hi,
I have created a Value contract and had used milestone billing plan and assortment module.
Problem
i have create a release value contract (release order)  with ref to the Value contract and done billing and also cleared the accounting.
But in the Value contract, status for the each milestone in the billing plan is always in A (Not yet processed) even after clearing of accounting.
Regards
Sivaraman

The only option i can think of is you have to check copy control settings for your contract order type and billing type and see if update document flow button is checked.
Or you have to detailed analysis in configuration to point out the problem.
Basically everything is working but only status is not getting updated. Something is wrong as document flow is not getting updated.

Similar Messages

  • Reg:  User Manual for Value contract

    Hi ALL
    Can anybody send
    usr manual for Material related value contract with milestone billing
    Regards
    Rams

    Hi,
    just mark your question as 'Answered' and give some comments.
    Thanks.

  • Value Contract-Milestone Billing

    Hi Friends,
    I want to know about the value contracts with milestone billing.
    How we use milestone billing in value contracts.
    with regards
    Azeez.Mohd

    Hi Azeez,
    Please go thru following thread.
    [Milestone billing|https://forums.sdn.sap.com/click.jspa?searchID=21566193&messageID=4014303]
    regards,
    Abhee.

  • Billing Request in Value Contract Document Type

    Dear Friends
    In Value Contract Document Type WK1 in [VOV8] Billing Request is IRC:- Debit Memo Request for Contract
    What is the use of it how i will see it is effect in standard business process
    Regards
    Arun

    The billing request is your call off sales document for the value contract e.g. USD 2,000 contract for which initially only USD 500 is billed, thus the debit memo request. The process applies to a situtaion where there is/are partial or staggered releases of contracted goods or services.

  • Missing billing plan value in header of contract

    We are using billing plan, but we don't see the value in the header for the contract.
    Though we can see the correct values of the billing plan on item level. Are there any customizing steps we have overlooked?
    Please take a look at picture
    <a href="http://img144.imageshack.us/img144/1849/missingbillingplanxd8.jpg">Missing billing plan value</a>

    Hi,
    We can maintain plans at header level and item level.
    If you enter billing dates/values at item level, system will not copy values to header.
    If you enter billing dates/values at header level, it will copy values to item.
    Eg.
    1) Item level billing plan
    You have 2 items in one sales order, and maintained different  billing dates and values for each item.System will not copy values to header.
    For same scenerio :
    2) Header level billing plan
         If you maintain blilling dates at header level, system will automatically distrubute dates and values  for both the line items.
    Best Regards,
    Chandrasekhar.S

  • Release orders for value contract

    Hi Folks,
    I have question on value contract.
    Customer contract is fullfilled by issuing orders against the contract. When a release order is created for the contract, the system automatically updates the released values in the contract. The release order value is calculated from the total of the open order and delivery values, plus the value that has already been billed to the value contract. System checks this value with "Outline agreement target value" in value contract and issues warning or error message depends on configuration settings in value contract item catagory.
    We have business scenario where system has to check net value of value contract rather than checking "Outline agrrement target value" in value contract. Because we offer some discounts to customer in value contract thus net value of the contract differs from agreement value. So that system will issue error message when release order value exceeds net value of value contract.
    Is there any customizing settings available to meet the requirement?
    Awaiting for your inputs.
    Regards,
    Prabhaharan

    Hi,
    In transcation VTAA at item level have your own cory requirment code which will calcullate net value of the doc, hope this works out
    regards
    sriky

  • Value Contracts for Credit note

    Dear Friends,
    Can we create Value contracts for Credit note processing?
    Please refer to the below scenario:
    I have certain budget that needs to be distributed to some of the customers depending upon the claims (Credit Notes).
    This budget is included in Value contract and values are released through orders (Credit note order). I specify total budget in Target Value of Value contract and as and when the credit note is created, the value of credit note is updated in Released Value.
    But when I create credit note, order value is being captured in Negative in released value of Contract document.
    If total target value is utilized, I need to restrict the user to create more credit note orders with reference to Value contract.
    Can anyone please help with the scenario.
    Regards,
    Praveen.

    Dear Sri,
    These are the steps to to configure the output type for credit note.
    SPRO>IMG>Sales and Distribution>Basic Functions>Output Control>Output Determination>Output Determination Using the Condition Technique-->Maintain Output Determination for Billing Documents
    -->Maintain Condition Tables
    -->Maintain Output Types
    -->Maintain Access Sequences
    -->Assign Output Types To Partner Functions
    -->Maintain Output Determination Procedure
    -->Assign Output Determination Procedures
    Here you just copy the standard output type RD00 then rename it according to you, then assign the Z form for that output type.
    Maintain condition record through VV31 transaction with your credit note document type.
    I hope this will help you,
    Regards,
    Murali.

