Hi Samson,
                  Even i haven't done much r n d  bout this but what i came to know is that, there might be a scenario where you may want to make a payment to your customer. In this case we can use the Outgoing payment for the same. The system doesnt stop you from doin so. I have seen this in SAP B1 2005B, PL34.
Regards,
Joseph

Similar Messages

  • How to create the relationship between ESSBASE 11 and DM in OBIEE11

    Hi Experts,
    I have one requirement that there is one property table named 'Store Master' in DW,and it contains a lot of attribute, such as Open Date, Close Date, IS 24 Hour etc.
    But another data source is essbase and based on this source, I create all reports.
    In ESSBASE, it has one dimension and hierarchy Location, and it has four level, Country(L1),Region (L2),Province(L3),Store(L4)
    So I want to know how to create the relationship between Location (ESSBASE) and Store Master (DM).
    I try to create one relationship in physical layer between Gen4,Location and Store, then drag the open date and close date into Location Dimension in BMM,then Presentation Layer.
    When I drag column 'Open Date' ,'Gen4,Location ' and 'Sales' into reports, it will generate the following error message:
    State: HY000. Code: 10058. [NQODBC] [SQL_STATE: HY000] [nQSError: 10058] A general error has occurred. [nQSError: 43113] Message returned from OBIS. [nQSError: 43119] Query Failed: [nQSError: 14020] None of the fact tables are compatible with the query request Dim Region.Store Open Date. (HY000)
    However, when I remove the column 'Open Date'. it will be ok.
    So what I missing the steps? Please help me. Thanks.

    >
    '2. Now, pull the 'Store' column from relational DB onto the Gen5, Location column from Essbase. This action now creates, two logical sources for your 'Store' column.'
    If the length from different data source is not same,such as 1001(DM),L_1001(ESSBASE), can I drag the 'Store' column from relational DB onto the Gen5, Location column from Essbase?
    I think it does not work.Right?Hi,
    I am not sure if you are talking about the length(as in varchar(128)) of the member value being different in different sources, or the member itself is different in both the sources.
    I am still assuming, that you are referring to the members not same in both the sources.If it is, the whole concept of federation is based on conforming dimensions. So, it needs that the same dimension information is present in both the sources and then only, you know we can analyze the numbers based on this dimension. So, either the dimension being different in both sources, or the members not present in both the dimensions might lead to incorrect numbers.
    So I select Store Attributes in relation DB and Location in ESSBASE in physical layer, then create the physical join, such as right("Hour Sales"."H_Sales".""."H_Sales"."Gen6,Location",4) = "Authorization".""."EDW"."T_EDW_MDM_STORE"."US_CODE", then drag the OPEN_DATE and CLOSE_DATE in relation DB to Location in ESSBASE in BMM,finially drag them into presentation layer.We create physical layer relationships, to send over the same relation to the underlying database during querying. So, creating a physical relationship between essbase cube and relation database would not help here.
    When you set up this federation, BI Server sends individual queries to each source and maps the conforming dimension members internally.
    Hope I was clear, and this helps.
    Thank you,
    Dhar

  • How to create the relationship between ESSBASE 11 and DM  in OBIEE 11G?

    Hi Experts,
    I have one requirement that there is one property table named 'Store Master' in DW,and it contains a lot of attribute, such as Open Date, Close Date, IS 24 Hour etc.
    But another data source is essbase and based on this source, I create all reports.
    In ESSBASE, it has one dimension and hierarchy Location, and it has four level, Country(L1),Region (L2),Province(L3),Store(L4)
    So I want to know how to create the relationship between Location (ESSBASE) and Store Master (DM).
    I try to create one relationship in physical layer between Gen4,Location and Store, then drag the open date and close date into Location Dimension in BMM,then Presentation Layer.
    When I drag column 'Open Date' ,'Gen4,Location ' and 'Sales' into reports, it will generate the following error message:
    State: HY000. Code: 10058. [NQODBC] [SQL_STATE: HY000] [nQSError: 10058] A general error has occurred. [nQSError: 43113] Message returned from OBIS. [nQSError: 43119] Query Failed: [nQSError: 14020] None of the fact tables are compatible with the query request Dim Region.Store Open Date. (HY000)
    However, when I remove the column 'Open Date'. it will be ok
    So what I missing the steps? Please help me. Thanks.

