes about 30+ minutes. We
    need to reduce this total publication time down to acceptable working values 10+- minutes.
    Environment information:
    Single App Server (Virtual): 16 Gb RAM, x64 4xCPU, HDD > 50 GB free disk space, OS Windows Server 2012 Standard Edition x64 Service
    Pack 1, MS SharePoint Server 2013 and MS Project Server 2013 with CU December 2013 (KB 2850024) applied.
    Single RDBMS MS SQL Server (Virtual): 8 Gb RAM, x64 4xCPU, HDD > 200 GB free space, OS Windows Server 2012 Standard Edition x64 Service
    Pack 1, MS SQL Server 2012 x64 SP 1 Enterprise Edition.
    We have 1Gbit LAN between APP, DB server and 1Gbit LAN between APP and Proj Prof Client.
    Yes, we are on the way of migrating to the Prod environment
    with 3-tiered architecture (with SP1 slipstream and CU December 2014 applied), but this issue also
    presents there.
    Project’s file information:
    Tasks in the file: [~4900], resources in the file [~396] enterprise task’s custom fields used in the file [~23].
    Project save procedure for this new project would last about 7 minutes. Project publication would last about 47 minutes. We noticed that
    tasks synchronization process took about 1 second for each ~2,5 tasks, to add them to the sharepoint tasks list. So for all 5148 tasks it took about 5148/3/60 =  34 minutes. Other 13 min was used for reporting database publication and other tasks relevant
    for new sharepoint site creation.
    Case 1: Issue description:
    During the Enterprise project’s file save and publication we have the following sharepoint 2013 log messages:
    07.31.2014 12:43:17.22 Microsoft.Office.Project.Server (0x0358) 0x3D5C SharePoint Foundation Monitoring b4ly High Leaving Monitored Scope
    (Persisting list changes). performing time =376.068676326181 22dca99c-4696-70f1-e9e2-06851d0bcffd
    07.31.2014 12:43:17.69 Microsoft.Office.Project.Server (0x0358) 0x3D5C SharePoint Foundation Monitoring b4ly High Leaving Monitored Scope
    (Persisting list changes). performing time =361.652807828928 22dca99c-4696-70f1-e9e2-06851d0bcffd
    It shows that sharepoint spend at least ~350 milliseconds (or 0,35 sec*4900 tasks = 1715 sec, or 28,5 min) for each task update during
    project publication. And we also have another log file that shows that about 0,7 sec (or 0,7 sec*4900 tasks = 3430 sec, or 57 min) sharepoint spend for save each task in project file to project server. So total save and publication time more then 60+ minutes
    for that project file. The same result we have even if user didn’t do any changes at the project file.
    We use only enterprise projects (dbo.MSP_EpmProject_UserView.projectvisibilitymode = «False»), and do not use sharepoint tasks lists,
    but the synchronization between MSP Plan and SharePoint tasks list works at any case.
    Case 2: Issue description:
    - For the second test we created a new project with new sharepoint project’s site on basis of our «issue» project, with total amount
    of tasks in it of 5148 (yes, we increased the tasks list default limit at the sharepoint site up to 6000 items in it – standard limits for sharepoint view list – 5000 items).
    - Project save procedure for this new project would last about 7 minutes. Project publication would last about 47 minutes. We noticed
    that tasks synchronization process took about 1 second for each ~2,5 tasks, to add them to the sharepoint tasks list. So for all 5148 tasks it took about 5148/3/60 =  34 minutes. Other 13 min was used for reporting database publication and other tasks
    relevant for new sharepoint site creation.
    -Then we deleted the
    tasks list for that new test project from the sharepoint site and republish the project plan one more time. This time project save procedure took about 7 minutes, project publication about 2 minutes and 3 minutes for other relevant queue jobs. So total time
    is 12 minutes.
    As a conclusion: yes, we have determined
    the exact problem - during synchronization process (from Project Server to SharePoint) it perform copying all tasks and related data from Project to SharePoint in spite of fact that you changed only ONE task or ALL of them. At any case, synchronization will
    copy ALL of them from Project Server to SharePOint task’s list.
    Our workaround is to disable the task’s synchronization for such big-sized project plans:
    – to delete the SharePoint «tasks» list at the SharePoint site tied with project plan.
    - or deattach the SharePoint site from the project plan.
    Thank you for reading this topic, please if you also forced with such issue provide us any known workaround or maybe any official response
    \ feedback from MS about it.
    Thank you in advance,
    Best Regards, Andrey

