Pushing Purchase Requisition from ECC to SRM via XI  in PPS

Dear Experts,
Environment SRM 7.0 ECC 6.0 ep4 and PPS 33.0
We are having an issue with pushing the Purchase Requisitions from ECC to SRM 7.0 via XI  using the SOA.                              There is an Application error on the receiving side in SRM (Faulty exchange Data)  when pushing the PR from XI to SRM using the inbound interface Purchasing RequestERPSourcing_In.                                                                                The outbound interface from ECC to Xi PurchasingRequest_ERPSourcing_Out is working fine without any errors.
Please let me know if any one has similiar issues in a PPS public sector implementation and any resolutions?
Thanks in advance for the help,
Scott

HI ,
If you have the xml in srm having status "Transfer to external application" then you can use the Forward Error Handling (FEH) concept in SOA. If you have done the required configuration for FEH and use transaction /n/SAPPO/PPO2 in SRM you will be able to see the actual error why xml is failing. Also rememeber to change the value for field Mode of postprocessing Order to 0 in the screen you get after running tranaction /n/SAPPO/PPO2
To configure FEH refer note: 1270081
Hope this helps.
Regards
Sam
Edited by: Sam Chacko Ninan on Feb 12, 2010 10:06 AM

Similar Messages

  • Unable to transfer Purchase Requisition from ECC to EBP

    Dear Friends.
    We are unable to transfer PR from ECC to EBP. System issue stop message in SLG1 transaction for object BBP_EXTREQ
    Stop Message Type: Document type for determined backend system is missing.
    Warning Message Type: Grant 1111 does not exist.
    As per configuration guide we have performed following setting in EBP client
    1. We have created organization unit “Entry Channel” under company code.
    2. Under Entry Channel we create Local Purchasing Organization.
    3. Under Loc Purchasing Org we created Local Purchasing Group with
        - attribute BUK as backend company code
        - attribute BSA as backend PR type (NB)
        - this group is responsible for Entry channel procurement (setting in Function tab)
    4. Under Loc Purchasing Group we assigned RFC user which is same defined as RFC user in both EBP and ECC client.
        - attribute DP_PROC_TY defined as backend ECC PO type (NB)
    5. Attribute CUR define for entry Channel.
    6. Remote connection established with the same user defined under Organization Unit
    7. Remote user has profile sap_all and sap_new authorization.
    8. Material group, Material Type and Vendors are replicated from backend system.
    9. Sourcing always allowed is set for all product categories in “Define sourcing for Product Category”.
    10. Extended Classic Scenario is active.
    11. Defined Tolerance check and assigned TOG attribute.
    Performed following setting in ECC client.
    12. Defined RFC connection and user same as defined in Organization unit.
    13. Defined profile which reference to EBP logical system
    14. Maintained table V_T160EX with Material group/Pur group/ Profile combination.
    Finally transfer Purchase Requisition from ECC to EBP via report BBP_EXTREQ_TRANSFER. Further the outbound Queue fails with status ANORETRY. Also the log displayed the error ‘Application aborted due to serious problems’
    SLG1 in EBP issues stop message “Document type for determined backend system missing” and warning message “Grant 1111 does not exist”.
    Any idea what could be the reason?
    Please help!!
    Sandeep

    Hi
    It seems there is some problem with the Configuaration settings in SRM as well as R/3 side.
    <u>Anyways, please have a look at the following links, which might help.</u>
    <b>Direct Procurement</b>
    http://help.sap.com/saphelp_srm50/helpdata/en/b7/15d4396898042fe10000000a114084/frameset.htm
    <b>Prerequisites for External Requirements</b>
    http://help.sap.com/saphelp_srm50/helpdata/en/18/db183d30805c59e10000000a114084/frameset.htm
    <b>Attributes for the SRM Scenario</b>
    http://help.sap.com/saphelp_srm50/helpdata/en/84/a7e3389870c05ce10000000a114084/frameset.htm
    <b>Direct Material Scenario: Other Planned External Requirements</b>
    http://help.sap.com/saphelp_srm50/helpdata/en/6a/4b9e3b891da20ee10000000a114084/frameset.htm
    <b>Number range settings</b>
    http://help.sap.com/saphelp_srm50/helpdata/en/5d/fd7d3cb7f58910e10000000a114084/frameset.htm
    http://help.sap.com/saphelp_srm50/helpdata/en/b7/15d4396898042fe10000000a114084/frameset.htm
    <b>Define Transaction types</b>
    http://help.sap.com/saphelp_srm50/helpdata/en/10/fd7d3cb7f58910e10000000a114084/frameset.htm
    <b>Direct Material Scenario with Planning in SAP APO</b>
    http://help.sap.com/saphelp_srm50/helpdata/en/d3/4b9c3b122efc6ee10000000a114084/frameset.htm
    Hope this will help.
    Regards
    - Atul

