Transporting BPC 10 from Development to Production

Hi all,
I am working on a BPC 10 project and it is time for us to test in production.
I am aware of two main routes to go from a Dev to Prod system, the first of which I attempted yesterday:
1. BW Transport
- Set the environment offline
- Log in to BW
- Transaction code RSA1
- Transport Connection
- Object types > More types > Environment > Select Objects ([see link|http://i39.tinypic.com/2wrpun6.png])
- We did select quiiiite a lot of data to transport which may have been an issue - everything in the environment
- Ticked all the objects on the right hand side, then clicked the van saying 'Transport Objects'
- We then logged into SE 10 and released the transport: ([see link|http://i44.tinypic.com/2gw9ir8.png])
2. Backup and Restore using UJBR transaction
- Back up the whole environment
- Restore onto production
The issue
- We have only done the first method as understand the UJBR one is a bit of a workaround and not as reliable
- We had an exceptionally high number of logs generated, causing the log drive to fill up and Short Dump in ST22
- It generated 8GB of logs on the Development server after the first attempt, we backed up and cleared out the logs and re-transported a new request which generated 45GB of logs - causing the same 'transactional log file' issue
Does anyone have any advice in terms of  BPC 10 transports? We found a decent how-to which essentially just walked us through part 1, then we've been checking ST22, SLG1 Analyse Application log, SM21 System log, and DB12 to check capacity to try and problem solve..
Thanks!
Nick
Screenshot of the error log: [http://i40.tinypic.com/2yzk9jl.png|http://i40.tinypic.com/2yzk9jl.png]
Edited by: Nick Carter on Feb 3, 2012 3:18 PM

Hi Rich - thanks for your advice.
I've taken your advice on board and deselected virtually everything to transport, with the exception of the model, model dimensions and an input schedule.
This is the selection this time around: http://i44.tinypic.com/a4ahw7.png
I then clicked the'Transport objects' button and made a request for transport: [http://i43.tinypic.com/17x1fc.png|http://i43.tinypic.com/17x1fc.png]
Followed by jumping to Transprot Organiser in SE10 and then 'Releasing directly' when selecting the base node NWDK903388 first, followed by the same action on parent node 'Projet Dragon Transport 005': http://i44.tinypic.com/2i8kh95.png
When looking at the transport logs, it appears it has released from NWD (Development) but not imported into NWP (Prod): http://i44.tinypic.com/2q1xvdl.png
We aren't experiencing the same issue of logs at the moment so it suggests it was related to a high volume data manager file?
Any help would be much appreciated!
Nick
NB: I have also made sure that on our Production server we had the identically named environment which is something we didn't have before, whichI think we needed(?) I also checked I have superuser access account on both Dev and Production to ensure that wouldn't be a problem.
Edited by: Nick Carter on Feb 3, 2012 4:34 PM

Similar Messages

  • Transport ALE Configuration from Development to Production System

    Hello All,
    We have created ALE-IDOC scenario in the development system and its working fine. Now we want to transport it to the Production / Quality system. How can we transport the settings like logical systems, port definition, partner profiles, distribution model , RFC destinations from one system to another system??
    Because the client numbers are different for development , quality and production systems.. Do we need to transport the logical system and client assignment using STMS or create directly in the target system??
    Thanx in advance...

