Transfer of non-valuated materials from ECC to SRM

I kindly request your help with an issue that I am facing.
The scenario is as follows :
1. There is a non valuated material X (material type UNBW).
2. MRP run happens and generates a PR with account assignment U.
3. Transfer report BBP_EXTREQ_TRANSFER is executed in order to transfer the PR to SRM.
4. The PR reaches SRM, but the SC is not created instead in SLG1 there is an error thrown, "No account assignment exist. Enter an account assignment".
5. In the backend now If I try to change the PR i get the error " 6Q204 (Procurement profile 36 cannot be changed).
Is this scenario supported ?? i,e, transfer of non-valuated materials from ECC to SRM.
Kindly let me know if you have any idea on this.

Hi,
As per your query you have not determind accounts assignment. Please do these activity.
Please see the below link.
http://help.sap.com/saphelp_srm30/helpdata/en/a9/cde93a2876a81ae10000000a11402f/content.htm
Regards,
Anil

Similar Messages

  • Errors while replicating Materials from ECC to SRM

    Hi All,
    I am trying to replicate materials from R/3 to SRM, in SMQ2 of SRM, the status of MATERIAL is still in yellow colour. when i checked in SMW01 tcode, the error is "Category for material group 013 does not exist" where as in R/3 also we dont have any material group as 013.
    All the Prod type & Prod category have been replicated into SRM from R/3.
    And no materials have copied in SRM.
    how to resolve this ?
    regds,
    CB
    Edited by: Channabasappa.K on Feb 17, 2011 10:30 AM

    Hi,
    DNL_CUST_PROD0 & DNL_CUST_PROD1 were in green colour now,
    DNL_CUST_BASIS3 is in yellow colour & i saw in some doc that DNL_CUST_BASIS3 is not reqd from SRM7.0 onwards.
    when i try to replicate MATERIAL, in SMQ2 i am getting status as SYSFAIL & after double clicking on that i got a pop up as "Error in Mapping (Details: transaction SMW01)"
    Upon checking in SMW01 i got the above errors as
    " Category for material group 013 does not exist
    Message no. COM_PRODUCT_API002
    Diagnosis
    If material groups are used in the SAP system, they must exist as categories in CRM/EBP before you import materials. When Customizing object DNL_CUST_PROD1 is imported, the material groups are imported automatically and created in the category hierarchy R3MATCLASS (material group).
    Procedure
    Check whether the material groups have been imported successfully and exist as categories.
    Proceed
    If necessary, import the Customizing object DNL_CUST_PROD1"
    Like this its showing 19 material groups and all these 19 mat groups were not present in ECC.
    Regds,
    CB

  • Split valuation for non-valuated materials

    Hi dudes,
    We are implementing SAP for our Subcontractor.
    our SC  receive all components from our company ( on free ) but sometimes they purchase the same material themselves for other uses. so we decided to use split valuation to separate valuated and non-valuated materials.
    I did configuration and created 2 valuation type ( valuated - nonvaluated )
    when I create Purchase order it askes for valuation type but even when I use non-valuation type in PO it asks for price!!!!
    do any of you have used split valuation for this target?
    have the same problem?
    what should I do actually??

    Hi,
    Is someone in the subcontracting plant going to do a process order on the materials you send them? Or are you only going to track the finished inventory once it reaches your plant?
    In the first case:
    1) Create a STO to the SC plant. This stock will have to be priced.
    2) Inventory reaches SC plant. They perform production process.
    3) finished inventory is sent using another STO.
    2nd Case:
    1) Create a SC vendor using the SC plant as a vendor.
    2) Create a SC PO to this vendor using this vendor and transfer goods to him. In this case, goods are transferred for 'free' as they really belong to you and not to the SC
    3) Once the production process is over and the finished product is sent back to you, do a GR. The raw material sent to the SC will be consumed.