    Regarding my topic, I also said that every time when sync works it updates All items from project’s plan at Project Server to corresponded task’s list at SharePOint server. Inspire of the fact that you changed only One task or group /
    all of them at your project’s plan.
    And it seems to me and my colleagues that it’s probably (maybe) a “bug” at the product. Here is what we have if looked a little bit closer to the code:
    Share Point determines what task to sync from Project’s plan to sharepoint list. To do that sharepoint needs to know was that task changed or not, based on the following fileds (check SQL stored procedure “[MSP_READ_TASKS_FOR_SYNCRONIZATION]”):
    TASK_UID    TASK_NAME    TASK_START_DATE    TASK_FINISH_DATE    TASK_PCT_COMP    TASK_PARENT_UID    TASK_OUTLINE_NUM   
    WSS_LISTITEM_UID   TASK_ID    TASK_IS_ACTIVE
    We noticed that at any case synchronization performs for all tasks, EXCEPT the ROOT one. Then we looked at the comparison of TASK_PARENT_UID field. So sharepoint compares TASK_PARENT_UID with ParentID (this is internal name for lookup
    field “Tasks” at the Sharepoint, and it stores their values at the format "ID;#Title").
    And comparison performs like following:
    SharePoint looks for Task at the Tasks’s list corresponded to Project’s plan with ID represented at the TASK_PARENT_UID field. Then it takes SharePoint ListItem ID (“int” type) and store it to the “num” parameter;
    num = this.GetCachedListItemByUniqueId(listItem.ParentList, nullable.Value).ID;
       2.Then it compares “num” with task’s “ParentID” at SharePOint as follow with operator “!=”:
    ((SPItem) listItem)["ParentID"] != (System.ValueType) num
       3. If comparison was success (true) – then it tell us that values (at the Project’s plan for tasks) was changed, then it need to be synchronized. Corresponded Method setup “true” flag, and then returns it.
    The “bug” is that this expression at the Step 2 will always return “true”, because in fact it compares “string” (see above – that this is lookup field at SharePoint side)
    with “number”. For example if the parant task ID is “55”, then we get:
    "55;#Task 1" != 55
    And by the rules of .Net the “string” will never equal “number”
    Furthermore this is approved by the SharePoint logs:
    In that case we always get the note “Setting ParentID to” at the logs (we see it if turns on Verbose for “Project Server” -> “Sharepoint Integration” category).
    So at any case of publishing project’s plan we always get that note at the logs for tasks that have Parent task, and we have Parent for all of them EXCEPT the ROOT one, exact logs represented further:
    10/15/2014 02:37:32.26    Microsoft.Office.Project.Server (0x07D8)    0x06E8    Project Server    Sharepoint Integration    ado0d   
    Verbose    Setting ParentID to 1    bf2fc29c-7727-b00d-fa4a-34f22ea9ec1d 10/15/2014 02:37:32.62    Microsoft.Office.Project.Server (0x07D8)    0x06E8   
    Project Server    Sharepoint Integration    ado0d    Verbose   
    Setting ParentID to 1    bf2fc29c-7727-b00d-fa4a-34f22ea9ec1d 10/15/2014 02:37:32.63    Microsoft.Office.Project.Server (0x07D8)    0x06E8    Project Server   
    Sharepoint Integration    ado0d    Verbose   
    Setting ParentID to 1    bf2fc29c-7727-b00d-fa4a-34f22ea9ec1d 10/15/2014 02:37:32.67    Microsoft.Office.Project.Server (0x07D8)    0x06E8    Project Server   
    Sharepoint Integration    ado0d    Verbose   
    Setting ParentID to 1    bf2fc29c-7727-b00d-fa4a-34f22ea9ec1d 10/15/2014 02:37:32.69    Microsoft.Office.Project.Server (0x07D8)    0x06E8    Project Server   
    Sharepoint Integration    ado0d    Verbose   
    Setting ParentID to 5    bf2fc29c-7727-b00d-fa4a-34f22ea9ec1d
    The following is the complete Method’s code from the corresponded reflector:
    private bool UpdateParentID(DataSet taskDS, DataRow row, SPListItem listItem, Dictionary<Guid, SPListItem> redoEntries)
    bool flag = false;
    int index = taskDS.Tables[0].DefaultView.Find((object) DataRowExtensions.Field<Guid>(row, "TASK_PARENT_UID"));
    if (index >= 0)
    Guid? nullable = DataRowExtensions.Field<Guid?>(taskDS.Tables[0].DefaultView[index].Row, "WSS_LISTITEM_UID");
    int num = -1;
    if (listItem.Fields.ContainsField("ParentID"))
    if (nullable.HasValue)
    try
    // STEP 1
    num = this.GetCachedListItemByUniqueId(listItem.ParentList, nullable.Value).ID;
    catch (ArgumentException ex)
    if (redoEntries != null)
    if (!redoEntries.ContainsKey(DataRowExtensions.Field<Guid>(row, "TASK_UID")))
    redoEntries.Add(DataRowExtensions.Field<Guid>(row, "TASK_UID"), listItem);
    //STEP 2
    if (num != -1 && ((SPItem) listItem)["ParentID"] != (System.ValueType) num)
    ((SPItem) listItem)["ParentID"] = (object) num;
    ULS.SendTraceTag(845443U, (ULSCatBase) ULSCat.msoulscat_PS_ProjectSharepointIntegration, ULSTraceLevel.Verbose, "Setting ParentID to {0}", new object[1]
    ((SPItem) listItem)["ParentID"]
    //STEP 3
    flag = true;
    else if (((SPItem) listItem)["ParentID"] != null)
    ((SPItem) listItem)["ParentID"] = (object) null;
    ULS.SendTraceTag(2495056U, (ULSCatBase) ULSCat.msoulscat_PS_ProjectSharepointIntegration, ULSTraceLevel.Verbose, "Resetting ParentID to null");
    flag = true;
    return flag;
    Any thoughts about it would be much appreciated!

