Can any one help me with this issue:
At my client location they did stack 14 upgrade recently. After this upgrade over head charges for goods issue from  one department to another department are not being calculated. I checked the configuration and every thing looks fine for me. But when i do KGI4 i don't see any over head being calculated.
Thanks in advance

na

Similar Messages

  • Error in Over Head Calculation

    Hi
    We are on new GL and ECC 6.0. Splitting is active based on profit center and every plant is also a profit center. We have created secondary cost element in the system to record activity performed on production order. When doing the over head calculation system generates a poting between two different profit centers, which forced the system to create a corresponding entry in FI. We have switched off account determination in the variant for real time integration between CO & FI and also supressed the error message. Now when we do the Over calculation against the production order, system displays the error that the secondary cost element used in Over Head Calculation has not been created as GL Account in Our chart of Accounts. Pls suggest
    Regards
    Sanil Bhandari

    na

  • How to get internal order and activity type other than from BSEG

    We want the Internal order and activity type fields. From BSEG, it is taking a long time, and it hangs.
    Is there any other table we can get these values from?
    Our query is this:
    select bukrs "Company code
    gjahr "Fiscal year
    belnr "Document no.
    buzei "Document Item no.
    aufnr "Internal order
    lstar "Activity type
    from bseg
    into table gt_add_info
    for all entries in gt_gl_detail
    where bukrs = gt_gl_detail-rbukrs"Comcode from G/L acct detail
    and buzei = gt_gl_detail-buzei "Doc item no. from G/L acct detail
    and belnr = gt_gl_detail-belnr "Doc no. G/L acct detail
    and gjahr = gt_gl_detail-gjahr."Fiscal yea
    Can advise please how to make it faster. My internal table (GT_GL_DETAIL) has over 100000 records. ? thanks.

    I did a SQL trace, and saw that tables CSLA, CSSL, COKL and COKA are being hit with the values I entered inthe Activity type in transaction FB50.
    Still not clear but where it gets stored. If in any of these tables, how do I get the object key?

  • Report to display Mat Cost Planned Labour Cost and Over head cost

    Hi Abapers,
    Greetings of the day..
    I need a Report that Display Material Cost , Planned Labour Cost,Actual Labour Cost and Over head value
    where do i start from and what are the tables involving in this report..
    if already done this A code snippet is more helpful...
    Thanks In Advance...
    Thanks & Regards
    Sathish

    Assuming you are talking about Maintenance Order.
    Use table: PMCO.
    Here the line with field VORGA having value KPPS gives the Planned Costs of the Order in the field WRT01.
    Similarly, the line with field VORGA having value RKL gives the Actual Costs of the Order in the field WRT01.
    Also have a look at Tcode KKBC_ORD.
    Jogeswara Rao K

  • Internal order and Cost center

    hi guys
    can anyone please explain me why do we have cost centers and internal orders?
    If we can track cost to cost center then why do we need internal orders?
    please give some detailed explanation.
    thanks

    when you are posting a document and if the g/l is created as a cost element then
    you have to either assign a cost center, profit center, internal order etc
    so when you are posting an expense and if its for that project you assign the
    internal order and when the project is finished you can settle it to a cost center.
    If we can assign both internal order and cost center i dont think so but not very
    sure. Best way to learn these things i would recommend is try it in test system
    that way you will understand better about the whole flow and it will stick in your
    mind.
    Regards,
    Zaid

  • BAPI KPF6 POST PLAN COST FOR INTERNAL ORDER AND COST ELEMENT

    Hi all gurus,
    I would like to use in a custom report a BAPI/Function Module that help me to simulate KPF6 in order to post planning costs for internal order and cost element (layout 1-401).
    So the input should be:
    1) Version
    2) period from
    3) periodo to
    4) year
    5) internal order n.
    6) cost element n.
    7) value
    I found a lot of BAPI but don't know the correct one and how to use it (example how to fill the input value).
    Can anyone help me on that?
    Kind Regards

    In additio  to the previous I found the BAPI_COSTACTPLN_POSTPRIMCOST but don't know if it's the correct one and how to use it (some example fitting the my case will be very appreciated).
    If the quoted BAPI is correct.
    I tested it filling all fields as following:
    HEADERINFO:
    CO_AREA=FFCA
    FISC_YEAR=2008
    PERIOD_FROM=001
    PERIOD_TO=012
    DOC_HDR_TX='blank'
    INDEXSTRUCTURE:
    OBJECT_INDEX=000001
    VALUE_INDEX=000004 (hope this point at Interna Order)
    ATTRIB_INDEX=000000
    COOBJECT:
    OBJECT_INDEX=000001
    ORDERID=ZO53-08IMZ
    TOTVALUE:
    VALUE_INDEX=000004
    COST_ELEM=3224048
    FIX_VALUE= 200,0000
    DIST_KEY_FIX_VAL=2
    The Return table is set to 0. Nothing happens.....I suspect something related to indexstructure or index is wrong..
    Could anyone help me on that?
    Kind Regards