  • Purchase Requisition transfer from ECC to SRM via XI

    Experts,
    Please let me know if you have any information on  the following issue:
    Environment : SRM 7.0,  ECC ep4,  Extended Classic scenario
    The purchase requisitions have been created in ECC and released. I believe in SRM 7.0  the PR's get automatically transferred to  SRM Sourcing cockpit via XI from ECC.
    One PR was pushed manually from SMQ1(Outbound queue ) in  ECC and this failed due to a login issue in XI.
    The XI was using the interface  PurchaseRequestERPSourcingRequest.
    My question is
    1. When the PR is released in ECC, where to check if the PR is pushed to XI. Do we need to schedule a job? When I checked SMQ1 (outbound queue, the queues are empty)
    2. Do we need to define the partner profile in ECC for XI in We20. If so, then what message types to use for the  IDocs going from ECC to XI.
    2. Do we need to configure the interface PurchaseRequestERPSourcingRequest in XI to map the incoming PR from ECC.
    3. In transaction SXMB_moni in XI  I am not able to pull the  XML messages. What options options do I need to
    set to pull the messages that errored out.
    Thanks,
    Scott.

    Hi All,
    Hope this helps you for XI configuration
       Importing Business Scenarios for Sourcing
    In this section, you transfer the business scenario Strategic Sourcing from the SAP Integration Repository, generate it, and activate it.
    Prerequisites
    You have:
    Defined the business systems for SAP Supplier Relationship Management (SAP SRM) and SAP ERP in the SAP System Landscape Directory. For more information about SAP NetWeaver Process Integration (SAP NetWeaver PI), see the SAP Marketplace
    Imported the SAP NetWeaver PI content for SAP SRM into the SAP Integration Repository.
    Procedure
    Log on to the SAP Netweaver PI system.
    Choose Integration Builder: Configuration.
    In the left pane, select the Objects tab.
    Choose  Service Without Partner  Business System .
    Right-click to display the context menu and choose  Business Systems  Assign Business System . This opens the wizard.
    Choose Continue. The wizard guides you through the required steps.
    Create the business system for both SAP SRM and ERP (you can bypass this step if the business system is already setup).
    Select a business system.
    You can create communication channels either manually or automatically. You can create them automatically here. In this case, the systems are applied from the SAP System Landscape Directory (SLD). Channels must be complete in terms of URLs and authentication information.
    Choose Finish, and then choose Close.
    11. On the main screen, choose  Tools  Transfer Integration Scenario from Integration Repository . This opens a wizard.
    Choose Name using input help SE_Sourcing_Enhancements
    Choose Continue. The scenario name is SE_Sourcing_Enhancements.
    Choose Finish and then choose Close. The Business Scenario Configurator opens automatically.
    Choose Component View.
    The Select Component View window opens.
    Choose Apply.
    Choose Assign Services. The Assign Services to Application Component window opens.
    Press F4 to retrieve the available services.
    Choose Assign.
    Select the related service and choose OK.
    Assign a business service to all roles.
    Choose Configure Connections.
    Select the connections from the Service Assignment tab.
    Press F4 in the Communication Channel field.
    Select a communication channel. This channel must be of type XI.
    Note
    If the systems are applied from the SAP Landscape Directory, the Integration Builder automatically creates the communication channels.
    If the systems are not applied from the SAP Landscape Directory, you create communication channels manually. To do this choose an existing service and then Communication Channel using context menu New. You must assign a communication channel for each connection.
    End of the note.
    Choose OK and then choose Apply.
    Choose Generate to open the Create Configuration Objects window.
    Choose Simulation, then Generate, then mark all in the list Scope of Generation.
    Choose Start to generate a log. Check the log for errors and save it if required.
    In the Close Integration Scenario screen, choose Apply.
    In the left pane, select the Scenarios tab; your scenario has been added.
    In the left pane, select the Change List tab.
    Expand the Standard Change List.
    Right click on the scenario name SE_Sourcing_Enhancements and choose Activate.
    Regards
    Sam