    The issue with transporting the ALE distribution model is that the source and target logical system names change between the dev, test and prod environments.
    Assume an ECC6 and PI landscape with dev/test/prod called E6D/E6T/E6P and PID/PIT/PIP with all systems using client 100.  By default (SAP recommendation) the logical system name for E6D client 100 is E6DCLNT100 and its PI partner in the dev landscape will be PID client 100 with logical system name PIDCLNT100.  In test the logical system names will be E6TCLNT100 and PITCLNT100 and in prod E6PCLNT100/PIPCLNT100.
    So, when a distribution model is set up in dev with a source system of E6DCLNT100 sending messages to a target system PIDCLNT100 everything works nicely.  This assumes that the PIDCLNT100 logical system partner in WE20/WE21 is mapped to a port which maps to an RFC destination pointing to client 100 of PID.
    When this model is transported to the test system it won't work because the logical system names are wrong.
    It is possible to create a logical system name called PISERVER in SALE and then map that, via WE20/WE21 to point to the corresponding PI instance.  Thus in E6D, WE21 would map logical system PISERVER to the RFC destination for PIDCLNT100 but in E6T the mapping would link to RFC destination PITCLNT100 and in E6P to PIPCLNT100.  In this way any ABAP programming trying to use the ALE distribution model would send messages to PISERVER and would be transportable.
    However, setting up the source system in the same way appears to be impossible.  When attempting to generate partner profiles, transaction BD82 stubbornly insists that the source system for which it will build profiles MUST be the logical system name defined for the execution client in SCC4.  Theoretically, mapping similar to that for PISERVER could be performed for ECC6SERVER and the ALE distribution model could be built to send messages from ECC6SERVER to PISERVER but BD82 won't honour this source system.
    This appears to make it impossible to transport an ALE Distribution Model.  Can anybody provide a process to overcome this apparent architectural limitation?

  • Transport of Scorecards from Development to Production [SCPM]

    Hi,
    Can we transport the scorecards, dashboards and reports created in the development environment into the test, pre-prod and finally into the prodcution environment rather than recreating them each time? If so, how do we do it.
    Regards,
    Vimal Gasper
    Edited by: vimalgasper on May 11, 2011 10:42 AM

    Hi,
    Please follow the SAP Note: 1491055 - Transport of SCPM Content. This note provides the details of how to transport content in SCPM 1.0. Let me know if you need more details.
    Regards,
    Tarun

  • Error occurred while transporting request no. from development to productio

    Hi Experts,
    I have created a zreport (having a request number ) and activate the zreport  ..
    While transporting this request from development to production I face the error zreport is inactive ….But when I check zreport in development server it is active ..
    So how to transport this request.? Please help ..

    Hello,
    Can you ask the basis person to check the transport log and tell as to what error has occured. Most of the time transport fails if  one of the dependent object fails to  move. For example you have structure that you have used for table declaration in your prog. You moved the program but the structure was not moved. When Tranported , the  program will result in an error and saying Struct not present.
    What you can do immediately is to go on your prodcution server and try to do a syntax check of the program. I am sure it will show some error and from that you can carry out issue resolution. Also ask the basis person to hvae a look in to ur transport(he can see the same via STMS Tcode).
    Regards
    Saket Sharma

  • How to transport the data contains in the table from development to product

    How to transport the data contains in the table from development to production.
    Please let me know ASAP.

    Hello Dilip
    Create a workbench request and add the following entries to the request:
    Object key: R3TR TABU <name of z-table>
    For this object add the following value key:
    - client-independent table: '*'
    - client-dependent table (e.g. client 100): '100*'
    See also: [SAP Network Blog: Transport Table Entries|/people/community.user/blog/2007/01/07/transport-table-entries]
    Regards
      Uwe

  • Transporting object from development to production server

    Hi Everyone,
    Could you plz tell me how can i transport a object from development server to production serevr if that object is local in production server. And also could u tell me if the transfer structure is replaced if the names are different in both the server???

    Could you plz tell me how can i transport a object from development server to production serevr if that object is local in production server.
    Case 1: Object is in Prod, but not in Dev. and you want to align the systems through transports.
    You will have to send it to D (which could be done by changing transport routes & then following normal transport procedure) & then will have to bring it back with overwrite originals.
    Case 2: Object is present both in Prod & Dev. 
    You can send the transports D->P with Overwrite originals (following the transport procedures).
    And also could u tell me if the transfer structure is replaced if the names are different in both the server???
    If technical names are different in both the servers, the transfer structure will not be overwritten.

  • Transport Web Template, Query from development to productive system

    Hi!
    How can I transport Web Template, Query, workbooks from development to productive system?

    RSA1 ---> Transport Coonection ---> Object Types -
    > Select Web Tempelate ---> Drag to right and group under transport
    Similary do for other objects
    Thanks
    Amit

  • VC Reports transport from Development to Production

    Hi all,
         How do we transport the VC Reports from Development to Production.
         How to transport the model.
         Do we need to create new System Object.
         please help me. Are there any standard document available.
    Thanks & Regards,
    kishore.

