Third party process - error

Dear all,
In the third party process, have we to create outbound delivery?
I have created PO from PR of  a third party sales order. And now, i don't understand to delivery to customer.
Pls tell me solution.
If we have to create outbound delivery from that sales order, i get errors:
Item category TAS is not defined and Item category TAS is not defined, so item 000010 will be disregarded. I also checked in VOV4, VOV6, VOV7.
Thank you,

Hi
In third party scenario the material is delivered to your customer thro out side vendor
You are billing your customer
Vendor is billing you for the material he has delivered to your customer
Here we dont make any delivery
Process Flow for 3rd Party Sales
Customize the third party sales in summary:
1. Create Vendor XK01
2. Create Material u2013 Material Type as "Trading Goods". Item category group as "BANS".
3. Assign Item Category TAS to Order type that you are going to use.
4. A sale order is created and when saved a PR is generated at the background 
5. With reference to SO a PO is created (ME21N). The company raises PO to the vendor.
6. Vendor delivers the goods and raises bill to company. MM receives the invoice MIRO 
7. Goods receipt MIGO 
8. Goods issue
9. The item cat TAS or Schedule line cat CS is not relevant for delivery which is evident from the configuration and,   therefore, there is no delivery process attached in the whole process of Third party sales.
10. Billing
SD -  3rd party sales order Create Sales Order
VA01
      Order Type
      Sales org, distribution channel, div
      Enter
      Sold to
      PO #
      Material
      Quantity
      Enter
      Save
SD -  3rd party sales order View the PR that is created with a third party sales order
VA01
      Order Number
      Go to Item Overview
      Item ->Schedule Item
SD -  3rd party sales order View the PR that is created
ME52N
      Key in the PR number
      Save
SD -  3rd party sales order Assign the PR to the vendor and create PO
ME57
      Key in the PR number
      Toggle the "Assigned Purchase Requisition"
      Execute
      Check the box next to the material
      Assign Automatically button
      Click on "Assignments" button
      Click on "Process assignment"
      The "Process Assignment Create PO" box , enter
      Drag the PR and drop in the shopping basket
      Save
SD -  3rd party sales order Receive Goods
MIGO_GR
      PO Number
      DN Number
      Batch tab , click on classification
      Serial Numbers tab
      Date of Production
      Flag Item OK
      Check, just in case
      Post
      Save
SD -  3rd party sales order Create Invoice
MIRO
      Invoice Date
      Look for the PO , state the vendor and the Material
      Check the box
      Click on "Copy"
      Purchase Order Number (bottom half of the screen)
      Amount
      State the baseline date
      Simulate & Post
      Invoice Number
      *Invoice blocked due to date variance
SD -  3rd party sales order Create a delivery order
VL01N
      In the order screen , go to the menu Sales Document , select "Deliver"
      Go to "picking" tab
      State the qty and save
SD -  3rd party sales order Create a billing document
VF01
      Ensure that the delivery document is correct in the
      Enter
      Go to edit -> Log
      Save
Hope the process is very clear to you now
Regards
Raja
Edited by: ramanathan raja on Sep 18, 2008 3:06 PM

Similar Messages

  • Third Party Process - forcing PO creation after error

    Hello eveybody,
    I am implementing the Third Party Process and everything is going well but I have a question. If I enter say 10 items on a sales order and one material does not have an info record/source list then that item does not get entered on the purchase req. This then blocks the automatic creation of the PO.
    If I fix the problem material and re-enter it on the SO, then that item gets ordered but the other 9 are not processed. Is there nany way to force the PO creation for the other 9 items ??
    Many thanks in advance.
    Brian

    Hi Stanton,
              When you precess the third party order the purchase requesition will be created to the respective schedule lines so you can get the two different purcahse requesition for the 10 items then you can combine those two purchase requesitions in the purchase order what is the issue.
    or you can run another PO for that problem item.
    I hope it will not give any problem while creating PO
    Thanks,
    Murali.

  • Error while doing GR in third party process

    Dear Friends,
    While doing Third party process, at GR (w.r.t. inbound delivery) the following message appears “Purchase order 4500000087 has no items” and stops creating GR. But the P.O has the Item. Do have any clue?
    Thanks,
    Hari.

