Purchase Order Change Restriction after MIGO and MIRO

Hi Experts,
I'd like to ask why Purchase Orders are allowed for change even when the Material Document and Invoice is already created under them, unlike the Sales Order in SD. Or is this some kind of configuration where I can configure the restriction of changes in these Purchase Orders?
Thanks a lot!

Hi,
You can set Release Indicator in designing Release procedure of PO & set Release Indicator 1 where release Indicator 1 is used for purchasing document cannot be changed/Change not allowed after release. & then You can do GR & MIRO.
Regards,
Biju K

Similar Messages

  • Purchase Order, MIGO and MIRO

    Dear All,
    Please guide me how to map the below scenario in SAP.
    We have to procure Material 'C' for that we have to get the Material 'A' from "X" Vendor. And it has to be delivered to "Y" Vendor. Then vendor "Y" uses Material 'B' and he does some processing and deliver Material 'C' to us. How to raise a purchase order, how to do MIGO and MIRO.
    Thanks & Regards,
    Kumar

    Hi Kumar,
    1. Raise the PO(1) against the X vendor (materila A). in PO give the delivery address as Vendor Y..( it is in PO itemdetail tab)...
    2. create one more PO(2) (as subcontract) with item cater as L and issue to Vendor Y....
    Item C should have BOM as mateila A...
    3. Now you receive the materila A at vendor Y as against the PO(1).... (vendor X deliver the materila directly to vendor Y)...
    Now for when you do migo for the PO(1), it will hapen for movement type 101 and in backgorund it create the 541movement type to vendor Y ( issue componet to sub contract vendor )
    4. Settle the Invoice of Vendor X in MIRO seperatly.
    5. receive the Goods from the subcontract vendor (y) throug MIGO
    6. do MIRo for PO(2)
    Hope you understoud this...
    REgards
    anand

  • SRM: "Purchase Order Change Approval " and "Invoice Approval"

    Hi,
    I would like to know the availability and details of the backend services for "Purchase Order Change Approval " and "Invoice Approval".
    Any pointers ?
    regards
    Sachin

    I want to know what are the Backend services exposed for the following processes :
    Purchase Order Change Approval in MM
    and Invoice Approval.

  • Returns to vendor agter MIGO and MIRO

    hI,
    I have made on PO, did MIGO and MIRO for the same (CIN)
    Now i want to send back the material to vendor in two scenarios
    1) After MIGO
    2) After MIGO and MIRO
    3) After payment has been done.
    Regards,
    Satyendra

    Hi,
    For First case you can use 102 mov type against material document to return material.
    For Second & Third cases
    1) Create a return po and check the return item field in the po detail.
    2) create a return goodds receipt with migo. 161 will happen automatically.
    3) create a credit memo thru. miro.
    4) crease a excise invoice for other movements thru J1IS (if material is excisable.)
    5) post a excise invoice thru J1IV
    Revert back if any doubts.
    Ashok
    Reward is useful.

  • What Message type and Process Code to use for Purchase Order Change in 4.6C

    I like to implement in SAP R/3 4.6C a scenario for Purchase Order Change, via inbound IDoc.
    I have been searching, but could not find what Message Type, Idoc Basic Type and Process Code to use.
    I can not imagine this functionality does not exist in 4.6C.
    Any suggestions for my problem are welcome.

    Hello,
    In this case you should use the message PORDCH and BAPI method BAPI_PO_CHANGE but only exist as of release 4.7.
    Function module    BAPI_IDOC_INPUT1
    Idoc Type              PORDCH01
    Message Type      PORDCH
    So check carefully the following OSS notes:
      [Notes 589066 - BAPI_PO_CHANGE: Incorrect account assignment to network |https://service.sap.com/sap/support/notes/589066] (not be fooled by the description)
    [ Notes 197958 - BAPIs for purchase orders - Missing Functions|https://service.sap.com/sap/support/notes/197958]
    Regards,
    Andrea
    Edited by: Andrea Olivieri on Sep 3, 2009 10:17 AM

