Revised Project Start & Finish Dates

Dear All,
Where i can see Project orignal start & finish dates and Revised start & finish dates
Is their any report or transaction available.
Pls confirm me.
Thanks in Advance.
Regards,
Sandeep N.Theurkar

Hi Sandeep,
The project system does not keep the original dates somehwere automatically. If you would like to have such 'baseline', a option is using version as mentioned above. An alternative is just transfer the basic dates to the forecast dates as base line, after the planning is finish.  In this way, you get two sets dates of the same object.
Kind regards,
Zhenbo

Similar Messages

  • Schedule start & finish dates - Project Management

    All
    Will there be any implications on performance /status reporting etc if we personolise Schedule start & finish dates.
    The reason to personlise is to have Transaction Start & Finish date instead of Schedulate start & finish dates.
    Needs your inputs....
    Thanks in advance.
    Regards
    Ajith

    Marc,
    When Project was first released there were only two basic start field, Start and Actual Start (in addition of course to the Baseline Start field and a few others). With the release of Project 2010, a manual scheduling mode was introduced. That's when things
    got a little more confusing. Instead of leaving the Start date as is, the Start field was converted to a text field and the old Start field was renamed as Scheduled Start. When in auto-schedule mode, both Start and Scheduled Start are exactly the same.
    Now to answer your questions. To keep it simple, let's assume you are using auto-scheduling.
    1. In order to keep the schedule dynamics intact, it is necessary to update the Start field to agree with what really happened, namely with the Actual Start date. If you do not enter anything into the Actual Start field, Project automatically assumes the
    task started as scheduled, on the Start date.
    2, Yes, Project does its scheduling based on the current plan which is represented by start, finish and other data. Once the project starts, that current plan must be updated so the actual date values come into play. As noted in the lead in paragraph, Scheduled
    Start and Start are the same for auto-scheduled tasks.
    3. Earned value is based on the actual values and the saved baseline data. The "point in time" you refer to is the timescaled data as of the status date.
    Hopefully, this clear up at least some of your confusion.
    John

  • Changing Operattion Earliest Start/Finish Dates?

    Hi EAM Gurus,
    I want to change the operation Earliest start/finish dates & times also. Is it possible?
    Also I am thinking if I create a custom report (similar to IW37n) which allows me to change operation earliest start/finish dates.
    Is there a USER EXIT/BADI which will allow me to change the dates?
    I can change the operation date & time in capacity planning table (tabular form - CM34) by using manual dispatch button. I want to incorporate same kind of functionality in a custom report.
    I am waiting for your expert advice/suggestions.
    Thanks in Advance
    Adi

    Hi,
    In the end, yes, once actuals are recorded, all these values are the same - but before that they can all be different!
    Before an actual start is recorded, the column shows "NA" (wich obviously is different from Start :-)). To the scjheduling engine, thsi means the start can be freely calculated (from predecessors or resource leveling, f.i.) whereas when a date
    appears in Actual Start, Project will take that value as carved in granite - it is supposed to show past reality, and reality is more powerful than values calculated by the scheduling engine!
    So these two values are not Always identical!
    As for Scheduled start, that is indeed meaningless for automaticlly calculated tassk. But for manually scheduled tasks it does play a role. For a manually schduled task, you can set any start value you want (even a litteral such as "when we have
    the time"). Still, there is an option to make manually scheduled tasks obey links - the result of that calculation is then put into scheduled start - and so there can be a difference between these two columns as well.
    So, no, these 4 values do not have the same function. They are ony identical as soon as actuals are recorded but what do you expect? There is only one past reality, Project does not work with a parallel universum :-)
    Hope this helps,

  • Basic Start/Finish Date and Requirment Date in Maintenance Order

    Sir,
    We want to know the link between Order Start/finish date and requirement date in Maintenance Order.
    As we are facing problem during change in dates.
    When we change either start date or finish date in the order, the system automatically change the requirment date as of ondate of all the materials which has been earlier issued and also consider the today date.
    Like in Maintenance Order
    Basic Start Date - 01.04.2009
    Basic End Date  - 31.05.2009
    We have issued materials on the order at different date by putting offset value for the requirement date.
    Now if we increase the Basic End Date of order to n30.062.009 or whatelse, the system automatically changes the requirement dates of all the materials issue based on current date. Suppose we changed the Basic End date on 10.11.2009, the system changes all the requirement dates by calulating offset value from 10.11.2009. However these materials has been issued earlier.
    I want to know if there is any remedy to stop to change the requirement dates automatically.
    With Regards
    Mudit Gupta

