HI Guys,
i have a requirement where 2 files has to be picked and post to two files.
conditions: if any one of the files are not picked then cancel the process.
Correlation: no common fields exist in the two files.so we can use constant.
can any one give me the steps to design the BPM
Thanks,
Madhu

HI Prateek,
I have done that process as you said.
one Block step and a fork step inside the block and two branches for the fork, each branch with one receive step and each can start the process.and a deadline branch to the block step with 1 minute and a control step to cancel process.
but, the files are picking and the messages are with the status "To be delivered" in integration engine.
please suggest
Thanks,
Madhu

Similar Messages

  • Reg: BPM design

    Hi All,
    I am bit confused on the solution approach of BPM design and I would like your suggestions in completing my task.
    Requirement :
    scenario is proxy to Jdbc .
    I will get two input files from the source system and I have combine two files information into database table :
    1) first file will come only once and have key field which I have to consider.
    2) second file  may come more than once based on bookings at source side( 3/5/6/8).
    with current design , able to capture only one output from this design . my current design is :
    Fork
    Two receive steps ( correlation enabled in two steps based on key value)
    transformation step
    send step.
    with the current design in bpm ,correlation will come out after the first message satisfies the condition. Now i want to loop in such away based on the second file input  correlation has to work ( there is no input from source to take count on files). pl guide me.
    Regards,
    Suman

    Hi,
    This is what happens: the first receive step starts the bpm. If you have, afterwards, some other receive steps you have to set up the correlation condition.
    Once a message is being sent, the engine looks at all the started BPMs and based on the correlation condition it assigns it to one of them (that's why it is important to have the correlation condition unique per instance).
    From what I understand, you have the first message and then you can get 1 to 4 more messages. So you always have at least two messages: the first one sets the correlation id for the second and further messages. This correlation condition/id is just a field in the message that corresponds. Now after you get the second message, you say that you already know how many other messages will follow, that's why I say put a loop block with the receive (which should have the same correlation as the other).
    Now the contents of the first message will be available to the other messages as long as you keep it in a separate container variable, and you can re-use it in the loop.
    Hope this helps,
    Horia

  • Reg:BPM

    Hi All,
    I am new to Business Process Management(BPM) can anyone tell me What is BPM? and the business scenario actual use of BPM and provide me any useful material on this.
    Thanks,
    Rahul.
    Edited by: rahul.girmaji on Dec 22, 2011 7:27 PM

    Hi Rahul,
    Hope this link will provide you with an insite : Workflow and Orchestration Solutions from SAP – Overview and Positioning
    Suggest you to go through the BPM page in SDN for more information.
    Regards,
    Mahesh

  • Reg:BPM Scenario

    Hi All,
    My scenario is Portal(SOAP)- - - R/3(RFC)- - -  MDM
    The webservice(Asyn) is being triggered from the portal ,it will update the data into ECC system by using a RFC(syn)  and from the response(status) of the RFC the message is passed to the MDM server.
    Could anyone suggest me on how to proceed the above stated scenario.
    Thanks in Advance.
    Regards,
    Lavanya

    Use Async  Sync bridge pattern with BPM
    Soap sender (async) ---> RFC(sync) --> Proxy or Idoc (async)
    For Soap sender refer this document
    To configure Asynchronous
    use Quality of Service:  Exactly Once 
    Follow this link for soap sender configuration
    http://help.sap.com/saphelp_nw04/helpdata/en/fc/5ad93f130f9215e10000000a155106/content.htm
    For Async sync pattern use this link... also Refer below link does RFC (sync)
    http://www.riyaz.net/blog/a-step-by-step-guide-to-bpm-asynch-sync-bridge/technology/sap/170/
    For Proxy or Idoc at the target side... This below link gives abap proxy receiver details
    http://wiki.sdn.sap.com/wiki/display/XI/Step-by-stepFTPtoABAPProxy
    Hope this helps.

