Reg PM Order Confirmation(IW41)

Hi,
  In PM Order internal Jobs time confirmation(IW41), i am in need to give the Personnel No. Can anyone please explain me where i have to configure the Personnel No in SPRO.? & How to link the personnel no field in IW41 page during time confirmation?

Hi,
For this you need to go to sproplantmaintenance&cutomer servicesmaintenanceandserviceprocessingservice confirmationcompletion confirmationset screentemplates for completion confirmation
here you create a new profile and the settings as below
choose header data as 3--customer service
screen area 1    1-Times for order operation
screen area 2    3-Goods movement
screen area 3     5-measurement or counter readings
remaining screens as you wish or keep it 0--not filled
and active push buttons check time, goodsmovement and measurement or counter readings.
after doing these settings save your profile and then go to iw42 screen
go to Extras-settings--give your new profile and save afterwards you will get your desired screen.
regards
satish

Similar Messages

  • Fm or bapi for service order confirmation (iw41)

    hi,
    Can you please tell me a fm or bapi for service order confirmation in iw41

    HI dido...
    you can use CRM_ORDER_MAINTAIN.
    you can process any document type you want
    regards
    Marco

  • Reg: "Production order confirmation details" table name..

    Hi,
    what is the table name for the production order confirmation details..
    Regards,
    Pavan.

    Hi
    It is the
    <b>AFRU</b> table
    <b>Reward points for useful Answers</b>
    Regards
    Anji

  • Reg process order confirmation cancellation

    Dear all,
    what is the table entry generated in AFRU table when we cancel a confirmation of a process order
    i want to know in which field we geta entry and how can we identify that a particular confirmation number is cancelled
    Thanks in advance
    Regards
    venkat

    Hi,
    In AFRU table, there is the STZHL field (Confirmation counter of cancelled confirmation)
    It's the confirmation counter of the original confirmation which was cancelled by the current confirmation.
    For example:
    Confirmation    Counter     STZHL
    1000                 1                blank
    1000                 2                1 --> this means that this is the cancellation entry for the line above.
    1000                 3                 blank
    I hope it helps.
    Regards,
    Marcelo

  • PM Order Confirmation using Personnel's Cost Center and Activity Type

    Hi All,
    Is it possible to have PM Order confirmation (IW41) using Cost Center and Activity type from Personnel instead of default from Work Center?  If it is, can it be done with some configuration or user exit?  Please advise.  Thank you.
    Dai

    Hi friend,
    Order confirmation will be done for order operations.While doing confirmation we post the actual work done by the repective work center and respective activity type assigned to the same workcenter.
    But these activity types are assigned to cost center for cost calculation.confirming the respective operation in maintenance order through workcenters gives the report of planned work and actual work done by the respective workcenter.
    We cannot confirm the operation using costcenter and activity type directly through transaction IW41.
    If you want to develop new confirmation screen and making confirmation of the respective order operation with only costcenter and activity type fields, you can do it .
    Regards,
    Pardhreddyc
    Edited by: Pardhreddyc on May 17, 2011 12:45 PM

  • Goods Movement on Order Confirmation

    Hi all,
    Whenever i issue a material while doing Order confirmation (IW41: Using goods movement option) , the material is issued but its cost doesnt get populated on the maintenance order. I guess i am missing some configuration end but can anybody guide me or give me hint where is the root cause lies of this problem.
    Why the material cost is not getting populated on the maintenance order.
    (Note: I am using my own Order Type not the standard one)

    hi
    I hope this is the problem in ur config
    Plant Maintenance and Customer Service - Maintenance and Service Processing - Completion Confirmations - Define Control Parameters for Completion Confirmations
    If u have tick at Materials, remove it
    It will give only plan cost, not the actual cost
    If u dont use this tick, you can do goods movement from iw41 and the cost will be calculated in the actual cost
    - Pithan

  • Document number-PM order confirmation by IW41

    Hi,
    For PM work order confirmations, I want to fetch the document number. In which table can I find the document number stored? I found it in AFRU-CATSBELNR, but only for CATS confirmation. For confirmation of work order through IW41 transaction, is there any table where I get the document number?
    Thanks and Regards,
    Jegashree

    Hi Jane,
    I am getting the confirmation number.but not able to fetch the document number (I need this document number to fetch the cost per line item/confirmation from COEP table) Does the PM order confirmation through IW41 transaction have any document number?
    Thanks

