TO item split needed

Folks,
I have the following requirement:
Material is subject to alternative UOM: 5 PCE = 1 PAK
Orders can be in both PCE and PAK
Because of that, ATP situation can result in partial PAK's.
Delivery for 14,8 PAK
Requirement:
TO with 1 item with 14 PAK and 1 item with 4 PCE.
I've tried MWMTO012 and MWMTO012 but both without results...Any other suggestions?
Thanks,
MZ

Hi,
  I don't think we can change UOM during TO creation. TO is always in WM/Alternate UOM. You better set up PAK as Storage Unit type instead of UOM. And always create Delivery with Base UOM or Alternate UOM. This way you can split TO items based on Full pallet and partial pallet quantities and is pretty standard in WM.
Thanks
Vinod.

Similar Messages

  • Line item split - open item clearing (FB05)

    Hi,
    when clearing open items we need to preserve the line item split in clearing document as it was in cleared items. For example if we have two line items with different assignment (ZUONR) system generates only one line item in the clearing document (where amount is equal to sum of amounts from both cleared items). We need one item per assignment in clearing document. Thanks for any suggestions.
    Regards,
    Michal Majer

    Hi,
    You can always go to the "Analysis" button in the Condition Tab of the Particular Line Item and see what has exactly happenned.
    Now to understand your setting.... Was that Manual Condition Type .. A Header Condition ....In process... Once you enter a value in the Header Level automatically it will be transfered to the Line Items in the document ???
    Regards

  • Line item split-pricing issue

    Hi,
    In my order we have the process where th line items splits automatically when there is no enough stock.
    The issue is we have manual condition type value from the first item is not copied to the second item after split.
    Please help to find out where in settings do i need to check to find out why manual price is not copied.
    Thanks

    Hi,
    You can always go to the "Analysis" button in the Condition Tab of the Particular Line Item and see what has exactly happenned.
    Now to understand your setting.... Was that Manual Condition Type .. A Header Condition ....In process... Once you enter a value in the Header Level automatically it will be transfered to the Line Items in the document ???
    Regards

  • I try to sync my nano and get:  the ipod cant be synced because there is not enough free space to hold all of the items in the items library (need 100MB) - I have a new computer?? can you help me understand this message: what to do?

    I try to sync my nano and get:  the ipod cant be synced because there is not enough free space to hold all of the items in the items library (need 100MB) - I have a new computer?? can you help me understand this message: what to do?

    Hello pryan1012,
    What this message means is that you have more music in your itunes library than there is free space in your ipod.
    I had this same issue at one time. This is what helped me put my music on the ipod. I used manually manage.
    Learn how to sync muisc here.
    Hope this helps.
    ~Julian

  • It doesn't work when I press "transfer purchased items from ipod" and I don't know specidicly whitch item I need to transfer

    It doesn't work when I press "transfer purchased items from ipod" and I don't know specidicly whitch item I need to transfer.
    Whenever i press "transfer purchased items from ipod", itunes sync's for about 3 seconds, but I still can't install updates on the ipod without itues warning me about purchased items on the ipod, that aren't in the itunes library. I've tried folowing the steps in itunes help, but I can only find a step guide for when you know the specific item that needs transferring, and I donøt know that specific item.

    This Apple Tech Note explains the process:
    http://support.apple.com/kb/ht1848
    It will transfer all purchased items that the computer you are transferring to is authorised to play: you don't have to select the items.

  • Web Catalog - Item Lock Needs Attention

    Hello, I am receiving an error in the web catalog (Item Lock Needs Attention). I tried to migrate about 22 files using the Catalog Manager, but it seems that the application placed a lock on the files.
    When I try to delete the file from the front-end, I received this error in EM (Item Lock Needs Attention:) (Context: 0, code: QM3V3HLV), and (access denied for user to path /users/myusername).
    I already tried stopping all the BI server components and restarting, but the error still persists.
    Any help is appreciated

    Login to Catalog Manager >> root >> users >> and assign full control to 'myusername' on 'My Folder' and restart OPMN.

