Resource assignment to multiple activities

Sir,
I am trying to assigning single resource "resource name : XYZ" to multiple activities using the option right click, .
After assigning using this option i had a problem with the resource.
Problem is for some activities the resource "XYZ" is getting assigned multiple times.
Any solution to this.
Thanks,
Imad

I think the problem is that the resource was already assigned to some of the activities. Which, incidentally, is a nice feature of P6 that you can do that.

Similar Messages

  • Resource assignment to Parallel activities

    Hi,
    this is regarding resource allocation to Parallel activities. I have two activities that occur in parallel 1. Preparing drawings for table, 2. Preparing drawings for Chari.
    Now these activities occur on the same day (one day duration) and done by one single draft man.
    I have assigned one draft man as a resource to both the activities. (Meaning one draft man will do both activities in one day), the problem is in the histogram it is showing two draft man as a required resource on this particular day.
    Qstn: How to make P6 understand that this single resource will do both activities in one day (and still assign one draft man as resource to both the activities.)
    Thanks in advance..
    Regards,
    Imad

    You need to reduce the units (hours) by one half for each of them. If you currently have them for 8 hours/day and the resources limit is 8, it will show as needing two.

  • Calculating Daily Labour Count from P6 Resource Assignment data

    Hello fellow P6 users,
    If resources are assigned on activities in P6, and have also been leveled, what would be the best way to calculate daily labor presence on site? Currently I have used Excel to import resource assignment at activity level spread on an hourly timescale, and then processed this data to transform it into number of person on site for every work day of the project during its currency. The process is OK but laborious. Wonder how others do it, if at all.
    I don't expect much response from P6 users as this is not a very common challenge in our industry but still hoping someone might have had enjoyed such experience to share here with us.
    Thanks

    Hello fellow P6 users,
    If resources are assigned on activities in P6, and have also been leveled, what would be the best way to calculate daily labor presence on site? Currently I have used Excel to import resource assignment at activity level spread on an hourly timescale, and then processed this data to transform it into number of person on site for every work day of the project during its currency. The process is OK but laborious. Wonder how others do it, if at all.
    I don't expect much response from P6 users as this is not a very common challenge in our industry but still hoping someone might have had enjoyed such experience to share here with us.
    Thanks

  • Resource rights on multiple tablespaces

    Hi,
    I am trying to do a full import of a database. Prior to that I am creating all the user accounts. One user has resource rights on multiple tablespaces. How do I assign multiple tablespaces to a user? I have already assigned a temp and default tablespace.
    Product info:
    Oracle Database 10g Enterprise Edition Release 10.1.0.5.0 - Prod
    PL/SQL Release 10.1.0.5.0 - Production
    Thanks.

    Anurag,
    The command provided by Krystian is what I was looking for.
    As to why I need to assign multiple tablespaces to a single user, its the way the data is setup.
    I am trying to create a test database from production database sized at 150GB having about 40-50 tablespaces.
    There are several users that are assigned quotas on multiple tablespaces. I found this by querying the DBA_TS_QUOTAS view.
    I split the test DB creation into two parts. I created a template of the production database using DBCA, used the template to create a DB on the test machine. I am now in the process of creating users. Following which I will import the data using IMP utility.
    Thanks.

  • Need to assign follow up activities to Service Quotations

    Hi All,
    can any one give me soluton on
    Need to assign follow up activities to Service Quotations (Create Service Quotation type "ZAV"...transaction code VA21. Need quotes to print out 90 days before service is due again in the following year.
    Thanks in advance.