  • Transferring field "Unloading Point" from ECC to SRM

    Hello Everybody,
    I need to pass the field "Unloading Point" from the ECC side to the SRM side. Currently, SAP doesn't transfer this field when we execute the program BBP_EXTREQ_TRANSFER.
    The field Unloading Point has been enabled in the SRM and is displayed properly for any Shopping Cart created there.
    In order to pass the field, I have explored the BADI - BBP_BADI_EXTREQ_OUT, but there is no field in this BADI which can be used for passing the Unloading Point.
    One solution that I have is to create a custom field in the BADI structure and then move the Unloading Point in this custom field. But then again, a question arises, how will SRM know that this is the Unloading Point field.
    Also, will any of the following BADI's do the trick?
    BBP_CREATE_REQ_BACK
    BBP_TARGET_OBJECTS
    BBP_CREATE_BE_RQ_NEW  
    BBP_GROUP_LOC_PO
    Please let me know if there is any solution for this problem.
    Thanks & Regards,
    Nikhil.

    Hi Disha,
    Thank you for your prompt reply.
    As per your recommendation, I looked at the BADI "BBP_DOC_CHANGE_BADI", but it seems that the BADI is triggered when we order or hold the shopping cart and not when we transfer Purchase Requisitions from ECC.
    Also, I had seen the thread previously, but it wasn't helpful to me.
    I will be just creating the PR in the ECC side, and won't be having any SC in the SRM before I execute the program BBP_EXTREQ_TRANSFER. I want the field Unloading Point to be moved for every PR created whenever the program is executed.
    If I have missed your point somewhere, do correct me.
    Thanks!
    Nikhil.

  • Error transferring a purchase requisition from R/3 to SRM

    Hello to all,
    Im trying to transfer a purchase requisition from R/3 to SRM using bbp_extreq_transfer report. The last error i have found debugging the outbound queu is BBP_PD 055 "FI logic system is not found; alert system gestor".
    Does anyone know where i have to include this data, in spro or in ppoma_bbp transaction
    Thanks in advance,

    Hi
    Kindly check once again whether Logical system has been currently declared / configured.
    In SRM
    SPRO - Supplier Relationship Management - SRM Server - Technical Basic Settings - Define Backend Systems
    In R/3 back-end
    Transaction - SALE
    Related link ->
    Backend system
    Kindly let me know any clarifications, Do you want document for how to create Logical system.
    Regards
    - Atul

  • Creation of Purchase Requisition from a BID

    Hi,
    I am trying to create a purchase requisition from a bid instead of a purchase order. Does anyone have any idea on this?
    Thanks
    Sunny

    Hello,
    are you trying to create a local SC or a backend PR ?
    If you are in classic mode (so PR and not SC), you could try to derive the PO flow to create a PR instead.
    But this is not really clean.
    The best way is to add a new button "Create PR" in quote screen (or rename the create PO if you don't use it), linked to your own fcode processing and finally call the META_REQUISITION_CREATE in SRM (instead of META_PO_CREATE).
    The last point would be to create a link BID_INV>BID>PR to be displayed in document flow. You have to check if it is possible, because sometimes the system is designed for limited possible flows and does not take into account the flow you want to add.
    In standard, you can create directly a backend PO only if the bid was created from a SC in the sourcing cockpit. Otherwise use local or extended PO (replicated in R/3).
    If this is the case, FM BBP_PD_SC_TRANS_MULTI_BE_PO will transfer the initial SC items to next document, which is a backend PO. You would need to operate some changes here to create PR.
    Rgds
    Christophe

