STO and Plant to plant materials transfer

Hi,
  We have three plant in three different compnay code we are doing material transfer with MB1B  and it is working fine  now we want configure the STO ,  what is the advantage of STO  comparing to simple plant to plant material transfer  and in case of STO how accounting entry wil be generate  , also can u give the steps for customizationn setting for STO  and some links for the same.
regards,
  zafar

Hi,
Confg steps for STO.
1. Define shipping points for plants
2. Create checking rule.
3. Define checking rule.
4. Assign deliery type to che. rule.
Create Customer in Suppling plant for receiving plant
Create vendor at receiving plant  for supplying plant.
maintain material with Sales view for shipping point,
create PO ME21n with Doc tyoe NB.
Outbound delivery  Vl10B
PGI --VL02N
GR --- MIGO
Acounting doc. at PGI.
Move type: 643 &101  2 step
                   645 & 101 1 step
Acc key
BSX -
GBB (VKA) +
Billing
Customer +
Other sales dedution -
Hope this will help.
SAM

Similar Messages

  • STO- Depot to Plant with Transfer of cenvat credit

    Dear All,
    I am having a scenario in which i am procuring capital material for depot and it lies in depot.
    Now the material is no use in depot and i want to transfer that material from depot to manufacturing Plant.
    and want to take the cenvat credit in manufacturing plant with respect to initial excise posted at depot.
    Now i created a STO and done the PGI. Create & POST the excise invoice in depot-J1IJ.
    But i am not able to capture excise invoice in MIGO in manufacturing plant.
    So how to transfer the material from depot to manufacturing plant with transfer of cenvat credit.

    Hi akshay,
      Follow this flow you can Transfer of cenvat credit.
    --->ME21N
    --->VL10B
    --->VL02N
    --->J1IJ
    ->VF01Proforma invoice (At depot plant)
    --->MIGO(At Mfg Plant)
    --->JV using T-code J1IH (To transfer cenvat credit to Mfg plant)
    Thanks,
    Swamy H P

  • Reg:T-CODE for open and close period for materials(new plant).

    hi sap guru's
    T-code for following process
        can anybody send me , how to create calendar to new plant . and what is the T-code to be use for open and close period of materials for new plant.
    thanks
    sakthi..

    Hi Sakthi,
    I am assuming that you are asking about the factory calendars which are assigned while difing the plant.
    Factory calendars are created through transaction "SCAL".
    Opening and closing of MM periods can be done through transaction MMPV.This is based on the company code.Before using MMPV ,you can look the last opened period in the transaction MMRV.
    Reward points if it helps.
    Regards
    Karan

  • Intercompany and Intracompany (plant to plant) Stock Transfer scenarios

    Hello!
    I have an issue regarding Intercompany and Intracompany (plant to plant) Stock Transfer scenarios.
    We are implementing Brasil. 
    Brasil has 11 different plants and all of them can transfer stock to each other, so the Intracompany stock transfer scenario has to be done for this country.
    Brasil also sends products to other countries (also with SAP implemented) from one of the 11 plants, so the Itercompany stock transfer scenario also has to be customized for Brasil and for at least one of the plants in Brasil.
    We have a distribution channel for Replacement market (L1), and another distribution channel for Export market (L7).
    In the scenario described above we have one plant being used for both scenarios, for Intracompany Stock Transfer and for Intercompany Stock Transfer, by two different distribution channels (Replacement market (L1), and another distribution channel for Export market.
    In the customizing we have a unique plant, but we have two different sales areas to be assigned to it, in order to be able to execute those processes.
    My question is:
    If the customizing to be done for the both scenarios is the same, my request is to have both scenarios for the same plant, and I have two different Sales Area for each scenario, is there a way to make both scenarios work together for the same plant and different sales area?
    Best Regards
    Cristina

    Please dont post the same question in multiple forums.  Continue in one thread
    thanks
    G. Lakshmipathi