    Have you already customized Copy Control for your Service Order? If you want to add other transaction types the setting is necessary.
    The customizing path is shown as below.
    SPRO
    -> CRM
      -> Transactions
        -> Basic Settings
          -> Copying Control for Business Transactions
            -> Define Copying Control for Transaction Types
    Regards,
    Web

  • How can we get the Latest Resource Assigned in the Approval Form

    I was wondering if there is any way to get the Latest Assigned Resources to a User in my Approval Form.
    I tried this <ref>waveset.resourceAssignments</ref> but it returned all the Resources assigned to a User. While creating a User with Resource Assigned it won�t be problem. While Update when a User is assigned a Resource & it comes for Approval to the owner, all the Previously assigned resources shows up. How can I get only the Latest Resource Assigned.
    Can anyone provide some hints on this..

    idm_guy, if you could elaborate more on what you mean with latest resource assigned it would help - but there are a number of options (if i interprent you correctly to solvethis). My guess is that the easiest way would be to determine if:
    waveset.accounts[<iterate through resources>].created = true or false
    and if
    waveset.accounts[<resource>].lastPasswordUpdate = <last updated date>
    The latter is of course only applicable to resource where you set a password. This value will be updated whenever you set the password and could be a possible value to check against.
    If the account is not created yet but assigned it might be another possibility to check, but again - clairfy a bit about what you mean with "Latest Resource Assigned".
    /Anders

  • Assign a role automatically based on resources assigned to the user?OIM 11g

    Hi,!
    i have a request and this is:
    in my scenario i have roles associated with access policies that assign resources .
    i have resources assigned by a target reconciliation ... what i need is assign a role based on resources that the user has..
    if the user has 4 resources added by a target reconciliation and these 4 resources make a role then the role has to be assigned automatically...
    any idea?? this is possible?? thnx..

    any idea?? ... this is possible??

  • CProjects-MS Project - import and export of task-role-resource assignment

    Hi,
    We are on PPM5.0
    We are currently working on cProjects-MSP client integration.
    What we have not been able to configure for import/export so far is:
    1. Task-Role-Resource assignment
    Whereas we are are able to import/export the "Person Responsible" and "Role Responsible" fields, we have not been able to align the task-role-resource assignments.
    We see a "Resource Name" column (Standard) in MSP. When we click on the drop down, we see all the roles from the cProjects project. But the alignment does not happen.
    Summary:
    On export and import, we need to automatically see the role-resource-task assignment. How is this possible?
    2. Code field to "VC_BUPA_GUID" gets a number which is not the BP ID.
    Is it possible to import the BP numbers in MSP. Also, how can we assign a number to the role in MSP such that on import into cProjects, the role is already staffed with the corresponding BP.
    3. Is it possible to export all the resources (BPs) into a drop down in MSP - like we see the Project Type, Role Type etc.
    Thanks.

    Hi Anuradha,
    Thanks for your inputs.
    When we export to MSP, we see the cProjects roles under the "Resource Name" drop down in MSP.
    However, they are only seen when we expand on the drop down.
    For e.g. RoleA, and RoleB are two roles in cProjects project, along with many other roles.
    Both of these roles are assigned to a task, say TASK1.
    When exported to MSP, we expect both of these roles to show against TASKI, as "RoleA, RoleB" under the "Resource Name" column. However, these roles are not seen. They only appear as elements of drop down, along with all other roles in the project, when we explicitly click on the drop down.
    Please let me know if I are missing out on something.
    Thanks.

  • What  is difference btw project Assignment, Resource Assignment and task Assignment.

    Hi,
    I am new project accounting Module .
    what  is difference btw project Assignment, Resource Assignment and task Assignment.

    Project Assignment, Resource Assignment refers to the resource management part and Task assignment is basically the work assignment to the resource.
    An assignment/requirement is created in PJR for create demand for the resource requirement of the project and when the resource is aligned he can be assigned to the task in the work plan.
    Refers to the top down approach in this case.
    Additionally a resource can be assigned to the work plan and a assignment can be created to get the resource allocated to the project.
    Refers to the bottom up approach in this case

  • Keywords cannot be assigned to multiple images

    A keyword can NOT be assigned to multiple images at the same time when following the procedures outlined in the Aperture help. I can't find this problem addressed in a FAQ or knowledge base. We're told to select multiple images in the Browser window then drag a keyword to any of the images to assign that keyword to all the selected images. This does not work -- only the specific image on which the keyword is dropped will actually be tagged with the keyword. The other images, though properly selected, do not receive the keyword. The keyword must be assigned to one image at a time. Needless to say, this is more time consuming than it's worth when you're faced with thousands of images that need to be tagged.
    I own two registered copies of Aperture, both up to date with the latest patches, and the problem occurs on both systems, so I know its not something related to a single computer.
    Surely I'm not the only person who has encountered this problem?