  • Invoice get twice to internal order and to accounting

    Hi All,
    The order is invoiced once in CRM but in ECC  internal order and in accounting the same invoice is getting twice.
    Any idea how this is happening and how to resolve such cases.
    Best Regards,
    DP

    Hi,
    is the internal order a real order or a statictical one?
    Regards,
    Greta

  • Default Internal order and cost center

    Hi Experts,
    i am uploading one file into sap and here i am giving GL accounts cost centers and WBS elements.
    once i have done with upload.when i am checking in BSEG its showing one internal order and one default cost center with internal order.
    i can not understand how its finding internal order and default cost cente(which diffetrent from those cost centers i have mentioned in excel).
    please help me to find.
    thanks,
    Vani

    HI,
    Thanks for your reply.
    i have checked OKB9 and KA03 but there is no default assignment.
    checked also OBBH and OKC9 but no subtitution and i can't post manually now.
    is there any option.
    Waiting for your reply.
    Thanks,
    Vani

  • BW Datasource for Internal Order and Budget

    Hi Gurus,
    I would like to ask what datasource I can use for FICO specifically for Internal Orders and Budget. I have looked at all the datasources under the CO node but i can't seem to find a datasource that has the details for the Internal Order and for the Budget.
    Thanks in advance
    - Kit

    Hi,
          Check these datasources once.
    0CO_OM_OPA_8-- Orders: Budget Line Items 
    0CO_OM_OPA_2 --Orders: Budget 
    Refer this link as well.
    http://help.sap.com/saphelp_nw70/helpdata/EN/43/de43fcf6e2154bbbbcecbc63cdf287/frameset.htm
    Regards
    Karthik

  • Hi ... I want Internal orders and Profit Center related study material....

    Hi
    Friend
    I want Internal orders and Profit Center related study material....i want to understand what these concepts...
    Thank you

    Hi
    Internal order configuration:
    I have uploaded 2 docs here
    http://rapidshare.com/files/27424591/IOrder1.pdf.html
    http://rapidshare.com/files/27424270/IO2.pdf.html
    Regards
    A
    Assign points if useful

  • Internal order and g/l number trying to give in miro screen

    hi experts
    i am facing a problem in miro screen. i want to change the internal order and g/l a/c in miro screen. is it possible to change in miro?as i know this internal order and g/l a/c is generally given at the time of po and grn. but my cleint want to change it in miro screen if requeired. can you please suggest me whethere it is possible or not. if possible then how can i configure it?
    thanks and regards
    rishi
    Moderator: Yes, it's configurable (OME9). Please, search SDN properly and post in the right forum. This questions relates to MM

    hi
    not possible in std configuration chek with user exit
    MBCF0002 ( EXIT_SAPMM07M_001 ).
    got the below patch from net try it
    ->However you cannot directly chnage as MSEG is available as importing parameter and whatever you change here will ->have no impact on main prog. Instead you can use following code -
    ->
    ->FIELD-SYMBOLS <F2> TYPE ANY,"Field Symbol for the GL ACCOUNT
    ->
    ->DATA : W_KONTO_NAME(50) VALUE '(SAPMM07M)DM07M-KONTO'.
    ->
    ->ASSIGN (W_KONTO_NAME) TO <F2>.
    ->MOVE "GLACCOUNT" TO <F2>.
    ->
    ->"GLACCOUNT" is the new GL account you want to change.
    ->
    ->or try field exit:
    ->
    ->report RSMODPRF
    regards
    kunal

  • Actual Over Head Calculation for process order

    hi!
    I have created a costing sheet for  over head, which will be based on labour activity cost.
    the base is labour cost for which I have given secondary cost element ( assigned in activity type for labour hours) in costing sheet and maintained over head rate for planned & actual. in credit of costing sheet for over head I have given secondary cost element with internal order.
    first question is : when internal order posting will happen? I am assuming , when production order settlement is done, over head cost has to be accrued to internal order. is my assumption is correct? because in line items of internal order , i couldn't see any thing.
    second question is : in process order, system is showing over head cost under planned cost, but it is showing ZERO in actual cost column. I have executed KGI2, system is not showing any senders or receivers. but when I executed KGI2 with dialog dipslay check box, system shows the calculations as per cost sheet correctly under condition value column.
    Please let me know where I missed ? how to get actual over heads in process order.
    in process order in cost analysis in the actual/target cost layout, system is showing the over head costs. but where as in "cost trend" layout, system is not showing over head cost.
    can any one help on above points.
    regards,
    ramesh b

    Hi
    Maintain the Overhead rate in KZM2 or KZZ2 as the case may be
    Then execute CO43... The moment overhead is charged to Process order, it would post credit to IO
    br, Ajay M

  • Internal order and accrual calculation.