  • Best Material Type for Handling Non-valuated Materials in Distribution

    Our distribution business will soon be handling non-valuated material and I am trying to determine the best material type to use.  I am considering material type UNBW but would like to know if anyone has advice.  We are strictly providing a service to the vendor for handling these non-valuated materials (for example, wood products).  We will not purchase or sell the product.  Our service consists of receiving the product into inventory from the vendor, tracking the inventory, (in Warehouse Management) and then shipping the material to a customer of the vendor's choosing.  For these non-valuating materials, we are paid strictly for our service of warehousing the material and shipping to a customer.
    Up until now, our distribution business has distributed only valuated materials, i.e., materials we purchase at a price and sell at a price.  We also use vendor consignment.  NOTE: This is not a vendor consignment scenario because we never buy the product.
    Here are our requirements:
    - We don't own the non-valuated product.
    - We need to be able to ship these new non-valuated products on the same shipments as the valuated product we own.
    - We use handling unit and warehouse management for all of our finished goods.
    - We would like to use our existing processes and HU/WM RF transactions to receive and pick the non-valuated product.  This means:
    1) Creating inbound deliveries and packing into HUs.  And applying our HU bar code labels.
    2) Physical inventory counts by HU.
    3) Creating sales orders that have both the non-valuated materials and valuated materials we own.
    4) Creating outbound deliveries and picking via transfer orders in WM.
    5) Assigning the outbound deliveries to a shipment.
    Questions:
    1)  Can a UNBW material that will be stocked but not valuated be received into inventory via a PO?  Any way to receive into inventory with an inbound delivery without using a PO?
    2)  Are there any problems with putting a non-valuated material on a sales order with a zero price?
    3)  Any challenges that other have run into?
    Thanks in advance.
    Rob

    I must be missing something regarding the use of material type UNBW.  When I post the goods receipt for a PO with a UNBW material, no inventory is created.  When I create the PO, an account assignment is required.  I tried both a cost center account assignment (K) and balance sheet account assignment (Z - using a Profit Center).  In both cases, I am forced to check the "Free item" checkbox to avoid entering a price; which also seems strange since the material is UNBW.
    I have searched everywhere for a "Best Practice" for my scenario with little results.  Again, we are simply managing the inventory for a vendor and shipping the inventory to our vendor's customers.  So we are acting as a third pary warehouse and shipper for the vendor.  We do not buy or sell the inventory - we are paid a monthly service fee by the vendor for warehousing their product and shipping it to their customers.  We may ship the product on sales order deliiveries that include both the "non-valuated" product (i.e., free goods we manage for this vendor) and goods that we actually own.
    As an alternative, I am wondering if I should look into somehow using vendor consignment with a settlement price (consignment info record price) of zero.  Vendor consignment is nice because you can track the stock by vendor.  However, we would never truly "settle" with the vendor because we would not be paying the vendor for the inventory and would never own it.
    Our business refers to this as "reload business" but I am not sure this is an industry standard term.
    Any other thoughts out there?

  • Non-valuated materials

    Hi,
    We have non-valuated materials in master data. We are using account assignment category K (Gl account and cost center purchase) while creating PO for non-valuated material. Hence, the material should get consumed at the time of GR. But we are observing that the material's qty. gets accumulated in unrestricted stock instead of getting consumed at the time of GR.
    If we issue the material again using MB1A then issued qty gets deducted from unrestricted store.
    Kindly explain.
    With Best Regards,
    Rajkumar

    Hi Rajkumar,
    The system is working fine in this case. Please, note the following:
    1) If the material is set to make value and quantity update and it is included in a Purchase Order with account assignment, a goods receipt will increase the consumption.
    2) If the material is set to quantity update but no value update and it is included in a Purchase Order with account assignment, a goods receipt will increase the stock.
    The reason is the following one:
    In the case 2) the account assignment is mandatory when the purchase order is created.
    In the case 1) the account assignment is not mandatory. We enter the account assignment as we need, but it is not compulsory. Therefore, in this case, the presence of account assignment is used to decide whether the goods are posted to consumption or to stock:
    - If there is account assignment the goods go to consumption.
    - If there is not account assignment the goods go to stock.
    In the case 2) this logic cannot be used, because the account assignment is mandatory, so the system "does not know" if you want to post the material to consumption or to stock.
    In this case 2) the material always goes to stock.
    If then the material is to be consumed you can do your consumption posting for a non-valuated material just as you mention: with MB1A and the movement type 201 for example.
    I hope this information helps!
    Best regards,
    Esther.

  • Non-Valuated Materials Purchasing Process

    Hi,
    Can some one please explain step by stem the process of purchasing for non-valuated materials. From PR to PO e.g. Account Assignments etc the whole works. If any one has any documents or screenshots that would be greate to just email them to me.
    1)When Creating a requsition it asks for an Account Assignment why?
    2)It also asks for a valuation price it doesn't accept 0 why? This is a non-valuated material and free?
    I am having problems as I have approval levels setup via classifications for all indirect purchasing from account assignment K if for all non-valuated materials I have to create reqs via account assignment K they will require approvals. I don't want that.
    please help points will be awarded
    thanks
    ADeel

    U NEED To create the material master with unbw or nlag material type
    > create pr
    mention the material code and in the valuation field u can put the price of material for internal valuation
    mention the account assign. categ.  K
    now the question is that you do not want to make use of the aac K THEN LET ME TELL U ONE THING
    for those material types having no quantity/ value updation it is must that u mention the account assignement category
    becuase if u r procuring the material but not storing it then it means u r directly consuming the goods at gr hence u need to tell the system where has the goods gone after gr ............and u r doing this via AAcategory
    --->po
    if u wan to recive free of cost goods then u need to mark the check box in po in front of your line item ...........