  • Training and event cost item split into cost centers

    Dear friends,
    My client wants to see his training and event cost items split into each event participant's cost center. Until now I could not find a way to do this neither via Activity Allocation nor Cost transfer Posting.
    Does anybody have a way to do this?
    Best regards,
    Renato

    Hi santhosh,
    You can get a lot of information on :http://help.sap.com/saphelp_erp60_sp/helpdata/en/77/bff8ab4a2911d182b80000e829fbfe/frameset.htm
    If you have any specific queries, you can ask on the forums.
    Hope it helps!
    arpita

  • HT1933 This does not work ! I've tried several times and it keeps saying too many hhtps or something. I have duplicate charges from the same item that needs refunding ?

    I tried to reply to an iTunes invoice where it asks if there is a problem with order and can never get
    It to work ! I am being charged multiple times for same item and need to get the duplicates
    Refunded !

    I tried to reply to an iTunes invoice where it asks if there is a problem with order and can never get
    It to work ! I am being charged multiple times for same item and need to get the duplicates
    Refunded !

  • Item split (into 2 lines) in billing document from one delivery (VF01)

    Hi,
    I need to split one item of one delivery into 2 items of billing (via VF01). Example:
    - I have a delivery 80941805 that has only one line with item material XXX and quantity 1000
    - I wish to create a billing document (from the delivery above) with 2 lines with the item XXX. First line with quantity 600, second line with quantity 400 (both the same material XXX). This is necessary due to different taxes in each line, one with taxes, other without taxes (different tax codes).
    It´s possible via some standard function or user-exit ?
    Best regards,
    Leandro Mengue

    Hi,
    ***This is under development !!! Only for tests purposes!!! ***
    Actually I working on a example routine where I split the itens in two lines (each line) with the half of original quantity each one.
    include LV60AB01:
    ENHANCEMENT-POINT XVBUK_XVBUP_XVBFA_AUFBAUEN_01 SPOTS ES_SAPLV60A.
    ENHANCEMENT 281  ZFATURAFIM.
    data: wx_lips like alips occurs 0 with header line.
    append lines of alips to wx_lips.
    loop at wx_lips.
      wx_lips-J_1BCFOP(1) = '7'.
      wx_lips-sortfeld+5(1) = '1'.
      modify wx_lips.
    endloop.
    append lines of wx_lips to alips.
    loop at alips.
      alips-lfimg = alips-lfimg / 2.
      alips-lgmng = alips-lgmng / 2.
      alips-ntgew = alips-ntgew / 2.
      alips-brgew = alips-brgew / 2.
      alips-volum = alips-volum / 2.
      modify alips.
    endloop.
    ENDENHANCEMENT.
    Include LV60AA22: (to be possible process the same line item two times)...
    ENHANCEMENT-POINT FAKTURA_LIEFERBEZOGEN_01 SPOTS ES_SAPLV60A.
    ENHANCEMENT 282  ZFATURAFIM.
       read table xvbup with key vbeln = lips-vbeln
                              posnr = lips-posnr.
       xvbup-fksta = 'A'.
       modify xvbup index sy-tabix.
    ENDENHANCEMENT.
    Contributions and comments will be apreciated !!!
    Best regards,
    Leandro Mengue

  • How is line item split during doc splitting

    Hi Everyone,
    during doc spitting where is the percentage of split  done
    eg: 2 line itmes are split (40 /100.........1st line  itme) & (60 / 100........2nd line itme)
    Regards

    Hi,
    PLease check the Below informaition. We will not specify the Percentage's. Its taken by system as per our postings. for mor information go throw the below information and Examples.
    Information on Document Splitting
        You can use the document splitting procedure to split up line items for
        selected dimensions (such as receivable lines by profit center) or to
        effect a zero balance setting in the document for selected dimensions
        (such as segment). This generates additional clearing lines in the
        document. Using the document splitting procedure is the prerequisite for
        as well as an essential tool for drawing up complete financial
        statements for the selected dimensions at any time.
        You can choose between displaying the document with the generated
        clearing lines either in its original form in the entry view or from the
        perspective of a ledger in the general ledger view.
        For document splitting to be possible, the individual document items and
        the documents must be classified. Each classification corresponds to a
        rule in which it is specified how document splitting is to occur and for
        which line items.
        SAP delivers a set of standard rules that should usually prove
        sufficient. If not, you can define your own set of rules and adapt these
        according to your needs.
        Example
        Example 1: Invoice
        Suppose a vendor invoice containing the following items is entered:
        Posting Key Account     Segment     Amount
        31          Payables                -100
        40          Expense     0001                      40
        40          Expense     0002          60
        Document splitting then creates the following Ledger view:
        Posting Key Account     Segment     Amount
        31          Payables    0001          -40
        31          Payables    0002          -60
        40          Expense     0001          40
        40          Expense     0002          60
        Example 2: Payment
       The payment for the above vendor invoice then contains the following
       items when entered:
       Posting Key Account     Segment     Amount
       50          Bank                    -95
       25          Payables                100
       50          Cash Discount Received  -5
       Document splitting then creates the following document in the General
       Ledger view:
       Posting Key Account     Segment     Amount
       50          Bank        0001          -38
       50          Bank        0002          -57
       25          Payables    0001          40
       25          Payables    0002          60
       50          Cash Discount Received  0001        -2
       50          Cash Discount Received  0002        -3     
    Thanks
    Goutam