  • Non Cenvatable material - Value not matching in MIGO and MIRO

    Dear SAP experts!
    We have the following problem.
    We are using TAXINN.
    We create a Purchase Order for a raw material, which is non cenvatable for a particular vendor.
    When we carry out Goods Receipt, we change the Material type from Raw Material to Non Cenvatable in the Material Type in the Excise Item Tab and post the BED and AED values, the values are getting inventorized correctly.
    And MIRO posting is also happening correctly. Both, MIGO and MIRO values are tallying. i.e, The total value is sum of Basic PriceBEDAED+CST.
    But, if we change any of the BED or AED value at the time of posting GR in the excise Invoice tab, then we are facing problem.
    Value during MIGO posting is correct. That is the total value is sum of Basic PriceBEDAED+CST.
    But, During MIRO posting, the value of BED and AED is not getting picked.
    The value during MIRO shows only Basic Price+CST and not BED amount and AED amount.
    Can any one tell me, where it is going wrong.
    Your response is highly appreciated.
    Thanks and Regards,
    Muthuraman.K

    you have to used non deductable condition type in Taxinn to post tax to inventory
    that is
    JMIP IN: BED inventory % say 8%
    JAIP IN AED inventory % Say 4 %
    JMX2     IN: A/P BED inventor  100 %
    JAX2     IN: A/P AED inventor  100%
    and the above condition should be assigned to proper Classify Condition Types
    TAXINN     JMIP     BEDINVENTP BED Inventory Percentage
    TAXINN     JAIP     AEDINVENTP AED Inventory Percentage
    TAXINN     JMX2     BEDINVENTT BED Inventory Total
    TAXINN     JAX2     AEDINVENTT AED Inventory Total
    And also u will have to assign condition type JMX2 and JAX2 in Maintain Excise Defaults
    this will solve your issue

  • Why req MIGO and MIRO in third party scenario

    Hello All,
    In third party scenario why we req to do MIGO in ref to PO.
    In 3rd party we create sales order with item cat TAS.
    We got the PR
    with ref to PR we create PO.
    then we do MIGO  and MIRO
    also If vendor is delivering the goods why we do the Delivery and PGI and then Invoice
    Why not Invoice with ref to sales order.
    regards,
    abhijit

    Hi
    In Third Party sales, the Item category is TAS ,if the Vendor directly supplies to the end customer.
    In Item category TAS, "Billing Relevance" is "F", i,e. Order related billing as per invoice quantity.
    If the Item category of the Third Party item is TAS, then Schedule line category is CS in standard. If you will go to CS, you will find , the "Delivery relevance" field is blank and there is no "Goods movement" also. That means no Delivery takes place against the Sales order, so no goods issue.
    This clearly indicates, we do not create any Delivery and no goods receipt takes place in third party sales process, when the vendor directly sends the goods to the customer.
    Once the goods are send to the end customer, Vendor creates an invoice and sends to the ordering company. Now, ordering company goes for Invoice verification ,what the vendor has sent to him. We only go for MIRO here and not MIGO.
    After that, the ordering company, creates the Customer invoice with reference to the Sales order(placed by its customer) and sends it to its customer.
    Complete process:
    Once the order is received from the custome(say ABC)r, the company (say XYZ) creates a Sales order ---> Purchase requisition is automatically triggered from the sales order -
    > from this Purch requisition a PO is created for the vendor -
    > aginst the PO, Vendor delivers the goods to the customer ABC and charge the ordering company,sends invoice for the same to the ordering company XYZ -
    > Ordering company XYZ does Vendor's invoice verification and creates a Customer invoice with reference to customer's(ABC) order and sends to the customer ABC.
    Some times Vendor sends the goods to the ordering company and then ordering company delivers the goods to its customer.
    Vendor does not deliver directly to the end customer in this case.
    In this case Item category is TAB and Schedule line category is CB.
    Here, Billing relevance is "A" - (Delivery related billing) in the Item category TAB, that means here Delivery takes place and Billing is created with reference to the Delivery created to the customer.
    In Schedule line category CB, you will find, 'Delivery relevance" field is activated and there is a movement type "601".
    So, Delivery and goods issue both takes place here.
    Here we go for both MIGO and MIRO.

