Replenishement directly from external supplier to production supply area

Hi Experts
I'm new in WM,
We have a big tanks for oil which will be used by the production as a component during the production process, these tanks is in the PSA "Production supply Area" and the supplier provide the oil directly to PSA ( not throug the Warehouse) so these tanks are under the production control.
we need to implement this process in SAP.
we need the stept by step implementation of that request
your support is highly recommanded for us
Many thanks in advance
Olfa

There are many ways to do your requirement. One among them is, Implement KANBAN Process using External Replenishment.
Evaluate options using PK01 .. External proc.
Regards,
Sathish

Similar Messages

  • I am trying to reinstall CS3 from a download I bought several years ago, and it is saying my serial number is invalid.  I am taking the serial number directly from the list of products on my Adobe account.  Please advise

    I am trying to reinstall CS3 from a download I bought several years ago, and it is saying my serial number is invalid.  I am taking the serial number directly from the list of products on my Adobe account.  Please advise

    Uninstall and try the Adobe Creative Suite Cleaner Tool before reinstalling - it helps resolve installation problems for CS3 thru CS6 and for Creative Cloud
    http://www.adobe.com/support/contact/cscleanertool.html

  • How can I change the source file so it is direct from external hard drive?

    I am trying to make a movie on imovie of a snowboarding trip that I went on, there is around 80 to 100 gig of mp4 movies that will not fit on my computer that I have stored on my external harddrive. I had the movie half finished then found I could do no more as I had no space left in my mac. I had to delete everything and start again but I'm not doing this until I can find a way of changing the source file so I can take them direct from my external hard drive as to not use up all my computers available space. I have moved imovie to my external hard drive but it still tries to read from a movie file on my mac, how can I change that so it will read from a source file on my external hard drive, is it possible?? Can someone help me??

    Hi Bengt, Thanks for your input, much appreciated.
    I have a WD 1TIG hard drive and are using usb connection, is it possible to use fire wire with these? I have had trouble with a lot of the videos I Imported, once they downloaded the file in the viewer window showed up blank and when I mouse over them it places a picture of another file in the window and wont drag and drop into the movie window, like their corrupted or something? Had to delete just about all of them and start again. Also is it possible to select a bunch of videos in the viewer window as to change the dates to the correct dates? All I have been able to do is "select all" which is no help.

  • Cannot open image direct from external hard drive in Elements 9

    I have recently upgraded from Elements 8 to 9 and when I search for an image in my external hard drive (where all my photos are stored!) I used to be able to double click on it and it opened in E8. When I try this in E9 I get a message: 'Photo image on hard drive 2671Jpg is not a valid win 32 application' and I cannot access my photo. Even if I right-click to 'Open with Elements 9', I get the same message.
    How do i fix this?

    Hi
    Thanks for your suggestion.
    However , right clicking opens PSE 9 (not editor) and this does not work.
    Get the same message each time.

  • HT204409 Do I need a computer to enable my air printer or can I do it directly from my IPad and iPhone they are both 8.1,1

    DO I NEED A COMPUTER TO ACTIVATE MY NEW PRINTER OR CAN I PRINT DIRECTLY TO MY IPAD IT IS AN AIRPRINTER  CANON, AND IS COMPATTIBLE
    WITH MY IPAD

    The printer has to be connected to your network. That may require a computer to do that. Check the setup instructions for the printer.

  • Wm to production supply issue

    Hi gurus ,
    My question is simple but i am not getting the answer .  Pls guide me.
    In our system  Warehouse is not subjected to Production.
    Only packaging is done for the material & material despatch takes place.
    In short work flow is.
    TR>TO>Packaging -->TO confirm >TR( for dispach)>TO -->confirm TO
    Now i want to cleare the concept for production plant.( with PP module & without PP module)
      The material which are related to Bom I mean
    the Mtrl(for e.g. A,B,C,D) which we supply to Procuction supply (100 st.type) will be processed which will now form single finished(for e.g. F) componant. this mtrl now we want to Put in Final storage bin (from 100).
    Now my point is how the system will treate in WM point of view i.e. we know the material A,B,C,D is present in the 100 st. type & Finished componant F is not present in st type 100??
    pls.guide me.

