I have a requirement to update a certain project (project B) whenever a certain other project is changed (project A).
For that, I am planning to create a subsystem that is called whenever project A is changed (works fine).
I am also able to load project B (cl_dpr_appl_object_manager=>LOAD_PROJECTS ).
However, how can I save project B?
Using cl_dpr_appl_object_manager=>SAVE_CHANGES will not work, since it will also save project A and therefore cause an endless loop.

Hi Daniel,
  A subsystem is a good idea. However, I am not sure you would run into an infinite loop. When you call a save on Project B, yes a save will be called on Project A as well. However, since A has already committed, there will be no changes on it (the method has_changes() will fail) and hence save will do no further processing.
  However, you might run into issue with DPR_TRANSACTION_MANAGER if not anything else.
  While you will have to play around the transaction manager, it would be a good bet to call the save in the method INITIALIZE_AFTER_SAVE() of the subsystem, since that will be called after the first project has been persisted.
  Do use the BAPI as mentioned in the other reply and not he save_changes() method of the object manager.
  If project B will be updated once 'save' is pressed, then another idea would be to write an exit that will be called immediately when the 'save' button is pressed and does all the required updates to B before handing control back to project A. Only one save will then be performed and both the projects will be committed (since both are in the same session). In this case, be sure that the subsystem doesn't do a save since the save of the first project will be sufficient.
Hope this helps,
Best Regards,
Prashanth

Similar Messages

  • Strange ... Projects opened from Projects View are no longer (3.3) selected on the Library tab of the Inspector.

    Strange goings on here with my Libraries: Projects opened from Projects View are no longer (3.3) selected on the Library tab of the Inspector.  When, in Projects View, I double-click a Project, that Project's contents are shown in the Browser, but the selection shown on the Library tab of the Inspector remains on "Projects" near the top of the tab.
    This is, imho, _very very very bad_.  Can someone confirm this behavior on their machine?  Is this announced or expected?
    Thanks.

    Hi Kirby,
    I never noticed!
    Can someone confirm this behavior on their machine?
    Confirmed! (on MBP und iMac)
    Is this announced or expected?
    Don't know - it does not follow from the release notes, as far as I understand them.
    Regards
    Léonie

  • How to get project GUID from project name?

    How to get project GUID from project name in Campaign mgmt ?

    hello,
    have a look in table CGPL_PROJECT.
    regards,
    Frédéric

  • Open "project.app" from "project.osx"

    Hi everyone,
    I created a Director splash using Director MX2004 on WindowsXP. I published my project for Mac ("project.osx"). I also have a seperate project created in Flash CS4 that was published for Mac ("project.app"). Using buddyAPI, I cannot open "project.app" from a button used on "project.osx". Is this even possible to do? I cannot find any type of documentation on this issue...
    thank you in advance for your help.
    Rafael.

    Well.... I figured it out. I changed my delimiter to ":" for Mac (instead of "\"). Also, I was NOT telling it to open "project.app", I was telling it to open "project.osx".
    Rafa.

  • Copied project missing from Project Library

    Copied a project from one desktop to an external hard drive than to a different iMac. Can see the project file in the Movies folder, but can't get iMovie to open it. Thoughts?

    You can't copy the project from the Finder of OS X, you have to do any moving and copying from within iMovie.
    Also you can Consolidate which combines the Project and the associated clips from your Events folders.
    The Project itself doesn't contain the actual video but rather references to the clips and clip segments you used from your events.
    In iMovie go to Help, type Copy Project in the search and select the first entry. It explains.
    Also you should search Consolidate and have a look at that.

  • Updating SharePoint online teamsite list with Project name from Project center (Project online)

    Hi,
    I would like to have the name of the project on a teamsite list automatically when a new project is published. Any workaround or best practice suggestion is highly appreciated. Thanks
    I have Office 365 E4 subscription, fyi.
    Ashraf
    www.MrOffice365.com

    Hi Ashraf,
    I'm not sure if it answers your need, but you could add the site list webpart on the PWA home page (or in any other PWA page):
    Hope this helps,
    Guillaume Rouyre, MBA, MVP, P-Seller |

  • Unable to Connect to Project Server 2013 from Project 2013

    Hello,
    I'm trying to connect to Project Server 2013 from Project 2013 but it is not working.
    I'm able to connect to the PWA from IE 10 on Windows 8 Enterprise
    On Project 2013, I configured account to connect to Project Server 2013 and I checked the "Log on to Project Server from Project Professional" global permission and it is on. 
    Any idea why it is not connecting?