  • Searching for Workflow for Purchase Order Change

    Hi experts!
    We are using SRM5.0 / extended classic scenario and backend R/3 4.7 Enterprise.
    We should implement an approver process for the purchase order changes. Does any one of you know whether there exists a standard SAP workflow?
    Many thanks for your help.
    Regards,
    Corinne

    Hi
    <i>Please refer to the following links for detailed step-by-step details.</i>
    <u>Workflows for Purchase Orders - n-step approval workflow ( WS14000145 )... Start WS14000075, WS14000089 or WS14000145...-step approval workflow ( WS14000145 )</u>
    http://help.sap.com/saphelp_srm50/helpdata/en/5a/c5173f5ff48443e10000000a114084/frameset.htm
    <u>Authorization - Purchase orders ( WS14000145 )</u>  
    http://help.sap.com/saphelp_srm50/helpdata/en/f7/a6a3415e34b05fe10000000a1550b0/frameset.htm
    <u>Setting Up SAP Business Workflow - WS14000145 ( n-step approval )... WS14000145... WS14000145 – N-step approval PO WS14000145 – N-step approval of contract</u>  
    http://help.sap.com/saphelp_srm50/helpdata/en/2c/e68d406b305537e10000000a1550b0/frameset.htm
    <u>Dynamic Modification - Purchase orders ( WS14000145 )</u>  
    http://help.sap.com/saphelp_srm50/helpdata/en/84/dda441e79ead5fe10000000a1550b0/frameset.htm
    <u>Back & Forth Processing and the Retain Function - Purchase orders ( WS14000145 ) </u> 
    http://help.sap.com/saphelp_srm50/helpdata/en/6b/eca441eea7ef0be10000000a1550b0/frameset.htm
    <u>Approval Workflows for Purchase Orders and Change Versions</u>
    http://help.sap.com/saphelp_srm50/helpdata/en/ec/fe163ff8519a06e10000000a114084/frameset.htm
    <u>Workflow for Contracts - Workflow for Purchase Orders ( WS14000145 )</u>
    http://help.sap.com/saphelp_srm50/helpdata/en/26/0f8b41ed891609e10000000a155106/frameset.htm
    <u>SRM Business Workflow - One-step Approval</u>
    http://help.sap.com/saphelp_srm50/helpdata/en/8b/4fa9585db211d2b404006094b92d37/frameset.htm
    <u>WS14000089</u>
    http://help.sap.com/saphelp_srm50/helpdata/en/5a/c5173f5ff48443e10000000a114084/frameset.htm
    <u>WS14000075</u>
    http://help.sap.com/saphelp_srm50/helpdata/en/2c/e68d406b305537e10000000a1550b0/frameset.htm
    http://help.sap.com/saphelp_srm50/helpdata/en/5a/af5efc85d011d2b42d006094b92d37/frameset.htm
    Regards
    - Atul

  • Purchase order changes through EDI

    Hi All,
    Is it possible to transmit only changes made againt each purchase order through EDI. If so how that can be done.
    For example if the quanity of purchase order changed then only changed quanity field should be transmitted through EDI.
    Thanks & Regards,
    N. Laxman

    Hi Laxman.
    What do you have on WE20?
    Usually you have two records. One to send the PO when you create and another one for changes;
    Partner role | Message Type | Message Function
    OA              | ORDERS           | 850
    OA              | ORDCHG          | 850
    For the message type ORDCHG in the config you have to set the message control as follow
    Application | Message type | Process code | Change
    EF               | NEU                 | ME11              | checked
    Hope this helps.
    Regards
    Eduardo

  • Update Ledger group in BKPF at the time of MIGO and MIRO

    Hi Friends,
    In our current implementation we have requirement to update a certain Ledger group, to restrict the postings in all ledgers, at the time of positng in MIGO and MIRO.
    Can you please let me know how we do this.
    Waiting for your reply,
    Madan Mohan

    Hi Santhosh,
    Thanks for your reply. But in the substitutions at header and line item level i didnt find the 'U300' userexit.
    Can you suggest me at what level i can find that user exit.
    Thanks and Regards,
    Madan

  • Tcode for Purchase order Changes

    Hello Expert
    I Know there is one Tcode from which we could find changes happen in Purchase order at item level . Can any one let me know on the same which Tcode.
    I know the regular option by selecting the line item Environment->Item changes
    thanks
    Abhi

    Hi,
    You have to develope an own ABAP report for this, based on the change tables CDHDR and CDPOS
    CDHDR - Header Change
    CDPOS - Item Change
    EREV - Version Change
    Go to SE11 / SE16 / SE16N, here enter Object value as "PO No" in Table CDHDR and get the Document No and then input this in CDPOS and get the changes details. You can also enter EKKO and EKPO tables and see the whole list.
    Check the link
    Purchase order change log
    SAM
    Edited by: Saminathan Gopalan on Jun 3, 2010 12:35 PM
    Edited by: Saminathan Gopalan on Jun 3, 2010 12:37 PM