  • Transfer Forecast data based on Customer information for product and plant

    Hi,
    This is the scenario.
    Our characterstics are Product,Plant and Customers
    and for 1 plant and product there may be 5 customers.
    My characterstics will be
    P1 L1 C1
    P1 L1 C2
    P1 L1 C3
    P1 L1 C3
    P1 L1 C4
    P1 L1 C5
    (P1-Product; L1 for Plant and C1,C2...are customers)
    Now forecast data will be different for different customers.
    I transfer demand from APO to ECC for PRoduct ,Plant and different customers.
    Then in ECC how to check for different customers.
    If you go to MD63 you can see for plant and product but not for customers.
    This is required as we are running MRP for that product for component planning.
    Thanks in Advance
    Raghavendra Pai

    Hi Ragvendra,
    In ECC we can transfer at material and plant level only and not information of customer. As you need for MRP run may be you can explore possibility of using some badi and get customer no in requirement plan number or some other feilds.
    Other option is planning with descriptive chartceristic in APO only. It is not possible to transfer demand with descriptive charcteristics to ECC.
    Here you can forcast demand on customer level. Transfer it as PIR with descriptive charcteristics to PPDS where you can plan for this demand.
    For information see link http://help.sap.com/saphelp_scm50/helpdata/en/c1/147a375f0dbc7fe10000009b38f8cf/frameset.htm.
    If your requirement is to transfer customer information to ECC from DP in standarad it is not possible as far as I know.
    Regards,
    Siddharth

  • BOM Explosions for Materials and Plant

    I am looking for the same functionality as in CS15 where I can check if a component within a BOM is part of another BOM.
    How can I achieve this?
    I have tried the FM: CS_BOM_EXPLOSION or CS_BOM_EXPL_MAT_V2, but I can not get these to work as I wish.
    I have material number and plant as a selection criteria as well as BOM usage.
    Does anyone have a good solution to this?
    Please help out as soon as possible, since I am stuck.
    Rgds,
    /Fredrik.

    Hi Fredrik,
    in the past i used FM CSEP_MAT_BOM_SELECT_WHERE_USED  (and afterwards CSAP_MAT_BOM_READ to get details).
    Also you could have a look at FM CS_WHERE_USED_MAT - it should be like CS15.
    Hope it helps,
    BR,
    Sebastian

  • Table for STO and his production order in manufacturing plant.

    Hello Experts,
    I would like to know in which table I can find a relation between STO and his related Production Order.
    Thanks in advance.
    Regards
    Mayur
    Edited by: mayur kshirsagar on Dec 19, 2007 1:48 PM

    Dear Mayur,
    For Production order related tables check in
    AFKO              Order Header
    AFPO               Order Item Detail
    AFVC               Order Operations Detail
    AFFL                Order Sequence Details
    AFFH               Order PRT Assignment
    AFBP               Order Batch Print Requests
    AFRU               Order Completion Confirmations
    AFFW              Confirmations -- Goods Movements with Errors
    AFRC               Confirmations -- Incorrect Cost Calculations
    AFRD               Confirmations -- Defaults for Collective Confirmation
    AFRH               Confirmations -- Header Info for Confirmation Pool
    AFRV               Confirmation Pool
    AFWI               Confirmations -- Subsequently Posted Goods Movements
    AUFK     Order master data
    AUFM     Goods Movements for Order
    VBAG                           Sales Document: Release Data by Schedule Line in Sch.Agrmt.
    VBAK                           Sales Document: Header Data                               
    VBAP                           Sales Document: Item Data                                 
    VBBE                           Sales Requirements: Individual Records                    
    VBBS                           Sales Requirement Totals Record                           
    are you meaning stock?
    then check in MARD.
    Regards
    Mangal

  • Plant to Plant Material Transfer through MM Route.

    We are making Material Transfers through STO (through MM Route with Account Assignment Category) from Plant to Plant.  On receipt of GR at receiving Plant, Quantity is not displayed and the stock is directly consuming.  As per our requirement, the stock must be displayed as unrestricted stock at our SL.
    Please advise to meet the above requirement.
    Thanks & Regards
    Satyanarayana

    hi dear Mr. samuel mendis
    Kindly note that Account Assignment Category is mandatory for non-valuates materials. We are transferring the Goods from one Plant to another Plant as follows :
    Example :Plant ABC
    In this Plant Materials are marked as Quanity updated and Value updated.  From this plant we are transferring the material to another Plant (Plant  XYZ).  In this XYS plant materials are marked as Quantity updated ONLY.  NO VALUE UPDATATION.
    When we transfer the Goods from Plant ABC to XYZ, in STO we need to mention Account Assignment Category becoz those materials (Material type and Plant combination) are only quantity updated and not value updated.
    While doing the above process, the materials are not being posted to Stores and directly posted to consumption.
    Hope you understand the above scnerio and our requirement.
    Please do give us a solution.
    Thanks and regards,
    Sathya