    I thought I had the same problem, but then did the following:
    1. In Browser (grid view) went ot lower right and turned off the "primary only button" (ie it should not be "lit")
    2. Highlighted the images I wanted to apply the same keyword to
    3. Opened the keyword HUD
    4. Clicked on the keyword I wanted and then dragged it to one of the highlighted images in the browser

  • No resource assignment found for user

    Hi All,
    I 'm getting following error after executing syncbo  Ztest_010  of type S01.
    "No resource assignment found for the user test."
    i have added  enteries in SPRO for the user test ,
    Can anyone suggest which entry might effect the extraction of data for Ztest_010.
    Regards,
    Nitika

    Hello,
    Check the  Transaction Code OKEU,there you have to maintain the source structure for the cost element .
    Hope it will help you
    Regards
    Ravi

  • Amending resource assignment information

    I'm an admin user trying to test some settings for resource assignments. Quite simply, I’d like to change the 'remaining early start' and 'remaining early finish' dates. Not sure why, but i am not able to. i CAN however, change the figures in the resource spreadsheet.
    Within the user settings, the tick box for "all resources access" is selected and the global security profile is set to <Admin Superuser>
    I am yet to find anything within this project schedule that i cannot change - apart from resource assignment settings.
    Any idea what I’m missing?
    Edited by: user12081115 on 24-Feb-2010 16:20

    You should not have a problem providing the new resource assignment dates you are selecting are within the activity date range

  • Resources assigned to a Work Center

    Hi Experts ,
    Is there any Function Module to get the 'Person Responsible' and the Resources assigned to a Work Center ?
    Thanks,
    Radhika.

    Hi Renjith,
    Thanks for the quick reply. The Second FM is exactly what i was looking for, but regarding the Person Responsible field, i need related to the Work center only not the Project Definition.
    Any idea of person responsible for work center ?
    Thanks.

  • How to Allow Assignment to Multiple Suppliers?

    In 11.5.9 there was a field called Allow Assignment to Multiple Suppliers on the Bank Accounts window.
    Does anyone knows where this field is in R12?

    Metalink note 560714.1

  • Can One technical system be assigned to multiple BS system

    Hi All,
    I just need small confirmation, i want to know wether one technical system(ABAP) with same client be assigned to multiple busines system..
    Regards,
    Raj

    Hi ,
    No, you cannot have 2 BS for the same technical system and same client.
    (you can have different BS for every client of a technical system)
    Raghu

Maybe you are looking for

  • Presentation Director and Access Connections when Docking

    When I dock my machine, it automatically selects the right presentation mode because of the way that I configured Presentation Director.  It would be nice if it could automatically select the right Access Connection too.  Is this possible?  Is there

  • Error SQL Statment

    I need help please. I got error when generate this code. objective : to convert '+' sign to be an AND operator for SQL query statement. eg: if user key-in game+car its will convert to = : where tajuk='game' and tajuk='car' . where TAJUK is field in D

  • How do I save a mp3 file?

    How can I save a free mp3 file to my iPad without using a computer to do so?

  • Default tab in JSP

    Hi, I am displaying two tabs in a main JSP page. tab1 is selected by default. When I click on tab2, I see content of tab1 jsp loaded on top of tab2 jsp content. How do I just display tab2 jsp content when I click on tab2? <html>     <head>         <m

  • Solution: iTunes 10.5 using 100% CPU / Not backing up your iPhone.

    This solution has been documented on this forum by several people, but the solution is usually deep in multiple threads.  I really don't know who came up with it first, but it does indeed work. I had an issue with iTunes.exe, APSDaemon, and AppleMobi