    Hi
    After importing the model as Dharmi explained, you might need to change the systems' names in the model to fit the production landscape. For example, if a backend system has an alias AAA in Dev and same system has alias BBB in prod. To do this, simply choose Tools > Manage services...
    If the landscapes are compatible, you can transport only the working iView using the portal transport capabilities. Navigate to System Configuration > Transport in the Dev portal, find your iView and add it to a transport package.
    Hope this helps,
    Shay

  • Transporting an Object from Development to quality and then to Production

    Hello SAP Friends
    I want to know the step by step navigation for Transporting an Object from Development to Quality and from there to production..
    Please give some detailed Navigation...

    Hi Kiran,
    use transport connection to collect the objects to request, rsa1->transprot connection.
    use infocube as starting point to collect objects, left side choose 'object type', middle frame choose 'infocube' expand 'select objects', locate/search your infocube' and 'transfer', it will go to right side.
    in right up, there are buttons, click 'mode' and choose manual, and grouping 'only necessary objects', and execute, this will collect infocube and required objects like infoobjects, infoarea, etc.
    after that change grouping 'in dataflow before' and execute, this will collect update rules, ods, infosource, transfer rules, datasource assigned etc.
    remember to assign source system, click yellow box with X icon and mark the source system.
    after that use grouping 'in dataflow afterwards' to collect query, web template, role etc.
    take a look transport docs
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/3010ba90-0201-0010-2896-e58547c6757e
    http://help.sap.com/saphelp_nw2004s/helpdata/en/0b/5ee7377a98c17fe10000009b38f842/frameset.htm
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/e883de94-0501-0010-7d95-de5ffa503a86
    http://help.sap.com/saphelp_nw2004s/helpdata/en/b5/1d733b73a8f706e10000000a11402f/frameset.htm
    http://help.sap.com/saphelp_nw2004s/helpdata/en/57/38e1824eb711d182bf0000e829fbfe/frameset.htm
    Re: Transport Organizer---
    transport query (bex objects)
    http://help.sap.com/saphelp_nw2004s/helpdata/en/38/5ee7377a98c17fe10000009b38f842/frameset.htm
    hope this helps.
    (Courtesy AHP from Re: transport)
    Bye
    Dinesh

  • Questions on Analyzer Upgrade and Moving Analyzer Reports from Development to Production

    Hi,We run Analyzer 5.0.3. We are planning to go to Analyzer 7.2. Did any body go thru this upgrade? If so, what is your opinion and tips that may help. Also, we never had Analyzer development environment. We are planning on having Analyzer development environment. In our installation, all of the Analyzer reports are centrally developed based on user requests. Once we have development and production at the same Analyzer version, if a report is developed in the development system, how can the report be mirateed/moved from development to production system?Thank you for your help,Prasant

    Balaji,
    Has this been done yet?
    Gary
    <BLOCKQUOTE><font size="1" face="Verdana, Arial">quote:</font><HR>Originally posted by [email protected]:
    We are working on a document using which one should be able to move a portal instance from one database to another. It is still in draft version, once it is finalized we will be putting it on otn.
    Thanks and Regards
    Balaji<HR></BLOCKQUOTE>
    null