    HI
    In general the requirement date will get changed only when the IMG settings in OPU7 permits the requirments dates should be adjusted towards the order basic start and end dates
    kinldy check and adjust as per the requirement
    regards
    thyagarajan

  • Production order scheduled start/finish dates

    Hello experts!
    I have a problem with prod. order scheduling. I set the date '07.05.2007' as order start/finish date. If I run <i>Functions -> Schedule -> Order</i> (or save the order) SAP set these dates to '02.01.2008', and scheduling also to '02.01.2008'. The scheduling type is <b>Forwards in time</b>. Scheduling margin: everything is 0.
    I have checked the <b>work center capacity</b>:
    from 20.04.2007 to 31.12.2007
    Lenght of cycle: 1 Start: 06:00:00 End: 23:00:00 Break: 00:00:00 Cap. util.: 100
    from 01.01.2008 to 31.12.9999
    Standard avail. capacity
    (01.01.2008 is non-working day)
    Routing exists for this material (valid from 02.03.2007).
    Based on what does SAP calculates these dates?
    (SAP 46B)

    Hello guys!
    I have found the reason and also the solution. It's a bug in SAP (46B). When it happens?
    1) Open work center
    2) Create interval with minimum 2 shifts and save
    3) Delete first shift of the interval
    4) Check table kapa -> field SCHNR (shift sequence number) for the 1st shift in this interval will contain number 2.
    If SAP calculates the scheduled date for order it excludes this interval from calculation. We had an interval 20.04.2007 to 31.12.2007 with deleted first shift, so the next workday for SAP was 02.01.2008.
    I have created a function, which can solve this problem:
    FUNCTION z_pp_fix_capacity_data.
    *"*"Local interface:
    *"  IMPORTING
    *"     VALUE(I_WERKS) TYPE  WERKS_D
    *"     VALUE(I_ARBPL) TYPE  ARBPL
    *"  EXPORTING
    *"     VALUE(E_CHANG) TYPE  INT4
    *"  EXCEPTIONS
    *"      FOREIGN_LOCK
    *"      SYSTEM_FAILURE
    *"      NOT_VALID_WORK_CENTER
    *"      DATABASE_UPDATE_FAILED
      DATA: l_kapid LIKE crhd-kapid,
            l_schnr LIKE kapa-schnr,
            l_error TYPE c.
      DATA: ikap LIKE kapa OCCURS 200 WITH HEADER LINE.
      CLEAR: e_chang.
      COMMIT WORK.
    *- Get the Capacity ID of the work center
      SELECT SINGLE kapid
               INTO l_kapid
               FROM crhd
              WHERE werks = i_werks
                AND arbpl = i_arbpl.
      IF sy-subrc <> 0.
        RAISE not_valid_work_center.
      ENDIF.
    *- Lock the work center
      CALL FUNCTION 'ENQUEUE_ECARPL'
           EXPORTING
                arbpl          = i_arbpl
                werks          = i_werks
           EXCEPTIONS
                foreign_lock   = 1
                system_failure = 2
                OTHERS         = 3.
      IF sy-subrc <> 0.
        CASE sy-subrc.
          WHEN 1.
            RAISE foreign_lock.
          WHEN 2.
            RAISE system_failure.
        ENDCASE.
      ENDIF.
    *- Select the whole capacity into internal table
      SELECT *
        FROM kapa
        INTO TABLE ikap
       WHERE kapid = l_kapid.
    *- Sort
      SORT ikap BY versn datub tagnr schnr.
    *- Set the correct sequence number
      LOOP AT ikap.
        ON CHANGE OF ikap-versn
                  OR ikap-datub
                  OR ikap-tagnr.
          l_schnr = 1.
        ENDON.
        IF ikap-schnr NE l_schnr.
          ikap-schnr = l_schnr.
          e_chang = e_chang + 1.
          MODIFY ikap.
        ENDIF.
        l_schnr = l_schnr + 1.
      ENDLOOP.
      IF e_chang NE 0.  " If change found, recreate data
    *- Clear error indicator
        CLEAR l_error.
    *- Delete old data
        DELETE FROM kapa WHERE kapid = l_kapid.
    *- Insert data
        IF sy-subrc EQ 0.              " Delete OK, insert
          INSERT kapa FROM TABLE ikap.
          IF sy-subrc EQ 0.            " Insert OK, commit
            COMMIT WORK AND WAIT.
            clear: l_error.
          ELSE.                        " Insert failed, rollback
            ROLLBACK WORK.
            l_error = 'X'.
          ENDIF.
        ELSE.                          " Delete failed, rollback
          ROLLBACK WORK.
          l_error = 'X'.
        ENDIF.
      ENDIF.
    *- Unlock the work center
      CALL FUNCTION 'DEQUEUE_ECARPL'
           EXPORTING
                arbpl = i_arbpl
                werks = i_werks.
      IF l_error NE space.
    *- Raise exception
        RAISE database_update_failed.
      ENDIF.
    ENDFUNCTION.
    I hope this helps someone! Anyway! Thank you for your answers!