  • Quantity / Value Contract

    Hi,
    I have the following queries on quantity / value contract :
    1)Is it possible to reflect quantity as well as value in the same contract and have control on both these parameters at the same time, as per my requirement? I would like to know much quantity and value is left there in the contract , ( i.e. qyt and its equivalant value and vice versa )  and if any of these two parameters exceeds the quantity /value of the contract, while making order,  it should pop a message and stop me to proceed further.( In item category, it is for any one parameter at a time i.e quantity or value . My requirement is for both at the same time for the same contract ).
    Please let me know the settings for this.
    2) How to see how much has been billed against a particular quantity / value contract, and how much balace is left. also how many contracts are open ? Is it by VA43 ?
    Thanks & regards,
    KVinod

    Hello,
    You have to decide what type of contract is required ?
    If the contract value exceed , it will not allow to create sch.agr ? Still if you want a pop-up , use user exit and control it.
    Thanks
    Rk

  • Value Contract - Pricing

    Hi,
    On what basis the pricing is carried out in the case of value contratcs.....With Billing Plan
    IF The billing document is carried out with reference to the COntract then what will be the pricing carried out in the billing....
    What is the business process requirement under which the Billing document is created with reference to the Contract.....??
    Under the contract processing.... if release orders are created and then the billing based on the release order then in that case what would be the pricing in the billing ???
    Regards
    Edited by: SAP2020 on Apr 21, 2010 2:44 PM

    Hi Krisn,
                   What I have said is a way to maintain the condition type for the discount to be applied. If you want the discount to be applied only when the sales order gets raised from Value contract. The easy and alternat way is go to "OVKK" and assign a pricing procedure without this discount type to the sales area and the customer pricing procedure and the contract pricing procedure. And for the sales order which is a followup of the value contract assign a different pricing procedure with the discount condition type. But you have to copy the standard order type "OR " and rename it and maintain this as an order type for the value contract and document pricing procedure for this should be some  customized one. Goto "VOK0"  and Create a new docu pricing procedure and assign this in "OVKK".Maintain the copy controls and pricing type shopuld be "C". Kindly please let me know If you need any more help on this.
    Regards,
    Ram Pedarla
    Edited by: RamPedarla on Mar 12, 2010 1:51 PM

  • Value Contract- Order- Invoice

    Hi
    I have Created Value Contrace of Service material.
    I am Creating SO with ref. to Value Contract.
    Since material is Service material it doesnot have "loading Group" in material Master, so it Neither determine Shipping point in  Sales Order nor allows me to enter manually.so SO is incomplete & doesnot allow to Process.
    There is no Delivery involved.Is Plant & Shipping Condition necessary in Processing SO-> Invoice?
    Reg,
    Antaa21

    Hi,
    This problem is due to the Incompletion procedure assigned to your Sales order type.
    At Incompleteness procedure, we add only mandatory or minimum fields (data), that user has to fill in the sales order without which system should not allow to save the sales order.
    As this incompleteness procedure must be assigned keeping the business requirement for finished products.
    Hence, you will need to copy the existing Sales order Type and create a new or Z/Y sales order Type for Service Materials.
    For newly created Sales Order assign new "Incompl.proced" and don't include the fields used for Finished Products.
    IMG->Sales-> Basic Functions->Log of Incomplete Items.
    at VOV8-> sales order type-> you will need to assign this incompleteness procedure
    Thank You.
    RB

  • Error in value contract

    hello gurus,
    I have created value contract and i was released that contract with reference  to the document number
    and  i was billed for the amount and i released to the accounting and payment also received but the problem is the contract document ovevral status is open
    can you pls tell me the solution to close the contract .
    shameer

    we got it

  • Mile stone billing for  service contract

    Hi gurus,
    can you help me for the following:
    i want to configure mile stone billing for service contract in my client business process,
    can any one send me the complete configuration process steps for mile stone billing.
    I'll reward you full marks,
    Thanks in advance
    nitchel