    Hi,
    If you use mvt 201 for component consumption, the GI happens in IM and WM movement comes after that. /This scenario differs from material staging with production supply (storage type 100) where the WM-movements happens before GI (independently from GI)./
    In this scenario a negative quant comes to existence in 911 + bin (bin correspond to the cost center) and you fill up this negative quant form normal storage bin.
    GI > WM-movements is the sequence and GR can happen independently form this because there's no real order and this way there's no realcontrol.
    Disadvantage of this scenario is that you cannot control your component flow in WH if there are several "production order" in progress with reference to the same cost center - the same bin is used in 911.
    If you want to have stronger control you should implement PP modul.
    Regards,
    Csaba
    Edited by: Csaba Szommer on Feb 24, 2009 10:22 AM

  • Any issues pulling files from external partners using PI File adapter?

    I would like to know if there are any issues with pulling files directly from external partners using PI File adapter.
    We are estimating 60 communication channels to pull files from the external vendors (25 vendors). Polling for these communication channels will be done for every 5 minutes. We have a load of around 500 files per day with peak size as 50MB and average file size as 2MB. We are currently using PI 7.0 SP12.
    Did any one face any problems with respect to performance or any other issues?

    The volume as described would be handled with no issues.
    Memory tuning and threads tuning may be required - see this guide:
    http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/2016a0b1-1780-2b10-97bd-be3ac62214c7?quicklink=index&overridelayout=true

  • Sample received from external company for testing

    Hi folks,
    My client is a testing laboratory where they receive samples from external company. Tested results are sent back to the customer along with a test certificate and is billed for the testing carried out.
    I have two things to clarify
    1) how is the sample receipt to be taken
    2) How the customer to be billed with respect to the testing done
    Stringent requirement. Suggestions are most welcome
    Regars,
    Sravan

    For your 1st query ---
    Posting Goods Receipt for Serviceable Materials
    Use
    You post goods receipt to record that the serviceable materials have arrived at your plant. You can also record receipt of other goods such as loaner items.
    Prerequisites
    You require a repair order in which you have recorded the customer's repair request.
    Procedure
    Choose Logistics ® Customer Service ® Service Processing ® Order ® Customer repair ® Returns delivery.
    On the Create Returns Delivery screen, enter the following information:
    Number of the repair order in the Repair order field
    You can search for the appropriate repair order using the RMA number.
    Delivery type in the Delivery type field
    In the standard system, delivery type Returns delivery (LR) has been defined for this purpose.
    Number of the shipping point in the Shipping point field
    Choose Enter.
    You reach the overview screen where you can post goods receipt by choosing Edit ® Post goods issue.
    Save the delivery.
    For the 2nd part solution mentioned above is correct . You need to implement some of the CS module part here for your requirement.
    Regards
    Amol

  • How to edit files directly from server?

    I'm new to dreamweaver (CS5) and I'm really lost when it comes to editing files directly in remote servers.
    When you add a new site, you have to select a Local Site Folder. I dont mind that html editor saves auto backups to my computer, but I really dont want to download files from the server, edit them and upload them back to the server. In my work I always edit files directly over SFTP servers.
    After spending time configuring DW, I can now connect to the remote server, edit a file and save it to the server (I know that really the files are automatically downloaded to my pc and sent back when saved). The only problem with this is that everytime I open a file from server, I get this annoying prompt "Do you wish to overwrite your local copy of [FILE]?"
    How can I disable this for good, or is the dreamweaver just not the right tool to edit files directly from servers?

    Again, if you are doing it the easy way, you don't download files from the server to edit them.
    Always edit local files. Then upload them.
    When you open Dreamweaver, your Files panel should be showing Local View, NOT Remote View. That way you are working with local files.
    The way you're doing it here's what happens:
    1. You doubleclick a file in the Files panel (Remote View)
    2. Dreamweaver connects to your server and MUST download the file and related content (because the software IS NOT installed on the server and you CANNOT edit there)
    3. When the file is downloaded, Dreamweaver asks if you wish to overwrite the local file because when you save it before putting the file back, your OS will not allow two files of the same name in the same location and the file MUST be saved before you can put it back.
    4. You then put the file to the server, overwriting the original file.
    All of that can be avoided by simply opening THE LOCAL FILE and editing it. Then you put it to the server, and overwrite the original with the edited file.
    "What if someone else modifies a file on the server after I saved it, when I open and edit a local file, wont I just replace it when I upload it?"
    If multiple people have access to the same files on the server, you NEED to have collaboration software so that when a change is made it can be saved by EVERYONE who has access to the site. Something like LiveCycle.
    Without that your site will be a mess in no time because six different people (or more) will have six different copies of six different sites locally and they will all be working on it at the same time and it will end up like a Three Stooges movie where Larry, Curly and Moe are all cooking dinner and each adds the same ingredients at different times.

