Purchase requisition - no GR processing time

Hi,
when you create a purchase requisition in transaction ME21n the goods receiving processing time is considered (from the material master MM02).
In some cases (e.g. Third-Party) we want that this GR processing time is ignored.
Is there a possibility in the standard to set up this functionality?
Or must we implement coding in an userexit or BAdi?
Thanks for your help.

SB,
Purchase requisitions are not normally created in ME21.  For manual creation, you would normally use ME51, or ME51N for the Enjoy version.
As far as I know, goods receipt processing time is specific to the Material/plant.  It is irrelevant to the source of the supply proposals.
Keep in mind that purchase requisitions are often created by MRP. Your ME51 mod will most probably have no effect on these PRs.   During MRP, at the time when the PR is being created, the completion date has already been determined, but the source has not yet been determined.  In addition, not all purchase reqs are sourced.  Your programmers will have an interesting task ahead of them if you want to make MRP, during PR creation, to consider GRPT on selected PRs, based on source of the PR.  Good luck!
Normally, if you wish to have sourced PRs act differently, depending on the source, you enter planned delivery time in the Purchase Info Record, and then configure your PRs to use Purchase Info record data rather than Material Master data.  This will not alter the finish date as GRPT will, but in some cases it gives you enough functionality to meet your business requirements.
Rgds,
DB49

Similar Messages

  • Purchase Order - Goods receipt processing time (User Exit)

    Hi All,
    I would like to know if there is any User Exits available for this scenario.
    In the Delivery tab of PO, we see GRPT & Planned Delivery Time, this information is picked up from the material master. In my case i have included the transport time in the GRPT time, so i have kept the GRPT = 25 days as the material is sent by sea. But in certain cases the material might be sent by air & the GRPT will then only be 5 days. So i want to use the Shipping instr field, where i select Shipping Instr1 & i want the system to force the GRPT time to be 5 days instead of the normal 25 days, when the PO is saved. Is this possible?
    Alternatively if there is a better solution, kindly advice me.
    Vivek

    Dear Vivek,
    Thanks for recognising me,and also serch for you some document i am giving sap  library link below.and also availble in first thread.
    http://help.sap.com/saphelp_46c/helpdata/en/e1/8e51341a06084de10000009b38f83b/frameset.htm
    Hope this will helps you.
    Prem.

  • Changing purchase requisition with processing status B

    How can I restrict purchase requisition changes with processing status B regardless release indicator. Rel 4.7

    Hi Mitra,
    You will find your answer here.
    MRP controller for PR document type
    Do let me know if it helped, as I might have to explore this option for an upcoming requirement.
    Thanks
    Shailesh

  • Cancellation of Release of a purchase requisition

    Hi,
    Currently the system allow to cancel the Release of a purchase requisition eventhought the Purchase Order already created for it.
    I could not locate the any system message that actually control this.
    How to disallow the cancellation of Release of a purchase requisition if the processing status is 'PO Created'.
    Best regards,

    Dear Eric,
    We cant do cancel of PR onece PO created.not only that onece release of PR we cant cancel the PR we can do only flag the release PR.
    Hope this will helps you
    Prem.

  • Outline Agreement is not visible within the purchase requisition.

    When creating purchase requisitions from a work order that reference an existing outline agreement the outline agreement is not linking to the purchase requisition (not visible from PR at all). The service masters are however being successfully referenced and are visible on the PR.
    1)The successful linking of the outline agreement appears to stem from the sequence of steps undertaken. If the requisitioner leaves the vendor field blank inititially and continues on to reference the required outline agreement and service master for the desired vendor then the outline agreement will be successfully linked.
    2)If however the requisitioner completes the vendor field and continues on to reference an outline agreement then the outline agreement is not visible within the purchase requisition. This is causing delays in the purchasing process as the purchase requisition cannot be processed until referencing the appropriate outline agreement.
    Please suggest if I need to make any config change for the second point.
    Regards
    Vishvesh

    Hi Pooja,
    Generally the Outline agreemtn will not trigger Purhchase requsitions , it will only trigger the Schedule lines.
    So kindly check the same.
    Reg
    Dsk

  • Purchase Requisition Processing Time

    I am currently facing an issue with the purchase requisitoin processing time functionality. It does not appear to work for items without a material master. So if I create a purchase requisition with material master line items and non-material master line items only the material master line items will have the delivery date increased by the purchase requisitoin processing time. Is this standard SAP or a bug?