    Hiya...
    Billing Plan for Milestone Billing
    Milestone billing means distributing the total amount to be billed over multiple billing
    dates in the billing plan.
    As each milestone is successfully reached, the customer is billed either a percentage of
    the entire project cost or simply a pre-defined amount.
    During sales order processing, the system determines from the item category whether a
    billing plan is required and, if so, which type of plan
    The type of billing plan that is determined at this point is set up in Customizing and
    cannot be changed in the sales document.
    Billing plans for periodic billing and milestone billing plans for project-related milestone
    billing have different overview screens so that you can enter data relevant to your
    processing.
    For example, for milestone billing, you must be able to enter data to identify the
    individual milestones.
    IMG configuration requires :-
    1.  Maintain billing plan types for milestone billing in OVBO.
    2.  Define date description in SM30 - V_TVTB.
    3.  Maintain Date Category for Billing Plan Type IN OVBJ.
    4.  Allocate date category in SM30 - V_TFPLA_TY.
    5.  Maintain date proposal for Billing Plan Type in OVBM.
    6.  Assign Billing Plan Type to Sales Documents Type in OVBP.
    7.  Assign Billing Plan Type to Item Categories in OVBR.
    8.  Define rules for determining the date in OVBS.
    Milestone billing is typically used for billing projects, such as plant engineering and
    construction projects. Such projects often include a series of milestones that mark the
    completion of different stages of the work. In the SAP R/3 System, milestones are defined
    in a network along with planned and actual dates for the completion of work. The milestones
    are also assigned to the billing dates in the billing plan.
    Each milestone-related billing date is blocked for processing until the Project System
    confirms that the milestone is completed.
    Delivery-relevant order items for which a milestone billing plan applies are billed on the
    basis of the requested delivery quantity and not on the total of the confirmed quantities.
    The connection between the project and the sales document item is made in the individual
    schedule lines of the item. Each schedule item can be assigned to a network in a project.
    To display the project-related data for a schedule line, proceed as follows:
    In one of the overview screens of the sales document, select
    1.  Item -> Schedule lines.
    2.  Mark the schedule line and select Procurement details.
    The following figure shows an example of milestone billing where only the Contract have
    been billed :
    Order  Item  Turbine    100,000
    Billing Plan
    Billing date Description    %  Value  Billing Block   Milestone   Billing Status
    01-10-94     Contract      10  10,000      -             x           x 
    01-03-95     Assembly      30  30,000      x             x          
    01-04-95     Maintenance   30  30,000      x             x
    01-05-95     Acceptance    30  30,000      x             x
    01-06-95     Final invoice ..    ..        x
    Network/Activities
    Milestone    Estimate      Actual
    Assembly     01-03-95      01-03-95
    Maintenance  01-04-95     
    Acceptance   01-05-95
    For each billing date in a milestone billing plan, you can specify whether the billing
    date is:
    1.  fixed
    2.  always updated with the actual date of the milestone
    3.  updated with the actual date of the milestone, if the date is earlier than the
        planned billing date for the date
    Keep Sapping
    Regards

  • How to create release order for value contract?

    dear experters,
    I create a value contract by T-code:va41, order type"WK1".I set a Assortment module to this order and mateirl "WKM1" to  it.
    then I create release order by T-code:va01 with refrence to this value contract,but it set the material "WKM1"  to the sales order, and I can't modify this material! I want to put another material which belong to the assortment module in the value contract. I want to know how.
    thanks.
    Best regards
    lance

    Assortment Module for Value Contracts
    This function enables you to define a list of materials that can be released from a value contract. Materials can be assigned to more than one assortment module.
    An assortment module is an entry tool and can be called up from the value contract. It is valid for a certain time period.
    If you delete a material from the assortment module, to which a value contract refers, you will be unable to release that material.
    In the value contract, only materials with the same sales organization and distribution channel as the value contract can be taken from the assortment module. All the other materials in the assortment module are not displayed in the value contract.
    To fulfill both these requirements, two types of value contracts are offered in the standard system:
    Value contract type WK 1
    You can specify a product hierarchy or a assortment module for value contracts with contract type WK 1. The system will always propose this type of contract, if you want to create a contract for several materials or a certain group of materials. All the materials in the relevant assortment, or belonging to the specified product hierarchy are then relevant for release.
    Value contract type WK 2 (material-related)
    You can create contracts for one material (usually configurable) with this type of value contract. A software company is an example of where this kind of contract is often used. There, a contract for the value of $500,000 is made with the customer for one specific software product.
    You can also agree on the length of the contract for this type. The contract duration can be agreed at item level and can be different from the contract duration specified at header level.
    You can store special price agreements for the value contract. These price agreements can then be used at any level. For example, a value contract can contain prices for individual materials, or discounts that are valid for every released material.
    Release Orders
    The customer fulfills a contract by issuing orders against the contract. The contract does not contain any exact dates for deliveries, so you need to create a sales order to release against a value contract.
    When a release order is created for the contract, the system automatically updates the released values in the contract. The release order value is calculated from the total of the open order and delivery values, plus the value that has already been billed to the value contract.
    The system also updates the released value for subsequent changes (for example, overdelivery of contract release, price changes in the billing document, partial deliveries, returns, rejection of order items, cancellation or reversal of orders, deliveries or billing documents).
    You can create a release order in any currency. The system automatically converts this currency into the one agreed upon in the value contract on the pricing date for the contract release order.
    Creating Assortment Modules for Value Contracts
    Procedure
    To create an assortment module, proceed as follows:
    1. From the initial screen choose Logistics >Sales and Distribution >Master data.
    2.Choose Products >Value contract - Assortment module > Create.
    You will then be in the Create assortment module: Initial Screen.
    Module type 6 is defined for the value contract.
    3. For external number assignment, enter a module number.
    You can then use existing modules as a reference by entering the name of the module under reference.
    4. Choose Enter.
    5. Enter a short description for the module.
    6. Enter a validity period for the product proposal.
    During a release, the system checks if the release date lies within the validity period.
    7. Create the materials that you wish to assign as items to a module.
    You can display a list of materials as a product proposal, which you can then copy into the assortment module. To do this, choose Suggest material, enter the selection criteria in the subsequent screen and copy the selected materials to the items. Use Edit > Delete item to delete the materials that you do not want to copy to the assortment module.
    8.Save your entries.
    Also Please check the copy control in VTAA
    Regards,
    Anbu