  • ERROR WHILE MIGRATING SSIS PACKAGE FROM DEVELOPMENT TO PRODUCTION IN EXECUTION

    HI,
    I have a problem while executing the package after migrating from DEVELOPMENT to PRODUCTION.
    We have two SQL database connections DEVMIDDLEWARE and PRODMIDDLEWARE for dev and prod respectively. When we have created package in development we have used DEVMIDDLEWARE and we have credentials in CONFIG file of that package and executed sucessfully. When
    we migrated this same package to PRODUCTION when have given credentials of PRODMIDDLEWARE in CONFIG FILE of this package we are getting error as below
    "Description: Failed to decrypt protected XML node "DTS:Password" with error 0x8009000B "Key not valid for use in specified state.". You may not be authorized to access this information. This error occurs when there is a cryptographic
    error. Verify that the correct key is available.  End Error  Error: 2014-10-28 07:41:44.24     Code: 0xC0016016     Source:       Description: Failed to decrypt protected XML node
    "DTS:Password" with error 0x8009000B "Key not valid for use in specified state.". You may not be authorized to access this information. This error occurs when there is a cryptographic error. Verify that the correct key is available. 
    End Error  Error: 2014-10-28 07:41:44.85     Code: 0xC0202009     Source: Package Connection manager "DEVBIZTALKDB01.RHUL_Staging.devmiddleware"     Description: SSIS Error Code DTS_E_OLEDBERROR. 
    An OLE DB error has occurred. Error code: 0x80040E4D.  An OLE DB record is available.  Source: "Microsoft SQL Server Native Client 10.0"  Hresult: 0x80040E4D  Description: "Login failed for user 'devmiddleware'.". 
    End Error  Error: 2014-10-28 07:41:44.85     Code: 0xC020801C     Source: Package Log provider "SSIS log provider for SQL Server"     Description: SSIS Error Code DTS_E_CANNOTACQUIRECONNECTIONFROMCONNECTIONMANAGER. 
    The AcquireConnection method call to the connection manager "DEVBIZTALKDB01.RHUL_Staging.devmiddleware" failed with error code 0xC0202009.  There may be error messages posted before this with more information on why the AcquireConnection method
    call failed.  COM error object information is available.  Source: "Package"  error code: 0xC0202009  Description: "SSIS Error Code DTS_E_OLEDBERROR.  An OLE DB error has occurred. Error code: 0x80040E4D.  An OLE
    DB record is available.  Source: "Microsoft SQL Server Native Client 10.0"  Hresult: 0x80040E4D  Description: "Login failed for user 'devmiddleware'.".  ".  End Error  Error: 2014-10-28 07:41:44.98    
    Code: 0xC0202009     Source: Package Connection manager "AGRDB01.abwr66"     Description: SSIS Error Code DTS_E_OLEDBERROR.  An OLE DB error has occurred. Error code: 0x80040E4D.  An OLE DB record
    is available.  Source: "Microsoft SQL Server Native Client 10.0"  Hresult: 0x80040E4D  Description: "Login failed for user 'CC\epsdbuser'.".  End Error  Error: 2014-10-28 07:41:44.98     Code:
    0xC020801C     Source: Data Flow Task OLE DB Source [1]     Description: SSIS Error Code DTS_E_CANNOTACQUIRECONNECTIONFROMCONNECTIONMANAGER.  The AcquireConnection method call to the connection manager "AGRDB01.abwr66"
    failed with error code 0xC0202009.  There may be error messages posted before this with more information on why the AcquireConnection method call failed.  End Error  Error: 2014-10-28 07:41:44.99     Code: 0xC0047017    
    Source: Data Flow Task SSIS.Pipeline     Description: component "OLE DB Source" (1) failed validation and returned error code 0xC020801C.  End Error  Error: 2014-10-28 07:41:44.99     Code: 0xC004700C    
    Source: Data Flow Task SSIS.Pipeline     Description: One or more component failed validation.  End Error  Error: 2014-10-28 07:41:45.00     Code: 0xC0024107     Source: Data Flow Task     
    Description: There were errors during task validation.  End Error  DTExec: The package execution returned DTSER_FAILURE (1).  Started:  07:41:44  Finished: 07:41:45  Elapsed:  0.859 seconds.  The package execution failed. 
    The step failed."
    Can anyone help for this error.
    Many thanx in Advance