  • Schedule run issue: Late dates earlier than start/finish dates

    Hi,
    I am running into an issue with one of my contractors. When the contractor sends the xer file, all the critical late start dates are a day earlier than the start date i.e. if the start date is Mar 03, 2011 then the late start date is Mar 02, 2011. I am able to fix it at my end when I run the schedule but the contractor is not. Is there some feature in the global setting that the contractor has to fix in his end to resolve this issue? Any help or advice would be great.
    Thanks.

    Marc,
    When Project was first released there were only two basic start field, Start and Actual Start (in addition of course to the Baseline Start field and a few others). With the release of Project 2010, a manual scheduling mode was introduced. That's when things
    got a little more confusing. Instead of leaving the Start date as is, the Start field was converted to a text field and the old Start field was renamed as Scheduled Start. When in auto-schedule mode, both Start and Scheduled Start are exactly the same.
    Now to answer your questions. To keep it simple, let's assume you are using auto-scheduling.
    1. In order to keep the schedule dynamics intact, it is necessary to update the Start field to agree with what really happened, namely with the Actual Start date. If you do not enter anything into the Actual Start field, Project automatically assumes the
    task started as scheduled, on the Start date.
    2, Yes, Project does its scheduling based on the current plan which is represented by start, finish and other data. Once the project starts, that current plan must be updated so the actual date values come into play. As noted in the lead in paragraph, Scheduled
    Start and Start are the same for auto-scheduled tasks.
    3. Earned value is based on the actual values and the saved baseline data. The "point in time" you refer to is the timescaled data as of the status date.
    Hopefully, this clear up at least some of your confusion.
    John

  • Microsoft Project 2013 - Finish-date drop-down arrow

    When I enter a finish date with year at 2000, 2001, ... and beyond, then click the right drop down arrow, to adjust the date via., calender view, the calender view is at 2079.  I have no
    idea why it jumps forward 79 years, but obviously it makes it impractical to use the calender view to make minor date adjustments.
    Any ideas would be appreciated.
    Thanks,
    Scott 

    Scott,
    Pardon my bumping in but let's make sure we're talking about the same thing. You use the term "calendar view" but I don't think that is what you meant. In Project the Calendar View is a whole separate defined view. You can find it on the ribbon under View/Task
    views group. One of the reasons I don't think you really mean the Calendar View is that I'm not aware of any right drop down arrow anywhere on that view, but then I don't have Project 2013.
    So, for clarity sake, do you really mean the small calendar that pops up when you activate a date field cell (e.g. Start, Finish, etc.) and then hit the selection arrow, (which is on the right side)?
    This may seem like a small thing but more than once have we gone round and round trying to help a user when part of the problem was a misunderstanding due to incorrect terminology.
    One other thing. I assume you realize that by entering dates directly into the Start for Finish fields, you will be setting a constraint on that task.
    With that, I'll leave it to Guillaume.
    John

  • Why do Start/Finish dates automatically change to match Actual Start/Finish dates?