  • Sales Order Line Item Split

    Hello,
    If the inventory needed to fulfill an order item is available in two plants, we want to split an order item into two line items, each having a different plant. I think this can be done systematically, probably via a user exit in MV45AFZZ – MOVE_FIELD_TO_VBAP. Since I have never done this before, I was trying to think of the complications I might have and whether it will work correctly when coded within the user exit.
    If you have done something similar before, please share your thoughts on it.
    Regards,
    Prayarna

    Hi Rajavardhana,
    I suggest you copy the PBO and PAI modules of the standard Items Table control screen and paste them in your custom screen. Now you cann try and see if the double-click and other functionalities are achieved or not.
    Previously I had a requirement to add a button to additional B tab and other required fields in a table control. we achieved most of the requirement but not the button functionality the reason being as follows in one of my replies.
    [Re: User exit in VA01 - adding push button]
    Reward accordingly.
    Thanks and regards,
    Maddineni Bharath.

  • Customer PO at item level needs to be populated to existing Z report

    Hi All,
    Just would like your confirmation on the below requirement.
    Requirement: Already there is existing Z open sales orders report is availble for which we need to add the below mentioned line item PO into the output of the report.Business manually change the line item PO that should be displyed into output of the report.
    And one more point already the header PO  number is alredy displying inth output of the report.
    My understanding is: Since the customer PO is unique to the entire document what ever the PO is maintained at header level which will be copied to all the line items, even i checked the line item and header table & field both are same VBKD-BSTKD hence eventhough user manually change the Line item PO number you can't get the same into the output the of the report is this my understanding is correct or we can display the line item PO details into output of the report?
    thanks,

    Thank you DB49 for your above answer,also checked with business why they want to maintain the line item wise the PO details.
    The answer is recently they have implemented high sea sales process during the Post go live they could not complete the total cycle thorugh SAP, only sales order created in SAP but not Vendor invoice and customer invoice etc were manged manually.
    In sales order it contains more than one line items. Business has compelted upto customer invoice for some line items( sales order in SAP and remaining through manual).
    So now when the user is trying to pull the open sales order report system is pulliing the above compelted line items also, sytem is doing correct beacuse in SAP only sales order created and remaining process through manually. But actually the report is wrong.
    So now the business will enter manully some description for those line items which is completed until billing ( sales order in SAP+ remaing process through manual). so that in the output of the report they can understand which which are all the line items in sales order are completed the billing.
    Hence they want to disply the line item PO into the output the report so i think it makes sense to me now, do you think any other alternative for the above requreiement ?
    thanks,

  • Free Goods sub item split in two line items

    Sir,
    I give free good along with  sale item ,but i want free goods quantity split in two lines ,so how I do  that?
    Please help .