    >
    '2. Now, pull the 'Store' column from relational DB onto the Gen5, Location column from Essbase. This action now creates, two logical sources for your 'Store' column.'
    If the length from different data source is not same,such as 1001(DM),L_1001(ESSBASE), can I drag the 'Store' column from relational DB onto the Gen5, Location column from Essbase?
    I think it does not work.Right?Hi,
    I am not sure if you are talking about the length(as in varchar(128)) of the member value being different in different sources, or the member itself is different in both the sources.
    I am still assuming, that you are referring to the members not same in both the sources.If it is, the whole concept of federation is based on conforming dimensions. So, it needs that the same dimension information is present in both the sources and then only, you know we can analyze the numbers based on this dimension. So, either the dimension being different in both sources, or the members not present in both the dimensions might lead to incorrect numbers.
    So I select Store Attributes in relation DB and Location in ESSBASE in physical layer, then create the physical join, such as right("Hour Sales"."H_Sales".""."H_Sales"."Gen6,Location",4) = "Authorization".""."EDW"."T_EDW_MDM_STORE"."US_CODE", then drag the OPEN_DATE and CLOSE_DATE in relation DB to Location in ESSBASE in BMM,finially drag them into presentation layer.We create physical layer relationships, to send over the same relation to the underlying database during querying. So, creating a physical relationship between essbase cube and relation database would not help here.
    When you set up this federation, BI Server sends individual queries to each source and maps the conforming dimension members internally.
    Hope I was clear, and this helps.
    Thank you,
    Dhar

  • In which table we can find the relationship between Role id and Task id

    Hi Experts,
    In which table we can find the relationship between Role id and Task id in Cprojects.
    Thanks
    Subhaskar

    Hi Subhaskar,
    Apart from DPR_ENTITY_LINK , you can also get it from table DPR_PART.
    Please go through the below link
    http://wiki.sdn.sap.com/wiki/display/PLM/cProjectstablesin+SAP
    I hope this will help you.
    Regards,
    Rahul

  • The relationship between production order and purchase requistion After running MPS

    Dear Experts:
         I met a issue . My users want to know the relationship between production order and purchase requistion . In my company we create production order and  purchase req. by  running MRP. our operations are:
    1. T-CODE: MD41  create planned order .
    2. T-CODE: CO41 convert planned order to production order .
    3. T-CODE: MD15 convert planned order to purchase Requisition.
      but I can't  find the  relation of them. would you like to give me some advices? thank you very much.

    Hello
    On the standard MTS process there is no link between the requirement (STO) and the replenishment element (production order).
    See the below extraction from note 12955:
    There is no index that the system could use to determine which issue element (sales order, planning, reservation, dependent requirement, ...) is covered by a certain receipt element (purchase order, production order, purchase requisition, planned order, stock level ...).
    A production order, for example, can be created to cover several different requirements, even when you are using lot sizing procedure EX.
    You can use transaction MD09 or MD04to determine the pegged requirements, but they are calculated dynamically and there is not fixed link between requirement and receipt.
    BR
    Caetano

  • What is the relationship between CGI-Executables and cgi-bin?

    I am trying to get CGIs working locally on my Mac and am having difficulty understanding the relationship between CGI-Executables/ and cgi-bin/.
    I have activated CGI in my httpd.conf file, and have the following perl test script: /Library/WebServer/CGI-Executables/test.cgi file, and have the file permissions set appropriatly
    If I call the script from the actual url: http://127.0.0.1/CGI-Executables/test.cgi, it doesn't work. If I use: http://127.0.0.1/cgi-bin/test.cgi, it works fine.
    Why cgi-bin and not CGI-Executables? What is the relationship between /Library/WebServer/CGI-Executables/ and cgi-bin?
    And how do I get CGIs working in individual users' Sites/ file? Do all CGIs go in the /Library/WebServer/CGI-Executables/ directory, or can each users' Site/ directory have it's own cgi-bin?
    Ti Powerbook G4   Mac OS X (10.4.4)  