  • Uploading Material and Plant Masterdata

    Hi BW experts,
    I am trying to upload master data from R/3 Prod for 0Material & 0MAT_PLANT.  My upload failed as some of the materials and plants created in R/3 have been created with a space character at the end of the name (i,e '1000 ' as a plant, note the space at the end).  This should normally happen as in R/3 a conv exits stops users creating unacceptable names but it seems the exit has been modifed!  What a pain! 
    I have decided to replace the space with a unscore character (i.e '1000_') so this way it can be read into BW, although we would not report on this errornous material or plant name.  The code is as follows:
    DATA: LEN TYPE I.
    LEN = STRLEN( TRAN_STRUCTURE-MATNR ).
    TRANSLATE TRAN_STRUCTURE-MATNR+LEN USING ' _'.
    and I have used it in the transfer routine for 0PLANT and 0MAT_PLANT.  The load goes on but fails with the following error for 0MATERIAL & 0MAT_PLANT:
    DATA_OFFSET_TOO_LARGE   
    CX_SY_RANGE_OUT_OF_BOUNDS
    An exception occurred. This exception is dealt with in more detail below   
    . The exception, which is assigned to the class 'CX_SY_RANGE_OUT_OF_BOUNDS',
    was neither                                                               
    caught nor passed along using a RAISING clause, in the procedure           
    "COMPUTE_MATERIAL" "(FORM)"                                               
    Since the caller of the procedure could not have expected this exception   
    to occur, the running program was terminated.                             
    The reason for the exception is:                                           
    The system tried to access field "TRAN_STRUCTURE-MATNR" with type "C" and  
    length                                                                    
    18 in the current program "GPBMDZFJE4YBL86FIMHZC52BNOE " using offset 18.  
    Partial field access is not allowed with an offset specification that is   
    larger than actual field length.                                           
    Could this be due to the code?
    Thanks for you help and guidance where you can provide.
    DV

    Hi Edwin,
    I am not too good with ABAP so you may need to help verify the code for me little.  Do you mean the code should look like this:
    DATA: LEN TYPE I.
    LEN = STRLEN( TRAN_STRUCTURE-WERKS ).
    TRANSLATE TRAN_STRUCTURE-WERKS+LEN-1 USING ' _'.
    If i have the code wrong can you please help?
    Thanks Edwin
    DV

  • Plannning Material and Plant for MRP Run

    Hi,
    If I have a material (01) extended on 2 plants, on one plant (A) we have production and planning/MRP + stock and on the other one (B), just stocking and transfer. B's requirements are to be entered and planned at A. I also want stock at B to be considered with stock at A when MRP runs at A. In the material master, I have some settings. I want to know if these would be any good:
    Material 01 on Plant A:
    MRP PD
    Strategy 40
    Lot size EX
    Coverage profile applied
    Material 01 on Plant B:
    MRP ND/PD tried both
    Strategy 40
    Lot size EX
    Coverage profile applied (same)
    Planning material: Material 01 itself
    Planning plant: Plant A
    I particularly want to know about points 5 and 6. Will they make any difference if I run MRP on scope of planning(all plants) or just plant A? Will stock at B be considered? What difference does that setting make in my case? Please help!
    Thanks!

    No sales on Plant A. Only transfers and STO's. Stock is STO'd to Plant B (and other Plants, as well)
    Plant B sells the stock.
    Yes, I want to load the forecast in Plant A (COPA to SOP to DM to MRP). What do I do in this case?
    I tried another case, as well. In that I put a special procurement on the material in Plant B view and marked it as external procurement. (the planning material and plant were there, didn't remove)
    Then I entered the forecast in both plants separately (PIRs for both Plants) The requirements from Plant B made STPO Planned orders in Plant B and STCK Planned orders in Plant A. I am using coverage profiles (period is month, standard length 25 days, target 10 days for 1st period for 2 months, target 10 days for 2nd period  for 1 month, target 10 days for the rest of the horizon) Not using any consumption modes.
    The results I am getting don't make sense to me. I have attached screen shots for both plants MD04 and the MRP + work scheduling views

  • MM STO between Plants under the same company code

    Hi experts,
    Please guide on the configuration steps for doing STO between Plants unders the same company code.
    We have company code 100 in that Plants A B & C are theie. Each Plant can do STO to other Plant.
    How to configure this scenario?