    So you are using Project Online and not Project Server 2013? Can other users access Project Online from Project Pro successfully in your organisation? If it was an authentication issue, Project would prompt for credentials.
    Paul
    Paul Mather | Twitter |
    http://pwmather.wordpress.com | CPS

  • BAPI for Getting Project Profiles in Project System

    hi,
         Can any 1 tell me the BAPI to invoke to get project profiles from project system.
    Thanks,
    Debashish Sarkar

    see if this thread is of any help
    Re: File Inputfield - ABAP functions to store files?

  • Hi i have just completed an imovie project and tried to save a hard copy on the desktop so i dragged the project file from the home page then movies folder and now the prioject seems to be lost , how can i get it back ?

    hi i have just completed an imovie project and tried to save a hard copy on the desktop so i dragged the project file from the home page then movies folder and now the prioject seems to be lost , how can i get it back ?

    It's a Finder feature, related to Quick Look. You can hit the space bar in the file list to get a preview.
    If that doesn't work, you may have an issue witha  preference file or similar. I find rebuilding the launch databse works quite well resilving tis kind of thing, as does trashing Finder preferences

  • Project Save "Getting Queued" from PWA

    Hi -
    In the past we have seen these save jobs that get stuck in the "Getting Queued" status; but these were related specifically to save jobs submitted from MS Project. In some cases these were bandwidth related (poor network from the client to the
    server) and in others, a case of the user closing the client software before the job has sent fully to the server.
    But now in PS 2013, we have seen this occur when the save job is submitted from PWA!!
    Has anyone experienced this or have any insight???
    Thanks
    Shane
    Shane O'Hanlon (Accenture)

    Shane,
    One more thing I would suggest you to check in that case, is the Project Schedule Template. I have seen this issue in the past, when my schedule template attached to the EPT was corrupt (or) has an issue in some way.
    Take the schedule template off and see if things work. if yes, then you will need to get into the troubleshooting of the template (or) build a new one.
    Cheers,
    Prasanna Adavi, Project MVP
    Blog:
      Podcast:
       Twitter:   
    LinkedIn:
      