  • How do I create a project site after I publish a project in Project Server 2013?

    How do I create a project site after I publish a project from project pro 2013 in Project Server 2013? I'm trying to look for an option in the ribbon but haven't found any. 
    Thanks
    James T.F

    Hi James,
    See in the article the procedure for site provisionning settings.
    Note that the project site is created based on the template associated to the chosen project type (EPT) when the user first publishes his project. Be aware that if you allow the user to choose weither or not he'll create a sharepoint site when publishing
    his project, he will be prompted in Project Pro with a dialog box giving the choice to create or not the site.
    Hope this helps,
    Guillaume Rouyre, MBA, MCP, MCTS |

  • Project server 2013 olap database remains in processing state

    Hi,
    In an attempt to restore the Reporting Database in Project Server 2013, I did an archive and restore of Custom fields. Both of these events were successful, however, the Reporting database refresh kept on hanging in "Waiting to be processed status".
    Before this was noticed, the OLAP Database was configured and a build was initiated. Now the status of the PWAOLAPDatabase build just remains in the "Processing..." status.  What am I to do here? Thanks!

    Hi Jaco,
    It seems like your reporting database refresh has failed, so the OLAP DB cannot be generated either. It could be due to a large resource pool.
    See reference below:
    http://social.technet.microsoft.com/Forums/projectserver/en-US/7ac3bb1b-6621-46f0-a6c5-d9a04f770418/reporting-database-refresh-project-server-2010?forum=projectserver2010general
    http://blogs.msdn.com/b/brismith/archive/2011/07/14/project-server-2010-reporting-database-refresh-failing-with-large-resource-pools.aspx
    Note also that you can click on "processing" (as per your screenshot) to have the OLAP DB creation log in order to have more information on the status.
    Hope this helps,
    Guillaume Rouyre, MBA, MCP, MCTS |