    Hi,
    Free goods has the following limitations:
    - Free goods can only be supported on a 1:1 ratio. This means that an order item can lead to a free goods item. Agreements in the following form are not supported: u2018With material 1, material 2 and material 3 are free of chargeu2018 or u2018If material 1 and material 2 are ordered at the same time, then material 3 is free of chargeu2018.
    - Free goods are not supported in combinations with material structures (for example, product selection, BOM, variants with BOM explosion).
    - Free goods are only supported for sales orders with document category C (for example, not quotations).
    - Free goods are not supported for deliveries without reference to a sales order.
    - Free goods cannot be used in make-to-order production, third-party order processing and scheduling agreements.
    - If you defined a free goods for variants in a generic article (only SAP Retail), you can only process the variants in the purchase order and goods receipt individually (as single articles). In other words, you cannot process them using the generic article matrix.
    Not all Sales Order can be used for free goods determination.  You have to check the SD document category if it does not work.  Only category 'C' are supported.  Check transaction VOV8.
    Assume that you want to configure an inclusive FREE goods routine.  Customers must order a minumum quantity of 5 before any free goods can be assign.  For every quantity of 3, the customer will be given 1 free goods.
    WC07 - Maintain Number Range Intervals
    e.g.
    No   From number       To number
    01    0000010000         0000099999
    IMG -> Sales and Distribution -> Basic Functions -> Free Goods ->
    Maintain Access Sequences
    New Entries
    Acsq
    NA00
    Save
    Maintain Condition Types
    New Entries
    Ctyp   Name             AcSq
    FREE  Free Goods    NA00
    Save
    Maintain Pricing Procedures
    Procedures
    New Entries
    Procedure   Description
    FREE           Free Goods
    Select Procedure FREE then click Control data
    Step   Cntr   Ctyp
    10       10      FREE
    V/N6 - Activate Free Goods Determination
    Assign Order Type OR with Document Procedure A with Procedure FREE
    VBN1 - Create free goods determination
    e.g.  FREE inclusive
    Material  Min qty   From   are free good   Calc Rule   Free Goods
                           5           3                1                      1                1
    In this example, if you create a Sales Order for a quantity of 10, SAP will prompt you 7 as the customer order qty and 3 will be free.  Customer only pay for the 7 quantity
    Hopefully this will help to resolve the answer.
    Thanks & regards,
    Pankaj Mahajan
    Edited by: PM on Apr 13, 2010 10:28 AM

  • BADI CRM_COPY_BADI for item splitting in Quote - Contract

    Hi all,
    i have this requirement to split the item quantity into 1 per line when a contract gets created from a quotation.
    im new to both CRM and BADI but after doing some research online i figure that my scope should involve creating an implementation of the BADI, configurating the transaction type, and then adding my splitting code in method PRODUCT_I.
    but problem is, i've created my implementation and put a breakpoint in both method COPY and PRODUCT_I... and when i try to create a follow-up from a quote to contract, only the COPY method breakpoint gets caught. however, im quite sure it's the PRODUCT_I method which i should be using as it contains the item level internal table being pass into it. but it doesnt seems to be called in this process (am wondering if it's some config thing which i've missed).
    can someone provide some guidance into BADI, CRM_COPY_BADI and possibly the requirement's approach?
    many thanks in advance.
    cheers,
    Ryan.

    Hi Karthik,
    thanks for the info!
    technically, my understanding is that when u create an implementation, the process should goes through all these methods at relevant point on relevant business transaction. but strangely after putting breakpoints in all the said methods above, it seems to just going through the COPY method everytime a followup is being created (from quotation to contract). btw, i'm processing it through tcode CRMD_BUS2000112-> openning an existing quote-> then creating a follow-up contract.
    or should should i instead be coding these method-calling manually (on ORDERADM_I and SCHEDLIN_I) or is there some config i'm missing?
    lost in badi, was working more on the old exits for MM/SD. any pointers are much appreciated.
    many thanks!
    cheers,
    Ryan.

  • GL open items report needs OSS Note

    Hi All,
    Report S_alr_87012282 is run at period end and year end to validate that A/P 21010000 is in balance against the open items report. For the 7th period (12/13/08) I could not run the report as it timed out. If you run this in the background there are 100,000 pages and you can not see the last page. I need a resolution for this report as accounting said I have to use to balance.
    I tried in foreground and it still timed out.  I recommended FS10N,Please provide the OSS for any performance improvement notes.
    Thanks in Advance
    Prathap

    Hello everybody:
    I need open clearing items to clearing with other items. For example in my job was issued a payment to a supplier, but was applied to the wrong invoice, for this reason I need to open this compensation payment and apply it to the right invoice, the Tx FBRA, tells me that I must cancel the payment, but the payment was delivered and collected by the supplier, so I can not avoid it and just need to open the clearing.
    Can us help me please????
    Thanks
    María

Maybe you are looking for