    Please excuse my ignorance, but what is the
    rationale for MS Project automatically changing the "Start" and "Finish" dates to match the "Actual Start" and "Actual Finish" dates when they are inputted?  Can this "feature" be disabled?
    Thanks in advance for any assistance.

    Hi,
    In the end, yes, once actuals are recorded, all these values are the same - but before that they can all be different!
    Before an actual start is recorded, the column shows "NA" (wich obviously is different from Start :-)). To the scjheduling engine, thsi means the start can be freely calculated (from predecessors or resource leveling, f.i.) whereas when a date
    appears in Actual Start, Project will take that value as carved in granite - it is supposed to show past reality, and reality is more powerful than values calculated by the scheduling engine!
    So these two values are not Always identical!
    As for Scheduled start, that is indeed meaningless for automaticlly calculated tassk. But for manually scheduled tasks it does play a role. For a manually schduled task, you can set any start value you want (even a litteral such as "when we have
    the time"). Still, there is an option to make manually scheduled tasks obey links - the result of that calculation is then put into scheduled start - and so there can be a difference between these two columns as well.
    So, no, these 4 values do not have the same function. They are ony identical as soon as actuals are recorded but what do you expect? There is only one past reality, Project does not work with a parallel universum :-)
    Hope this helps,

  • Trying to update Project scheduled finish date - newbie help needed!

    Guys, I am super new to Oracle Projects, I have never used it before.  I've just learned a few things in the UI and read through the docs documenting the stored procs.  My question is simple (hopefully)   In the UI I choose a responsibility, then under "Projects : Delivery" I choose "Search Projects", I enter the Project ID in the field and click Go, I am able to see all the project details and the Tasks.  No problem there!  What I would like to do through the Update_Project API is to change the "Scheduled Finish Date" of the Project.
    I have the following information that I have managed to scrape up:
    Project_id, Responsibility_id, User_id, Resp_Appl_Id
    I retrieved the project id using:
             Select project_id,name from pa_projects_all
              where name = 'My Project';
    So first I call set_global_info with the appropriate parameters, then this:
        -- SET GLOBAL VALUES
         pa_interface_utils_pub.set_global_info(
         p_api_version_number => 1.0,
         p_responsibility_id => fnd_profile.value('57203'),
         p_user_id => fnd_profile.value('1013415'),
         p_msg_count => l_msg_count,
         p_msg_data => l_msg_data,
         p_return_status => l_return_status);
         l_project_in.pa_project_id := 4608;
         l_project_in.scheduled_finish_date := to_date('2008-02-27', 'YYYY-MM-DD');
      --UPDATE_PROJECT
              pa_project_pub.UPDATE_project(
                        l_api_version_number,
                        p_commit => l_commit,
                        p_init_msg_list => l_init_msg_list,
                        p_msg_count => l_msg_count,
                        p_msg_data => l_msg_data,
                        p_return_status => l_return_status,
                        p_workflow_started => l_workflow_started,
                        p_pm_product_code => null,
                        p_project_in => l_project_in,
                        p_project_out => l_project_out,
                        p_key_members => l_key_members,
                        p_class_categories => l_class_categories,
                        p_tasks_in => l_tasks_in,
                        p_tasks_out => l_tasks_out);
    What I am getting is the message "error :Project ID is invalid" and the status is "E"
    I'm not sure why it is invalid as it is the exact Project ID from the projects table.  The only thing I can think of is that the p_pm_product_code is set to null but I am not sure where this value comes from and why it even matters.  I checked the documents and it says it refers to some external system.  Why does the external system code matter if I am changing data within Oracle Projects?