    Now I am having trouble getting CGI to work in the user directories. I have a perl script that works for 127.0.0.1/cgi-bin/test.cgi, but not for 127.0.0.1/~joe/cgi-bin/test.cgi.
    My apache error log says:
    [Tue Feb 14 08:14:23 2006] [error] [client 127.0.0.1] Options ExecCGI is off in this directory: /Users/joe/Sites/cgi-bin/first.cgi
    Permissions for Library/WebServer/CGI-Exectuables/test.cgi and /Users/joe/Sites/cgi-bin/ are 777.
    I think the problem is somewhere in my directory configs. Apache has so many, it's hard to know what's what.
    Here's the first directory directives in httpd.conf:
    # First, we configure the "default" to be a very restrictive set of
    # permissions.
    <Directory />
    Options FollowSymLinks
    AllowOverride Options
    </Directory>
    Farther down, there's this, which I added ExecCGI and index.cgi:
    # Control access to UserDir directories. The following is an example
    # for a site where these directories are restricted to read-only.
    <Directory /Users/*/Sites>
    AllowOverride FileInfo AuthConfig Limit
    Options MultiViews Indexes SymLinksIfOwnerMatch Includes ExecCGI
    DirectoryIndex index.html index.cgi
    <Limit GET POST OPTIONS PROPFIND>
    Order allow,deny
    Allow from all
    </Limit>
    <LimitExcept GET POST OPTIONS PROPFIND>
    Order deny,allow
    Deny from all
    </LimitExcept>
    </Directory>
    Then down at the bottom of the file is something I suspect was added automatically when the user account was created:
    Include /private/etc/httpd/users/*.conf
    <Directory "/Users/joe/Sites/">
    Options Indexes MultiViews Includes
    AllowOverride None
    Order allow,deny
    Allow from all
    </Directory>
    To further confuse things, there is another file /etc/httpd/user/joe.conf that has additional user-directory directives:
    <Directory "/Users/joe/Sites/">
    Options Indexes MultiViews
    AllowOverride None
    Order allow,deny
    Allow from all
    </Directory>
    Is there something in all these directory configurations that is preventing the user from accessing cgi-bin? Can I add directives to an .htaccess file in the user directory.
    Ti Powerbook G4   Mac OS X (10.4.4)  

  • What is the Relationship between Update Rule and Infopackage/Transfer Rules

    Hello Experts,
    can you help explain these scenarios to me:
    What is the relationship between update rules and infopackges?
    What is the relationship between transfer rules and infopackges?
    What is the relationship between update rules and transfer rules?

    Hello,
    Info-packages trigger the data load into BW system from the source system. An info-package is created for a specific data source and info source combination.
    1) When you trigger the info-package it sends an request to the source system to start the extraction process and this corresponds to the step "Data Request Received" in monitor under details tab. It is the first step.
    2) Then the selections specified in the info-package are transferred to the source system to select the requested data from BW system. Then it is sent back to BW system.
    3) Once it reach BW, it gets into the PSA and then it gets updated into the data target (depends on what settings are made in IP). No rules (Transfer rules / update rules) comes into picture when data is stored in PSA. Only the transfer structure is used to map the BW info-objects with the source system fields.
    4) After data is stored into PSA, the update into the data targets begins. First the transfer rules are applied -> data then flows through the communication structure -> update rules are applied and finally the records gets updated into the data target. 
    The extraction flow is: -
    Source System (DS) -> PSA -> Transfer Rules -> Communication Structure -> Update Rules -> Data target.
    Info-package actually triggers the whole data flow in BW system.
    Hope it gives you a clear picture.
    Thx,
    Soumya

  • AP- Why exchange rate type between Post invoice and Post payment is differe

    AP- Why exchange rate type between Post invoice and Post payment is different ?
    Hello,
    I have question
    when post AP invoice , document type KR
    document date = 11.12.2009
    posting date = 31.12.2009
    entry date = 05.01.2010
    this document using exchange rate type B (standard translation at bank selling rate) on 31.12.2009 (use posting date )
    but when post payment for above document,document type ZP
    document date = 25.06.2010
    posting date = 25.06.2010
    entry date = 24.06.2010
    this document using exchange rate type M (standard translation at average rate) on 23.06.2010
    please answer
    why do post invoice and post payment use different exchange rate type?
    and why at payment donot use posting date for get exchange rate ?