    Hi Hariharan,
    In standard third party process you won't get the goods physically they are delivered by your vendor directly to your customer. In this process there's no meaning of creating inbound delivery I guess...
    You can do statistical goods receipt ('ghost GR' as it was called by someone in SD forum) but even this GR isn't a must (it's based on your invoicing scenario).
    I'm not sure but I'm afraid you cannot create inbound delivery for it if your settings are proper.
    BR
    Csaba

  • Intercompany invoice not getting created in third party processing

    Dear Gurus !
    I am facing a problem in creating the intercompany invoice in case of third party order processing.
    In our organisation , for any type of sale two billing documents are creared :
    1) Commercial Invoice under the co. code for which sales org. is maintained at the sales order bookin level .
    2) Intercompany Invoice under the co. code in which plant is maintained which is used at the sales order level as delivering plant.
    So, as per the configuration req. for third party processing  , i have created Sales order ( with automatic Purchase requistion generated ) , Purchase order creation with reference to the Purchase requisition , goods reciept ( MIGO ) and invoice reciept ( MIRO ) , then billing doc. or commercial invoice ( VF01 ) with the generation of accounting document and finally the intercompany invoice ( VF01 ) .
    But i am facing the problem in final stage , that is , intercompany invoice creation .
    Error Message : No open billing quantity has been determined .
    I have checked the copy control for sales order to intercompany invoice and still not able to resolve it .
    Please reply which setting needs to be done for this .   
    Awaiting your response , that what copy control settings is required .
    Thanks .....

    Hi Buddi / Mahesh / Kiran ,
    It ' s good to see all of your opinion . But my problem has not been resolved .
    I am implementing third party processing in my organisation , where the customer is an export customer ( outside India ) . Hence , this is a merchant export .
    All the configurations / Customisations have been done for this process .
    The process is running fine till commercial invoice , but the problem is in intercompany billing doc. creation.
    I am again repeating - Error message : No open billing quantity has been determined.
    Explanation of the process :
    1) The order has been booked with item category TAS alongwith the item cat. group as BANS for the material used in the order .
    2) The sales area is 1020 / 30 / 35 . Here , 1020 is sales org . under company code 0079 , 30 is export's distribution channel and 35 is the division for components .
    3) The delivering plant used in the sales order is 1009 which is under co. code 0077. The price / condition record maintained for this material is in USD / EUR as it is a case of merchant export .
    4) The purchase requisition is generated automatically when the order is saved . It can be seen at VA02 - > Item details - > Schedule Lines .
    5) With the help of this PR no. , i have created a purchase order for vendor which is maintained under co. code 0077 asking for material in plant 1009 which we need to export / supply to the customer.
    6) The value of material per piece in the P.O. is coming from the material master record -> Accounting 1 view - > Moving av. Price .
    7) Now, the Purchase order is saved . With the help of this P.O. no. , goods reciept ( MIGO )is done .
    8) After MIGO , Invoice reciept or MIRO is done under company code 0077.
    9) After MIRO , customer ' s invoice is created through VF01 .
    Remember : This is an order relevant billing , no delivery or PGI will happen here because the material is not coming into the plant 1009 .
    10)The billing document ( order - related billing doc.) is created and the accounting document is also created under co. code 0079 in USD .
    Till this stage , everything is running successfully as per business requirement , but i am facing the problem in the final stage , that is creation of intercompany invoice under co. code 0077 which is in INR .
    In all other sales document types used in our industry , the process is same , that is : a) Sales order creation b) Delivery and PGI c) Billing doc. creation with accounting doc. under co. code 0079 and finally d) Intercompany invoice with accounting doc. under co. code 0077 and excise invoice creation with reference to intercompany invoice.
    In the above, problem is not there becuase orde is delivery relevant , hence copy control is maintained for interco. billing to delivery type.
    But in the new process , that is , third party processing , sales order relevant billing is done . so i suppose there will be a copy control for intercompany billing and sales doc. type , but i am not able to resolve it .
    Hence , please understand the process before suggesting .
    Thanks and awaits reply........