    Dear MM Project.
    PR processing time/ GR processing time etc are fields which are mentioned in the material master for each material.
    while you process the document with a master record, these details make an impact in those documents. however we may or may not have master records for consumables. the consumables which have a master record will show this impact. these are material types UMBW and NLAG.
    for consumables which doesnt have any master record, you can not expect system to impact these values.
    hence if you need to have the impact of PR processing time, please create a master record for all those materials and process documents further.
    Raghavan

  • BZTEK - Purchasing Processing Time to convert PR in PO

    Hi all,
    In SAP stanrdard, Purchasing Processing Time to convert PR in PO is maintainable in customizing at plant level.
    As anyone any advice of solution to implement when there is a business need to have this time depending on:
    - PO type
    - PO type / material
    Thank you,
    Laetitia

    Hello, Laëtitia,
    not in standard; but you can modify the field FRGDT "Purchase Requisition Release Date" through customer enhancement MEREQ001 "Customers' Own Data in Purchase Requisition" / function EXIT_SAPLMEREQ_005 "Checking Customer's Own Purchase Requisition Data" -- yep, it sounds strange that you can change some standard fields thou function called " "Checking Customer's Own Data", but that is how it works (see enhancement documentation for details).
    Of course, the PO type (or rather PREQ type) / Material Purchasing Processing Time will have to be stored in custom tables.
    Kind Regards
    TomT

  • Reg purchasing department processing time MRP

    Is The purchasing department processing time defined for the plant is taken into consideration by MRP while calculating purchase requisition release date??? If not then what is the use of this ? [Where do we configure this in SPRO] ?
    SAP help says ..
    The planned delivery time from the purchasing info record and the GR processing time are only taken into account if the purchase requisition was generated via materials planning.

    This is what i understood please correct me if i am wrong
    Requirement Date <GR Processing Time> Delivery Date <Plan Delivery Date>PODate <Plant purchase processing time> PR Release Date
    Purchase process time will have effect on PR Release date not on Delivery date
    Edited by: sasibhushan334 on Apr 28, 2010 2:08 AM

  • User exit/BADI  for Purchase requisition through release of Process order

    Hi ,
    i need to add some text to the Pur Req.
    The Pur Req will be created THROUGH the release of PROCESS order. Please let me know any exits are available for the same.
    regards

