Total shipment quantity for shipping costs

Dear Colleagues,
I am an SD consultant and I have a difficult requirement from a client to determine shipping costs per delivery quantity.
The scenario is that the freight rate will be entered for a "load" (e.g. $1000 / Truck)
There are multiple deliveries on this truck (e.g. delivery 1 = 78 units; delivery 2 = 22 units) (each delivery with multiple items)
We then need to determine the total shipment quantity (e.g. 100)
Divide the freight rate by total quantity (e.g. $10)
Determine the condition value by multiplying the delivery item quantity (78) by freight rate ($10) = $780
AT first I thought that I could do it as follows:
Call table VFKP to get the shipment number - field REBEL
Call table VFTA to have access to all deliveries on the parituclar shipment and add up all quantities - field RFMNG
However, these tables do not seem to be "reachable" from my pricing routine.
If anyone can help with suggestions I would really appreciate it.
Kind regards
Kikas41

Dear Silvia,
Would you please tell us how you can adapt this requirement?
Appreciate your reply asap.
Thank you very much in advance!
Best Regards,
Duc Lam.

Similar Messages

  • Aproval Process for Shipping cost document and settlement

    Hi
    Is there any approval process for capturing shipping cost and settlement (Using t codes VL31N,vt01n &VI01)?
    MVRao

    Hi
    This has been closed and done through development.
    Maganti rao

  • Need total consumption quantity year to date for item in inventory

    Hi All,
    I have a requirement as below.
    I need to find the total consumption quantity for a item year to date in inventory i.e i need to find out total issued quantity from year to date for a item.
    so i need following details.
    Consumption 1st year
    Consumption 2nd year
    Consumption 3rd year
    we are following fiscal year JAN-DEC.
    I am looking for a query to find out the above details, please help me out
    Thanks

    Hi Prashant,
    I will try this out. If I remember correctly this did not work especially since we are using the same base condition across the board. I may have to try copying this standard condition and re-assigning it accordingly.
    Thanks for the suggestion
    Anirudh

  • Capturing shipping cost at the time of GR

    Hi
    Dear all LE consultants
    I have one problem .I have created PO. At the time of PO creation , i do not know some shipping/transport costs.So I have configuring Transport module and done VL31n,VT01n,VT02n and VI01 t.codes Shiping costs are being fully calculating, but at the time GR , it is neither loading to material cost during MIGO against in bound delivery nor PO is also not being created for shipping costs.pl guide me
    MVRao

    HI,
    Thank you for the quick response..
    Despite following the steps given in  *OSS Note 427944 - Info: Shipment costs as delivery costs during goods receipt* the shipment cost is not being loaded at the time of GR.
    We observed that Note 427944 is apllicable till 4.7 but not for ECC 6.0(which is our version), probably that would be the reason its not working for us.
    Please suggest me further.
    Regards
    Maganti

  • Total Planned Quantity

    Hi every one
    I hope that someone can help me.
    I'm in the process of planning and i am using the transactions:
    KP06 to plan Cost Centers
    KP26 to plan Activities
    KPSI to execute the plan price calculation
    I Completed the transacción CS01 and CA01, the last one with the information of the work center and the estimated owrs
    But in the production order -> Cost -> Analysis I have the following information
    Total Planned Quantity For Activities equal to the value that I loaded in the transacción CA01
    Total Planned Quantity For Components Equal Zero (I completed the transación CS01)
    Is there any missing customining?
    Regards

    Divraj,
    Thank you for your answer, the information of the CK13N for period 07.2011 is the following:
    1 E     Activity 9004HN     9001741     116.580,00     116.580,00     ARS     30,0     HR
    2 M     Material 85442     9111999     2,00     2,00     ARS     2,00     ST
    3 M     Material 85941                    9111999     6,95     6,95     ARS     1,00     ST
    The information of the Planned Quantity cames from the Costing Run execution?
    Regards

