when i create a sales order today (18102008) sales order cannot be created  for the delivery date before 20.10.2008
how the system is checking the 2 days duration for delivery date - which table is having this duration days.
is it dependent on sales order type.....
actually i checkeup in V0V8 - even then i couldn't  solve this error when i am creating the sales order.
Pls suggest

Dear Selvamuthu
In normal circumstances, you can create as many as sale orders as you can irrespective of delivery date, and system will not  prevent to create unless you apply some user exit for some reason.
Check any user exit is applied for that sale document type where some logic would have been written in such a way that if stock is available, sale order can be created.
thanks
G. Lakshmipathi

Similar Messages

  • Sales order as complete and change the delivery status.

    Hello All,
    We  produces an order but then the customer calls and does not want the material so we in turn will scrap the material against the production order using transaction MB1A mvmt type 951 E. 
    Since the material were scrapped and no material were shipped against the sales order, the sales order u201Coverall statusu201D remains open and the delivery status is u201Cnot deliveredu201D.
    To close the order  we u201CRejected line itemu201D and moved on.
    I would like to know if there is another way we can set the sales order as complete and change the delivery status. 
    Regards
    Amit

    Hello,
    you can use the status profile for the same. but a better way would still be to use the rejection reasons . the rejectionr reasons are very well integrated with the document flow as well as transfer of requreiemnts to Production
    so a best practise would be to use rejection reason
    hope this helps
    Thanks
    akasha

  • Foreign key cannot be created for the selected field A907-MWSKZ

    Dear Guru's,
    I am having the requirement for creation of access sequence having country/Plant/vendor/tax code but during creation of condition table i am getting the error as
    Foreign key cannot be created for the selected field A907-MWSKZ.
    Anything i am missing please let me know.
    Regards,
    Umesh

    Hi Umesh,
    Actually i am also facing exactly the same problem as mentioned by you that is "Foreign key cannot be created for the selected field A769-MWSKZ ".
    I think you found some solution regarding this..can you please help me to solve it.
    Looking forward for your prompt reply..
    Thanks & Regards,
    Sandeep Sharma

  • Depot Sales - Goods issue not done for the delivery

    Hello Experts,
    I am trying to capture a Excise Invoice in the Depot Sales Process TCode - J1IJ.
    I am getting the follwoing message - GI not done for the Delivery.
    Process which we are following here is
    Depot
    SO - Delivery - Picking - Packing - J1IJ - Shipment creation - Shipment Planning - Loading Start - Shipment Start (Will do PGI) - Shipment end (Will create invoice & Excise Invoice).
    Excise invoice is captured during MIGO at Depot.
    Can you please suggest..
    Thanks & regards
    Mahesh

    Hi mahesh
    Change the process to following manner
    Depot
    SO - Delivery - Picking - Packing - Shipment creation - Shipment Planning - Loading Start - Shipment Start (Will do PGI) - Shipment end -J1IJ(Will create invoice & Excise Invoice).
    u r problem will be solved.
    Regards
    kedasu.a

  • Urgent :--------- Transfer Requirement creating for the delivery

    Hi Gurus,
    For a Delivery document Transfer Requirement and as well as Transfer Order is creating,
    Based on Transfer Order picking was happening in the WMu2026 the PGI for the delivery and Billing properly is happening.
    But Open Transfer Requirements are laying for each delivery document, here source is respective storage type and bins and destination storage type 916 and bin is delivery number.
    Please suggest me how the it is happening where we did configuration mistake.
    Regards
    madhu

    Hi,
    I think you set TR creation indicator for IM mvt 601 (reference mvt) under SPRO > LE > WM > Interfaces > IM > Define Movement Types - LE-WM interface....
    Please check it. If it is set delete it.
    BR
    Csaba

  • AFS ARun: sales order not been selected for the allocation run.

    Hi,
    I am setting up the Purchase-to-Order (similar to Indiv PO item sales order) Process for SAP AFS.
    When doing the Allocation Run (trx J3AT) after Goods receipt of Sales order stock, I get an error that ARun terminated because no requirements were selected. The delivery check report (/AFS/LIEF_CHECK) indicates that the sales order has not been selected for the allocation run.
    For this process, I have set-up an Allocation type with
    1.     Requirement selection that does not exclude MTO/PTO orders
    2.     Set-up stock selection which includes physical stock type for MTO/PTO orders to the customer special stock MSKA with the segment KALAB.
    Can someone suggest what I may have missed?
    Regards,
    PD

    Hi Pankaj, I have same exact issue. How did you fix this ?
    Thanks,
    Mahesh

  • Repeat credit check does not happen for already released sales orders when CMGST =D, for the second time using FM SD_ORDER_CREDIT_CHECK