  • Third Party Processing in SRM 4.0

    Hi,
    We are working on Third Party Processing in SRM4.0 & SAP R/3 4.7.
    We were able to transfer the Third party Requisition from Backend R/3 to SRM 4.0 Sourcing Cockpit as an External Requirement.
    When we try to process the Third Party External Requirement to create a PO in Sourcing Cockpit, the system is not identifying the Customer Number as a Business Partner in SRM 4.0 and it is throwing a dump with the error message <b>'Partner xxxxxxxxxx not found'</b>
    Please help us to understand the procedure for replicating the Backend R/3 Customer Masters and its Address into SRM 4.0
    Where can i find documentation for Third Party Processing in SRM 4.0 as i could not find anything in SAP Help
    Please do let me know if you need any details/clarifications
    Thanks in advance
    Regards,
    Sunil

    Hi Vitthavat,
    All you have done is fine.
    As per you SO - PR is already automated, now to automate PO creation from PR:
    Do the following thing:
    1. Activate u2018Automatic PO' indicator for material master
    2. Activate u2018Automatic PO' indicator for vendor master
    3. The purchase requisitions with vendor assignments are converted into POs by a batch job using transaction ME59/ME59N and ABAP program with requisite parameters.
    This ensures automatic creation of POs.
    So result: When SO is saved PR and corresponding PO will be generated automatically.
    Your problem will be solved.
    Regards,
    Anirban Roy

  • Problem in third party processing billing document

    dear all,
    I am facing problem in creating the billing document for third party processing.
    The error is : Item category ZEXM TAS cannot be invoiced by using billing type ZFAZ.
    I think the problem is  in copy control for billing document item . Kindly tell the solution.
    Thanks...

    Dear Buddi ,
    Now , the billing document is getting saved after changing the copy control for item category.
    But , the system is giving error ( The accounting document is not generated ) .
    I have checked all the settings in VKOA against the account keys maintained in pricing procedure for this merchant exports case.
    One another problem related to this issue is : Which setting is required to capture the Price maintained in item - > conditions at the VA01 level in EUR or USD . I have maintained the condition record in EUR in VK11 , but still while making order , the error is coming mandatory condition type ZBPR( Basic Price ) is missing .
    Awiating your response .

  • Logical GR in Third Party Process

    Hi Friends
    There is logical GR involved in third party process. What if we do not want to trigger it?

    very useful thraed for your Qn-
    [stock not updating after doing MIGO (gr) for third party sales |stock not updating after doing MIGO (gr) for third party sales;
    BR
    Raj

  • Free of charge third party process.

    Dear Gurus,
    I want to create a sales order with a third party material with zero price, create a PO and invoice the PO with zero value.
    Could you please tell me how this can be achieved and what are the necessary settings in config to be changed?
    Thank You
    Kumar

    Hi Kumar,
    the third party process is as follows:
    1.Customer will order the material from the Company X.
    2.Company X will not have stock of the material.
    3.Company will raise a PO for the material to the Vendor & asks the Vendor to deliver the material to the customer.
    4.Vendor will directly deliver the material to the customer & will send the invoice to the Company X.
    5. Company X will then raise a invoice to the Customer wrt on the Sales order.
    Create a Sales order with item category TAS, Schedule line category CS(standard).Once the SO is saved, go to the change mode of the SO, go to Schedule lines tab, & note down the PR number.
    With reference to the PR, create the PO & then MIGO and MIRO.
    Then create the invoice wrt the SO.
    Let me know if you hav any problems.
    Regards,
    MP

  • Credit Check with Third Party Process

    Hi Gurz,
    I know about third party process but my problem is with credit check of the customers.
    If customer has not got enough credit limit to process the order in normal senario credit controller has to manually release the order as system blocks it. In third party process system will give you warning message when saving sales order about customer credit limit but allows you to save sales order. Once saving sales order it authomatically creates Purchase Requisition. From PR purchasing creates P.O. with out knowing about customer credit limit issue. and so on. In other words goods supplied to customer even though credit limit has exceeded. This user don't know untill raising the invoice to the customer which is too late.
    Can we stop creating Purchase requisition or block purchase requistion for credit check ? or there are better way of handling the process for credit check?
    Thanks in advance

    Hi,
    Try to implement OSS note -738171 - Delivery block does not influence purchase requisition.
    Following is the details of the note;
    Summary
    Symptom
    The delivery block in a sales order does not prevent the generattion of the purchase requisition in a third-party or individual purchase order item. Regardless of the Customizing settings in the delivery block, the system confirms the TAB or TAS item and generates the purchase requisition.
    More Terms
    Order, purchase requisition, PReq, TAB, individual purchase order, individual purchase order item, TAS, third-party, third-party item, SD order, delivery block, VBAK-LIFSK, VBEP-LIFSP
    Cause and Prerequisites
    Solution
    Create a user-specific user requirement (for example, 902: BEDINGUNG_PRUEFEN_902 in Include LV07A902) as a copy of standard user requirement 102 and assign it to requirement 'Preq' by using Transaction OVB5.
    In the source code of the user-requirement, program a check for the delivery block which, if necessary, triggers an ERROR_EXCEPTION which prevents the generation of the purchase requisition.
    You can use the existing check for the credit block as a template.
    Regards,