  • Purchase Requisition from CRM Service Order

    Hello Everybody,
    I am trying to create Purchase requisition from Service Order for Service(Material type DIEN) as well as Material (Material type HAWA). I have maintained all the necessary configuration in CRM as well as ECC, like in CRM,  Logistic integration we maintained settings for Purchase requisition and in ECC we have maintained Document type and schema for the purchase requisition.
    For information purpose, I have created Service Material in ECC as DIEN and item category group as LIES.
    As soon as we save the Service Order in CRM with that item category, it should create Purchase requisition in ECC and the document flow in CRM should get activated.
    Currently we are not able to create Purchase requisition in ECC.
    Kindly let me know if there’s any configuration settings missing in CRM as well as ECC or if note to be applied.
    Best regards,
    Anup Bansal

    Hi Anup,
    I am facing purchase requisition creation problem for service products from crm.
    I have seen your query which was posted on same issue, so i thought i could get some help.
    The problem here is when i am saving the service order i am getting the below message.
    Enter a (default) purchasing group for material group SUB_MC (Notification E CRM_SRV_LOG_EXT_OLTP 002).
    I have actually downloaded mat_dien materials from ecc to crm and for material purchase group is already assigned for one plant, but still not able to recognise.
    Please help me out.
    Thanks in advance.

  • Mandatory fields to replicate vendor from ECC to SRM

    Hi all,
    I created a vendor in ECC with all mandatory fields. But when I tried to replicate the vendors to SRM from ECC, I am getting errors like mandatory fields are missing. Can you please tell me what are the mandatory fields in SRM when we replicate vendors from ECC to SRM. Its Urgent.
    Regards,
    Balaji.S

    Hi Balaji,
    When you create Vendors properly in ECC it should not give such an error. You have to maintain basic data, Accounting data and purchasing data. Rest all are optional.
    For replicating vendors from R/3 to SRM you should have a Vendor root org / group in SRM. BBPGETVD is used to replicate vendors to SRM by mentioning the logical system and Vendor Group ID.
    Hope this makes you clear. Please explain the error clearly for further help.
    Award points for helpful answers.
    Rgds,
    Teja

  • Purchase Requisitions from APO to R3

    Hi,
    when iam transferring purchase requisitions from APO to R3, other snp orders are also automatically tranferring to R3 . How to prevent this?
    Thanks,
    Dhanush

    Go to the following menu path
    SPRO> APO>Supply chain planning> SNP> Cnfigure transfer to OLTP systems
    Based on your requirement: only transfer SNP generated Purch Reqs and dono transfer SNP generated planned orders to ECC, you have 2 options
    Option 1--Immediately transfer SNP generated Purch Reqs and never transfer any SNP planned orders
    Config required: (1)SNP( Select Radio Button- Immediate Transfer)  (2) Check the " NO SNP PLANNED ORDERS" (3) Check whether the Dist Definition for the plant is maintained for External Procurement
    (4) Check the CIF queues and clear or reset the status
    Preferred Option2 for future projects in mind--- As this is a global setting, it is better to have periodic transfer set and then use C5 transaction to send the Purch Reqs to R3 using the Filter as Order Type.
    This way you are not putting a hard stop for sending the planned orders to ECC as in OPTION 1.
    Config Required: (1) SNP( select Radio Button- Periodic Transfer) (2) Run C5 transaction and give in your plant/product selection and APO order type=21(ext Procurement)
    Thanks
    Kumar

  • How to transfer data from ECC to CRM via IDocs (Clfmas01),

    Hi all,
    how to transfer data from ECC to CRM via IDocs (Clfmas01), that to material master data from ECC to Production master data in CRM.    
    Need Information regarding, how to upload file to CRM from ECC, through, IDocs......Plz help me...
    Edited by: khaja fareed on Jan 11, 2010 12:44 PM

    First of all push ECC data in to GTS server through T.code:/N/SAPSLL/MENU_LEGALR3. First click on Master data tab there enter customer/vendor number then execute.
    2-Go to document tab there enter Sales order no/PO number then execute it.
    Then go to GTS server in compliance management module you can get all the information.
    Regards
    Sitanshu Panigrahi