    Hi,
       I have written a routine which will call the FM SD_ORDER_CREDIT_CHECK whenever there is a rejection and again unrejection of a same sales order, we are only concerned about already credit released sales orders, the scenario is as follow
    1). Sales order created in the system --> Credit check --> Credit blocked
    2). Release credit block manually CMGST =D
    3). Reject sales order then unreject the same
    4) Routine will determine rejection and unrejection of the order while saving and will call the FM SD_ORDER_CREDIT_CHECK
    5)   The order is credit checked and blocked if necessary
    All goes well till this point
    but when the same sales order is rejeceted and unrejected multiple times either partially/ fully then the Custom routine calls the FM for credit check but the FM fails to put the order back on credit hold
    in short the FM works only for the first time incase of mutiple rejection and unrejection of teh same sales order then the FM SD_ORDER_CREDIT_CHECK fails to put the order back on credit hold from the second time onwards
    if some one any idea of the behavior of this FM please share your thoughts and inputs . thanks !!

    Issue resolved
    The Standard FM “SD_ORDER_CREDIT _CHECK” uses the field  “Release date of the document determined by credit management  VBAK – CMFRE”
    For any sales order that is manually credit released in a single day, Only one credit check is triggered (per day) if there is any change in the sales order and then the order goes back to credit hold and if again the order is manually credit released for the second time in a single day there will be no credit check  (still the order will pass into FM but  the update entry in the internal table will be blank)this is a standard functionality
    Process of rejection and unrejection :
    Blocked order -->released-->blocked again (first time after manual release same day) unrejected (same day) -->but no credit check  (all this in a single day)
    note : OVA8 - released document still unchecked = 0 Days , Deviation %= blank

  • Foreign key cannot be created for the selected field S999-PRCTR

    Hi there,
    Why is there Profit Center be a characteristics field when it comes to LIS?? Anyone tried to assign Profit Center field as a char field for the LIS structure?
    Thanks.
    Regards,
    Andrew

    Depending on what chars do you bring in from LIS.
    If "that" is related to profit centre, then you can.
    Ravi Thothadri

  • How to cancel the second ATP after changing the delivery date in the SO

    Hello,
    our solution creates automaticly a production order accorting to sales order.
    The system calcule ATP for each items at the creation of the sale order.
    Sometime, we change the delivery date on the scheduled line and SAP do another ATP. If the composants are not available we get an TSUP status on the order production.
    How can we cancel the second ATP ?
    Is it possible to cancel it when we change delivery date ?
    Thanks
    Regards
    Pierre

    I think its not possible to skip the atp during change of the sales order.  All these determinations will trigger before saving the order
    regards,
    Ramana

  • Can the Delivery Date be left with no value in Purchasing Order?

    Hi SAP Experts,
    Good day!  I just want to ask if it is possible for the Delivery Date in the Purchase Order to be left with no value?  Whenever we remove the delivery date, it comes back when we save the PO.  Is there a way for it to be blank?
    Thanks,
    Matt

    hi Senthil P,
    Here is the situation.  For most of the PO that we are creating, we rarely use the delivery time.  However, there are rare occasions where we put the delivery date.  We made an enhancement of our PO print out and the date in the delivery date field was taken from the table.  Is there a way where the delivery date in the printout can be left blank and show it when we need to?
    Thanks,
    Matt

  • Why does old sale order (The deliver date before current date) show VSF (independent requirement) in MD04?

    Dear All,
    I face one issue, the old sales order (the delivery date before current date) has became VSF (independent requirement) in MD04, could someone let me know why and how to fix it?
    Take 01.09.2014 as example, we have one 50PC's sales order with delivery date as 25.08.2014, in MD04, the system will show two independent requirements, one is 50PC's customer order and another is 50PC's VSF.
    We are looking forward to your kind help and answer, thanks in advance!
    Best Regards,
    Gavin

    Hi Gavin
    If I understood the issue correctly, system is showing both the sales order and the PIR on the same date, right?
    If this is the case, it's probably a PIR consumption issue. Take a look on the following note, especially question 10:
    772856
    FAQ: Consumption of planned independent requirements
    BR
    Caetano

  • System does not propose the delivery date based on factory calendar

    Hi,
    I am creating a sales order for a delivery date for this sat which is (2/22/09)
    I have maintained 2 separate calendars for
    1) shipping point
    2) for the route
    The route has a transit time of 1 day and the calendar has sat and sunday as non working.
    the Shipping point has a pick/pack time of 1 day and the calendar has sat and sunday as non working
    The material is available in the warehouse
    Now when i create this sales order i enter the delivery date as 2/22/09, the system does not propose me the delivery date of monday (i.e 2/23/09) It accepts the 2/22/09 delivery date.
    In the schedule line i do see the date as 2/22/09 only.
    The delivery was created with the following dates
    Picking = 2/17/09
    Transportation Planning = 02/18/2009
    Loading =02/18/2009 
    Planned GI= 02/18/2009
    Delivery Date = 02/22/2009
    How can the system give me the delivery date of a sunday when the calendar doesnt allow sunday as working day.
    Also the route time is 1 day in transit so i am not sure why the system is proposing a 3 day transit time?
    Can any one explain the behaviour of SAP for the delivery date logic

