Re: Shipment Cost configration and settings

Hi
Can any one send me <b>configuration and setting of shipment cost and settlement</b> of shipment cost.
E mail id: [email protected]
Points will be rewarded.
regards
Prasanna R

Hi Raju,
Please find below the complete doc on Shipment Cost:
Shipment cost in shipping contains create the shipment cost doc., process the shipment, monitor the shipment, calculate the shipment and settle the shipment.
Shipment cost doc. contains calculate the shipment, assign to accounting, transfer to FI and settle the shipment cost.
Shipment cost doc. divided into header, item and sub item data.
We need to assign transportation planning point to com. code to calculate and settle the shipment cost.
1. Define date rules:- In this IMG activity you define the date rules that determine which dates are chosen for determining the pricing date and the settlement date and the sequence in which they are accessed. The dates can be, for example, the end of transportation planning or the start of lading.
2. Define and assign tariff zones:-In this IMG activity, you define the tariff zones and assign postal code areas to the tariff zones for each organizational key. The tariff zones are represent geographical influencing factors during the calculation of shipment costs.
3. Define no. ranges for shipment cost:-In this IMG activity you define the number interval for the shipment cost documents. When creating a shipment cost document, a unique number is generated. The number comes from the number range that you create in this menu point as the internal number range.
You can also create an external number range. The option to specify a number from the external number range when creating the shipment cost document is, however, not currently supported.
4. Shipcost types and item cat.:-In this IMG activity, you define the shipment cost types and item categories that contain all important control features for the shipment cost document, such as:
Number range
Status requirements for the shipment documents
Parameters for shipment costing
Parameters for shipment settlement
5.shipcost relevance and default for shipcost types:-In this IMG activity you assign the shipment cost types to the shipment types and set an indicator to show whether the cost type is relevant to shipment costing. You do this for every cost type in every shipment type. .
Example
For the 'individual shipment' shipment type, you set the indicator for the cost types shipment header and leg, but not for the cost types border crossing or load transfer point. You also assign a shipment cost type to the shipment type. When you create a shipment cost document, this shipment cost type is determined automatically.
6. Settlement:-
Certain control elements must be maintained for calculating shipment costs with the transportation service agent and for forwarding of shipment costs to FI and CO.
you can maintain these control elements and carry out the corresponding assignments.
-- Assign purchasing data
--maintain acc. assignment cat.
--automatic G/L acc. determination
--automatic determination of CO assignments
--invoices and credit memos
A2. Shipment cost:
The process of calculating the shipment costs for a shipment.
Shipment costs:
The total costs involved in the shipment of a product. Not just pure freight costs, but also cleaning costs, insurance, and other costs as well
check this link
http://help.sap.com/saphelp_46c/helpdata/en/4f/fceb47b535d1118b3f0060b03ca329/frameset.htm
and
http://help.sap.com/saphelp_470/helpdata/en/d5/2285347860ea35e10000009b38f83b/frameset.htm
A3. Please follow below steps.
1) Create the transportation planning point for the company codes.
2) Maintain transp. relevance for the dly doc. type, item cat and routes
3) Define the shipment types
4) Define the shipment cost types
5) Define shipment cost item categories and assign
6) Define shipment cost relevance
7) Maintain pricing
8) Assign purchasing data
9) OBYC
10) OKB9
AND Please check the below:
Step1: T.Code: VL01N: Just Create Delivery Note here. Do not do the Picking and Packing.
(This is Client Specific)
Step 2: T.Code: VT01N: Create Shipment.
Here mention your Transportation Point and Shipment Type you Configured for this and Click on deliveries ICON.
GO to W.ref to
Outbound Delivery : Give your Delivery Number that you created earlier for this shipment and F8( Excute)
Then Select the Delivery and Click on Overview
Here Click on Planning then automatically Route( If route determination is done) and Vendor Number get generated and Save the Data.
Step.3: T.Code: VL02N: Change Delivery. Here give the Delivery no and
Do picking, Packing (If necessary) and PGI.
Please Reward If Really Helpful,
Thanks and Regards,
Sateesh.Kandula