    Hi
    Check the following Exits and BADI for Pur Requisition
    Enhancement
    MEVME001                                WE default quantity calc. and over/ underdelivery tolerance
    MM06E001                                User exits for EDI inbound and outbound purchasing documents
    MM06E003                                Number range and document number
    MM06E004                                Control import data screens in purchase order
    MM06E005                                Customer fields in purchasing document
    MM06E007                                Change document for requisitions upon conversion into PO
    MM06E008                                Monitoring of contr. target value in case of release orders
    MM06E009                                Relevant texts for "Texts exist" indicator
    MM06E010                                Field selection for vendor address
    MM06E011                                Activate PReq Block
    MMAL0001                                ALE source list distribution: Outbound processing
    MMAL0002                                ALE source list distribution: Inbound processing
    MMAL0003                                ALE purcasing info record distribution: Outbound processing
    MMAL0004                                ALE purchasing info record distribution: Inbound processing
    MMDA0001                                Default delivery addresses
    MMFAB001                                User exit for generation of release order
    MRFLB001                                Control Items for Contract Release Order
    AMPL0001                                User subscreen for additional data on AMPL
    LMEDR001                                Enhancements to print program
    LMELA002                                Adopt batch no. from shipping notification when posting a GR
    LMELA010                                Inbound shipping notification: Transfer item data from IDOC
    LMEQR001                                User exit for source determination
    LMEXF001                                Conditions in Purchasing Documents Without Invoice Receipt
    LWSUS001                                Customer-Specific Source Determination in Retail
    M06B0001                                Role determination for purchase requisition release
    M06B0002                                Changes to comm. structure for purchase requisition release
    M06B0003                                Number range and document number
    MEQUERY1                                Enhancement to Document Overview ME21N/ME51N
    MELAB001                                Gen. forecast delivery schedules: Transfer schedule implem.
    MEFLD004                                Determine earliest delivery date f. check w. GR (only PO)
    MEETA001                                Define schedule line type (backlog, immed. req., preview)
    ME590001                                Grouping of requsitions for PO split in ME59
    M06E0005                                Role determination for release of purchasing documents
    M06E0004                                Changes to communication structure for release purch. doc.
    M06B0005                                Changes to comm. structure for overall release of requisn.
    M06B0004                                Number range and document number
    Business Add-in
    ME_PROCESS_REQ_CUST                     Enhancements for Processing Enjoy PReqs: Customer
    ME_PROCESS_REQ                          Enhancements for Processing Enjoy PReqs: Internal
    ME_PROCESS_PO_CUST                      Enhancements for Processing Enjoy Purchase Order: Customer
    ME_PROCESS_PO                           Enhancements for Processing Enjoy Purchase Order: Intern.
    ME_PROCESS_COMP                         Processing of Component Default Data at Time of GR: Custome
    ME_PO_SC_SRV                            BAdI: Service Tab Page for Subcontracting
    ME_PO_PRICING_CUST                      Enhancements to Price Determination: Customer
    ME_PO_PRICING                           Enhancements to Price Determination: Internal
    ME_INFOREC_SEND                         Capture/Send Purchase Info Record Changes - Internal Use
    ME_HOLD_PO                              Hold Enjoy Purchase Orders: Activation/Deactivation
    ME_GUI_PO_CUST                          Customer's Own Screens in Enjoy Purchase Order
    ME_FIELDSTATUS_STOCK                    FM Account Assignment Behavior for Stock PR/PO
    ME_DP_CLEARING                          Clearing (Offsetting) of Down Payments and Payment Requests
    ME_PURCHDOC_POSTED                      Purchasing Document Posted
    SMOD_MRFLB001                           Control Items for Contract Release Order
    EXTENSION_US_TAXES                      Extended Tax Calculation with Additional Data
    ARC_MM_EKKO_WRITE                       BAdI: Enhancement of Scope of Archiving (MM_EKKO)
    ARC_MM_EKKO_CHECK                       BAdI: Enhancement of Archivability Check (MM_EKKO)
    MM_EDI_DESADV_IN                        Supplementation of Delivery Interface from Purchase Order
    MM_DELIVERY_ADDR_SAP                    Determination of Delivery Address
    ME_WRF_STD_DNG                          PO Controlling Reminder: Extension to Standard Reminder
    ME_TRIGGER_ATP                          Triggers New ATP for Changes in EKKO, EKPO, EKPV
    ME_TRF_RULE_CUST_OFF                    BADI for Deactivation of Field T161V-REVFE
    ME_TAX_FROM_ADDRESS                     Tax jurisdiction code taken from address
    ME_REQ_POSTED                           Purchase Requisition Posted
    ME_REQ_OI_EXT                           Commitment Update in the Case of External Requisitions
    ME_RELEASE_CREATE                       BAdI: Release Creation for Sched.Agrmts with Release Docu.
    ME_DEFINE_CALCTYPE                      Control of Pricing Type: Additional Fields
    ME_CHANGE_OUTTAB                        Enrich ALV Output Table in Purchasing
    ME_CHANGE_CHARACTER                     Customer-Specific Characteristics for Product Allocation
    ME_CCP_DEL_DURATION                     Calc. of Delivery Duration in CCP Process (Not in Standard)
    ME_CCP_BESWK_AUTH_CH                    BAdI for authorization checks for procuring plant
    ME_CCP_ACTIVE_CHECK                     BAdI to check whether CCP process is active
    ME_BSART_DET                            Change document type for automatically generated POs
    ME_BAPI_PR_CREATE_02
    ME_BAPI_PR_CREATE_01
    ME_BAPI_PO_CREATE_02
    ME_BAPI_PO_CREATE_01
    ME_BADI_DISPLAY_DOC                     BAdI for Internal Control of Transaction to be Invoked
    ME_ACTV_CANCEL_PO                       BAdI for Activating the Cancel Function at Header Level
    MEGUI_LAYOUT                            BAdI for Enjoy Purchasing GUI
    ME_CHECK_ALL_ITEMS                      Run Through Items Again in the Event of Changes in EKKO
    ME_COMMTMNT_REQ_RE_C                    Check of Commitment Relevance of Purchase Requisitions
    ME_COMMTMNT_REQ_RELE                    Check of Commitment Relevance of Purchase Requisitions
    ME_COMMTMNT_PO_REL_C                    Check for Commitment-Relevance of Purchase Orders
    ME_COMMTMNT_PO_RELEV                    Check for Commitment-Relevance of Purchase Orders
    ME_COMMITMENT_STO_CH                    BadI for checking if commitments for STOs are active
    ME_COMMITMENT_RETURN                    Commitment for return item
    ME_CIP_REF_CHAR                         Enables Reference Characteristics in Purchasing
    ME_CIP_ALLOW_CHANGE                     Configuration in Purchasing: Changeability Control
    ME_CIN_MM06EFKO                         Copy PO data for use by Country version India
    ME_CIN_LEINRF2V                         BADI for LEINRF03 excise_invoice_details
    ME_CIN_LEINRF2R                         BADI for CIN India - Delivery charges
    ME_CHECK_SOURCES                        Additional Checks in Source Determination/Checking
    ME_CHECK_OA                             Check BAdI for Contracts
    Reward points if useful
    Regards
    Anji

  • Unnecessary Purchasing Processing Time in scheduling agreement

    According to its business logic, the scheduling agreement is a document  that has  already been  released  by purchasing department,  and  its scheduling lines, that have been created by MRP  are valid for goods receipt without any need for additional purchasing  processing time. However, MRP scheduling incorrectly takes purchasing processing time into account (as defined in the IMG in plant parameters for external procurement - TCODE  OPPQ) when calculating planned availability date. Please advise how to correct this issue.
    Best Regards,
    Itzik Eshed

    This can be customized in
    SAP Customizing Implementation Guide
    -> Production
    --> Material Requirements Planning
    ---> Planning
    > Procurement Proposals
    > Define External Procurement
    Here you can select the indicator "Scheduling according to purchasing info record or agreement" either at plant or MRP group level.