  • OKE Project Contracts - Generate Supplier invoice directly from Deliverable

    Dear All,
    In Project Contracts, Customer does not want to initiate requisition for the deliverables (Buy Contract - Non Item), instead they want Supplier invoice to be generated directly from the deliverables.
    The process flow which the customer looking for in Oracle project contracts is as follows,
    1. Create a Contract for Buy Intent - Non item deliverables
    2. Authoring the Contract
    3. Create Default deliverables
    4. IN DTS, based on the deliverables, system should generate Supplier Invoice directly with contract and Project references.
    Standard Flow - Contract Authoring > Default Deliverables > Initiate Requisition > Purchase order creation > Supplier Invoice > Interface costs to Projects
    Proposed Flow - Contract Authoring > Default Deliverables > Initiate Supplier Invoice > Interface costs to Projects
    Show some lights on this requirement.
    Regards,
    Kottee

    Hi
    As you may understand, the required flow is not delivered by Oracle.
    You might consider a customization. Develop a program that finds the completed deliverables and create from them a supplier invoice. The program might insert the supplier invoice into AP open interface. From there you should import the invoice into Payables, validate and approve it.
    Dina

  • Supply chain alerts generated from external services

    I am interested in having supply chain alerts generated from external services.
    An example could be an alert based on predicted temperatures over the next few weeks, which would be of use to demand planners using SAP SCM.
    So we would need an external service providing predicted temperatures, which could be modelled by the new SAP BPM tool to generate alerts for users.
    Has anyone any experience of this?
    Thanks,
    Bob Austin, Atos Origin

    Hi,
    I have been involved in the building of UI-layer where we used the ES provided from SAP as of the latest releases for DP. I would suggest that you have a look at these services as I assume the external application would be able to call APO DP and input the data using these services.
    From a technical standpoint we had no problems to use the services provided from SAP. The only area where we ran into some issues was the authentification where we had to build some new web services to handle some customer-specific requirements. But I assume you would not even need these specific features in your scenario.
    Have a look at this link to find all the detailed information:
    http://esoadocu.sap.com/socoview(bD1lbiZjPTAwMSZkPW1pbg==)/render.asp?packageid=DBBB6D8AA3B382F191E0000F20F64781&id=FA437A82630A11DA36BB000F20DAC9EF
    Good luck
    Fredrik

  • Material batches from Production Supply Area St. Type

    Hello Team,
    1.  User do LP12 for WM Staging [MvT 319]
    2.  He Goto LB11 and creates TO.
    3.  But when User creates TO for 319 MvT, system picks up batch from Production Supply Area.
    It should NOT pick up material batches from Production Supply Area.
    Please suggest at earliest..
    Thanks
    Tushar

    Hi,
    Check customizing settings
    check PK05, check if you have maintained the proper production supply area , WM storage loc. As I see it you are doing prod supply for release order parts. Also see cr02, basic data , see if you have assigned proper production supply area.
    check storage type 100 is properly defined , movement type 319  are created and their assignment made in WM.
    Also check if you have activated PP/WM interface.
    If all the settinsg are done , there should be no problems.
    Regards

  • User is not able to Login from external supplier, using the WSS (ICH)