Similar Messages

  • Shipment cost condition and purchasing conditions

    Hi Experts,
    I read OSS Note 427944 and I have configured few PO item conditions (relevant to ship. costing) . Each of them has different account keys assigned.
    I have created the same account keys in shipment cost pricing.
    I have created shipment cost document with one condition and when I post GR the system post it on the first condition in the purchasing schema and not on the condition with the same account key as supposed to be.
    In addition, when I have entered 2 conditions in shipment cost doc.
    and posted Goods Receipt the system sum and post the total amount on the first condition in the purchasing schema .
    How can I make a relationship between the "PO item conditions" and the "shipment conditions"?
    Thanks,
    Michal

    michallll wrote:
    Hi,
    >
    > First thanks for the reply.
    >
    > I did all that but still when I post GR the system does not linked the conditions correctly .
    > When I use one condition I expect the system to post the delivery costs to the exact condition in purchasing.
    > If I use condition zm00 in shipment cost than it is supposed to post the delivery costs on zm00 in purchasing pricing.
    > Instead , The delivery costs are posted on the first condition according to purchasing schema regardless of the account key of the condition.
    > When  I use 2 conditions in the same shipment item category, for example, conditions zm00 and zm02, The system sum them and post it on the first condition according to purchasing schema.
    >
    > Michal
    Hi,
    In your Po condition type in control2 tab please check on "Copy shp cost" and condition should be percentabe based and same condition should be in the shipement cost pricing procedure.
    hope this will solve your query

  • Shipment cost-G/L Acc and cost center automatically

    Hi gurus,
    I want to get G/L account and Cost center automatically during shipment cost creation I mentioned account assignment category as "U" in the purchase order.currently it is manually entered at the time of shipment cost creation.
    How can i determine the G/Laccount and cost center automatically at the time of shipment cost creation?
    Is it possible or not.
    Thanks in advance

    Dear Sameer,
    Reqd. settings are reqd. o maintain under
    *1*. T. Code: OBYC
    maintain the G/L accounts against the vaild combination, i.e.
    Chart of accounts
    Transaction
    General modifier
    Val Class
    GL Account
    Note: T. Code: OMWD - Assign Val. Grp. Code to Avl Area, if not.
    *2*. T. Code: OKB9 - GL Account / Cost Element & Cost Center Linking
    Maintain entries for default account assignment i.e. maintain entry for combination:
    Company Code -- Cost Element (G/L), and assign Cost Center in "Detail per Profit Cener" from Dialog structure.
    Once done, check setting in
    T. Code: T_56
    (SPRO --> IMG --> Logisitcs-Execution --> Transporation --> Shipment Costs --> Shipment Cost Document --> Shipment Cost Type and Item Category)
    From left-hand side Dialog structure, Click: Assign shipment cost types and item category
    Check, Column: Automatic Propsal, is maintained as "Automatc" or "Manual" for valid Item Category.
    Best Regards,
    Amit

  • Automatic creation of PO from shipment cost document

    Dear Experts
    PLease let me know the settings with description to understand for the creation of PO from shipment cost document. It seems inegration with FI is also needed. Request your explanation with the settings in SPRO
    Thanks
    Ganesh

    For automatic Generation of Purchase Order
    SPRO > Logistics Execution > Transport > Shipment Costs > Shipment Cost Document > Shipment Cost Types and Item Categories > Define item Categories (T_56)
       In the Generate PO, Enter one of A, B, C.
           Do not generate purchase order
    A    Generate purchase order for validity period of 1 day
    B    Generate purchase order for validity period of 1 week
    C    Generate purchase order for validity period of 1 month
    For assigning posting in G/L Accounts
    SPRO > Logistics Execution > Transport > Shipment Costs > Shipment Cost Document > Shipment Cost Types and Item Categories > Assign shipment cost types and item categories
    Based on the item category created before, assign the valuation class.
    Assign the Valuation class to the Shipment header or leg (whichever is planned for ) and the item category you created before.
    Assigning the Shipment cost type to the shipment type
    SPRO > Logistics Execution > Transport > Shipment Costs > Shipment Cost Document > Shipment Cost Relevance and Default for Shipment Cost Type (T_57)
    Assign the Shipment cost type to the Shipment type and mark it as relevant for shipment cost.
    Checking the assignment of G/L Accounts to the Valuation Class
    SPRO > Logistics Execution > Transport > Shipment Costs > Settlement > Automatic G/L Account Determination
    Select the Account Assignment - GBB - Enter the Chart of Accounts - Check if VBR was assigned the G/L accounts for the Valuation class you specified before.