  • Reg:BPM Modelling

    In BPM Modelling an individual  swim lane contains business scenarios from same company or from same application ?
    Regards

    It could be both. It depends upon how you want to design your business flow. However, designing one only for an application is not that common.
    Regards,
    Prateek

  • Reg:BPM collect timeout

    hi guys,
    Iam trying to do a scenario where i need to insert a deadline branch within the block step.In the block step i inserted the exception branch,after that when am trying to insert the deadline branch,it is going to the same level.How to insert it at next level,and i also need to insert the control step with in it.
    regards
    chandrakanth.k

    Hi,
    the order was like:
    start -> receive1 -> send1
    ->
    (block
    -- receive2 -> send2
    -- exception branch
    -- deadline branch
    block)
    -> end
    Regards
    Patrick

  • Reg:BPM execution

    hi can i know where exactly the integration process executes
    in IE/BPE
    Regards
    chandrakanth

    Hi,
    It will execute in BPE which is part of Integration server
    check this link for more
    http://help.sap.com/saphelp_nw04/helpdata/en/3c/831620a4f1044dba38b370f77835cc/frameset.htm
    Sachin

  • When we will go for BPM

    Hi,
    I want to know when exactly we go for bpm and how to work simple bpm scenario.

    Hi Sreenu,
    BPM is used for Stateful communications,suppose u have to delay message processing,or wait for other messages to arrive and then semd them all together,in that case use BPM.
    We will use BPM when ever we want to do the following:
    1.Controling or Monitoring of messages in XI
    2. Collect or Merge the messages in XI
    3. Split the messages in XI
    4. Multicast a Message
    5. Need to send an Alert
    6. Transformation
    With its BPM capability, SAP NetWeaver:
    • Exploits business-process efficiency by giving your business
    users the ability to directly model, manage, monitor, and
    analyze business processes
    • Enables continuous process improvement and the dynamic
    modification of business processes
    • Extends the value of your company’s core business investment
    and maximizes the return on its strategic assets by providing
    the ability to change process rules without additional IT
    investment
    • Provides greater visibility into critical business operations for
    better decision making by delivering the right information at
    the right time
    • Allows the integration of people, applications, and internal
    and external resources
    Process step types:
    Message relevant:
    Receive: We use it to receive a message. By receiving a message we are sending the data into process. We can use it to start a process. We can use it for activating or using correlations.
    Send: We use it to send either an asynchronous or synchronous message or an acknowledgement.
    Receiver Determination: We use it to get a list of receivers for sub sequent send step. It calls the receiver determination that we configured in the integration directory and returns receivers list.
    Transformation: We use it to change a message inside the process. E.g. bundling multiple messages into 1 or splits a message into multiple.
    Using this we can create N:1 or 1:N or 1:1 transformations. In general scenario 1:N transformation is possible.
    Process flow control Relevant:
    Container: We use it to set a value for target container element at runtime. Target container element and assigned value must have same value.
    Control: We use it to terminate the current process and to trigger an exception and to trigger an alert.
    While Loop: To repeat the execution of steps within the loop.
    Fork: We use it when you want to continue a process in branches that are independent of each other. E.g. to communicate with two systems that are independent to each other
    Block: We use it to combine steps that you want to execute one after the other and which are to access the local data.
    Empty: It has no influence on the process flow. We use it as a place holder for a step that has not yet been defined, and as a step with no functions for test purposes.
    Wait: We use it to incorporate a delay in the process.
    Switch: We use it to define different processing branches for a process
    T.Codes for B.P.M:
    SXMB_MONI_BPE
    SXWF_XI_SW11
    For Example a Small Explanation reg BPM for this Req we used BPM
    A background program should be scheduled to run every 10 minutes to analyse any material records that have been created or changed or deleted that have occurred to the material master records in the last minute.
    There are two Message Mappings involved in the whole scenario. First mapping is N:1 Mapping which will be used in BPM and second Mapping is 1:1 Mapping:
    1. First Message Mapping  N: 1 u2013 Mapping between IDoc (occurrence u2013 0...unbounded in u201CMessagesu201D tab) to IDoc with changed occurrence of its top node (IDOC) as 0...unbounded. This message mapping will be used in BPM u2013 transformation step.
    Description: This BPM collects all Idocs for 10 minutes which are of Message Type (ZMATMAS05) according to Receiver Partner Number (Field u2013 RCVPRN) and calls N: 1 mapping to bundle the collected Idocs in a One External Definition for that IDOC.
