Hi Experts,
Is there any report available to get the list of Materials planned in Unit Cost Planning.
Thanks in advance.
Vinodh

Hi Vinvidh_18,
I have also been trying for capturing list of Materials planned in UCP in reports for quantity comparisions.
If you please explain the development you have done on this along with the linked tables for the same, it will be useful a lot.
Thanking you in advance,
Best wishes,
Mohan, SAP PS

Similar Messages

  • List of materials planned in a MRP Run

    Hi,
    We are running MRP through background job...after completion of MRP Run how to see the list of materials planned in that particular MRP Run...
    plz help
    Thanks
    Kumar

    Hi ,
    If you goto  BG job logs in SM37-Enter Job name or user name -Execute  and then Hit the Spool  and Mark the Spool chek box against the spool number generated after the job finished  and click on detail ( magnifying glass)- Here you will get the list of materials for BG run of MRP.
    Regards
    JH

  • Stock, Outstanding & Consumption Report for List of Materials

    Dear all,
    Is there any standard transaction / procedure to get the current stock, outstanding PO (external only) & PRs and the consumption (MvT to be selected by the user) of list of Materials (collective) in the selected Time period and Plants & S Locs.
    Thanks & regards,
    Sheeja.

    hi
    what u want cant be avalilable at time
    u can get all std reports in SAP using t code SAP1
    current stock      MMBE
    outstanding PO (external only) ME2N 
    PRs  ME5A
    and the consumption  MB5B
    http://www.sap-img.com/materials/how-to-get-the-total-stock-consumption-data.htm
    http://www.sap123.com/showthread.php?t=398
    regards
    KI

  • Report for list of materials supplying by particular vendor

    How to find vendorwise list of materials supplying by him.

    Hi
    Go to MM03 and in the selection crieteria select MATERIAL BY VENDORS MATERIAL NUMBER and there you give the vendor and the list of materials will be displayed.
    This information will be available once you have any purchasing doucments like inforecords, source list, PO, Contracts, SA etc. because you will no where give the vendor while you create a material master. Other way is to link vendor material number to sap generated material number.
    You can use ME1M, ME2L
    Thanks & Regards,
    Kiran.

  • Report for list of chargeable / non chargeable materials .

    Hi,
    What is the Tcode for getting report for list of chargeable / non chargeable materials .
    Tx
    Uts

    Hi,
    Try to use t-code MB52, maybe it could help you!
    Good day
    Tao

  • Report which gives list of materials

    Hi All,
    I am about to write a report which gives the list of materials.
    Foe\r that I want to know the relations between the tables
                MARA
                MAKT
                MARC
                MARM
                MVKE       
    Its a little bit urgent
    Edited by: ravee indra on Mar 21, 2008 1:57 PM

    Hi Ravee,
    umm...I'm a little reluctant to give you this advice as it sounds a bit like a rant, so please accept it in the spirit it is intended.
    You do not need to know anything about the data model to get a list of materials.
    Way back when ABAP  was a boy, knowing which tables held which data and the relationships between them was a key ABAP  developer skill. It does not need to be now.
    (Yes I know this is not an absolute truth - no flame wars please guys.)
    As a general rule all SAP backend business functionality is exposed via standard and open interfaces. These interfaces can take several forms, but in general they are implemented using remote-enabled function modules.
    In the case of materials (and most of the old ERP  functionality) SAP has "modeled" business objects inside the Business Object Repository (BOR). These models include the data model itself, but also include methods to interact with the model in the form of Business Object Application Programming Interfaces (BAPI's). These BAPI's are implemented as remote-enabled function modules.
    You can use these interfaces to interact with the backend data and be comfortable that SAP will (generally) not change these interfaces. So even if an upgrade makes major changes in the data model the BAPI's should still work as before.
    So taking your example of wanting a list of materials. If you go to the BAPI  Explorer, transaction BAPI , and use either the hierarchical or alphabetic navigator to find the Business Object called "Material" you will see it has a number of methods.
    One of these methods is called GetList and if you double-click on it you will see that it provides a List of Materials with Description. You can display the documentation for the method which shows you to call the method, and in the Detail tab you can see that the method is implemented as a function module called BAPI MATERIALGETLIST. You can even double-click on the function module and to go to the Function Builder where you can test the method.
    If you place these entries in the MATNRSELECTION data structure...
    MATNRSELECTION-SIGN = 'I'.
    MATNRSELECTION-OPTION = 'CP'.
    MATNRSELECTION-LOW = '*'.
    ...and execute the function module it wiull return a complete list of all materials defined in the system in the MATNRLIST itab.
    You may find that you want more details about each material, say for example availability. If you go back to the BAPI  Explorer you can see there is another method called "Availability" that is implemented using function module BAPI MATERIALAVAILABILITY, and so on....
    This is the way you should be looking to do all your development work. Look for the SAP delivered standard interfaces and use them, avoid direct database access as much as possible.
    Cheers
    Graham Robbo