  • Delivery costs with shipment costs

    Dear Sir,
    I want to capture the delivery costs from shipment cost document.
    I did all bellow mentioned settings:
    For freight cost to be transfered as delivery cost, the Purchase order need to have a freight condition with zero value. Also the freight condition need to have indicator set in config for 'copy shipment cost'. Once this is set up and shipment cost document created, do PGI and it should create a DCGR document in PO History.
    Even after all these settings, i tried but no result. It is not creating ths DCGR in PO History.
    Can any body tell me this bellow setting: Where is this exactly. I tried no field with the name Relevant for costing
    Shipment cost item categories Under the Shipment cost types and item categories activity, set the Relevant for costing field to A = Relevant for calculating delivery costs (Delivery costs). This results in the shipment costs not being transferred directly into accounting. The accounting is done via the purchasing functionality for delivery costs.
    Can any body give me the solution?
    With regards
    Lakshmikanth

    Hi
    I think that you have had your question answered so if you are happy with this can you please award points if you want to but mainly can you please mark your question as answered so that it is easier to navigate around the open questions in the forum as the number of pages are growing and growing and it takes too long to go through everything especially if a satisfactory answer has already been given and people like me who want to help will give up and so some people may not get any help.
    Thanks for this
    Frenchy.

  • Shipment costs to appear as delivery costs in Purchase

    Hi,
    we want the shipment costs to appear on the purchase order.
    I have followed the sequence as below
    Created a purchase order
    Created a delivery VL31N
    Created a shipment VT01N
    Created a shipment cost document VI01
    I have goods receipt using VL32N, but the shipment cost did not appear in Purchase Order.
    in configuration i have created a new condition in Purchasing ZFRB which has copy shipment cost slected, and added this to the purchasing schema.
    for the shipment cost item category, i configured the settement to delivery costs and left the generate PO blank.
    i would be grateful if someone could help me with configuration that i've missed,
    thanks in advance
    Shadaab

    Please read OSS note 427944 and check SAP online help:
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/83/218ad1068a11d2bf5d0000e8a7386f/frameset.htm
    Prerequisites
    To add shipment costs to delivery costs in the incoming shipments, you need the following settings in Customizing:
    Shipment cost item categories
    Under the Shipment cost types and item categories activity, set the Relevant for costing field to A = Relevant for calculating delivery costs (Delivery costs). This results in the shipment costs not being transferred directly into accounting. The accounting is done via the purchasing functionality for delivery costs.
    Conditions in the purchase order
    Under the Define condition types activity, set the Condition type field to B = Delivery costs. In addition, select the Transfer shipment costs field. The system only shows this field, if you have chosen delivery costs as condition type. In the purchase order, you have to enter the condition type in the item category section. However, you do not enter a value since this value will be determined by the shipment cost document and will then be automatically transferred to the goods receipt document.
    Goods receipt
    To find the relevant shipment cost documents, you must know the corresponding inbound deliveries. Therefore for incoming goods this must relate to confirmation-related goods receipts. Under the Set up confirmation control activity, select the GR-relevant and GR assignment fields for the appropriate confirmation control key (which is then entered in the purchase order).
    Regards,
    Csaba

  • Shipment cost in customer billing doc

    Hi all
    I want to include shipment cost in billing document I want to know the detail process.
    After rising shipment cost doc vi01 this will get reflected in
    Shipment doc vt01n
    I need to charge the cost to customer .i want to include cost in customer billing document VF01
    I want to know from shipment document how will the condition types will be copied into billing document
    1.Should I have to maintain any copy control between these two docs?
    If yes what confi settings need to be done
    Pls let me know  the steps in detail
    regards
    srijen

    Hi mukund thanks for reply
    in copy control i need to maintain "D" or "F"
    i want to know from shipment cost document Vi01 how the conditions are copied to delivery document
    for example- i maintained ZF01,ZF02 in shipment cost doc and i need these two conditions to be displayed in customer billing Vf01
    1) from shipment cost doc how i have to get them in billing doc
    what confi settings are needed
    regards
    sujan