  • Unable to edit the Project details from PWA in Project server 2013

    I am Migrating the project from MS Project 2007 to MS Project 2013.In that i save the project as a file first in 2007 and then open that file in  MS Project 2013 And publish it.But in some Project when i am Trying to change the projects details from
    PWA in Project server 2013 and then trying to save then the projects are not saving and are generating the error as shown below
    •GeneralQueueException:◦GeneralQueueException (9131). Details: id='9131' name='GeneralQueueException' uid='f7bb5d93-20e9-e411-b302-005056ae159c' messageID='2' exception='System.TimeoutException: This request operation sent to net.pipe://localhost/pscalc_13c43af4a7d34a2c8145b776b325a865
    did not receive a reply within the configured timeout (00:05:00). The time allotted to this operation may have been a portion of a longer timeout. This may be because the service is still processing the operation or because the service was unable to send a
    reply message. Please consider increasing the operation timeout (by casting the channel/proxy to IContextChannel and setting the OperationTimeout property) and ensure that the service is able to connect to the client. Server stack trace: at System.ServiceModel.Dispatcher.DuplexChannelBinder.Request(Message
    message, TimeSpan timeout) at System.ServiceModel.Channels.ServiceChannel.Call(String action, Boolean oneway, ProxyOperationRuntime operation, Object[] ins, Object[] outs, TimeSpan timeout) at System.ServiceModel.Channels.ServiceChannelProxy.InvokeService(IMethodCallMessage
    methodCall, ProxyOperationRuntime operation) at System.ServiceModel.Channels.ServiceChannelProxy.Invoke(IMessage message) Exception rethrown at [0]: at System.Runtime.Remoting.Proxies.RealProxy.HandleReturnMessage(IMessage reqMsg, IMessage retMsg) at System.Runtime.Remoting.Proxies.RealProxy.PrivateInvoke(MessageData&
    msgData, Int32 type) at Microsoft.Office.Project.Server.Interfaces.ICalcService.OpenProjectRemappedProject(CalcServiceCallState callState, Guid realProjectGuid, Guid remappedProjectGuid, EngineSessionState& sessionState, EngineSessionType sessionType,
    PSError& psError) at Microsoft.Office.Project.Server.BusinessLayer.CalcServiceChannel.OpenProjectRemappedProject(CalcServiceCallState callState, Guid realProjectGuid, Guid remappedProjectGuid, EngineSessionState& sessionState, EngineSessionType sessionType,
    PSError& psError) at Microsoft.Office.Project.Server.BusinessLayer.CalcServiceProxy.<>c__DisplayClass2.<OpenProjectRemappedProject>b__1(ICalcServiceChannel calcServiceChannel, PSError& localPsError, EngineSessionState& localSessionState)
    at Microsoft.Office.Project.Server.BusinessLayer.CalcServiceProxy.<>c__DisplayClass6e`1.<RunCalcServiceOperation>b__6c() at Microsoft.Office.Project.Server.Base.IdentityUtilities.<>c__DisplayClass1`1.<RunWithAccessToAppTierServices>b__0()
    at Microsoft.SharePoint.SPSecurity.<>c__DisplayClass5.<RunWithElevatedPrivileges>b__3() at Microsoft.SharePoint.Utilities.SecurityContext.RunAsProcess(CodeToRunElevated secureCode) at Microsoft.SharePoint.SPSecurity.RunWithElevatedPrivileges(WaitCallback
    secureCode, Object param) at Microsoft.SharePoint.SPSecurity.RunWithElevatedPrivileges(CodeToRunElevated secureCode) at Microsoft.Office.Project.Server.Base.IdentityUtilities.RunWithAccessToAppTierServices[T](Func`1 action) at Microsoft.Office.Project.Server.BusinessLayer.CalcServiceProxy.RunCalcServiceOperation[T](CalcServiceOperation3`1
    func, EngineSessionState& sessionState, String scopeName) at Microsoft.Office.Project.Server.BusinessLayer.CalcServiceProxy.OpenProjectRemappedProject(Guid realProjectGuid, Guid remappedProjectGuid, EngineSessionState& sessionState, EngineSessionType
    sessionType) at Microsoft.Office.Project.Server.BusinessLayer.ProjectEngineUpdate.OpenProject() at Microsoft.Office.Project.Server.BusinessLayer.ProjectEngineUpdate.HandleUpdate() at Microsoft.Office.Project.Server.BusinessLayer.ProjectQueueDispatch.HandleProject2(MessageContext
    mContext, ProjectMain project, ServerEventManager sem, ProjectDataSet dataset, Guid projectUid, Guid sessionUid) at Microsoft.Office.Project.Server.BusinessLayer.ProjectQueueDispatch.InternalDispatchMessage(IPlatformContext context, Message msg, Group messageGroup,
    JobTicket jobTicket, MessageContext mContext)'. 
    •Queue:◦GeneralQueueJobFailed (26000) - ProjectUpdate.ProjectUpdate2Message. Details: id='26000' name='GeneralQueueJobFailed' uid='f8bb5d93-20e9-e411-b302-005056ae159c' JobUID='a6fa36de-1fe9-e411-b302-005056ae159c' ComputerName='1af8030b-7714-4c8f-8738-903b73e87a82'
    GroupType='ProjectUpdate' MessageType='ProjectUpdate2Message' MessageId='2' Stage='' CorrelationUID='0a4aff9c-dd6b-7015-87a8-29d876e1540c'. For more details, check the ULS logs on machine 1af8030b-7714-4c8f-8738-903b73e87a82 for entries with JobUID a6fa36de-1fe9-e411-b302-005056ae159c. 
    What will i do .Please help.

    Hi Jeremy,
    Thanks for the reply .I try the steps that is given in link above but its not working.Please suggest something.What
    should i do.

  • Project Pro hangs while opening a schedule from Project 2010 server.

    Hi,
    We have an issue with opening a schedule from Project server 2010. Project client is not responding. when we try to open schedule in PWA. I am getting unable to open file do you want to open in default view. No matter which view I choose keep getting the
    same error. The only view i can see resource view however it will not let me edit. I did notice Project Manager had entered resource names first, last name format which do not exist in our resource pool.  We can open other schedule except this particular
    one. 
    Thank you

    Obviously, my first thoughts are that this plan is corrupted in some fashion. Entering Resource names differentluy should not cause this issue, they will just not be recognized as Enterprise Resources by the system.
    Are you experiencing the issue if you try to open the schedule from PWA? If you are able to open from PWA, try publishing it from PWA and see if it throws any errors.
    Also, how about trying it from a different machine?
    And finally, it might be worthwhile to check if you have the latest Client Update for Project installed (or atleast matching with the server).
    If none fof these work,
    a) you could try restoring it from Archive Database (assuming you have a daily schedule backup running)
    b) If you are able to open it from another machine, you could use the "Save for sharing" feature to try and resolve any corruption with the schedule itself.
    Prasanna Adavi,PMP,MCTS,MCITP,MCT http://thinkepm.blogspot.com