  • I'm an admin of this site, but now can't access some pages in Project Server 2013 e.g. Project center, PWA setting

    I'm an admin of this site, but now can't access some pages in Project Server 2013 e.g. Project center, PWA setting

    it may be your browser.  CHeck the folloinwg
    1) Turn on Compatibilty mode
    2) Security Options / Make it a local trusted site
    3) Turn of Protected Mode in the browser under Security
    and have you tried it from Chrome
    CHeers!
    Michael Wharton, MVP, MBA, PMP, MCT, MCTS, MCSD, MCSE+I, MCDBA
    Website http://www.WhartonComputer.com
    Blog http://MyProjectExpert.com contains my field notes and SQL queries

  • Project Server 2013 Tasks differ in project site and plan

    I have an Project Server 2013 enterprise plan that I created with an associated project site. The plan has tasks added to the timeline. The project site has a timeline webpart but the problem is the tasks added to the timeline differ.
    Does anyone have any ideas what could be the problem here? I checked the timeline webpart and it's correct.
    Thanks!
    [Images below].
    The following image is taken from the schedule PDP.
    This image taken from the project site depicts what is out of sync.

    Hi Guillaume,
    Yes, I've checked the queue while publishing the project. It's successful without any errors. I don't remember if I checked the ULS logs, but what I suspect is that it will say something along the lines of orphaned tasks in the project site.
    Anyways I've tried a number of things and I think the only 2 options I have are:
    Re-create the project site then sync the plan to it
    Ask MSFT for a script to resolve the orphaned tasks
    For the same of time, I'm going to assess how long it would take to re-create the project site.
    Thanks,
    Roland

  • Project Server 2013 Project Site Permission

    Hi All,
    Q1: We are using project server 2013, most of the time the projects are created by the PMO coordinators and it will be assigned to the project manager. Project coordinator and Project Manager belongs to "Project Manager" group. After assigning
    the project when the project manager tries to access Project Site, he is getting "why you want to access this site". When I checked project site permission only project coordinator name is added to the Owners group. Normally the project owner should
    have the permission to the project site, how to fix it.
    Q2: We have different enterprise project type with different site templates. When the project type is changed from one type to another, is it possible to delete and recreate the respective project sites automatically.
    Thanks in advance, Taj

    Taj,
    Q1) this is a question related to how your security is set up. If you are using Project Server Permission mode, people in Project managers groups, who have edit ability on your project will get added to the Project manager Synchronized group on the project
    site upon publish. You just need to make sure your secueiry ctegories and groups are set up as such.
    Alternatively, you could set the owner of the project to be the project manager once they take ownership.
    Q2) This will be a manual activity. You need to disconnect the site under server settings, then delete site. Then you can create the site, which will pickup the new EPT set project site template automatically.
    Cheers,
    Prasanna Adavi, Project MVP
    Blog:
      Podcast:
       Twitter:   
    LinkedIn:
      

  • Project Server 2013 Project Site Documents

    Hi All,
    We are using project server 2013. The project site (template) document library is configured with the project folders and templates. i.e. when the project is created, the project site will be created with required project document templates. We want to delete
    the project document templates from the projects sites which was created already, how can we achieve this.
    Thanks in advance, Taj

    Taj,
    The simplest way I can think of is to use PowerShell. Be careful with it, though, and test in a test enviroment, so that you do not end up deleting files that you actually want.
    This article should give you a good start: https://habaneroconsulting.com/insights/Delete-SharePoint-Files-With-PowerShell#.VOGMePnF-So
    Cheers,
    Prasanna Adavi, Project MVP
    Blog:
      Podcast:
       Twitter:   
    LinkedIn:
      

  • Project Server 2013 project site navigation

    Hi All,
    We are using project server 2013. We have customized the project site template. We want to display the Project Web App navigation (link) in the top of the project site. While customizing the project site it is showing the Project Web App link at the
    top. Once it is configured in the project enterprise project type and created project the Project Web App link is not appearing. It is showing only the project name.
    Thanks in advance, Taj