    Nanas,
    Sorry if im not  being clear...
    My point is: the difference rates customization for payments is done at FBZP.
    At Paying Company Codes, you have 4 flags for exchange rates differentes.
    At Control Data look:
    *Do not Post any Exchange Rate Differences:
    If the indicator is not set, the difference between the exchange rate at the time of posting and the exchange rate at the time of payment is determined for items which are posted in foreign currency. The payment program uses the translation rate in the currency table in the system for this purpose.
    *No Exchange Rate Differences for Partial Payments:
    Has the effect that the payment program for partial payments (requests for payment using transaction F-59) does not post exchange rate differences.
    *Processing of Bill of Exchange Payments:
    *Separate Payment for each Payment Reference
    Regards
    Bruno

  • Display the Repetative area in Incoming and Outgoing payments

    Hi Experts,
    Can any one help me how to Display the Repetative area Header,Repetative area and Repetative area Footer in the
    Incoming and Outgoing payments....
    Urgent .... Pls...
    Karthi

    Hi Sumpath,
    Then how can i get printout for posted Incoming payments with Row Level data.
    Per day 10 Numbers of Payments are made, For that i need to take printout daily with row details...
    By default SAP Print out also not executing row level datas, i dont why or any other procedure to enable row level datas..
    karthi

  • Where is the link between Sales Invoice and Downpayment Invoices

    We made a downpayment invoice. And processed incoming payment for such invoice.
    Then proceed to Sales Invoice, which was applied to the Downpayment invoice. Everyting went well.
    We tried to use crystal report to extract the Sales Invoice (OINV, INV1) and link to the downpayment table (ODPI) to print the breakdown in the invoice form. We could not find the relationship in this table.
    Can someone help ?
    KC

    Could it be helpful for you to use view in enterprise manager ? I just see the docentry field as the link field among OINV, INV1 and OPDI.
    If you use down payment request, I think you could not since it is a note and must be reconciled after invoice created
    Rgds,

  • What is the relationship between OPOR, OPDN and OIGE Table ?

    Dear Experts,
    We want to develop one report as per project wise Item Consumtion.
    We want data from Purchase Order, Goods Receipt PO and Issue for Production.
    The purpose of this report is to find out that what item should create PO
    and based on that PO what the GRN should be taken
    and based on that GRN this particular item should used for that project
    which mentioned in GRN at the time of Item selection.
    We develop an Query for that but this query are not as per standard process to get data.
    select
    OPOR.CardCode as VendorCode, OPOR.CardName as VendorName,
    POR1.ItemCode as POItemCode, POR1.Dscription as POItemDesc,
    OPOR.DocNum as PONo, OPOR.DocDate as PODate, OPOR.DocDueDate as PODueDate,
    POR1.Project, POR1.OpenQty as PendingQty, POR1.Quantity as POQty,
    PDN1.Quantity as GRNQty, IGE1.Quantity as IssueQty,
    ((POR1.PriceBefDi-(POR1.PriceBefDi*POR1.DiscPrcnt/100))*POR1.Quantity) as 'POPrice'
    from OPOR
    inner join POR1 on
    POR1.DocEntry=OPOR.DocEntry
    LEFT JOIN PDN1 ON
    POR1.DocEntry= PDN1.BaseEntry AND
    POR1.LineNum=PDN1.BaseLine
    Inner JOIN OPDN ON
    PDN1.DocEntry = OPDN.DocEntry
    Left join IGE1 on
    IGE1.ItemCode=PDN1.ItemCode and
    IGE1.Project=PDN1.Project
    WHERE 
    POR1.Project='{?Project}'
    Can anybody tell me that how i can create standard query as per SAP Standards.
    Thanks & Regards,
    Nishit Makadia