  • Shipping Cost Price

    Hi,
    To estimate shipping cost in sales order, i use the shipping cost information under extras tab in sales order, ofcourse had to do intial set tup like creating shipping profile.
    But why is the shipping price calculated only in billing document? I maintain the condition type make it manual on the sales/del/ billing pricing procedure. It is the same condition type maintained on the shipment side. I also maintained in the del to billing copy control pricing type 'F' for shipping cost.
    I do see the condition type show value in billing document, once the shipping is settled and posted, but not sure why the pricing doesn't show up in delivery. Though it is flowing from del to billing. Any suggestions??

    answered

  • While making transfer at Shipping cost document

    Hi All,
             When Iam making transfer at Shipping cost document system is giving information " No purchage item found for shipping cost item $0001 000001" and it is not allowing to transfer.
    Can you please reply back ASAP
    Regards,
    Murali.

    hello, friend.
    in addition to what the others have forwarded, please check if you have a valid service PO which will be used for shipment cost calculation.
    regards.

  • Delivered quantity for each schedule line

    Hi,
    Our scenario is that we have an order for each order's each item we can have multiple schedule lines, when any of the schedule line is delivered the delivered quantity colum is updated, the schedule lines table in VBEP but the thing is it doesnot have the delivered quantity, system calculates it at runtime or may be it is keeping it in some other table.
    I hope some body can help in this regard.
    Thanks
    Khusro Habib

    It is a calculated value, not a value of a table field. Also, it may lead to wrong results if you don't pay attention to this description of the field here under in bold.
    Delivered quantity in sales units
    The quantity from the schedule line that has already
    been delivered.
    Use
    When there is more than one schedule line for an item,
    the system distributes the total delivered quantity for
    the item across the schedule lines according to the
    sequence of their delivery.
    Example
    A sales order item has three schedule lines, each with
    an order quantity of 50 pieces. You make two subsequent
    deliveries: the first for 20 pieces, the second for 60
    pieces. The delivered quantity for the first schedule
    line is 50 pieces, for the second 30 pieces, and for the
    third zero.
    If you delete the first delivery (20 pieces), the
    delivered quantity for this schedule line is still 50
    pieces. However, the system reduces the delivered
    quantity for the second schedule line to 10 pieces.

  • Shipping cost document

    Please provide a solution,
                In VI01, the amount, tax column is comin as zero. What are the essential condition types to be maintained for shipping cost document . Also provide some information about account assignment for shipping cost document (which g/l account to be posted in). How is settlemet carried out...??
                                                                                    Thanks.

    Hi,
    Check for the pricing procedure. It need to picked up properly.
    First check for VT01N when you are creating the Shipping documents , try simulatiing the document , Here if you have maintained the condition records you will get the simulated values. (say weight dependent / delivery documnet dependent.)
    Then in the following step try doing VI01, here you will capture the actual cost for the shipping documnet and will the settlemnet for the cost, and account determination.
    Cost settlement wil be done against the cost center. in the Shippmnent Part.
    Plz try doing it.
    Thanks
    Rishi

  • Step configuration guide for Shipping, Transportation & Shipment Cost Calcu

    Hi Gurus,
    Does anybody have the step by step configuration guide for Shipping, Transportation & Shipment Cost Calculation.Its very urgent.
    My email id is [email protected]
    Thanks in advance
    Regards
    Message was edited by:
            Sumit Rayaguru

    <b>Hi
    Pls don't post e mail id to share information . Make small search n sdn before posting the query.</b>
    Help Me!!!!!!!!!!!!
    Help Me!!!!!!!!!!!!
    Please Follow below steps.
    1)Create the transportation planning point for the company codes.
    2) Maintain transp. relevance for the dly doc. type, item cat and routes
    3) Define the shipment types
    4) Define the shipment cost types
    5) Define shipment cost item categories and assign
    6) Define shipment cost relevance
    7) Maintain pricing
    8) Assign purchasing data
    9) OBYC
    10) OKB9
    AND Please check the below:
    Step1: T.Code: VL01N: Just Create Delivery Note here. Do not do the Picking and Packing.
    (This is Client Specific)
    Step 2: T.Code: VT01N: Create Shipment.
    Here mention your Transportation Point and Shipment Type you Configured for this and Click on deliveries ICON.
    GO to W.ref to
    Outbound Delivery : Give your Delivery Number that you created earlier for this shipment and F8( Excute)
    Then Select the Delivery and Click on OverView
    Here Click on Planning then automatically Route( If route determination is done) and Vendor Number get generated and Save the Data.
    Step.3: T.Code: VL02N: Change Delivery.Here give the Delivery no and
    Do picking, Packing (If necessary) and PGI.
    Message was edited by:
            SHESAGIRI.G