    Dear,
    Please follow bellow path
    1. Create a vendor for the Company code of the receiving plant using account group 0007 via T-Code XK01.
    2. In the purchasing data view assign the supplying plant and the schema group
    3. Create customer with the sales area of the vendor.
    4. The shipping conditions, the delivering plant and the transportation zone determine the route in the STO.
    5. In the pricing procedure determination relevant to the STO assign document pricing procedure and customer pricing procedure to get the pricing in the invoice.
    6. Maintain condition records for pricing condition.
    7. Maintain carrier as a partner in the customer master.
    8. In OMGN select the supplying plant and assign the company code and sales area. Similarly select the receiving plant and assign the company code and sales area (The company code to which the plant is assigned to).
    9. Assign the delivery type and checking rule to the document type.
    10. And finally, assign the purchasing document type to the supplying plant and the receiving plant.
    11. Create the STO using T-Code ME 21N and save.
    12. Check for release strategy if any and release using T-Code ME 28.
    13. Create delivery in background using VL10G.
    14. If delivery is created, it is an indication of correct configuration and master data creation.
    Stock transfer between two plants in different company codes is known as inter company stock transfer.
    Material should be maintained in both supplying and receiving plant MM01
    Stock should maintain only in supplying plant MB1C
    Create receiving plant as a customer in supplying plants company code and sales area XD01
    Assign this customer number in receiving plant details OMGN
    Assign supplying sales area in supplying plant details OMGN
    Assign delivery type NB for in combination of supplying/ receiving plants.
    Create STO ME21N
    As it is normal there in the item details we should get shipping date i.e. customer number
    Go for Delivery VL10B
    Shipping point *****
    Select PO go for execute
    then select the delivery then go for delvy ............create delvy,,,, delvy number generated.
    Goods Issue VL02
    Delvy doc **********
    Click on picking
    enter the picking qty
    Click on PGI
    in the mean time check in the PO history you will get the details
    Goods receipt MIGO
    Stock transfers that include deliveries and billing documents/invoices are only possible between plants belonging to different company codes.
    If you want to carry out a cross-company-code stock transport order with delivery but without a billing document, you must set the Relevant for Billing (data element FKREL) indicator in Customizing of the item type to "blank" (Not relevant for billing).
    The following applications are involved in this type of stock transfer:
    ? Purchasing (MM-PUR) in entering the order
    ? Shipping (LE-SHP) in making the delivery from the issuing plant
    ? Billing (SD-BIL) in creating the billing document for the delivery
    ? Inventory Management (MM-IM) at goods receipt in the receiving plant
    Invoice Verification (MM-IV) at invoice receipt in the receiving
    Transfer of goods from one location to another location, it may be between plants within the same company code or in different company code's plants.
    within the company code, but plants,
    receiving plant will raise the STO in Supplying/issuing plant-ME21n,
    Supplying plant will deliver the goods to receiving plants ,
    then we need to pick n post the Goods Issue-VL02n,
    now when we can observe that the STO qty will be added into receiving plant and reduced in Delivering plant,
    To do this, we need do prior customization in SPRO-IMG,-
    material should be created in both plants( receiving & Supplying)
    -maintain the stock only in supplying plant
    -create a dummy customer in supplying plant's sales area(if u have one sales area, create in tat comp code n sales area)
    -assign this customer number to receiving plant's details along with the sales area,
    -Assign the STO doc type(UB) to Supplying plant, along with checking rule
    -Assign the Del type (NL/NLCC) to Supplying n receiving plant.
    Stock Transport Order:
    http://help.sap.com/saphelp_47x200/helpdata/en/4d/2b911d43ad11d189410000e829fbbd/content.htm
    http://help.sap.com/saphelp_47x200/helpdata/en/4d/2b917843ad11d189410000e829fbbd/content.htm
    http://help.sap.com/saphelp_47x200/helpdata/en/4d/2b918543ad11d189410000e829fbbd/content.htm
    u can also use the SAP building block
    with delivery
    http://help.sap.com/bestpractices/BBLibrary/html/P36_IntStockTransDel_EN_IN.htm
    without delivery
    http://help.sap.com/bestpractices/BBLibrary/html/P38_IntStockTransWithoutDel_EN_IN.htm
    Regards,
    Mahesh Wagh