  • Need someone on PC to open and save Pro 1.5 project file in CS3

    I am trying to salvage one of my old project files from when i worked on a PC. i can't do this because CS3 for Mac won't import old PC project files.
    If anyone would be so kind as to accept my small project file and save it in Premiere Pro CS3 on their PC i would be much obliged.
    -Dave

    theaveragedave,
    On the Mac, the Project file will *usually* appear without any file extension. Instead there will be one, or more, "helper/locator" files. These will usually be the filename, but with "._" (or similar) prepended to it. These are of no use to a PC.
    All that I did was Copy the Project files to a new folder, and in it, added the ".prproj" extension. All opened fine. (Actually, since this was a pre-Pro version, I think that I added ".proj," but you would use ".prproj.")
    If I were going to "convert" the Project, I'd gather up all Assets, keeping the folder structure exactly the same. Gather up the Project files (renaming, as is necessary), and furnish all of this to the person doing the conversion. This *should* keep your Asset Links working*. The other option would be to just convert the Project file, but then you will have to manually re-Link every Asset. If one gets lucky, and the Assets are stored in one folder, PP *might* be able to have you locate the first missing Asset, and then automatically locate the rest. I hesitate on this last comment, because you will have converted the Project, so things do not always work 100% the way they would otherwise. I had to do a lot of re-Linking, but I was jumping several versions and from Mac to PC. Still, once the Assets were re-Linked, all has worked perfectly.
    Good luck finding a PC operator with CS3. Should not be that hard. Wish I could help you more, but CS2 won't cut it, for what you need to do.
    Hunt
    * Keeping the drive letter the same will be a big step to keeping your links. Let's say that you are working on your D:\ drive (sure that Mac would call it something else), and you copy over to an external. I'd have the PC operator copy the Assets (with folder structure) to their D:\, just to keep the Links. Does this make sense?
    PS one little consideration is Mac's not using NTSF HDDs and the file size limitation of Fat-32 HDDs. However, you already have your Project and its Assets on a Mac, so this is probably moot.

  • Publication of the big-sized Enterprise projects from Project Professional 2013 to Project Server 2013 takes about 60+ minutes.