  • Shipping Costing - Invoice for the FWD Agent

    Hello:
    I am working with PO, Inbound Deliveries and Shippment in order to assign the import costs to all the items related to the shipment.
    I have a concern. I have created a Shipping Cost Document related to a Shipment, This document has a FWD Agent assign.
    Is there a way to register the Invoice (MIRO) of the FWD without having a PO created for the service?
    I have reviewed that in the MIRO, if I select "Purchase Order /Scheduling Agreement" and at the right I put "Planned Delivery Cost", the system brings the cost of the FWD related to that PO,
    The thing is that I want to register the whole cost of the FWD Agent related to a Shipment. So in the MIRO I select "Transportation Service Agent" and select the Shipment N°, but the system is not showing any line items.
    My question is, is there an option of registrating the FWD Agent invoice (MIRO), without a PO created and for the whole Shippment?, And if the answer is YES, how?, maybe some configuration is missing.
    Thanks in advanced,
    Regards,

    A freight PO (service PO) is required.  When you settle shipment cost document,  the service acceptance document is created.  This in turn will either add an entry to the already exist service/freight PO or generate a new service/freight PO (depend on how you configure the shipment cost item category).  This will allow you to create invoice in MIRO using the shipment document.
    The service/freight PO is required because you want to create invoice for the FWD agent.  The service/freight PO is just for a specific FWD agent.

  • Two Shipment and Shipping cost docs using a single delivery doc.

    SAP Gurus,
                       I'v a delivery document with a single line item and i would like to create two shipmt and shipping cost document since the material movement will be handled by two different freight vendors from the point of origin - transfer - Destination. I have a route setup for these stages, and i assigned each service agent to each stage(legs) and also marked each leg is shpcost-relv. My question is the system keeps creating only two shipment doc without any service agent on a header level but its not creating any shpping cost doc.
    Thanks

    Please post into Logistics Execution forum. MM forum is not the right place for this question.
    Regards,
    Dominik Modrzejewski

  • Analyse cost component split for planned costs:total/level/lower

    Hi!
    when I am executing the CK13N, I am able to get total cost , this level cost, lower level cost for each cost componenet and same thing from report CK80_99.
    But My client is asking a report to know the level cost for header material in process order with actual production quantity.
    So, I need to know, what are the tables, where i can see total, this level, lower costs each cost component structure wise.
    I have checked KEKO & KEPTH, but not able to get this level cost directly.
    can any one give tables regarding this.
    regs,
    ramesh

    Hi
    Its not possilnbe... In Prod order, you issue material at say iits Std cost.. This will be issued at one single value.... You dont get breakup of the SFG material in the FG Production order
    br, Ajay M

  • Sales order in B2B. Shipping Costs and Total Gross Price

    Hi
    I have question about 2 fields in the B2B-order:
    1. Shipping Costs
    2. Total Gross Price
    Which codition is using for calculate these 2 fields? How system understanding what is this condition?
    How we can change rules for these fields?
    Denis.

    Hi,
    DJ, thank you for answer.
    I have researched this customize setting.
    Unfortunately, I can't understood how filled these fields:
    1. Shipping Costs
    2. Total Gross Price
    Denis.
    Edited by: Den Kh on Jun 23, 2011 1:03 PM

  • Shipping cost not getting calculated in CRM IC webclient for a certain regi

    HI all,
    I have an issue where when we create an order, the shipping cost is not getting calculated automatically.. and so we are having to manually enter the shipping cost..this is happening only for Apac regions. for all other regions it seems to be working. but the shipping cost is getting calculated in R/3. can anyone provide input for this?
    Also, what factors determine the shipping cost?
    Thanks,
    Preethy

    This is a funtional issue... You'll be better of opening this message in the right Area.... or open an OSS message for SAP.
    Regards
    Juan

Maybe you are looking for