  • Third Party Process and Inventory

    We are using the SAP function "Third-Party Processing". We are using the function in it's standard (SAP R/3 4.7).
    The auditor now has the following issue: Shipping the goods starts after paying the goods. Out of this, while shipping the goods, we are the owner of them. In this circumstance the ship is our warehouse.
    SAP does not allow an Inventory Management within Third-Party Processing:
    "Since a third-party order involves a movement from the vendor direct to the customer, Inventory Management is not in any way affected. If you wish to document the movement in the system, however, you can create a goods receipt for the third-party order."
    With the SAP functions in this scenario it is correct that the warehouse stock is not being impacted. This is a conflict with the opinion of the auditor.
    Let me explain in detail what is wrong out of the view of our auditor:
    For example we initiated the order of a customer in June and we have paid the goods in June. The shipment starts in June and the goods will arive in July. Due to the fact, that we are the owner of the goods on the ship, we have to increase the stock. This is the opinion of our auditor.
    Does any body know, how to solve the issue? How do you manage Third Party Processing & Inventory?

    Some auditors just dont understand the SAP process. Instead of talking to weak users, they should talk to SAP directly.
    What about shipments from standard sales orders that are shipped end of June and do arrive at the customer in July?
    When do you bill your customer? when the goods arrives there, or earlier? Depending on the Incoterms you may still be the owner until the truck is unloaded.
    If you change your process and post goods receipt to your warehouse, then you show inventory where no physical inventory is, you posted a goods receipt without a physical receipt. I am sure the next auditor will not allow such therotical process.
    Get together, IT consultants of FI and MM and SD, strong business people for the same modules and the auditor, and discuss and find an optimal solution.And let the auidor sign the decision paper!!! Very important, I recently had to convice German auditors because they had different opinion than the Australian and US auditors of the same auditing company (and the issue had nothing to do with local legal requirements).

  • Third party process with Valuated sales order stock

    Hi All,
    We have third party sales order process with valuated sales order stock. The problem is that in the theird party PR which is triggered directly from the sales order it determines a stock account which is assigned to the BSX key in OBYC.
    But since this is third party processing as per my understanding a consumption account assigned to key GBB-VAX (since account assignmnt category is X) should get determined, so that when the GR is done against the PO a consumption posting is done in the background.
    I am not able to understand if the system is determining the stock account due to the fact that it is valuated sales order stock and if so, what should happen after GR. Should we have a stock created for the material which is physically directly delivered to the customer?
    Regards,
    V S

    Hi,
    Check GBB-VKA which is defined in OME9 for your ''E'' Account Assignment Category that SAP will debit upon GR posting
    Also check "X" GBB-VAX and the G/L account assignment in OBYC
    The posting on GR should be debit KBS -Credit GR-IR
    Thanks
    Diwakar

  • Third Party Process ASN

    We have configured a third party process for specific sales orders.  We receive an inbound ASN with shipment information and then we create the outbound invoice, directly from the sales order, after we post the inbound invoice.  Is it possible, and how, to create an outbound ASN, from our system to the end consumer, based on the information in the inbound ASN?  We would prefer not to create an outbound delivery document in our system and would like to generate the outbound ASN off the outbound invoice or the original sales order.
    Thanks for the help.
    Chris

    We have configured a third party process for specific sales orders.  We receive an inbound ASN with shipment information and then we create the outbound invoice, directly from the sales order, after we post the inbound invoice.  Is it possible, and how, to create an outbound ASN, from our system to the end consumer, based on the information in the inbound ASN?  We would prefer not to create an outbound delivery document in our system and would like to generate the outbound ASN off the outbound invoice or the original sales order.
    Thanks for the help.
    Chris

  • Third party process as inventory value

    Dear Experts,
    Kindly need help for third party process.
    We have third party process which triggered from Sales Order. This Sales Order will automatically created PR. PR will be convert into PO.
    The issue is we would like to have goods in Sales Order (or Purchase Order in next process) as inventory value when receiving goods.
    Can third party process be treated as inventory value when receiving it?
    Thank you in advance.
    Best Regards,