    Hi Taj,
    Have you followed procedure below from Prasanna post?
    http://www.prasannaadavi.com/2013/05/project-site-navigation-in-project.html
    Was the link correctly working in the project site before saving it as a template? Try creating a project site directly from the template (without creating a project first). Also be sure that you associated the correct site template to the EPT you chosen
    in PWA project center for creating the new project.
    Hope this helps,
    Guillaume Rouyre, MBA, MCP, MCTS |

  • Unable to edit the Project details from PWA in Project server 2013

    I am Migrating the project from MS Project 2007 to MS Project 2013.In that i save the project as a file first in 2007 and then open that file in  MS Project 2013 And publish it.But in some Project when i am Trying to change the projects details from
    PWA in Project server 2013 and then trying to save then the projects are not saving and are generating the error as shown below
    •GeneralQueueException:◦GeneralQueueException (9131). Details: id='9131' name='GeneralQueueException' uid='f7bb5d93-20e9-e411-b302-005056ae159c' messageID='2' exception='System.TimeoutException: This request operation sent to net.pipe://localhost/pscalc_13c43af4a7d34a2c8145b776b325a865
    did not receive a reply within the configured timeout (00:05:00). The time allotted to this operation may have been a portion of a longer timeout. This may be because the service is still processing the operation or because the service was unable to send a
    reply message. Please consider increasing the operation timeout (by casting the channel/proxy to IContextChannel and setting the OperationTimeout property) and ensure that the service is able to connect to the client. Server stack trace: at System.ServiceModel.Dispatcher.DuplexChannelBinder.Request(Message
    message, TimeSpan timeout) at System.ServiceModel.Channels.ServiceChannel.Call(String action, Boolean oneway, ProxyOperationRuntime operation, Object[] ins, Object[] outs, TimeSpan timeout) at System.ServiceModel.Channels.ServiceChannelProxy.InvokeService(IMethodCallMessage
    methodCall, ProxyOperationRuntime operation) at System.ServiceModel.Channels.ServiceChannelProxy.Invoke(IMessage message) Exception rethrown at [0]: at System.Runtime.Remoting.Proxies.RealProxy.HandleReturnMessage(IMessage reqMsg, IMessage retMsg) at System.Runtime.Remoting.Proxies.RealProxy.PrivateInvoke(MessageData&
    msgData, Int32 type) at Microsoft.Office.Project.Server.Interfaces.ICalcService.OpenProjectRemappedProject(CalcServiceCallState callState, Guid realProjectGuid, Guid remappedProjectGuid, EngineSessionState& sessionState, EngineSessionType sessionType,
    PSError& psError) at Microsoft.Office.Project.Server.BusinessLayer.CalcServiceChannel.OpenProjectRemappedProject(CalcServiceCallState callState, Guid realProjectGuid, Guid remappedProjectGuid, EngineSessionState& sessionState, EngineSessionType sessionType,
    PSError& psError) at Microsoft.Office.Project.Server.BusinessLayer.CalcServiceProxy.<>c__DisplayClass2.<OpenProjectRemappedProject>b__1(ICalcServiceChannel calcServiceChannel, PSError& localPsError, EngineSessionState& localSessionState)
    at Microsoft.Office.Project.Server.BusinessLayer.CalcServiceProxy.<>c__DisplayClass6e`1.<RunCalcServiceOperation>b__6c() at Microsoft.Office.Project.Server.Base.IdentityUtilities.<>c__DisplayClass1`1.<RunWithAccessToAppTierServices>b__0()
    at Microsoft.SharePoint.SPSecurity.<>c__DisplayClass5.<RunWithElevatedPrivileges>b__3() at Microsoft.SharePoint.Utilities.SecurityContext.RunAsProcess(CodeToRunElevated secureCode) at Microsoft.SharePoint.SPSecurity.RunWithElevatedPrivileges(WaitCallback
    secureCode, Object param) at Microsoft.SharePoint.SPSecurity.RunWithElevatedPrivileges(CodeToRunElevated secureCode) at Microsoft.Office.Project.Server.Base.IdentityUtilities.RunWithAccessToAppTierServices[T](Func`1 action) at Microsoft.Office.Project.Server.BusinessLayer.CalcServiceProxy.RunCalcServiceOperation[T](CalcServiceOperation3`1
    func, EngineSessionState& sessionState, String scopeName) at Microsoft.Office.Project.Server.BusinessLayer.CalcServiceProxy.OpenProjectRemappedProject(Guid realProjectGuid, Guid remappedProjectGuid, EngineSessionState& sessionState, EngineSessionType
    sessionType) at Microsoft.Office.Project.Server.BusinessLayer.ProjectEngineUpdate.OpenProject() at Microsoft.Office.Project.Server.BusinessLayer.ProjectEngineUpdate.HandleUpdate() at Microsoft.Office.Project.Server.BusinessLayer.ProjectQueueDispatch.HandleProject2(MessageContext
    mContext, ProjectMain project, ServerEventManager sem, ProjectDataSet dataset, Guid projectUid, Guid sessionUid) at Microsoft.Office.Project.Server.BusinessLayer.ProjectQueueDispatch.InternalDispatchMessage(IPlatformContext context, Message msg, Group messageGroup,
    JobTicket jobTicket, MessageContext mContext)'. 
    •Queue:◦GeneralQueueJobFailed (26000) - ProjectUpdate.ProjectUpdate2Message. Details: id='26000' name='GeneralQueueJobFailed' uid='f8bb5d93-20e9-e411-b302-005056ae159c' JobUID='a6fa36de-1fe9-e411-b302-005056ae159c' ComputerName='1af8030b-7714-4c8f-8738-903b73e87a82'
    GroupType='ProjectUpdate' MessageType='ProjectUpdate2Message' MessageId='2' Stage='' CorrelationUID='0a4aff9c-dd6b-7015-87a8-29d876e1540c'. For more details, check the ULS logs on machine 1af8030b-7714-4c8f-8738-903b73e87a82 for entries with JobUID a6fa36de-1fe9-e411-b302-005056ae159c. 
    What will i do .Please help.