  • Billing plan value with reference to start & End date

    Hi Experts,
    Request your earliest support for the achieving the below requirement.
    Scenario:We have Billing plan set up for the all contracts - valid for one year.Monthly rental amount for each contract item is maintained as base price for the contract. When the billing plans starts in the middle of the month then, the billing value need to be calculated only for the relevant no of days in 'settlement' and 'To' date of billing plan. How to achieve this?     
    Net value of the contract item
    Net value of the item   102.00  GBP     
    Tax  for the item         15.30          
    Net value of billing plan for the contract item                                                                                .
    Item Net value  408.00                GBP                                                         
    Billing plan and contract validity details for contract item                                                                               
    Billing Plan Type - PM- Monthly in Advance                                    51- Monthly on First of                                                   
      Contract Start date       07/15/2009 (02)-Contract Start Date        Billing plan Dates from  07/16/2009  02                                    
      Contract plan End date 10/14/2009 (09)-Contract End Date          Billing plan Dates until 10/14/2009 09                                    
      Horizon -                                                                                Cal-Id - 01                                                                               
    Dates                                                                               
    Settlement       To                      Billing date         Bill.value    Crcy  Block  BillSt  Man.  Cor  PayT  DCat  Billing Ty  Price cal           
       07/16/2009      07/31/2009        08/01/2009         102.00       GBP   FA     A                                   01      ZC           01 -
    > This needs to calculated upon net value for 16 days only   
       08/01/2009      08/31/2009    09/01/2009              102.00       GBP   FA      A                                 01      ZC            01--->           between 07/16/2009 to 07/31/2009=102/31*16 = 52.65
       09/01/2009      09/30/2009   10/01/2009               102.00       GBP   FA      A                               01      ZC            01                  
       10/01/2009      10/14/2009    11/01/2009              102.00       GBP   FA      A                               01      ZC            01                                                                               
    Please suggest if this can be achieved through Billing plan configuration or any user exit that can be used to resolve the issue.
    Thanks,
    Priyabrata

    as far as I know there is NO such standard report.
    you would try to build sap query based on VBAK/VBAP using VBFA checking LIKP/LIPS and VBRK/VBRP...
    but you may request abaper for more professional report with MKPF/MSEG and BKPF/BSEG

  • Can we have UPK on Oracle Project billing ie for Contract Projects???

    Can we have UPK on Oracle Project billing ie for Contract Projects???

    Iin the pop up I need to have only one field, say Search field
    - Create the ViewCriteria for the LOV ViewObject, consisting of that one field you want to search.
    Then, in the List UI Hints for LOV VO, adjust 'Include Search Region" to the criteria you just created in the previous step.
    +On entering a value in Search field and clicking on 'Search' button it should try to match the value in empid, projectid and deptid. It should return all the records wherever these values match.+
    - Create two bind variable for LOV VO, and create another one ViewCriteria for LOV VO, consisting of another two fields attributes (empid, deptid).
    In that criteria, set attribute values to appropriate bind variables.
    Them, when you place a View Accessor for that LOV, click 'Edit (selected View Accessor)' button.
    On the dialog box that appears, move the View Criteria you just created from Available to the Selected list.
    At the same dialog box, you need to set Bind variable values.
    Assign them the values of the EmpId, DeptId respectively.