    Dspsac,
    Delivery date can be any date.  For instance, if your customer insisted on a Sunday delivery, you would accommodate him, regardless of any calendar.
    From the delivery date, the system counts backwards USING THE FACTORY CALENDAR ASSIGNED TO THE ROUTE by the number of days in the route.  You have to consult the FC assigned to your Route to determine if the GI date has been properly calculated.
    From the GI date, the system counts backward Pick/pack time, using the shipping point calendar, to arrive at Material availability date.
    Calculations are explained in SAP online help
    [Transportation and Delivery Scheduling|http://help.sap.com/erp2005_ehp_04/helpdata/EN/dd/5607e7545a11d1a7020000e829fd11/frameset.htm]
    Regards,
    DB49

  • SALES ORDER CAN NOT BE LESSER THEN POSTING DATE

    Hi everyone
    Can any one tell how can I restrict sales delivery date less then posting date. Like if user create a sales order on 22,03.14 then delivery date should not be before 22.03.14. I saw in system if I enter sales delivery date before 22.03.14 then system accept the date

    Hi,
    Try this:
    IF @transaction_type in ('A') AND (@OBJECT_TYPE='17')
    BEGIN
    If exists (SELECT t0.docentry FROM ORDR T0 WHERE T0.[DocDueDate] < T0.[DocDate] and  T0.DocEntry =  @list_of_cols_val_tab_del)
    Begin
    SET @error = 10
    SET @error_message = 'Not allowed to enter delivery date less than posting date'
    End
    End
    Thanks & Regards,
    Nagarajan

  • Using BAPI_SALESORDER_CHANGE to update the delivery date

    Hi All-
    I am using BAPI_SALESORDER_CHANGE, to update the delivery date on the schedule lines...If I have 2 lines of schedule, needs to be updated the second one ETENR '0002'...
    Bapi returns message that successfully processed, when I go back and look at Sales order, I don't se any changes on schedule line..
    I am pssing into BAPI, sales doc and schedule line with the delivery date and the flag 'U'..and also I am using BAPI commit...
    But, let me know if I am missing something and also let me know is it possible to change schedule delivery date or not?
    Thanks,
    Sony
    Please try to use a meaningful subject.
    Edited by: Rob Burbank on Feb 25, 2009 2:08 PM

    give a meaningful title to ur thread, so that, people get u back quickly. Just tip that, try to do ur requirement online, then Observe How the system is behaving....thanq

  • How to get the pricing hierarchy based on the delivery date for sales order

    Hi,
    How to get the pricing hierarchy based on the delivery date for sales order other than system date.
    My requirement is to get the Pricing hierarchy based on the delivery date other than system date.
    Waiting for kind response.
    Best Regards,
    BDP

    HI Sai,
    please refer teh document already how to write FM based extration on generic extractors.
    and here  the logic to find the latest records values:-
    -> get the data in an internal table
    ->Sort the internal table data based from date descending
    -> Using READ statement , we can read the first record of the table which is nothign but your latest record.
    Regards.
    Sakthi

Maybe you are looking for

  • How can i get a refund for photoshop element

    I don't know why it's taking so long to get a refund on my photoshop element

  • Personal domain and idisk

    Hi, my question is, can i use the idisk to host my own personal website that is currently being hosted at another site, and use my own domain name? I am not using iweb but i do have idisk. I simply want to move my current website thats being hosted e

  • Function module to read Purchase Requestions

    Hi all, As you must be knowing that  in /SAPAPO/RRP3  transaction we can create the Purchase Requisitions. Now my requirement is that I want to read all the Purchase Requisitions from today onwards for all product and location combination. Please sug

  • Reg. IDOC's

    Hi All Can any please help me in getting the TCODE(the tcodes other than WE81, WE82) for viewing all the Standard IDOC's provided by SAP and the corresponding segments of those IDOC Types. Thanks in advance ... Vijay.

  • Varaint  :Variant var_1 ofprogram /1BCDWB/DBVBAK is not thecurrent version?

    Hi All, I am trying to save the variant for vbak table which i have to use on daily basis for some reporting purpose in Production system. But Next day it throws an error stating : "Variant var_1 of program /1BCDWB/DBVBAK is not the current version"