    Hi Gurus,
    The user is not able to login to the server externally from url.
    dev_icm is giving below warnings:
    [Thr 11052] IcmWatchDogThread: watchdog started
    [Thr 11309] ** WARNING => HttpPlugInInit: Parameter icm/HTTPS/trust_client_with_issuer or icm/HTTPS/trust_client_with_subject not set  => do
    not trust any intermediary*
    X.509 cert data will be removed from header [http_plg_mt. 720]
    [Thr 11309] =================================================
    [Thr 11309] = SSL Initialization  on  IBM RS/6000 with AIX
    [Thr 11309] =   (700_REL,May  3 2008,mt,ascii-uc,SAP_UC/size_t/void* = 16/64/64)
    [Thr 11309]   profile param "ssl/ssl_lib" = "/usr/sap/SCA/SYS/exe/run/libsapcrypto.o"
               resulting Filename = "/usr/sap/SCA/SYS/exe/run/libsapcrypto.o"
    [Thr 11309] =   found SAPCRYPTOLIB  5.5.5C pl16  (Jun 10 2004) MT-safe
    [Thr 11309] =   current UserID: "scaadm",  env-var USER="scaadm"
    [Thr 11309] =   using SECUDIR=/usr/sap/SCA/DVEBMGS41/sec
    [Thr 11309] =  secudessl_Create_SSL_CTX():  PSE "/usr/sap/SCA/DVEBMGS41/sec/SAPSSLA.pse" not found,
    [Thr 11309] =      using PSE "/usr/sap/SCA/DVEBMGS41/sec/SAPSSLC.pse" as fallback
    [Thr 11309] = Success -- SapCryptoLib SSL ready!
    [Thr 11309] =================================================
    HTTPS (SSL) settings are as below, i think which means that no ssl certifiacts are required.
    icm/HTTPS/verify_client        = 0
    Kindly help urgently.
    regards,
    MJ

    this is SCM system.
    SSL CA's are set.
    what should be value of the parameters?
    icm/HTTPS/trust_ client_with_ issuer or
    icm/HTTPS/trust_ client_with_ subject
    http and https ssl conections are correctly set.
    I think the SAPSSLA. pse" not found, is not the problem as the parameter icm/HTTPS/verify_ client = 0 is set, it means that no ssl certifiacts are required.
    problem is coming when the system is being accessed from externally using other secure domain name.
    the system is being accessed ok from web urs which is internal, but not external.
    for example in strust tcode  the domain name is *abc.com, which is running fine when accessing the system internally.
    but when the user is accessing this sytem from other secure login from *xyz.com, which is also the same companys domain, then the user not able to login, its showing errir.

  • Production supply area (PSA) and supply area

    Hi,
    Is there any difference between supply area and Production supply area. it woul be good if you could explain me the difference.
    Thanks,
    Maxx

    Both are same
    Production Supply Area is the link between Warehosue Management and Production function.
    Production supply areas (PSAs) are used for material replenishment and are situated directly on the shop floor in the production department. The supply area groups work centers near production storage bins based on the material staging methods. You need to enter the PSA in the work center master data.
    http://help.sap.com/saphelp_46c/helpdata/en/c6/f8412f4afa11d182b90000e829fbfe/frameset.htm
    Hope this helps.
    An area on the shop floor where material is provided that can be directly used for production.
    The supply area is used, for example, in KANBAN production control and for material staging using Warehouse Management (WM).
    Proposed Supply Area in Material Master Record                                                                               
    The supply area is used as an interim storage area on the shop floor    
         which is used to provide materials directly at the production line.                                                                               
    The proposed supply area is mainly used for KANBAN materials that are   
         only or usually provided at one supply area in a plant. Here, this supply
         area can be easily saved in the system.                                                                               
    The proposed supply area is used, for example, to determine the supply  
         area for the dependent requirements of a material.                      
         The supply area in the dependent requirements of a material is required:
         o  to enable the system to calculate the KANBAN control cycles          
            automatically                                                        
         o  to enable you to select requirements in the pull list with reference 
            to a supply area

  • Sources of supply for product

    Hi all
    Why can i remove assigned vendor in the shopping cart (Sources of supply for product/Service Agent) when i choose a product from the "Internal Good/services" way, but i can´t remove it when i choose it from the SRM-MDM Catalog way???? the thing is that we have a contract for this product but in different ways we can remove and another way we can not...
    We dont know if this is a bug... or what.
    Obviously we are testing with the same product.
    Note: we are using SRM 5.0. (SRM_PLUS - SAPKIBK012; SRM_SERVER - SAPKIBKT12; ST-PI - SAPKITLQI5); SRM-MDM Catalog 2.0 SP03 Patch01.
    Plase help.
    10x
    Pp.

    Hi Jose,
    the catalog consists the agreed price list of the products with one specific vendor, therefore neither the vendor can be removed nor the price can be changed.
    This is the standard behavior.
    Regards,
    Peter