  • Incorrect message type in IDOC for Purchase order change

    Hi Gurus.
    Please advise on below.
    We have several purchase orders that are configured to trigger IDOC upon change. But accidentally, someone has deactiveted the automatic proposal of EDI message type for these Purchase orders which resulted to not transmitting purchase order change documents automatically.
    As a workaround, we have proposed to create EDI message manually during Purchase order change. But upon checking in tcode WE09, message type is ORDERS which is PO create instead if ORDCHG for purchase order change.
    Please kindly advice on why it is behaving like this for purchase orders with EDI message previously deactivated.
    Thanks in advance.
    Acel.
    To simulate.
    Create PO. go to messages, select EDI message then deactivate permanently. Save PO. Release PO if needed. Change PO. go to messages, EDI is not automatically proposed. create EDI message mamanually. Save PO. Release PO id needed. check tcode WE09, for PO create, no IDOC since it was deactivated permanently. For PO change, IDOC was triggered but with incorrect message type ORDERS instead of ORDCHG.

    Hi Acel,
    You will need to check the settings in transaction WE20 - You will be using a Partner Profile to determine the outbound message, either for each vendor or a generic one.
    on the outbound parameters, you will need to ensure that ORDCHG is set up as a message type. If not, add it, ensuring that you use the message ORDCHG, the basic type (or extension) that you are using, usually ORDERS05 and make sure that in message control, you have process code ME02 set up. This should enable the correct message type to be determined.
    Regards,
    Rob

  • Value difference for GR/IR Clearing Account in case of MIGO and MIRO.

    Hello Experts,
    One of our client has asked me about clarification regarding GR/IR Clearing Account shows different values when MIGO and MIRO posting. Scenario is that,
    SEZ
    Calculation of import Duty
    Input goods
    Material Base Value
           2,171,385
    Landing Cost
                 21,714
    For computing Customs landing charges need to be added
    BED @
    10%
               219,310
    Loaded in material cost
    CVD, @
    12%
               289,489
    Credit taken
    Customs Education Cess
    3%
                 15,264
    Loaded in material cost
    ADDL Duty
    4%
               108,686
    Credit taken
    Customs Duty
               632,749
    CVD
    12%
               219,310
    All duty
    4%
               108,686
    Cenvat
               327,996
    CST
           43,427.70
    2214812.7
    Hence Material cost in GR/IR should be Rs. 22,14,813
    Diff (2219092-2214813= 4279)
    Whereas it is taking Rs. 22,19,092
    My concern is that GR/IR Clearing Account consider only Material cost and non deductible tax amount i.e. CST which is loaded on material cost but system consider some different values, please check the above calculation. When user post MIRO in that case system automatically konck off GR/IR Clearing Account and post difference amount i.e. RS. 4279 to Inventory Account which is wrong. I dont know how system behaves in such manner.
    Please giude me on this issue as soon as possible.
    Regards,
    Vishal Jadhav

    Discussion moved. Please use Internationalization and Unicode for CIN related queries.

  • Purchase Order Dashboard using Adobe Flex and AIR

    Hi ,
      I have written a AIR apps for displaying the Purchase Order using OPen source Flex and AIR making Web Service calls to our SAP R3  6.20 Backend System . If anybody would be interested in taking a look at it and expanding the apps please free to post at those forum with the your email ID . I can send the AIR apps along with the source code .
    Thnks
    V

    I have uploaded the zip file containing my code . If anybody is interested can download from this link .
    http://www.mediafire.com/?8mfesdczsuv
    Vinod

  • Message "Purchase Order Changes are awaiting approval"

    Hi all,
    while changing a PO document which is in status "in Approval", SRM (5.0) throws a popup message:
    "The Purchase Order Changes are awaiting approval, Continue processing?"
    Does anybody know the place were SRM throws this message?
    I want to suppress the message completely.
    I can`t find the message within table t100.
    Any ideas?
    Thanks
    Regards
    Andreas

    Hi Yang,
    thanks, this answer I was looking for
    Best regards
    Andreas

Maybe you are looking for