  • Shipment cost not added to material

    hello Gurus
    In inbound Transportation, shipment cost is not getting loaded to material cost while doing PGR... Pls Help
    Rgds

    Dear Guru's
    With refernece to this note:
    To add shipment costs to delivery costs in the incoming shipments, you need the following settings in Customizing:
    Shipment cost item categories
    Under the Shipment cost types and item categories activity, set the Relevant for costing field to A = Relevant for calculating delivery costs (Delivery costs). This results in the shipment costs not being transferred directly into accounting. The accounting is done via the purchasing functionality for delivery costs.
    Conditions in the purchase order
    Under the Define condition types activity, set the Condition type field to B = Delivery costs. In addition, select the Transfer shipment costs field. The system only shows this field, if you have chosen delivery costs as condition type. In the purchase order, you have to enter the condition type in the item category section. However, you do not enter a value since this value will be determined by the shipment cost document and will then be automatically transferred to the goods receipt document.
    Goods receipt
    To find the relevant shipment cost documents, you must know the corresponding inbound deliveries. Therefore for incoming goods this must relate to confirmation-related goods receipts. Under the Set up confirmation control activity, select the GR-relevant and GR assignment fields for the appropriate confirmation control key (which is then entered in the purchase order).
    Can any one let me know how can i enter condition type in item category section? and also tell me can load shipment cost to material in case of outbound delivery.
    Regards,
    Rashid Masood

  • Shipment cost for inbound deliveries

    HI ALL,
    pls can anyone tell me how to transfer or add the frieht cost calculated during the inbound shipment to the material cost(inventory costing).
    how is it doneand in which transaction it is done
    pls ASASP
    thanks in advance

    Hi Vijay
    You have to follow few mm and transportation module configuration settings: These are
    1. In MM Pricing condition types: The freight condition type need to check, that is the option called Copy Shipment costs in MM Freight condition types(FRB1) should be activate.
    2. In Purchase order the freight condition type(FRB1) with zero value always.
    3. In transportation module in shipment cost item categories settings, you have to assign A-Shipment costs as a delivery costs in Shipment Relevant field.
    4. You have to do the PGR after creating shipment and shipment cost documents.
    5. Once you do the PGR the system will copy the shipment costs to material costs and system will generate separate line item in POHistory
    With regrad
    Lakki

  • Getting error while creating shipment cost document

    Dear Guru's
    I have created STO then made delivery and then shipment. All documents are ok but when i m creating Shipment Cost document
    agains shipment getting error Enter Cost Center. Where  I should enter cost center and how can i make cost center value as a default.
    Regards,
    RM

    Hi
    On double clicking on the item level, respective item details of the material is displayed and then click SHIFT+ F6 to see the COSTCENTER in the shipement cost document.
    Configuration:
    1) In Item category configuration account assigment category is Cost Center.
    Logistics Execution>Transportation>Shipment Costs>Shipment Cost Document>Shipment Cost Types and Item Categories-->Define item categories
    2) In the Transaction code OKB9 Costcenter is assigned to the company code , in order to automate the determination of CO assignments in case of Shipment cost document creation
    Logistics Execution>Transportation>Shipment Costs>Settlement>Automatic Determination of CO Assignments
    Edited by: Bhaskar C.R on Jun 17, 2010 10:13 AM

  • Shipment cost: number of items in service entry sheet

    Dear Experts,
    Is there a customizing setting that restricts the maximum allowed number of lines in service entry sheets?
    Context:
    Once I transfer shipment costs, several goods receipt sheets and service entry sheets are created.
    I first thought that there was a one-on-one releationship between a shipment cost item and a service entry sheet. I.e. if there are e.g. 7 shipment cost items, than 7 service entry sheets are created.
    The shipment cost distribution level is set on "delivery item": if for one shipment cost item, there are 250 delivery items, the cost is distributed all over these 250 delivery items. For each delivery item, a line is created in the service entry sheet. However, in my case 3 service entry sheets are created with on:
    - 1st service entry sheet: 99 items
    - 2nd service entry sheet: 99 items
    - 3nd service entry sheet 52 items
    Is there a way to avoid that several entry sheets are created for one . In my case that only 1 entry sheet with 250 items is created after transfer.
    Thanks for the help!
    Kind Regards
    Thiago Santos

    If you are not posting the delivery cost on the material value, then use A - Shipment costs item in the item category.
    Delivery sub-item - A shipment cost sub-item will be created for every relevant delivery sub-item.
    Shipment costs item - One shipment cost sub-item will be created.