    Hi,
    Try this query for production order issued serial number.
    SELECT T0.[DocNum] as Prod#, T0.[CardCode] as CustCode,T0.[OriginNum] as SO#,T0.[Project] as JobNo, T0.[ItemCode], T1.[ItemCode], T1.[IssuedQty], T3.[IntrSerial],T0.[Comments] as Remark
    FROM OWOR T0  INNER JOIN WOR1 T1 ON T0.DocEntry = T1.DocEntry left join  SRI1 T2 on  T2.[BsDocEntry] = t0.docentry and T1.[LineNum] = T2.[BsDocLine] inner join  OSRI T3 ON T2.SysSerial = T3.SysSerial and t3.itemcode = t2.itemcode
    WHERE T2.[BsDocType]  = '202' and  T0.[Project]  = [%0] and  T2.[BaseType] = '60' and T0.[Status] IN ('r','l')
    GROUP BY T0.[DocNum], T0.[ItemCode], T1.[ItemCode], T1.[IssuedQty], T3.[IntrSerial],T0.[Project],T0.[CardCode],T0.[OriginNum],T0.[Comments] order by T0.[DocNum]
    Thanks & Regards,
    Nagarajan

  • Question about the relationship between a project and Mobile Me album

    Hello esteemed members of the Aperture community
    I have a puzzling issue. I have published a project on MobileMe. My project is arranged somewhat chronologically, and I want MobileMe to follow this. However, the MobileMe album in Aperture does not synchronize with the project, and subsequently, the gallery on MobileMe does neither. How do I tell the MobileMe album in Aperture to synchronize itself with my project, and update changes as I edit the project, or am I just totally confused...always a possibility?
    Thanks in advance

    You sort of answered your own question in the title: Your Mobile Me gallery is an album. By design, changing the sort order of a project does not affect the sort order of related albums and vice versa. You'll have to make those changes in the album to have them reflected in the gallery.
    I know of no way to have an album synchronize with a project. (Note: if you make adjustments to images or delete images from a project, those changes will be reflected in the album, but the sort order will not.)
    DLS

  • What is the relationship between Change management and Issue tracking?

    What is in general change management and what is issue tracking in a SAP point of view?

    Hi
    See this thread
    Re: SAP APO
    Additional inputs :
    APO refers Advanced planned and optimizer
    APO is similar to BW in the sense it is also a OLAP processor intended for reporting needs
    Supply chain management
    http://help.sap.com/saphelp_nw2004s/helpdata/en/25/79eb3cad744026e10000000a11405a/frameset.htm

  • Please explain the relationship between sequence setting and output

    I am looking for an explanation of the sequence setting and the output settings (Mac Quad core, 10.7.4 - CS6 Production Premium, PR)  I am primarily working in AVC-I 100 and XDCam. I've found that I can drop in AVC-I into a Seq and it will set the Seq to that codec. Many times I'll need to send the in-progress and final edits to my clients as an WMV (HD) video file. In FCP, I would export the self contained seq and use Episode to transcode to wmv. I'm having trouble understanding the best way to do this in PR (CS6).  I've found that if I leave the Seq setting to the AVC-I, the render and the file output is a 50% quality mpeg-I. Is it best to set up a custom sequence w/ ProRes as the render codec? I'm having a hard time finding or getting an explanation of best practices for this type of operation. Any guidance would be appreciated.
    Thanks,
    jim

    Remember I said you could force Pr to use your rendered preview files instead of the source media for export?  Selecting Match Sequence Settings in the Export Media dialog is how you force it.  Don't do that.  And don't shoot the messenger -- I've lobbied against that label for that control for 2 versions now.
    Some Export formats, like H.264 Blu-ray and MPEG2-DVD, have an available Preset called "Match Source Attributes".  If you choose that Preset, you get something like this:
    For details on setting up a sequence, see the Help files:
    http://help.adobe.com/en_US/premierepro/cs/using/WS3E67AF4C-B2A2-4f04-90B4-F8CCFB74B144.ht ml#WSd79b3ca3b623cac941d41a681247d1f35a4-7fff
    Jeff

  • Table having the link between  Clearing document and the Invoice document

    pls can someone tell me the table that having the relationship between clearing document and the Invoice document.
    Thanx .

    Hi,
    You can try with the following tables: BSE_CLR, BSEG, BSAD, BSAK.
    Regards,
    Svetlin