    Hi Jeremy,
    Thanks for the reply .I try the steps that is given in link above but its not working.Please suggest something.What
    should i do.

  • How to import the Issues list from an Excel File in Project Server 2013

    Hi,
    I'm using Project Server 2013.
    A Project Manager has been playing with the Issues List, deleting some fields, creating new columns and modifying some columns name. The result of this is that I'm getting this error everytime the task
    Reporting (Project Sync) is executed:
    General
    Reporting Wss list sync failed:
    ReportingWssSyncListFailed (24018) - 1100. Details: id='24018' name='ReportingWssSyncListFailed' uid='4feafda7-f147-e411-940d-005056957f05' SPListType='a1efd9a9-bd03-4604-91f3-31a2cc5693ff' Error='1100'.
    ReportingWssSyncListFailed (24018) - 1100. Details: id='24018' name='ReportingWssSyncListFailed' uid='5deafda7-f147-e411-940d-005056957f05' SPListType='a1efd9a9-bd03-4604-91f3-31a2cc5693ff' Error='1100'.
    ReportingWssSyncListFailed (24018) - 1100. Details: id='24018' name='ReportingWssSyncListFailed' uid='69eafda7-f147-e411-940d-005056957f05' SPListType='a1efd9a9-bd03-4604-91f3-31a2cc5693ff' Error='1100'.
    ReportingWssSyncListFailed (24018) - 1100. Details: id='24018' name='ReportingWssSyncListFailed' uid='75eafda7-f147-e411-940d-005056957f05' SPListType='a1efd9a9-bd03-4604-91f3-31a2cc5693ff' Error='1100'.
    ReportingWssSyncListFailed (24018) - 1100. Details: id='24018' name='ReportingWssSyncListFailed' uid='81eafda7-f147-e411-940d-005056957f05' SPListType='a1efd9a9-bd03-4604-91f3-31a2cc5693ff' Error='1100'.
    ReportingWssSyncListFailed (24018) - 1100. Details: id='24018' name='ReportingWssSyncListFailed' uid='8deafda7-f147-e411-940d-005056957f05' SPListType='a1efd9a9-bd03-4604-91f3-31a2cc5693ff' Error='1100'.
    Reporting message processor failed:
    ReportingWSSSyncMessageFailed (24016) - RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.. Details: id='24016' name='ReportingWSSSyncMessageFailed' uid='5beafda7-f147-e411-940d-005056957f05' QueueMessageBody='ProjectUID='a1efd9a9-bd03-4604-91f3-31a2cc5693ff'.
    ForceFullSync='False'. SynchronizationType='Issues'' Error='RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.'.
    ReportingWSSSyncMessageFailed (24016) - RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.. Details: id='24016' name='ReportingWSSSyncMessageFailed' uid='67eafda7-f147-e411-940d-005056957f05' QueueMessageBody='ProjectUID='a1efd9a9-bd03-4604-91f3-31a2cc5693ff'.
    ForceFullSync='False'. SynchronizationType='Issues'' Error='RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.'.
    ReportingWSSSyncMessageFailed (24016) - RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.. Details: id='24016' name='ReportingWSSSyncMessageFailed' uid='73eafda7-f147-e411-940d-005056957f05' QueueMessageBody='ProjectUID='a1efd9a9-bd03-4604-91f3-31a2cc5693ff'.