  • ABAP Dump :  IW41 Transaction : PM Order confirmation  save

    Dear all .,
    System - Upgraded ECC 6.0 ( from 4.6C)
    Testing in QA .
    Transaction - IW41 : Create PM Order Confirmation>Tick Final confirmation>saved
    Runtime Errors         SYNTAX_ERROR
    Date and Time          06.10.2007 16:41:09
    Short text
         Syntax error in program "RMCX0013 ".
    What happened?
         Error in the ABAP Application Program
         The current ABAP program "SAPLMCS0" had to be terminated because it has
         come across a statement that unfortunately cannot be executed.
         The following syntax error occurred in program "RMCX0013 " in include "RMCX0013
          " in
         line 0:
         "The program "RMCX0013" is not Unicode-compatible, according to its pro"
         "gram attributes."
         The include has been created and last changed by:
         Created by: "DDIC "
         Last changed by: "DDIC "
    Please help
    Thanks & Regards ., GSD

    Hi Guruprasad,
    RMCX0013 is generated by a LIS structure. I don't know what's the reason in detail, but I hope if you re-generate your LIS structures, this can be overcome.
    RMCX0013 (or Forms in this program) will be called dynamically (see list of active programs in the dump). If the calling program is active for unicode-check and the called not, this leads to incompatibility.
    Regards,
    Clemens

  • Exit/Badi for to Stop PM Order Confirmation using IW41

    Hi,
    My Requirement is while doing PM Order Confirmation based on Order and Operation in IW41, system needs to check WBS element status.
    If WBS element status is closed, It has to stop the Order Confirmation.
    Kindly suggest any Exit or Badi for this.
    Thanks in advance.
    Regards,
    Kumar

    check below thread it has all the badis and exits summed up for iw41:
    http://scn.sap.com/thread/1121303

  • BAPI/ FM for Order Confirmation Tcode IW41

    Hi Experts ,
    I want to do auto order confirmation  using the Tcode iw41, is there any BAPI or Function module available to the order confirmation  , Please suggest if any other way we can do
    Babumiya Mohammad

    Hi,
      Please check the following BAPI's.
       BAPI_ALM_CONF_CREATE
      BAPI_ALM_ORDER_MAINTAIN       
      BAPI_ALM_NOTIF_SAVE
    If you want any other function module please search BAPI_ALM *   like that.
    Regards
    Pugal

  • Reg:Bapi for mass creation of production order/confirmation

    Dear Experts,
    I wanted to know with the following BAPI is it possible to create Multiple production orders for different semifinshed Materials along with material availability check and other functions similar to CO01 transaction.
    I knew there are standard transactions for mass confirmation for production orders. But i need a confirmation on this BAPI . As i am planning to go-ahed with ,mass creation of production order creation / Order confirmation in single custom transaction.Need back flush activity even supported.
    BAPI_PRODORD_CREATE to create the orders.
    BAPI_PRODORD_RELEASE to release the orders.
    BAPI_PRODORDCONF_GET_TT_PROP to get the default data for the confirmation.
    BAPI_PRODORDCONF_CREATE_TT to ost the confirmation of production order.
    Along with this BAPI do i need to commit any other BAPI to carry out back flush for components.
    Need your suggestions to take it further.
    Regards,
    Daya.

    Dear SAP Daya
    If the issue has been solved, please close this thread.
    You have already mentioned that the issue has been resolved, thefore, you should not ask for help on another thread before closing this one, as it looks like you are trying to force people to answer your threads.
    Users are always trying to answer as many threads as possible on good will we don't need this kind of "incentive".
    Please read carefully the The SCN Rules of Engagement, especially point 8:
    Be responsive. If an SCN member has answered your question, please mark the answer as "helpful” or “correct”. Mark the discussion as “answered,” so that other members can find the answers more easily
    Also, I checked your old threads and I could observe that there is only one closed. Please review your old threads and close those already solved.
    BR
    Caetano

  • PM order confirmation cancellation -reg

    Hi ,
    Using IW45 transaction code , we can do PM order confirmation cancellation by giving one by one order . Is there any other T code where we can give multiple orders as input and do confirmation cancellation for multiple orders at a time ? or LSMW is the only way ?
    regards,
    Madhu kiran

    Hi,
    Go to T.Code IW47, execute with inputs as the order nos/ confirmation nos  whose confirmation you want to cancel and execute. You will get a list display. Then select the confirmations you want to cancel (multi selection) and click on cancel button available at top. System will give a warning msg. Just ignore and cancel all the documents.
    Else you may also go for an LSMW program.
    Regards,
    S.Basu

  • Any function module or BAPI for PM order confirmation

    Hi all,
    I'm trying to confirm a PM order (IW41) background. Is there any existing BAPI or FM for me to do that? Thanks in advance.