  • Creating Purchase Requisitions in ECC for CRM Service Items

    Hi,
    We are implementing ECC6.0 and CRM5.0 for a client.
    In this implementation we require to create a scenario for Procurement of services.
    I have maintained the basic settings in CRM and ECC.
    But i am still unable to generate a Purchase Requisition for the service order created in CRM for service material of type DIEN.
    Looking forward to help.
    Thanks and Regards,
    Rekha Dadwal

    Hi Rekha,
    We are still struggling to create a purchase requisition in ecc from service order.
    I know you should have faced gthe same problem and I understand you might have solved it as well. Please guide us if possible on the same.
    rightnow we are facing the error in which the system is tryig to create a purchase requisition but it is picking a default purchasing organisation 0001 from somewhere... and trying to check its assignement with the material plant.
    is there somwhere we assign a default purchasing org in crm ecc integration... or where is it picking up this default purchasing organisation...
    i will award you with points
    Surendra More

  • How to get G/L account and cost centres from ECC to SRM...

    Dear All,
    How to get G/L account and cost centres from ECC to SRM...
    Please let me know the steps...
    Thanks
    Ravi

    Hi
    GL account - You can define in SPRO- Cross application settings--Account assignment ->Define GL account for product category and account assignment category.
    or you can use BADI BBP_DETERMINE_ACCT.
    In Organisation Strucute - You can Map the backend cost center via KNT  cost center attribute .
    Regards
    Muthu

  • Creation of purchase requisition from Webdynpro Java

    Hi all,
        I have a requirement that i should create purchase requisition from webdynpro java. i imported all required BAPI in the webdynpro. But i am not getting what should i have to give as input paramater. I have imported the Bapi_Requition_Create. Please help me on thin what sould be the input parameter i should pass.
    Regards,
    Shreeharsha

    Shreeharsha,
    you can check out the fm inse37 and see what are the importing and tables parameters
    Thanks
    Bala Duvvuri

  • Transfer Data from ECC to SRM

    Hi ,
    I'm trying to transfer data from ECC to SRM for creating bid document ( Function : BBP_PD_BID_CREATE ). After transferring the data I want to get the data back to ECC ( I need bid document number to write on delivery document's field ). What's the best way to do this ?
    Regards.

    Hi vinit ,
    I've written code to call 'BBP_PD_BID_CREATE' in ECC. But ECC and SRM have different structures. So i am not sure how i can define data to send SRM.
    Here is my code in ECC program
    CALL FUNCTION 'BBP_PD_BID_CREATE' IN BACKGROUND TASK
       DESTINATION 'XXX'
       IMPORTING
         I_REF_GUID    =
         I_BAPIMODE    =
         I_PARK        =
         I_SAVE        =
         I_TESTRUN     =
         I_HEADER      = I_HEADER ?
         IT_ATTACH     =
         IT_DYN_ATTR   =
         IT_CONDITIONS =
        EXPORTING
          E_HEADER      = E_HEADER ?
          ET_ATTACH     =
          ET_DYN_ATTR   =
          ET_CONDITIONS =
        TABLES
           I_ITEM        =
           I_PARTNER     =
           I_LONGTEXT    =
           I_SDLN        =
           I_ORGDATA     =
           I_HCF         =
           I_ICF         =
           I_TOL         =
           I_WEIGHT      =
           IT_EXCHRATE   =
           E_ITEM        =
           E_PARTNER     =
           E_LONGTEXT    =
           E_SDLN        =
           E_ORGDATA     =
           E_HCF         =
           E_ICF         =

  • Transfer of PR from ECC to SRM

    Hi experts,
    I am new to SRM & my questions can be bit easy. We have implemented PDP & while transferring the PR from ECC to SRM, the PR got stuck in sxmb_moni in SRM. Now when i  see the error /sappo/ppo2 it shows "cannot save template: Insert Items".
    I have checked the Org. Structure and i think the attributes defined to the RFC_USER is also correct because i can create the shopping cart without an error from this user.
    So please help me.
    Thanks & Regards
    Himanshu singh phartyal

    Hi,
    Would you please apply note 1821480 and retest the issue with a new PR?
    Regards,
    Ivy