    Use
    You use a wait step ( ) to incorporate a delay in a process. Usually, you use a delay to define when the next step in the process is to start. You can define a delay as either a point in time or a period of time.
    At runtime, the step waits until the specified point in time is reached or the specified period of time has passed. The system then continues the process by proceeding with the next step.
    Expalined clearly how to do a file to file scenario with BPM :
    /people/krishna.moorthyp/blog/2005/06/09/walkthrough-with-bpm
    it is File>RFC>File using BPM then refer this blog.
    /people/arpit.seth/blog/2005/06/27/rfc-scenario-using-bpm--starter-kit
    BPM-1 /people/krishna.moorthyp/blog/2005/06/09/walkthrough-with-bpm
    BPM-2 /people/krishna.moorthyp/blog/2006/04/08/reconciliation-of-messages-in-bpm
    BPM-3 /people/arpit.seth/blog/2005/06/27/rfc-scenario-using-bpm--starter-kit
    BPM-4 /people/michal.krawczyk2/blog/2005/06/11/xi-how-to-retrieve-messageid-from-a-bpm
    Integratio Scenario
    /people/venkat.donela/blog/2006/02/17/companion-guide-to-integration-scenario
    /people/siva.maranani/blog/2005/08/27/modeling-integration-scenario146s-in-xi
    Schedule BPM
    /people/siva.maranani/blog/2005/05/22/schedule-your-bpm
    Use of Synch - Asynch bridge in ccBPM
    /people/sriram.vasudevan3/blog/2005/01/11/demonstrating-use-of-synchronous-asynchronous-bridge-to-integrate-synchronous-and-asynchronous-systems-using-ccbpm-in-sap-xi
    Use of Synch - Asynch bridge in ccBPM
    https://www.sdn.sap.com/irj/sdn/weblogs?blog=/pub/wlg/1403 [original link is broken] [original link is broken] [original link is broken] [original link is broken]
    without BPM
    /people/henrique.pinto/blog/2007/08/02/syncasync-scenarios-without-bpm
    without BPM1
    /people/venkataramanan.parameswaran/blog/2007/01/18/syncasync-communication-in-jms-adapter-without-bpm-sp19
    IDOC BPM
    /people/pooja.pandey/blog/2005/07/27/idocs-multiple-types-collection-in-bpm
    To deal with Multiple sender and receivers based on the conditions we could use BPM. Its one of the feature of BPM, but its not mandatory to go for BPM for each n every case. Its depends upon scnenario.
    /people/marilyn.pratt/blog/2007/10/12/clubhouse-las-vegas-a-bpm-roadmap
    BPM Process Patterns:Repeatable Design for BPM Process Models
    http://www.bptrends.com/publicationfiles/05%2D06%2DWP%2DBPMProcessPatterns%2DAtwood1%2Epdf
    BPM Steps link : http://help.sap.com/search/highlightContent.jsp
    BPM-BUSINEES PROCESS MANAGAEMENT
    *Transformation Error and still stuck ? *
    /people/shabarish.vijayakumar/blog/2005/12/07/transformation-error-and-still-stuck
    Walkthrough with BPM
    /people/krishna.moorthyp/blog/2005/06/09/walkthrough-with-bpm
    Reconciliation of Messages in BPM
    /people/krishna.moorthyp/blog/2006/04/08/reconciliation-of-messages-in-bpm
    Reconciliation of Messages in BPM Contd. - Restart Workflow
    /people/krishna.moorthyp/blog/2006/04/08/reconciliation-of-messages-in-bpm-contd--restart-workflow
    *XI: How to... retrieve MESSAGE_ID from a BPM *
    /people/michal.krawczyk2/blog/2005/06/11/xi-how-to-retrieve-messageid-from-a-bpm
    XI: Do you realy enjoy clicking and waiting while tracing BPM steps?
    /people/michal.krawczyk2/blog/2005/09/04/xi-do-you-realy-enjoy-clicking-and-waiting-while-tracing-bpm-steps * *
    BPM:Single Sender and Multiple Receivers based on synchronous exchange(switch) part-1
    /people/prasadbabu.nemalikanti3/blog/2006/03/10/bpmsingle-sender-and-multiple-receivers-based-on-synchronous-exchangeswitch-part-1
    Collecting IDocs without using BPM
    /people/stefan.grube/blog/2006/09/18/collecting-idocs-without-using-bpm * *
    *Multi-Mapping without BPM - Yes, itu2019s possible! *
    /people/jin.shin/blog/2006/02/07/multi-mapping-without-bpm--yes-it146s-possible
    Sync/Async scenarios without BPM
    /people/henrique.pinto/blog/2007/08/02/syncasync-scenarios-without-bpm
    XI/PI: BPM modeling in Aris for SAP Netweaver - a teaser
    /people/michal.krawczyk2/blog/2006/11/27/xipi-bpm-modeling-in-aris-for-sap-netweaver--a-teaser
    *XI: who said he cannot be stopped? BPM JIM - SP17 *
    /people/michal.krawczyk2/blog/2006/06/27/xi-who-said-he-cannot-be-stopped-bpm-jim--sp17
    *Schedule Your BPM *
    /people/siva.maranani/blog/2005/05/22/schedule-your-bpm * *
    *how to integrate unified worklist to xi-BPM *
    https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/bb9100f8-0c01-0010-ac8e-e017351f3fc1
    *Usage of Sync-Async when both Sender and Receiver are Synchronous Apps *
    https://www.sdn.sap.com/irj/sdn/weblogs?blog=/pub/wlg/1403 [original link is broken] [original link is broken] [original link is broken] [original link is broken]
    Using a BPM to collect messages for a set interval of time
    /people/daniel.graversen/blog/2006/09/07/using-a-bpm-to-collect-messages-for-a-set-interval-of-time
    Sync/Async scenarios without BPM
    /people/henrique.pinto/blog/2007/08/02/syncasync-scenarios-without-bpm * *
    *Illustration of Multi-Mapping and Message Split using BPM in SAP Exchange Infrastructure *
    /people/sudharshan.aravamudan/blog/2005/12/01/illustration-of-multi-mapping-and-message-split-using-bpm-in-sap-exchange-infrastructure
    Regards,
    Vinod.