    In third party process your customer gets the goods directly from your vendor.
    You only make a statistical GR ("phantom" GR) in the system, the goods are physically received by your customer and your customer's inventory will increase after your customer's GR and not yours. Knowing this your question doesn't make any sense I think.
    If your third party process is not a real third party process and you receive the goods physically and after that you sell it your customer you can use individual PO scenario.
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/dd/5601d4545a11d1a7020000e829fd11/frameset.htm
    Regards,
    Csaba

  • Third Party Process Issue

    Hello Friends,
    Need Your Inputs for below issue"
    in third party process: SO is created with 2 line items, -->PR-->PO--> Vendor delivers only 1 item and MIRO is done for it,
    But
    During Creation of Customer invoice Both Line items are considered in the Invoice(F2)
    1st line item with the Value of X Rs,  and 2nd Line item with zero value ( as there is no delivery done to customer and hence no invoice via MIRO)
    Requirement is:
    The 2nd Line item should not be considered at all during Customer invoice creation.
    Item cate used is TAS with billing relevance F (i,e standard config)
    Kinldy help
    regards

    hello srinu..
    SO is created with 2 line items, PR is auto created. 1 PO is created (with 2 line items)
    MIRO is done w.r.t PO line item 10 only,
    then when i create customer invoice from SO i get 2 line items, for 1st line item there is value populated. 2nd line item has zero value,
    The requirement is that if there is no Processing of SO for line item 2 ,, then it should not be populated in the customer invoice.
    Regards

  • Third Party Process in Materail Management (No SD)

    Hi,
    Our Business would like to outsource the Stationary materials to supply the required materials directly to requester.
    I believe the best possible solution for this requirement is to implement third party process in Material management as we do not have SD Module.
    In this scenario, which material type we need to use (Item category group, Field ref, Sref material type and field ref) and the config part.
    Secondly, does it have any effect on MRP, Stock levels? Also please explain the process involved in Goods returns
    Appreciate, if you could share your experiences.
    Regards
    Kumar

    Creating a Third-Party Item Manually
    To enter a third-party item in a purchase order without an SD order or purchase requisition, proceed as follows:
    Enter a third-party item manually in the same way as the purchase requisition.
    After entering the account assignment, you receive a screen in which you can enter the address of the sold-to party.
    Enter either the customer number or a delivery address.
    Check whether goods receipts can be made for the third-party item. Goods receipts are possible if the goods receipt indicator is set in the item.
    Save the purchase order.
    Setting the Goods Receipt Indicator
    The account assignment category X in the Customizing system of Purchasing determines whether a goods receipt can be posted for a third-party item. Here you define whether a goods receipt is possible, not allowed or compulsory.
    If a goods receipt is possible, the GR indicator in the purchase order item is changeable. When you enter the purchase order, you decide if a goods receipt is to be posted or not.
    Mat Type can be use ROH or Trading
    For Return you can do return to your plant or ask vendor to pivk and replace the goods or issue the creadite to customer and take from vendor

Maybe you are looking for

  • Apple TV apple keyboard

    Can you connect a Apple keyboard through blue tooth to Apple TV ?

  • Problems trying to correlate BAM over multiple Send Ports

    I am having an issue with BAM in BizTalk 2010.  I have a Messaging only solution using 3 Receive Ports and 3 Send Ports.  The Processing received an XML file which contains Inventory updates for product items.  The flow is as follows: 1) Receive a fi

  • How to transport an inner table to a subroutine with change return content?

    now ,i want to perform a subroutine with a inner table,and i will delete some records from the inner table in the subroutine,but i don't want the change in the subroutine break into my main program.in other words,the content of the inner table which

  • Selection in a JEditorPane

    Hello, MY code is as follows: HTMLDocument document = ( HTMLDocument )jeditorpane1.getDocument(); String htmlString = "<ol><li><p></p></li></ol>"; HTMLEditorKit newKit = jeditorpane1.getKit(); try newKit.insertHTML( document, editorPane.getCaretPosit

  • CFMAIL stopped working

    I have numerous CFMAIL tags on the website. Generally, about 100 messages are sent per day. Approximately five days ago, mail stopped being sent. When you send mail, no CF errors occur. I've checked the "Verify mail server connection box" in the CFAd