  • Report to see all materials assigned to an inspection plan

    Hi,
    Is there any way to list all materials with a inspection plan assigned to them?
    Kind regards,
    Kristoffer Pehrson

    HI,
    another way could be the use of QP03.
    Select your inspection plan. In the plan overyou press the button "material assignment". YOu should get a listof all materials that are linked to the plan. But you should keep an eye on thegroup counter, as all group counters and assignments are shown.
    Another way could be to build query with SQ01.  
    Hope that helps.
    Jens

  • List of materials with no associated routing...report

    Hi all,
    I need to develop a program to display a list of materials that do not have an associated routing. SAP tcode C223 lists materials with associated production versions. Do you think there is another standard SAP transaction that might get me close to my goal?
    regards,
    Mat

    Not sure about a standard transaction, but I have written a program to do this same exact thing in the past.
    Really all you need to do is check against table MAPL.
    Regards,
    Rich Heilman

  • Break Up of Actual Costs in a report for list of orders

    Hi All,
    SAP standard reports displays only the total planned & total actual costs.
    Is there any standard report available which can display break up of planned & actual costs along with total costs, for list of orders (e.g: time, material and external resources consumption).
    Thanks in advance
    JK

    hi
    you can find the material cost,external service etc in the standard cost report itself select the change layout and select the items you want to display ,you can get the result
    regards
    thyagarajan

  • List of materials with total PR, PO qty, and stock

    Dear All,
    Is there any std report to check the list of materials along with total PR qty, PO qty and Current stock.
    This is to check, what is the total requirement of the materials and whether Purchase team has raised the PO or not ?
    Please advise.
    Regards
    Vinoth.

    Hi,
    MD04 gives us the details of individual part no.
    But, we would like to see similar details in the form of list of materials, with cumulative demand, cumulative OPEN PR Qty, Open PO Qty and Stock.
    Please help.
    Regards,
    Vinoth.

  • Report Internal Order needed - showing Plan and Budget Values?

    Hello,
    I want to create a report (Report Writer/Painter) which shows for example in one column the planned values and in another column the budget value of an order group.
    I know the standard reports S_ALR_87012993 - Orders: Actual/Plan/Variance and the other standard report S_ALR_87013019 - List: Budget/Actual/Commitments.
    My question: Is it possible at all to have these both values plan and budget by order/order group in one report? - Or it is not possbile because these values are stored in different tables and different libraries?
    If it is possible with Report Writer, I would be very glad - if not, is there any other chance (e.g. individual programmed report)?
    For any comments or hints thank you in advance.
    Regards,
    VCG

    HI,
    both are report painter reports for libraries 6O1 and 6O2 which are based on reporting tables CCSS and RWCOOM.
    Try to find all value fields that you need in 6O2 / RWCOOM as this is the "big brother" of 6O1/ CCSS.
    Best regards, Christian

  • How to develop a report for display unused materials

    how to develop a report for display unused materials? where can i find them?