  • Want Scenarios for BPM

    Hi All,
    Can anybody pl. provide some BPM Scenarios, BPM Docs, or any related Docs for BPM.
    i want some  Scenarios for BPM.
    Thanks in advance,
    Shweta

    Hi Shwetha,
    BPM is used for Stateful communications,suppose u have to delay message processing,or wait for other messages to arrive and then semd them all together,in that case use BPM.
    We will use BPM when ever we want to do the following:
    1.Controling or Monitoring of messages in XI
    2. Collect or Merge the messages in XI
    3. Split the messages in XI
    4. Multicast a Message
    5. Need to send an Alert
    6. Transformation
    With its BPM capability, SAP NetWeaver:
    • Exploits business-process efficiency by giving your business
    users the ability to directly model, manage, monitor, and
    analyze business processes
    • Enables continuous process improvement and the dynamic
    modification of business processes
    • Extends the value of your company’s core business investment
    and maximizes the return on its strategic assets by providing
    the ability to change process rules without additional IT
    investment
    • Provides greater visibility into critical business operations for
    better decision making by delivering the right information at
    the right time
    • Allows the integration of people, applications, and internal
    and external resources
    Process step types:
    Message relevant:
    Receive: We use it to receive a message. By receiving a message we are sending the data into process. We can use it to start a process. We can use it for activating or using correlations.
    Send: We use it to send either an asynchronous or synchronous message or an acknowledgement.
    Receiver Determination: We use it to get a list of receivers for sub sequent send step. It calls the receiver determination that we configured in the integration directory and returns receivers list.
    Transformation: We use it to change a message inside the process. E.g. bundling multiple messages into 1 or splits a message into multiple.
    Using this we can create N:1 or 1:N or 1:1 transformations. In general scenario 1:N transformation is possible.
    Process flow control Relevant:
    Container: We use it to set a value for target container element at runtime. Target container element and assigned value must have same value.
    Control: We use it to terminate the current process and to trigger an exception and to trigger an alert.
    While Loop: To repeat the execution of steps within the loop.
    Fork: We use it when you want to continue a process in branches that are independent of each other. E.g. to communicate with two systems that are independent to each other
    Block: We use it to combine steps that you want to execute one after the other and which are to access the local data.
    Empty: It has no influence on the process flow. We use it as a place holder for a step that has not yet been defined, and as a step with no functions for test purposes.
    Wait: We use it to incorporate a delay in the process.
    Switch: We use it to define different processing branches for a process
    T.Codes for B.P.M:
    SXMB_MONI_BPE
    SXWF_XI_SW11
    For Example a Small Explanation reg BPM for this Req we used BPM
    A background program should be scheduled to run every 10 minutes to analyse any material records that have been created or changed or deleted that have occurred to the material master records in the last minute.
    There are two Message Mappings involved in the whole scenario. First mapping is N:1 Mapping which will be used in BPM and second Mapping is 1:1 Mapping:
    1. First Message Mapping  N: 1 u2013 Mapping between IDoc (occurrence u2013 0...unbounded in u201CMessagesu201D tab) to IDoc with changed occurrence of its top node (IDOC) as 0...unbounded. This message mapping will be used in BPM u2013 transformation step.
    Description: This BPM collects all Idocs for 10 minutes which are of Message Type (ZMATMAS05) according to Receiver Partner Number (Field u2013 RCVPRN) and calls N: 1 mapping to bundle the collected Idocs in a One External Definition for that IDOC.
    Use
    You use a wait step ( ) to incorporate a delay in a process. Usually, you use a delay to define when the next step in the process is to start. You can define a delay as either a point in time or a period of time.
    At runtime, the step waits until the specified point in time is reached or the specified period of time has passed. The system then continues the process by proceeding with the next step.
    Expalined clearly how to do a file to file scenario with BPM :
    /people/krishna.moorthyp/blog/2005/06/09/walkthrough-with-bpm
    it is File>RFC>File using BPM then refer this blog.
    /people/arpit.seth/blog/2005/06/27/rfc-scenario-using-bpm--starter-kit
    BPM-1 /people/krishna.moorthyp/blog/2005/06/09/walkthrough-with-bpm
    BPM-2 /people/krishna.moorthyp/blog/2006/04/08/reconciliation-of-messages-in-bpm
    BPM-3 /people/arpit.seth/blog/2005/06/27/rfc-scenario-using-bpm--starter-kit
    BPM-4 /people/michal.krawczyk2/blog/2005/06/11/xi-how-to-retrieve-messageid-from-a-bpm
    Integratio Scenario
    /people/venkat.donela/blog/2006/02/17/companion-guide-to-integration-scenario
    /people/siva.maranani/blog/2005/08/27/modeling-integration-scenario146s-in-xi
    Schedule BPM
    /people/siva.maranani/blog/2005/05/22/schedule-your-bpm
    Use of Synch - Asynch bridge in ccBPM
    /people/sriram.vasudevan3/blog/2005/01/11/demonstrating-use-of-synchronous-asynchronous-bridge-to-integrate-synchronous-and-asynchronous-systems-using-ccbpm-in-sap-xi
    Use of Synch - Asynch bridge in ccBPM
    https://www.sdn.sap.com/irj/sdn/weblogs?blog=/pub/wlg/1403 [original link is broken] [original link is broken] [original link is broken]
    without BPM
    /people/henrique.pinto/blog/2007/08/02/syncasync-scenarios-without-bpm
    without BPM1
    /people/venkataramanan.parameswaran/blog/2007/01/18/syncasync-communication-in-jms-adapter-without-bpm-sp19
    IDOC BPM
    /people/pooja.pandey/blog/2005/07/27/idocs-multiple-types-collection-in-bpm
    To deal with Multiple sender and receivers based on the conditions we could use BPM. Its one of the feature of BPM, but its not mandatory to go for BPM for each n every case. Its depends upon scnenario.
    /people/marilyn.pratt/blog/2007/10/12/clubhouse-las-vegas-a-bpm-roadmap
    BPM Process Patterns:Repeatable Design for BPM Process Models
    http://www.bptrends.com/publicationfiles/05%2D06%2DWP%2DBPMProcessPatterns%2DAtwood1%2Epdf
    BPM Steps link : http://help.sap.com/search/highlightContent.jsp
    Regards,
    Vinod.

  • Help Required IN Business Process Monitoring?

    Hi,
    i have few clarifications reg BPM in solution Mangager
    1.What is monitored in BPM,Business Process interfaces or the business Process data( at does t monitors at data level)?
    2.if interfaces are monitored in Solman BPM,how different it is from Netweaver Business process management.?
    3.if possible can anyone brief out what XI process monitoring is and how is it different from SOLMAN BPM?
    helpful answers rewareded
    rgds,
    rajesh