    Dear Sirs,
    I need your support over the following MS EPM 2013 issue:
    Publication of the big-sized Enterprise projects from Project Professional 2013 to Project Server 2013 takes about 30+ minutes. We
    need to reduce this total publication time down to acceptable working values 10+- minutes.
    Environment information:
    Single App Server (Virtual): 16 Gb RAM, x64 4xCPU, HDD > 50 GB free disk space, OS Windows Server 2012 Standard Edition x64 Service
    Pack 1, MS SharePoint Server 2013 and MS Project Server 2013 with CU December 2013 (KB 2850024) applied.
    Single RDBMS MS SQL Server (Virtual): 8 Gb RAM, x64 4xCPU, HDD > 200 GB free space, OS Windows Server 2012 Standard Edition x64 Service
    Pack 1, MS SQL Server 2012 x64 SP 1 Enterprise Edition.
    We have 1Gbit LAN between APP, DB server and 1Gbit LAN between APP and Proj Prof Client.
    Yes, we are on the way of migrating to the Prod environment
    with 3-tiered architecture (with SP1 slipstream and CU December 2014 applied), but this issue also
    presents there.
    Project’s file information:
    Tasks in the file: [~4900], resources in the file [~396] enterprise task’s custom fields used in the file [~23].
    Project save procedure for this new project would last about 7 minutes. Project publication would last about 47 minutes. We noticed that
    tasks synchronization process took about 1 second for each ~2,5 tasks, to add them to the sharepoint tasks list. So for all 5148 tasks it took about 5148/3/60 =  34 minutes. Other 13 min was used for reporting database publication and other tasks relevant
    for new sharepoint site creation.
    Case 1: Issue description:
    During the Enterprise project’s file save and publication we have the following sharepoint 2013 log messages:
    07.31.2014 12:43:17.22 Microsoft.Office.Project.Server (0x0358) 0x3D5C SharePoint Foundation Monitoring b4ly High Leaving Monitored Scope
    (Persisting list changes). performing time =376.068676326181 22dca99c-4696-70f1-e9e2-06851d0bcffd
    07.31.2014 12:43:17.69 Microsoft.Office.Project.Server (0x0358) 0x3D5C SharePoint Foundation Monitoring b4ly High Leaving Monitored Scope
    (Persisting list changes). performing time =361.652807828928 22dca99c-4696-70f1-e9e2-06851d0bcffd
    It shows that sharepoint spend at least ~350 milliseconds (or 0,35 sec*4900 tasks = 1715 sec, or 28,5 min) for each task update during
    project publication. And we also have another log file that shows that about 0,7 sec (or 0,7 sec*4900 tasks = 3430 sec, or 57 min) sharepoint spend for save each task in project file to project server. So total save and publication time more then 60+ minutes
    for that project file. The same result we have even if user didn’t do any changes at the project file.
    We use only enterprise projects (dbo.MSP_EpmProject_UserView.projectvisibilitymode = «False»), and do not use sharepoint tasks lists,
    but the synchronization between MSP Plan and SharePoint tasks list works at any case.
    Case 2: Issue description:
    - For the second test we created a new project with new sharepoint project’s site on basis of our «issue» project, with total amount
    of tasks in it of 5148 (yes, we increased the tasks list default limit at the sharepoint site up to 6000 items in it – standard limits for sharepoint view list – 5000 items).
    - Project save procedure for this new project would last about 7 minutes. Project publication would last about 47 minutes. We noticed
    that tasks synchronization process took about 1 second for each ~2,5 tasks, to add them to the sharepoint tasks list. So for all 5148 tasks it took about 5148/3/60 =  34 minutes. Other 13 min was used for reporting database publication and other tasks
    relevant for new sharepoint site creation.
    -Then we deleted the
    tasks list for that new test project from the sharepoint site and republish the project plan one more time. This time project save procedure took about 7 minutes, project publication about 2 minutes and 3 minutes for other relevant queue jobs. So total time
    is 12 minutes.
    As a conclusion: yes, we have determined
    the exact problem - during synchronization process (from Project Server to SharePoint) it perform copying all tasks and related data from Project to SharePoint in spite of fact that you changed only ONE task or ALL of them. At any case, synchronization will
    copy ALL of them from Project Server to SharePOint task’s list.
    Our workaround is to disable the task’s synchronization for such big-sized project plans:
    – to delete the SharePoint «tasks» list at the SharePoint site tied with project plan.
    - or deattach the SharePoint site from the project plan.
    Thank you for reading this topic, please if you also forced with such issue provide us any known workaround or maybe any official response
    \ feedback from MS about it.
    Thank you in advance,
    Best Regards, Andrey