  • FM or BAPI for  date and time for the creation of a Purchase Requisition

    Hi people:
    Does anybody knows about a FM, BAPI or table in which i have de detail for the date and hour of the creation of a Purchase requisition?
    Points for helpfull answers.
    Thanks in advanced

    Hi,
    If you want to get the time along with the creation date then use the tables CDHDR and CDPOS, but be careful while passing the data need to pass the entire primary fields data else it will fail in the performance test.
    Reward points if useful.
    Regards,
    Suman

  • Purchasing department processing time

    Hi All,
    I am looking for a report to see the Procurement department turnaround time. i need the numbers of days from when the requisition was released to when the PO was created.
    I tried to use ME5A and I was going to do the calculation in excel but the requisition release date field is not when the requisition was release but rather specifies the date on which the purchase order should be initiated on the basis of the purchase requisition (according to SAP help F1).
    I am thinking a custom report might be required but would like to make sure first.
    Your Help would be appreciated.
    Regards,
    GA

    Hai,
    You have to develop new Z report with the tables -
    1.Purchase requistion EBAN - Fields BANFN - PR number & FRGDT Release date
    2.Purchase order Header EKKO - Fields AEDAT Created date
    3. Purchse order item EKPO - Field BANFN - PR number.

  • Purchase efficiency and processing time in purchasing

    Hi friends,
    here purchase efficiency they want to find out, please suggest me any report and please do let me know use of  processing time in purchasing
    Thanks and regards,
    Balakrishna R.V

    Processing time-
    It is the time required by buyer to convert PR into PO.
    You can maintain the Processing time on plant basis.
    The processing time is taken into account during the scheduling process for externally procured materials within the framework of materials planning and control
    for example- Planng time (to produce the material at vendor end)  + Processing time (time required by buyer) +GR processing (after receiving the material at plant) = the material available date ...Forward scheduling
    in reverse scheduleing it will bve otherway round to calculate the date on which I should communicate the vendor so that my schedules are met.
    You can see the details in SPRO > MM >Pur Req

  • Extract of gr processing time in open purchase order

    to display gr processing time in open purchase order .give me query for extract the gr processing time which table and which field we have to take

    Hi
    Check the tables<b> MKPF and MSEG</b> tables for this
    these 2 tables only will store the data related to the GR and GI's
    <b>Reward points for useful Answers</b>
    Regards
    Anji

  • A problem while assign and process purchase requisitions using Me57

    Hello everybody:
           Today I used me57 to assign and process purchase requisition of 0010000732, but there is only one vendor when assign automatically , however two vendors were assigned with me01 when maintained source list,  what's the possible reason of the problem,  Thank you everyone in advance, cheers.

    hi,
    Check in source list ie ME04 whether fixed vendor is ticked.
    Thanks
    suresh

Maybe you are looking for

  • How to create an animation with Image Sequence?

    Im have Quicktime Pro and I want to make an animation. I tried selecting some pictures I have saved "random," but I could only select 1 at a time. So, Im thinking that making an Image Sequence is a separate operation from making it come alive? My que

  • AirPlay Won't Work on my Macs

    Hello, I have been having some problems with AirPlay lately. When I go on any of my Macs and try to AirPlay something from iTunes (running 10.4.1 on OS 10.7.1) it just locks up iTunes with the progress bar and later says it can not connect to the App

  • How do I stop Firefox blocking my bank log in sites, when I click allow the bank resets to default which then Firefox blocks again.

    Every time I try logging into my bank accounts ie Nat West, Lloyds or Barclays I get the Firefox pop up bar saying "Firefox prevented this page from automatically redirecting to another page" and when I click on allow the bank log in page goes back t

  • In Captivate 4 swf output, box borders break up. How can I prevent that?

    I'm working in Captivate 4. If I capture a screen that includes a box with a thin border, the border sometimes breaks up in the published swf. Parts of the border are missing, and lines display where they shouldn't. (See included image.) Anyone know

  • IE for the Mac

    I know all the arguments against using IE for the Mac and I subscribe to all of them. However, we are trying to set up remote access for me from my Mac where I work into the network at my husband's office. I can switch over to the XP side on my Mac a