    Hello Rajesh,
    please refer to https://service.sap.com/bpm --> Media Library --> Customer Information --> "Business Process & Interface Monitoring - Part 2" to get a comprehensiver overview about what is available out-of-the-box for BPMon in SolMan.
    BPMon in SolMan and BPM in Netweaver adress different target groups and can be seen a complementary functionalities.
    BPMon in SolMan is primarily targeting at the 2nd level application support and should ensure a stable and smooth processing of Business Processes from a technical as well as application perspective. The processes have a granularity down on transaction or background job level.
    Technical monitoring could be average response time of a transaction or a job cancellation.
    Application monitoirng is providing about the throughput numbers of documents like sales orders, deliveries or backlog figures indicating that there are erronuous documents or documents that need manual intervention. Looking at this last aspect it is clear that a second target group is key players on business unit side, like sales reposnibles, plant owners etc.
    On interface side you can monitor IDocs, qRFCs, Batch Input session for certain statuses, check if files arrived or do some XI messaged based alerting.
    BPM in Netweaver is a technical layer deeper and based especially on XI/PI. So this is an integration engine itself. When you look at the capabilities of XI/PI where you can split or correlate messages with ccBPM this is related to so called integration processes which could be a more detailed sub-process from what is looked at BPMon in SolMan. Other aspects that BPM in Netweaver is supports is Business Activity Monitoring BAM which cannot easily explained with  a few sentences. But here the target groups with BAM are either real business end-users or C-level management for business efficiency analysis.
    Hope this answer could clarify a few things.
    Volker

  • Reg: Message and BPM

    Hi
    I'm having a scenario where i use a JDBC adapter to extract data from a DB. As a result of the query say, 10 rows are returned as message to XI server. I have a transformation (BPM) set and the receiver(target system) is a file. When i open the file to see its contents i can see only the first record been transfered. The mapping part used for the transformation node is having IF condition. But all the fetched records satisfies the conditions in the mapping.
    Pls let me know the corrective step.
    reg: Prabhu

    Hi,
    1)Check the input XML i.e all 10 records are coming into XI . This you can check in SXMB_MONI
    2) Then you can test the mapping in the integration Reposiotry .. So now you can get if any mapping problem. For this , check is the occurence of target strcuture is 1..n or 0.n
    /people/michal.krawczyk2/blog/2005/09/16/xi-how-to-test-your-mapping-in-real-life-scenarios
    3) If mapping is correct , then check the RWB->Message Monitoring->Message Display Tool and check the payload.
    4) If this is correct, then check the File COntent Conversion of the Receiver File Adapter.
    Hope this helps,
    Regards,
    Moorthy

  • Reg:Container variables in BPM

    Hi...
        I have done one scenario with BPM.
    In that i have  used the below steps.
    1. Fork with  2 receive steps.
    2. and two container steps for the 2 recieve steps ( vara= "I" for the first recieve step, and varb= "S" for the second receive step)
    3.wait -- for 1 min
    4. switch (if  vara ="I" and varb="S", then branch 1 should execute, if vara="I",then branch 2should execute else we need to cancel the process)
    the above steps i have used and executed the scenario. It is working fine. BUt i am having problem with the containers.
    I am not able to satisfy the condition for [if  vara="I" and varb="S",]
    The switch is not going to check the above conditon because whenever the file is recieved the container variable will get updated and wait for 1 min and will go for  switch contion. So here i can check only for single condition at a time.
    Can you please help me how to check the both the container variables at an time..?
    Regards,
    Leela

    Can you please help me how to check the both the container variables at an time..?
    So when the Switch Step is executed are both the variables filled with the required values (I am not able to understand your query clearly)....if both the variables are filled then in the condition editor you can define the condition based on both the values (use And...it will be Insert Expression ...for executing Branch 1)
    It will be something like var1 = I And var2 = S .....while selcting the left operand select the appropriate message.
    If you are on 7.1 then create two condition variables representing var1 and var2.
    Similarly when defing condition for Branch2 it will be only var1 to be used.
    Regards,
    Abhishek.

  • Reg:Whether to use BPM or not when the channels are controlled externally

    Dear All,
    My scenario is File to File and for this the channels are controlled  externally.
    This is achieved through the  Abap proxies to Http receiver scenario, where udf is being implemented for this.
    UDF:
    DynamicConfiguration conf = (DynamicConfiguration) container.getTransformationParameters().get(StreamTransformationConstants.DYNAMIC_CONFIGURATION);
    DynamicConfigurationKey trig = DynamicConfigurationKey.create("http://sap.com/xi/XI/System/HTTP", "UrlParamOne");
    DynamicConfigurationKey trig1 = DynamicConfigurationKey.create("http://sap.com/xi/XI/System/HTTP", "UrlParamTwo");
    DynamicConfigurationKey trig2 = DynamicConfigurationKey.create("http://sap.com/xi/XI/System/HTTP", "UrlParamThree");
    DynamicConfigurationKey trig3 = DynamicConfigurationKey.create("http://sap.com/xi/XI/System/HTTP", "UrlParamFour");
    conf.put(trig,action);
    conf.put(trig1,party);
    conf.put(trig2,service);
    conf.put(trig3,channel);
    return "";
    If the value of the Action is START then the existing communication channel should be stopped and restarted  again .
    If the value of the Action is STOP then the stop action should be performed.
    For this I have implemented two mappings  and condition is being given in Interface determination
    so as to have the splitting of messages when the start action is performed.
    Can anyone suggest me how to implement this by using a single mapping or this could be achieved only through BPM?
    Thanks in Advance,
    Lavanya .B
    Edited by: Lavanya Balanandham on Aug 4, 2010 2:24 PM