    Hi Phani,
    I didnt get what u acually mean by unsued material. These are some sample materail types which u can find in table 'Mara'  field 'Mtart'.
    ABF  Waste                   
    AEM  Samples                 
    BLG  BLG Empties  External   
    BLGA BLGAEmpties  Fixed assets
    CH00 CH Contract Handling    
    COMP Prod. alloc., purchased 
    CONT KANBAN Container        
    COUP Coupons                 
    DIEN Service                 
    DOCU documentary batch       
    ERSA Spare parts             
    FERT Finished product(fert)  
    FGTR Drinks                  
    FHMI Prod. resources/tools   
    FOOD Foods (excl. perishables)
    FRIP Perishables             
    GR01 material type 01        
    GR02 material type 02        
    HALB Semi-finished product   
    HAWA Trading goods           
    HERS Manufacturer parts      
    HIBE Operating supplies      
    IBAU Maintenance assembly    
    INTR Intra material          
    KMAT Configurable material   
    LEER Empties                 
    LEIH Returnable packaging    
    LGUT Empties (retail)        
    MODE Apparel (seasonal)      
    NLAG Non-stock material      
    NOF1 Nonfoods                
    PIPE Pipeline material       
    PLAN Trading goods (planned) 
    etc.
    ex:
    select * from mara where mtart = 'ABF'.
    Regards,
    Kiran B

  • List of Materials with out POs

    Hi,
    I want to know the list of materials for which no PO was created so far.
    Is there any report or T.code to get the material list.
    Regards.
    Chinna
    Edited by: Chinna Veerappa on Apr 28, 2009 11:03 AM

    Hi,
    do you want to know the open purchase requisitions for which No PO is created , then you can check the same in ME5A and keep Processing Status as "B" or some thing else you want ?
    Regards,
    Vikas

  • Daily check report to list the vendor name, material, quantity

    hi friends,
    can you help me to write daily check report to list the vendor name, materials and quanitity?
    thanks in advance

    HI ,
    What do you mean my daily check report..
      Do you want to see the status of the PO sent to a Vendor on a daily basis..
    Thanks
    Mahesh

  • Displaying list of materials in module pool

    Hello frds,
    i have senario where i have to select a push button to display list of materials in the next screen based on the range .In reports v write a select query but in module pool its not working.
    PLZ help me out with simple example

    Hi sai,
    Please refer th procedure.
    For the select-options you might have defined a selection screen.
    Next you can fetch the entire data that you wanted to display in a module pool into an internal table.
    you can call the screen you defined for o/p upon the selection.
    Then, You define a screen XXXX  and a table control in the scree, and in the PAI module of the screen
    you write a chain end chain processing in which you can display the contents of your internal table.
    OR
    if you want the selection also to be in the module pool,  then for displaying the O/P you can definr a sub-screen of the initial screen and you can call that sub-screen on selcting, which can be done with a function code.
    Hope this helps

Maybe you are looking for

  • Maverick update, Lost my sent mail mailbox, but the inbox is still there and contains no messages!

    I lost my sent box after maverick update, the sent box that used to appear under the paper airplane icon. The inbox is still there, but it contains no messages. I have tried to Rebuild the mailboxes, removed and added again, restarted my computer, sy

  • Alu iMac shuts down when burning a disc

    If I try to burn a CD or DVD, the computer shuts itself down. Not a proper shutdown, just power off. When re-booted, it has no idea it crashed, but the disc is half burnt! I am not getting many other problems at all, just this one. I am waiting for A

  • Missing one song in purchased CD

    I just purchased the moody blues 20th century collection and iTunes won't let me d/l the song called Voice. It keeps saying the file seems to be cprrupted and to redownload using Store ..check for purchases. But this just results in the same error me

  • Jumpfilereturn disabled

    I have a number of pieces that are designed to work together. I connect them with the jumpfilereturn function. However, this is not working as intended. The function works alright to jump from one piece to the other. But when I quit the second piece,

  • WE  ARE  FOLLOWING  MAKE TO ORDER  IS IT  ESSENTIAL  THAT  WE  DO  COSTING

    Dear  All, we  are  doing   make  to  order scenario  is it  essential  that  we  do  costing  run  . for   finished  products  and  semifinished  products. regards sree