    Regarding my topic, I also said that every time when sync works it updates All items from project’s plan at Project Server to corresponded task’s list at SharePOint server. Inspire of the fact that you changed only One task or group /
    all of them at your project’s plan.
    And it seems to me and my colleagues that it’s probably (maybe) a “bug” at the product. Here is what we have if looked a little bit closer to the code:
    Share Point determines what task to sync from Project’s plan to sharepoint list. To do that sharepoint needs to know was that task changed or not, based on the following fileds (check SQL stored procedure “[MSP_READ_TASKS_FOR_SYNCRONIZATION]”):
    TASK_UID    TASK_NAME    TASK_START_DATE    TASK_FINISH_DATE    TASK_PCT_COMP    TASK_PARENT_UID    TASK_OUTLINE_NUM   
    WSS_LISTITEM_UID   TASK_ID    TASK_IS_ACTIVE
    We noticed that at any case synchronization performs for all tasks, EXCEPT the ROOT one. Then we looked at the comparison of TASK_PARENT_UID field. So sharepoint compares TASK_PARENT_UID with ParentID (this is internal name for lookup
    field “Tasks” at the Sharepoint, and it stores their values at the format "ID;#Title").
    And comparison performs like following:
    SharePoint looks for Task at the Tasks’s list corresponded to Project’s plan with ID represented at the TASK_PARENT_UID field. Then it takes SharePoint ListItem ID (“int” type) and store it to the “num” parameter;
    num = this.GetCachedListItemByUniqueId(listItem.ParentList, nullable.Value).ID;
       2.Then it compares “num” with task’s “ParentID” at SharePOint as follow with operator “!=”:
    ((SPItem) listItem)["ParentID"] != (System.ValueType) num
       3. If comparison was success (true) – then it tell us that values (at the Project’s plan for tasks) was changed, then it need to be synchronized. Corresponded Method setup “true” flag, and then returns it.
    The “bug” is that this expression at the Step 2 will always return “true”, because in fact it compares “string” (see above – that this is lookup field at SharePoint side)
    with “number”. For example if the parant task ID is “55”, then we get:
    "55;#Task 1" != 55
    And by the rules of .Net the “string” will never equal “number”
    Furthermore this is approved by the SharePoint logs:
    In that case we always get the note “Setting ParentID to” at the logs (we see it if turns on Verbose for “Project Server” -> “Sharepoint Integration” category).
    So at any case of publishing project’s plan we always get that note at the logs for tasks that have Parent task, and we have Parent for all of them EXCEPT the ROOT one, exact logs represented further:
    10/15/2014 02:37:32.26    Microsoft.Office.Project.Server (0x07D8)    0x06E8    Project Server    Sharepoint Integration    ado0d   
    Verbose    Setting ParentID to 1    bf2fc29c-7727-b00d-fa4a-34f22ea9ec1d 10/15/2014 02:37:32.62    Microsoft.Office.Project.Server (0x07D8)    0x06E8   
    Project Server    Sharepoint Integration    ado0d    Verbose   
    Setting ParentID to 1    bf2fc29c-7727-b00d-fa4a-34f22ea9ec1d 10/15/2014 02:37:32.63    Microsoft.Office.Project.Server (0x07D8)    0x06E8    Project Server   
    Sharepoint Integration    ado0d    Verbose   
    Setting ParentID to 1    bf2fc29c-7727-b00d-fa4a-34f22ea9ec1d 10/15/2014 02:37:32.67    Microsoft.Office.Project.Server (0x07D8)    0x06E8    Project Server   
    Sharepoint Integration    ado0d    Verbose   
    Setting ParentID to 1    bf2fc29c-7727-b00d-fa4a-34f22ea9ec1d 10/15/2014 02:37:32.69    Microsoft.Office.Project.Server (0x07D8)    0x06E8    Project Server   
    Sharepoint Integration    ado0d    Verbose   
    Setting ParentID to 5    bf2fc29c-7727-b00d-fa4a-34f22ea9ec1d
    The following is the complete Method’s code from the corresponded reflector:
    private bool UpdateParentID(DataSet taskDS, DataRow row, SPListItem listItem, Dictionary<Guid, SPListItem> redoEntries)
    bool flag = false;
    int index = taskDS.Tables[0].DefaultView.Find((object) DataRowExtensions.Field<Guid>(row, "TASK_PARENT_UID"));
    if (index >= 0)
    Guid? nullable = DataRowExtensions.Field<Guid?>(taskDS.Tables[0].DefaultView[index].Row, "WSS_LISTITEM_UID");
    int num = -1;
    if (listItem.Fields.ContainsField("ParentID"))
    if (nullable.HasValue)
    try
    // STEP 1
    num = this.GetCachedListItemByUniqueId(listItem.ParentList, nullable.Value).ID;
    catch (ArgumentException ex)
    if (redoEntries != null)
    if (!redoEntries.ContainsKey(DataRowExtensions.Field<Guid>(row, "TASK_UID")))
    redoEntries.Add(DataRowExtensions.Field<Guid>(row, "TASK_UID"), listItem);
    //STEP 2
    if (num != -1 && ((SPItem) listItem)["ParentID"] != (System.ValueType) num)
    ((SPItem) listItem)["ParentID"] = (object) num;
    ULS.SendTraceTag(845443U, (ULSCatBase) ULSCat.msoulscat_PS_ProjectSharepointIntegration, ULSTraceLevel.Verbose, "Setting ParentID to {0}", new object[1]
    ((SPItem) listItem)["ParentID"]
    //STEP 3
    flag = true;
    else if (((SPItem) listItem)["ParentID"] != null)
    ((SPItem) listItem)["ParentID"] = (object) null;
    ULS.SendTraceTag(2495056U, (ULSCatBase) ULSCat.msoulscat_PS_ProjectSharepointIntegration, ULSTraceLevel.Verbose, "Resetting ParentID to null");
    flag = true;
    return flag;
    Any thoughts about it would be much appreciated!

  • How to save a video/slideshow project on my PC in a format that is still editable in elements?

    I'm trying to save a file as a back-up so I need to save it to my PC in a file format that is editable in elements 8

    Simply save the project file from the slideshow editor interface, after adding your video and stills.
    To find your saved projects type PSESS into the Organizer search bar.

Maybe you are looking for