  • STO for PLant abroad

    Hi,
    Is there any specific steps to create intra company STO for plant abroad. In help i can see the below
    note. How to do this?
    Stock transfer
    Replenishment deliveries between different EU countries are relevant for billing. The billing status is A.
    Appreciate your quick response on this.
    Thanks,
    Suresh

    hi
    if the plant belong to same company code, then you need to capture the duties etc that would come into picture cause it would also involve import duites for reciving countries. therefore you will have to change the calculation scheme and capture this. also if billing is involved you need to take delivery type NLCC.
    Thanks
    Ankit

  • Error in Return STO Process(Plant to Plant within company code)

    Hi All,
    I am doing the return STO Process(Plant to Plant within same company code) .
    Scenario:
    STO from Plant 1300 to 1400
    STO Process: ME21N->VL10B->PGI-> VF01(Proforma)->MIGO
    Return STO from Plant 1400 to 1300
    STO Return Process: ME21N(item with return indicator)->MB01(MT 101 w.r.t Return STO PO)->VL10B->PGR(Error)
    It is giving me the following error.
    Deficit of PU GR quantity 5 KG : 20027183 1330 2000 16
    Message no. M7021
    Kindly help me
    with regards
    Azeez.Mohd

    Dear,
       Please go through this link,
        [Deficit of PL Stock in transfer 10 EA : 100100051 IBM2;
        [Accept material in MIRO without any limitation?;
        [migo-return delivery-credit memo;
    Regards,
    Sandip

  • Movement Type 161error in STO return (Plant to Plant) at the time of goods issue .

    Hi all...
    Am getting the following error while posting goods issue through VL02N
    Update control of movement type is incorrect (entry 161 X X _ L)
    Message no. M7226
    Diagnosis
    The system could not find entry 161 X X _ L in any of the movement type control tables.
    Process : STO Return Plant to Plant.
    Purchase Order ( STO) done.
    Goods issue done.
    Goods receipt at the receiving plant.
    Amended Purchase order, added one more line item and ticked return.
    Inbound delivery done.
    VL02n Goods issue am getting the error.
    Pls help.
    Suhas
    MM consultant

    Update control of movement type is incorrect (entry 161 X X _ L)
    Have a look into your OMJJ customizing for 161 movement type:
    It probably looks like mine:
    the error message has the info in exact the same sequence
    161 X X _ L
    this is 161, checkmark checkmark blank L  in the table above.
    L would mean reference to a delivery.
    But as you can see here, there is no L, everything is B which means reference to purchase order.
    It is not allowed to add items in a delivery without purchase order reference, it is technically possible, but it finally ends in the error you have.
    The process has to start from the purchase order.

  • Inter plant stock transfer

    Dear Experts,
    Assigned to different valuation areas, a cross plant stock transfer will lead to a value update in the stock accounts.
    An accounting document is created in addition to the material document.
    What entry will the accounting document carry?
    Say valuation in plant A is 1000 ( 100 units * $10 per pc)  for the material being transferred to plant B where the valuation is $9.
    And what if they belong to the same valuation area , does that mean the price of the material has to be the same for both the plants or it can differ? will there be any accounting document
    Anticipating your replies.
    Regards,
    Akhil

    1.  In your case Accounting entry would be
    if Moving Average Price is set
    Stock Account        (Receiving Plant-Valuation Area)              Dr                    1000
    Stock Account        (Sending Plant- Valuation Area)                Cr                    1000
    if Standard Price is set at Plant B"
    Stock Account     (Receiving Plant-Valuation Area)               Dr                    900
    Price Differenece Account                                                     Dr                     100
    Stock Account     (Sending Plant- Valuation Area)                Cr                    1000
    2. if you have set Plant as a valuation area then all cross plant transfers will be generated with accounting document.