    ForceFullSync='False'. SynchronizationType='Issues'' Error='RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.'.
    ReportingWSSSyncMessageFailed (24016) - RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.. Details: id='24016' name='ReportingWSSSyncMessageFailed' uid='7feafda7-f147-e411-940d-005056957f05' QueueMessageBody='ProjectUID='a1efd9a9-bd03-4604-91f3-31a2cc5693ff'.
    ForceFullSync='False'. SynchronizationType='Issues'' Error='RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.'.
    ReportingWSSSyncMessageFailed (24016) - RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.. Details: id='24016' name='ReportingWSSSyncMessageFailed' uid='8beafda7-f147-e411-940d-005056957f05' QueueMessageBody='ProjectUID='a1efd9a9-bd03-4604-91f3-31a2cc5693ff'.
    ForceFullSync='False'. SynchronizationType='Issues'' Error='RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.'.
    ReportingWSSSyncMessageFailed (24016) - RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.. Details: id='24016' name='ReportingWSSSyncMessageFailed' uid='97eafda7-f147-e411-940d-005056957f05' QueueMessageBody='ProjectUID='a1efd9a9-bd03-4604-91f3-31a2cc5693ff'.
    ForceFullSync='False'. SynchronizationType='Issues'' Error='RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.'.
    Queue:
    GeneralQueueJobFailed (26000) - ReportingWSSSync.WSSSyncMessageEx. Details: id='26000' name='GeneralQueueJobFailed' uid='98eafda7-f147-e411-940d-005056957f05' JobUID='9e937da7-f147-e411-940e-005056957f0d' ComputerName='b579360a-53ab-4fe0-bf9b-c62f5e8d3529'
    GroupType='ReportingWSSSync' MessageType='WSSSyncMessageEx' MessageId='1' Stage='' CorrelationUID='0945bd9c-0d6a-a0f1-47b0-68cdfcfbff9a'. For more details, check the ULS logs on machine
    b579360a-53ab-4fe0-bf9b-c62f5e8d3529 for entries with JobUID
    9e937da7-f147-e411-940e-005056957f0d
    What I'm trying to do is to create a new Project from the scratch, update the Issues List, not deleting or modifying columns, just creating new columns in order to match the names he (the Project Manager) put in his Issues List, then Export the list to Excel,
    and then create a datasheet view matching the Exported list, but here I don't know how to import the list (copy / paste or whatsoever it can be done...)
    Do you know how to do it, or do you know another/any method to solve this problem?
    Thank you in advance,
    José Espases

    Hi José,
    2 considerations: 
    The first one is that (as you experienced) one should not delete or rename any of the predefined columns in the risk/issue list. What you did is the right way, meaning keeping the native column as is and creating new ones based on the business needs. Finally
    you just need to create view with the appropriate fields.
    Then for importing risks from an Excel list, I can't test it right now, but you should have a datagrid view (MS Access type) allowing you pasting data from Excel.
    Hope this helps,
    Guillaume Rouyre, MBA, MCP, MCTS |