  • GRN of Non Valuated Materials

    Hello Experts,
    Please explain me the inventory management of Non Valuated Materials.
    How the GRN of such materials is done.
    What are the documents generated for goods movement related to non valuated materials.
    Regards,
    MM

    Dear,
    Please explain me the inventory management of Non Valuated Materials.
    Non-valuated materials are managed on a quantity basis, but not by value
    How the GRN of such materials is done.
    GRN of these materials will be done in normal way with mvt 101, only difference will be there won't be any accounting document generated at the time of GRN.
    What are the documents generated for goods movement related to non valuated materials.
    Once you do GRN for Non Valuated Materials then there will be only material document created, there won't be any accounting document generated.
    Hope it helps.
    Utsav

  • Transfer Data from ECC to SRM

    Hi ,
    I'm trying to transfer data from ECC to SRM for creating bid document ( Function : BBP_PD_BID_CREATE ). After transferring the data I want to get the data back to ECC ( I need bid document number to write on delivery document's field ). What's the best way to do this ?
    Regards.

    Hi vinit ,
    I've written code to call 'BBP_PD_BID_CREATE' in ECC. But ECC and SRM have different structures. So i am not sure how i can define data to send SRM.
    Here is my code in ECC program
    CALL FUNCTION 'BBP_PD_BID_CREATE' IN BACKGROUND TASK
       DESTINATION 'XXX'
       IMPORTING
         I_REF_GUID    =
         I_BAPIMODE    =
         I_PARK        =
         I_SAVE        =
         I_TESTRUN     =
         I_HEADER      = I_HEADER ?
         IT_ATTACH     =
         IT_DYN_ATTR   =
         IT_CONDITIONS =
        EXPORTING
          E_HEADER      = E_HEADER ?
          ET_ATTACH     =
          ET_DYN_ATTR   =
          ET_CONDITIONS =
        TABLES
           I_ITEM        =
           I_PARTNER     =
           I_LONGTEXT    =
           I_SDLN        =
           I_ORGDATA     =
           I_HCF         =
           I_ICF         =
           I_TOL         =
           I_WEIGHT      =
           IT_EXCHRATE   =
           E_ITEM        =
           E_PARTNER     =
           E_LONGTEXT    =
           E_SDLN        =
           E_ORGDATA     =
           E_HCF         =
           E_ICF         =

  • Vendor Transfer from ECC to SRM-EBP

    I want to transfer vendor from ECC to SRM-EBP.I tried the T code BBPGETVD. But I am getting the below log:
    "Error: Error while Creating Business Partner (BP) Module: BUPA_CREATE_FROM_DATA Vendor: 0000100011".
    Please suggest.

    Hi
    I have seen this error. However kindly check in SRM side
    In BP transaction 0000100011. Is this vendor is vailable or not.
    OR
    do some cosmetic change in this vendor in XK02 and when you run BBP_VENDOR_sync REPORT BRINGS you this vendor in SRM
    Muthu

  • Restrict issue of non valuated materials

    dear experts,
                             Is there any way to restrict issue of non valuated materials against a production order.
    Regards,
    krishna mohan

    sir ,
         After discussing with u about the issue again i discussed with my pm and got the exact requirement,
    what exactly he want is the price of the material is 0 zero , it should not be allowed to be issued against a production order.
    please tell me if we can do with configuration  which is the best way or else we have to use  any exit.
    if we use exit  we will check in MBEW table and field verpr, if the verpr field value is  0 zero then we will not allow else we allow the material to be issued.
    regards
    krishna mohan

  • No Business Partner generated for new employee transfer from ECC to SRM

    Hi All,
    I am working on SRM 5.0 with ECC 6.0 backend. The HR structure is replicated from ECC using ALE, message type:HRMD_ABA.
    When I am trying to replicate a new employee from ECC to SRM, I run the O-insert first, then the S-insert and then the P-insert using PFAL transaction.
    The Org structure was already in place in SRM, so it just adds the new position to it by A003 relation. The S-insert generated idoc shows status as '53' in both ECC and SRT with the relation A003, B007 and A008. But, when I check the table HRP1001, the A008 entry is missing. Due to this, no CP is generated for this position and also no business partner is generated for this user.
    When I run the P-insert for this employee, the idoc is posted in ECC. But, the status of the idoc in SRT is '52' and the message shown is "The Parameter Country Has Not been Entered During Naming Format Check" Message No. R11206.
    I checked the Name Format for this employee, and it is maintained as 2.
    Where am I going wrong? Why is no CP person generated even when the idoc status is 53? Why isn't the new employee getting transferred to SRM server?
    I have checked the SAP notes related to HR-ECC Org transfer, but I am unable to figure out the reason for this problem.
    Could anyone help me out in this?
    Regards,
    Ancy

    Maintained the name format tables (SA13)on ECC and SRM side.