    Hello,
    Looks like you are not setting the Initialization values correctly. Oracle Project APIs are Org specific and require proper initialization before being called for them to work.
    Few things i noticed from the code is :
    1.  The following is being used to set the User ID and Responsibility ID  :
         p_responsibility_id => fnd_profile.value('57203'),
         p_user_id => fnd_profile.value('1013415'),
    I think the call should be like this. This should be used only if you are going to call the API through a concurrent program from the submit request window (Oracle Apps environment). fnd_profile.value will get the responsibility id and the used id of the user running the program and assign it to the variables.
         p_responsibility_id => fnd_profile.value('RESP_ID'),
         p_user_id => fnd_profile.value('USER_ID'),
    Or If you are directly passing the IDs hardcoded then, This can be used if you are running the script from a Non-Oracle Applications environment, for example from SQL*Plus.
         p_responsibility_id => 57203
         p_user_id => 1013415
    2. I notice that you are not passing P_OPERATING_UNIT_ID parameter in the call to pa_interface_utils_pub.set_global_info. This is fine if you are not using MOAC  and you have set MO: Operating Unit profile for the responsibility being passed.  If you are using MOAC or are not sure, then it is always a good practice to explicitly  pass the P_OPERATING_UNIT_ID parameter in the call to pa_interface_utils_pub.set_global_info.
    Note :  DO NOT use fnd_profile.value('ORG_ID') to set the P_OPERATING_UNIT_ID parameter. In a MOAC environment this may not work.
    3. Always ensure you check the return status of the pa_interface_utils_pub.set_global_info for success before calling the Project APIs. This will save you a lot of frustration when testing.
    4. You might find the following note useful
    Project API Overview and Reference (Doc ID 1424156.1)
    Regards,
    Raghavan Gopalakrishnan

  • Export Project and Change the Duration Cause the Finish date error

    I use VB.NET to create a MS Project Instance and use this Instance to add task, and set task's Name, Start and Finish, the Project file is created successfully, and the Duration value will be automatically generated by Project, but if I change the Duration
    value in Project, the Finish date isn't correct, for example, if I set the the Start is "10/21/2014" and Finish is "10/31/2014", the generated Project file has a Duration value is "9 days", and if I change the Duration value to
    "2 days", the Finish date will be changed to "10/21/2014", why this problem happen? I have no idea about this problem.

    when you set Start is "10/21/2014" and Finish is "10/31/2014", the generated Project file has a Duration value is "9
    days" because it is taking Saturday and sunday as non working days.
    By default in Project server calendar both Saturday
    and Sunday are non workng days. If you want to make these day as working day you have to configure the calendar once you will do it then it will display duration value as 11.
    When you change the value then after changing value click on Calculate button so that project server can calculate value correctly it is not required to click on Calculate
    all the time but some time project server takes time to reflect the chnages but if you will publish the project it will calculate correctly and display proper finish date ( I
    change the Duration value to "2 days", the Finish date will be changed to "10/21/2014 as 10/23/2014)
    kirtesh

  • The system could not calculate the fiscal year start or finish date message

    While running the transaction FMO1 and FMOA in funds management we have confronted with the following problem.
    Message no. FI 500
    The system could not calculate the fiscal year start or finish date.
    WE are using year dependent fiscal year and are implementing Funds Management for the first time.
    SAP Version – 4.0 B
    Priority – Urgent
    For the same problem in Version 4.5 and 4.6 there is a note number 213713 available on service.sap.com.

    No, there is no bug.
    Those activities that have asterisks (Stars) next to their start or finish dates (despite having no constraints) have "External Early Start" or "External Late Finish" dates, respectively, assigned to them. These dates get imported with XER and represent links to activities of those projects that are not in your database but in the external database where the XER originated from.
    To remove, filter out all such activities (with stars) and delete their "External" dates. However, be aware that Start or Finish dates of such activities might change if you delete theire External dates. If getting rid of asterisks does alter your schedule, ask the person who sent you the XER to confirm start/finish dates of all such (starred) activiites.
    Cheers

  • Basic start date & Basic finish date based on Priority

    Dear Experts,
    When I am creating Notification & selecting Priority, System gives pop-up “do you want to specify new dates?” If I select yes system automatically change required start & required end based on Priority.
    Now my question is do we have same functionality for Maintenance order as priority field is available there (If we are directly creating a MO)?
    Even if we are creating WO from notification, required start & end dates copies to Basic start & Basic finish but if we change priority then no change in basic start & finish dates. Why?