  • SAP transparent table stores condition value of Shipment cost

    HI
    I need to know which SAP transparent table stores condition value of Shipment cost document (specific for Freight condition which derived from Bulkiness group).
    Background:
    Minimum load calculation logic
    In the pricing procedure for shipment cost we have two conditions: One is ZMIN (similar with SP00)  which is having condition class u201CHu201D, Calculation type u201CGu201D which determine Bulkiness group according to access sequence. Bulkiness group is where we define different group with different minimum load. e.g. ZCEM16 u2013 25.TON (22.68) Second condition is ZAFR (Similar with FB00), ZAFR calculates the base value from ZMIN (Compare actual weight with Min weight value of Bulkiness group), if the net weight is 23 ton, it will calculate at 25 ton because of the bulkiness group.
    Now I need to know in which table system stores dynamic value of ZMIN?  Just like we have PR00 in KONV which we can find from KNUMV of billing / sales order.  If I use the same logic then I donu2019t find ZMIN Condition type and value in KONV table for the specific shipment cost document.  Please advice how to and from which Table I can find Bulkiness group value of Shipment cost document.
    Thanks

    Hi,
    Get the shipment cost number from shimpment document (document flow or shipment document header).
    Goto VFKP table,enter shipment cost number and choose detials. get the document condition number from  KNUMV field.
    Now goto KONV and enter document condition number and choose details. you can see condition type and value.
    Thanks & Regards,
    Chandrasekhar

  • Shipment cost - Change definition of condition types

    Change definition of condition types in work pricing procedure
    hey all ,
    we implemented the shipment cost module and now we have to make some changes
    in working condition types because the requirements of the customer changed .
    is it recomended and what are the effects of changing the definition of condition types
    and by that changing working pricing procedures .
    for example if i change condition type from D - wight, V - Volume F - Formula to   T scale
    ( and makeing the properchanges in the scale )  or add some more condition the existing pricing
    procedures ?
    BR
    ASA
    Edited by: ASA MOKED on May 22, 2009 3:33 PM

    hey and thanks for the reply ,
    did you make changes in the definition of existing condition types ?
    for example change condition calc.type from d-weight to t-scale ?
    BR
    ASA .

  • Purchase order is created with less amount than the shipment cost amount.

    Hi All,
    Shipment has got 2 stages but the system wants to split the shipment cost to 3 parts (33% each) If we add the amount with manually to shipment cost document and we transfer it the PO will be created only for 2/3 (66%) part of the shipment cost.
    What could be the reason?

    from http://help.sap.com/saphelp_40b/helpdata/fr/dd/2d547bb435d1118b3f0060b03ca329/content.htm
    User exit M06E0004 is provided to enable you to adapt the release strategy determination process to meet your requirements.
    This user exit allows you to change the communication structure for determining the release strategy for purchasing documents.
    The following user fields are available:
    USRC1
    USRC2
    USRN1
    USRN2
    In addition, communication structure CEKKOZZ is available, allowing you to use your own fields.

  • Service Entry sheet Creation for Shipment cost Document

    Dear All,
    While creating a shipment cost document .A service PO is getting generated in the back ground based on which a service entry sheet is created and LIV is made.But in the configuration we are mapping the Transportation planning point to Purchase organisation alone.
    Can some one let me know whether the generation of PO in the back ground for a shipment cost document in the back ground is a standard SAP feature if so can you tell me the configuration steps.
    Regards,
    K.Vivek

    Hi,
    Creation of Service PO in shipment cost document is based on the following SPRO setting or T-code.
    T code : T_56.
    SPRO > LE > Transportation > shipment cost Document > Shipment cost types and item categoires.
    Get into the details of item categoires, you can see the indicator Generate PO.
    hope this helps.
    Harish