    Hi ,
       My requirement is ,I need to merge two mappings into one mapping without using BPM.
    My File to File scenario communication channel is controlled externally by using Proxy-to-Http scenario.
    For this I have used two mappings say when the value for the action is START then the File receiver communication channel should be stopped(which is already polling) and again the Action START should passed to the Receiver File Channel to start again using the proxy-http scenario.
    Now I need to merge the two mappings into a single mapping so as to perform the above stated flow without using BPM.
    lavanya

  • Reg Alerts using with & without BPM.

    Dear Experts,
               The flow of the inbound message is Customers>( Seeburger Adapter which receives the message and passes to the integration of XI CENTRAL HUB) CENTRAL XI HUB> XI HUB-->SAP System and the out bound is viceversa.
    1. A Message failed with the Mapping Exception Error in the SXMB_MONI of the CENTRAL XI Hub. An alert should be raised for thsi error in the form of email..how this can be done WITHOUT BPM ? or WITH BPM ?
    2. How to integrate This type of alerts with with Tivoli to raise a ticket with the support team ?

    Hi,
    How you checked acknowledgment for IDOCs
    https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/f6d2d790-0201-0010-9382-b50b499b3fbe
    For proxy acknowledgment please refer to help.
    Best regards,
    Wojciech

  • Reg: Blocks in BPM

    Hi,
    We have a scenario where the requirement is to make 'n' number of transactions with SAP System using the Block in BPM. When the number of branches are around 700 the scenario works fine. But if we have more than 1000 branches the whole scenario fails. We are not able to start the proces again in BPM also.
    Regards,
    Venkatesh

    Hi,
    >>> is to make 'n' number of transactions with SAP System using the Block in BPM
    why do you need n numeber of transactions ?
    do you use IDOCs ?
    if you use IDOCs you can create number ot transactions (documents)
    with one call - wihtout the block - idoc bundling - described in my book
    <a href="/people/michal.krawczyk2/blog/2006/10/11/xi-new-book-mastering-idoc-business-scenarios-with-sap-xi"><b>Mastering IDoc Business Scenarios with SAP XI</b></a>
    Regards,
    michal
    <a href="/people/michal.krawczyk2/blog/2005/06/28/xipi-faq-frequently-asked-questions"><b>XI / PI FAQ - Frequently Asked Questions</b></a>

Maybe you are looking for

  • Podcast syncing iOS6 (don't want to go to 7 to lose it completely)

    This may be an unfixable problem due to changes in iTunes itself but maybe someone can shed some light. First, I've been reading all about how terrible the podcast app is and that it is the only option for iOS7 now. I used the podcast app for a coupl

  • Typewriter Text Color Acrobat 9 Pro

    I have a pdf with many typewriter text boxes in it.  I now need to change those font colors...is there a way to do it all at once without going box by box to change the font color?

  • [HELP!]open a pop-up and lock the window

    Hi guys, the thing is : In a page (call it P1), when click a button there will come a pop-up page(P2), when P2 shows, P1 is locked, user can not perform any action on P1. the point is, P2 is not a real pop-up, it's inside the same window as P1. just

  • JDBC - CallableStatement - Error in Accessing Stored Procedure of MS SQL

    Dear Friends, The following is the code to access a stored procedure of MS SQL Server 7.0 sp4,           try                CallableStatement cstmt;                ResultSet rst;                cstmt = connection.prepareCall("{call backupdb[?,?]}");

  • Seeking workarounds to give effect of INSERT...SELECT...RETURNING

    What is the most efficient way to get record counts from subqueries within an INSERT INTO () SELECT () statement on Oracle 11g? I feel like I'm too close to the code to see the obvious answer here. Background: I am building a dynamic data quality tes