    Greetings Parag,
    You may select the Priority in the initial screen of IW31 and the dates will shift accordingly, if you maintained the Relative Start &/or Relative End in
    SPRO > Plant Maintenance > Maintenance Processing > Maintenance & Service Orders > General Data > Define Priorities > Define Priorities for Each Priority Type
    If you want to change date based on Priority on the Order header screen, it's not possible in the standard to my knowledge, but you may easily develop an enhancement utilizing the user exit
    IWO10012 Maintenance order: Priority handling on central header
    or
    IWO10009 PM Order: Customer Check for 'Save' Event

  • Start/Finish vs Schedule Start/Finish vs Actual Start/Finish

    Hi,
    I'm new to MSP 2013 and I'm confused on the way MSP handles Start/Finish dates. While I understand the rational of it adjusting the schedule so you see how actual dates impact the schedule, I find it confusing that there are multiple columns with different
    labels performing the same function?
    "Scheduled Start" would lead you to believe this is your initial planned start date and remains static while "Actual Start" would be, well, the Actual Start date. So one value by definition would be different than the other, yet when any
    of these dates, "Scheduled Start", "Actual Start", or "Start" are changed, they all change to the same value.
    My questions are:
    Why do the "Scheduled Start", "Actual
    Start", and "Start" dates all change to the "Actual Date" when entered?
    Is there a scheduling technique or purpose for this to work this way?
    Also, since the "Scheduled Start" date changes, how does MSP 2013 handle Earned Value?
           Since Earned Value calculations rely on your Planned Value which would be based on the Budgeted Cost of Work Scheduled          and the Earned Value which is
    the Budgeted Cost of Work Performed vs. the Actual Cost of the Work Performed at "a point          in time," how could it provide a reliable figure if the scheduled date is moving? Is it using the "Baseline Start/Finish"?
    I hope you can answer this for me or direct me to a resource that can. Thank you for your consideration.
    Marc      

    Marc,
    When Project was first released there were only two basic start field, Start and Actual Start (in addition of course to the Baseline Start field and a few others). With the release of Project 2010, a manual scheduling mode was introduced. That's when things
    got a little more confusing. Instead of leaving the Start date as is, the Start field was converted to a text field and the old Start field was renamed as Scheduled Start. When in auto-schedule mode, both Start and Scheduled Start are exactly the same.
    Now to answer your questions. To keep it simple, let's assume you are using auto-scheduling.
    1. In order to keep the schedule dynamics intact, it is necessary to update the Start field to agree with what really happened, namely with the Actual Start date. If you do not enter anything into the Actual Start field, Project automatically assumes the
    task started as scheduled, on the Start date.
    2, Yes, Project does its scheduling based on the current plan which is represented by start, finish and other data. Once the project starts, that current plan must be updated so the actual date values come into play. As noted in the lead in paragraph, Scheduled
    Start and Start are the same for auto-scheduled tasks.
    3. Earned value is based on the actual values and the saved baseline data. The "point in time" you refer to is the timescaled data as of the status date.
    Hopefully, this clear up at least some of your confusion.
    John

  • PM Orders Basic & schedule finish date

    Hi Experts,
    I want the basic start & finished date similar to schedule start & finishe date  in any condition.For e.g. if i change the basic start & finished date the schedule start & finished date should become similar to basic start & finish date and vise versa.May I know how to do the customization setting.
    AR

    AR,
    This can be done through transaction OPU7.
    For the plant and order type combination, set the Adjust dates field to either"Adjust dates, Adjust dependent requirements to operation start" or "Adjust dates, Adjust dependent requirements to Order start".
    Regards
    Narasimhan

  • Resource Durations (Start /finish) are not align with activity durations

    Gurus,
    My Resource Durations (Start /finish) are not align with activity durations and hence the Budgeted % are going crazy. Any idea?

    hi,
    the default start/finish dates for resource assignments are the activity start/finish dates. if for any reason you changed that, you can check and reset both Original Lag and Remaining Lag to 0 for all/ some of your resource assignments by adding the columns in the Resource Assignments window and performing either a fill down or a Global Change operation. let me know if you need help with any of these.
    best of luck.

Maybe you are looking for