    Mil,
    check this
    BAPI_PRODORDCONF_CREATE_TT,
    below are other ones which may use for you...
    BAPI_PRODORDCONF_CREATE_ACT Enter Activity Confirmation
    BAPI_PRODORDCONF_CREATE_HDR Enter Order Confirmations
    BAPI_PRODORDCONF_CREATE_TE Enter Time Event Confirmation
    BAPI_PRODORDCONF_CREATE_TT Enter Time Ticket Confirmation
    BAPI_PRODORDCONF_EXIST_CHK Existence Check for Confirming Production Order
    BAPI_PRODORDCONF_GETDETAIL Detailed Data for Production Order Confirmation
    BAPI_PRODORDCONF_GETLIST Confirmations List
    Don't forget to reward if useful....

  • Mass reversal of work order confirmations

    Hi all,
    Can we do a mass reversal of work order confirmations which we do through IW41 transaction,instead of reversing the confirmations one by one, if so please explain how.
    Thanks & Regards,
    Jegashree

    Dear,
    There is no mass confirmation cancellation Txn available in standard SAP.
    Use
    BAPI_ALM_CONF_CANCEL     Cancel confirmation for maintenance/service order
    Hope it will help you.
    Regards,
    R.Brahmankar

  • Service order confirmation/completion

    Hi,
    Can anyone tell me what exactly is meant by service order completion ( flag order) and confirm ( IW41). At what state of the business process do I need it.
    To my understanding a service order is complete after billing and confirmed once customer approves.
    Please throw a light on this.
    Thanks
    Sam

    Hi ASHIsh,
    We do not have the customer service module or the service management but we have the confirmation of service in the document flow. The flow is as follows. standard order ( OR ) - > delivery ( LF ) - > Handling unit - > Confirmationof service. I checked the document flow table VBFA and I see that these confirmation of service is for items which are of item category TAP ( sales BOM header ). That is what I concluded that it shows up for TAP since this item is not pickable ane hence not packable. And we have this come up for all the sales BOM deliveries where there is an item category of TAP for sales BOM header. Still if any one can please throw some light on this that would be greatly appreciated.
    Service Order:Short-term agreement between service provider and service recipient, in which one-time services are ordered by the service recipient and resource-related billing performed upon completion.
    The service order is used to document service and customer service work. In particular, you can use the service order to:
    Plan services specifically with regard to usage of material, utilities and personnel
    Monitor the execution of services
    Enter and settle the costs which arise from the services
    The data for the service order is entered in the history and is important for evaluations and future planning.
    You can also create a one-time customer in the order and transfer the data, for example, to the sales order.
    A service order contains operations that describe the individual work steps. An operation can be divided into sub-operations for greater detail.
    Spare materials and utilities, which are required for service work, can be planned in the operation.
    T.Code: [IW41]
    Path: Logistics -> Customer Service -> Service Processing -> Confirmation -> Entry -> Individual Confirmation.
    After a service order is entered in the system, a service activity would be carried out for the customer. Using this option we would enter the person who carried out the activity, the time taken, the material used with their quantity. Further a billing request would be raised based on these details.
    Reward points if iit helpful
    Cheers,
    Govind.

Maybe you are looking for

  • Windows 8 will not activate with new SSD (second) hard drive

    I added a new SSD drive in the second hard drive bay. I used the HP restoration media to install Windows 8 on the new SSD drive. Windows 8 will not activate. After spending 90 minutes on the phone with HP support (and paying $150), they told me to co

  • Can not install a plugin in CS4

    hi there i tried to install three plugins on my cs 4 (using x64 SEVEN OS), it finished installing but there were no sign of that plugin in filter menu ... i tried "Imagenomic Portraiture Plugin v10.1008" but there were same reslut ... the point is th

  • ATI Rage Pro 3D

    Hi, I just installed Archlinux on my old PC and I'd like to configure the graphic card properly. With the default settings it works but I see flickering while moving the windows on the screen. Searching the web I found this wiki page, that refers to

  • Data Guard - MRP stuck issues on a physical standby database

    Hi, Oracle 11.2.0.3 DG running. When i do a switchover the physical standby database has error with following error ARC0: LGWR is actively archiving destination LOG_ARCHIVE_DEST_2 ARCH: Archival stopped, error occurred. Will continue retrying ORACLE

  • Air Installation Error

    I get the following error when trying to install Adobe AIR on a stand alone machine. How can I get around this? ADOBE AIR---Sorry, an error has occurred An error has occurred while installing AdobeAir. Installations may not be allowed by your adminis