    My Client right now uses excel sheets to keep track of marketing expenses. He uses this to find out how much accrual marketing expenses to post at the end of each month (This is reversed next month).
    example:
    Lets say the client is doing Television Campaign:
    Begin Date: 10/29/2007
    End Date:   11/18/2007
    Month End Date: 11/3/2007
    Effective days of campaign=11/18/2007-10/29/2007+1=21 days
    Budget for 21 days is say 91 dollars.
    Days to Accrue at month end (11/3/2007)=6 days.
    Total accrual for the month end 11/3/2007=6/21*91 dollars
    = 26 dollars
    So for the above scenario If i want to use internal orders. Can I use "Work Start", "End of Work", "Estimated Costs" field under General Data.
    And write an SQ01 query, report to calculate the accrual expenses for each marketing internal order?
    Is this a good approach?
    Thanks,
    Hari Gadi.

    Hi venkata,
    I'm afraid you are talking about field AUFK-AUTYP (order category) (instead of AUFK-AUART).
    That's easy! Just access table DD07T for domname = 'AUFTYP' and ddlanguage = 'EN'. And domvalue_l = (order_category). Then you'll have the description into dd07t-ddtext.
    I hope it helps. Best regards,
    Alvaro

  • How the Sales OH (Over Head) Calculated

    Dear Experts,
    I have query regarding Sales OH Calculation,
    How the Sales OH (Over Head) will be calculated  and what basis system will take it.
    My requirement is OH reporting in COPA.
    And send me customizing steps for Sales OH Calculation.
    I am awaiting for your kind perusal.
    Thanks,
    KBR

    Hi Kurru Bhaskar,
    If u want to apply OH to material or production that will come from define costing sheet under product costing and assign  to valuation variant OKKN keep ur costing sheet under overhead tab in valuation variant.
    if u want specifically want to apply indirect cost to sales order define sepeate costing sheet and give that costing sheet .
    IMG>Controlling>Product Cost Controlling>Cost Object Controlling>Product Cost by Sales Order>Control of Sales-Order-Related Production/Product Cost by Sales Order>Check Requirements Classes.
    under requiremetn type under costing sheet tab.
    let me know any douts ML Bhaskahr.
    thanks
    kareem

  • Foreign currency posting to Internal order and settlement

    Hi All,
    The payment posted to an internal order was in a foreign currency then translated into usd.  The settlement used a different exchange rate so in usd there was a balance.
    How do we rectify this..?
    Regards
    Ashok PRabhu

    Hi
    I am not sure how IS-H works.. But for sure, it should allow you to enter 3 stat objects...
    There would be some ABAP trick pertaining to IS-H which I am not aware of...
    I can guide you a bit...  During SD billing, ask abaper to put a break point and manually enter the values for cost center and IO and then post the doc.... One of these 2 will be the outcomes
    a. Either it will get posted or
    b. It will get over written before posting....
    based on the outcome, you will have to decide your next course of action
    Also, if your cost center to IO is one to one mapping (Chances would be rare), you can simply write a substitution which would always prevail
    I am sorry I could not offer you a complete solution.. But, this is what comes to my mind...
    Regards
    Ajay M

Maybe you are looking for

  • How to rebuild index on a table in a faster way

    Hi All, We have using Oracle 9.2.0.3 On weekly basis we are loading around 20-30 million of data into a table using sqlloader. Before loading the data into the table, we are dropping all the indexes adn rebuilding the same once done. There are 6 inde

  • What Bluetooth headsets are compatible with the iphone 4

    What Bluetooth headsets are compatible with the iphone 4

  • 1 week old 27" 3.4 I7 freezing and rainbow spinning pinwheel

    Hello,   I bought a new 27" imac 3.4 I7 a few weeks ago and started having issues with it.  Returned that one and now I am having the same issues with the new one.  When I wake the computer from sleep I get the SPOD (spinning pinwheel of death)  you

  • Read JMS Map message in BPEL