  • POS for non valuated materials

    Now I am creating POS for non valuated materials. But system is asking Price for Non Valuated Materials. Please tell me how can create POS with our price for Non valuated Materials.

    Hi,
    Are you purcahsing non valuated material (UNBW material type) for free.If not keep a price in PO  ( with account assignment category K)& do GR (where it will hit expense acoount & GR/IR account) &then IR.
    For more check OSS Note: 456691
    Regards,
    Biju K

  • Unable to load Materials from ECC to Cloud due to UoM errors

    Dear experts,
    We are working to set up the ECC integration with C4C through HCI, we maintained all necessary settings in ECC and HCI.
    When we are trying to send Material data from ECC to C4C they are failing in Cloud with error "Solve Configuration Issue in Code List Mapping for field MeasureUnitCode with value PCE", but we maintained all the Material specific UoM in cloud and mapped them with ECC values in Code List mapping.
    Can someone give your input in which scenario this error comes and how UoM Conversions gets updated in Cloud, like ECC Material master.
    Thanks & Regards
    Naren..

    Hi Naren,
    we have experienced a similar problem when loading materials from ECC to C4C.
    What we have seen is that you have to:
    - maintain the basic UoM of the material in C4C
    - maintain all the UoM mentioned in the conversions for the material
    - maintain the Code Mapping for these UoM if the codes are different from ECC and C4C
    Nevertheless we had a problem for materials that in ECC in the UoM conversions section of master data have conversions like: 1 MTR = 1000 MMT (1 meter = 1000 millimeter).
    In C4C we have activated UoM MTR and MMT, and MMT is defined as 0.001 MTR. So the conversion rate is defined in C4C.
    If ECC sends this conversion for the material to C4C we have an error.
    We have solved it modifying the mapping in HCI for the iflow *.erp2cod.material.*: in the mapping, the conversion element is not transferred if the basic UoM is MMT and the conversion UoM is MTR.
    This is an example and a simple workaround that allows us to load these materials.
    Maybe could be useful.
    Regards
    Piero

  • DIFFERENCE BETWEEN NON-STOCK AND NON-VALUATED MATERIALS

    HI ALL,
    I WANT TO KNOW WHAT IS THE DIFFERENCE BETWEEN NON-STOCK AND NON-VALUATED MATERIALS. WHY THESE TYPE OF MATERIALS ARE COMING UNDER COST CENTER AND WHEN CREATING PO FOR THIS TYPE PARTICULAR MATERIALS WHY WE ARE NOT MAINTAINING PRICE, MEANS WHY WE ARE DEFINING THE PRICE FOR THIS PARTICULAR MATERIALS?

    Hi,
    Hi,
    non-valuated material (Material Type UNBW):
    This type of material is managed on a quantity basis, but not on a value basis. This makes sense for materials of low value, stocks of which nevertheless have to be monitored (for example, operating manuals).
    Non-stock material (NLAG) (Material Type NLAG):
    Inventory management is not possible for these materials either on a quantity or value basis. For frequently required consumables, the use of this material type nevertheless enables you to store the information required to create
    purchasing documents (such as texts and units of measure).
    When a material is procured directly for consumption, no material master record is necessary. In connection with consumable materials, you can distinguish between the following cases:
    • Consumable material without material master record
    • Consumable material with material master record that is not subject to
    inventory management (on either a quantity or value basis)
    • Consumable material with material master record that is subject to inventory management on a quantity, but not a value, basis
    pherasath

  • Transfer of PR from ECC to SRM

    Hi experts,
    I am new to SRM & my questions can be bit easy. We have implemented PDP & while transferring the PR from ECC to SRM, the PR got stuck in sxmb_moni in SRM. Now when i  see the error /sappo/ppo2 it shows "cannot save template: Insert Items".
    I have checked the Org. Structure and i think the attributes defined to the RFC_USER is also correct because i can create the shopping cart without an error from this user.
    So please help me.
    Thanks & Regards
    Himanshu singh phartyal

    Hi,
    Would you please apply note 1821480 and retest the issue with a new PR?
    Regards,
    Ivy