    Hi Babloo,
    According to the error message, the package may have failed are as follows:
    The user account that is used to run the package under SQL Server Agent in PRODUCTION server differs from the original package author.
    The user account does not have the required permissions to make connections or to access resources outside the SSIS package.
    The package may not run in the following scenarios:
    The current user cannot decrypt secrets from the package. This scenario can occur if the current account or the execution account differs from the original package author, and the package's ProtectionLevel property setting does not let the current user
    decrypt secrets in the package. In this scenario, we can change the SSIS Package ProtectionLevel property to EncryptSensitiveWithPassword, then modify the SQL Server Agent job step command line to include this password.
    File access fails because the current user does not have the required permissions to write to the file share that the connection manager accesses. In this scenario, we can create a SQL Server Agent proxy account. This proxy account must use a credential
    that lets SQL Server Agent run the job as the account that created the package or as an account that has the required permissions.
    References:
    SSIS package does not run when called from a SQL Server Agent job step
    Run an SSIS Package Under a Different Account
    Thanks,
    Katherine Xiong
    Katherine Xiong
    TechNet Community Support

  • SSIS package fails because of excel connection manager when deploying package from development to production

    Hello,
    When I move the package from development to production package fails due to excel connection manager.
    Error message---
    Message
    Executed as user: Answers\Administrator. ...lt: 0x80040154  Description: "Class not registered".  End Error  Error: 2014-06-27 05:10:26.50     Code: 0xC0202009     Source: CPRO_Prod_to_XLS_Worksheet_Basic_EX
    Connection manager "Excel Connection Manager"     Description: SSIS Error Code DTS_E_OLEDBERROR.  An OLE DB error has occurred. Error code: 0x80040154.  An OLE DB record is available.  Source: "Microsoft OLE
    DB Service Components"  Hresult: 0x80040154  Description: "Class not registered".  End Error  Error: 2014-06-27 05:10:26.50     Code: 0xC0202009     Source: CPRO_Prod_to_XLS_Worksheet_Basic_EX
    Connection manager "Excel Connection Manager"     Description: SSIS Error Code DTS_E_OLEDBERROR.  An OLE DB error has occurred. Error code: 0x80040154.  An OLE DB record is available.  Source: "Microsoft OLE
    DB Service Components"  Hresult: 0x80040154  Description: "Class not registered".  End Error  Error: 2014-06-27 05:10:26.50     Code: 0xC0202009     Source...  The package execution
    fa...  The step failed.
    Any help would be appreciated.

    Hi Vinay,
    As Visakh mentioned, the issue usually occurs because the package runs in 64-bit runtime, however, the Excel driver is 32-bit. According to your another thread, it seems that you use SSIS 2005, right? In SSIS 2005, there is no “use 32 bit runtime” option
    for the package executions of a SSIS package job step. In this condition, you have two choices:
    Install the 64-bit Microsoft ACE OLE DB 12.0 Provider on the production server. Here is the download link (AccessDatabaseEngine_x64.exe):
    http://www.microsoft.com/en-in/download/details.aspx?id=13255 
    Create a CmdExec type job step instead of SSIS Package job step, so that we can call 32-bit DTExec.exe to execute the package within command line. For more information, please see:
    http://support.microsoft.com/kb/934653/en-us 
    Regards,
    Mike Yin
    TechNet Community Support

  • Query related to request transfer from development to production server.

    Hello,
    I am transfering request from development to production server , the error occured is object REPT of particular program is inactive.
    What is this error ?
    Plz give answer as early as possible .
    Thanks in advance.
    Vikram.

    Did You try my solution'
    Hi..,
    go to the request in SE09...
    in the menu
    Request/Task->Complete Check-> Display Inactive objects..
    you will get the objects which are inactive and u can active them there itself.
    santhosh

  • Transport user exit frm development to production server.

    HI Gurus!
    please tell me how to transport user exit frm development to production server.
    Points Sure!
    Regard,
    Rahul .

    Hi Rahul,
    You have to create a project in CMOD transaction you can use the avialable one also.
    after that attach your userexit to that Project.
    The function modules which are used in that userexit must be activated.
    Then transport the request with the help of basis Person.
    Reward points if u find this suggestion helpful.
    Thanks and Regards,
    Yuvaraj

  • OWB propagation from development to production environment

    Our department is in need to implement overall security around our production data warehouse.
    One issue that seems to bother our management is having only one OWB Designer where developers would have to be responsible enough to use snapshots and export mappings to mdl files. Management would like to have development and production OWB Designer Repository where production designer would always be in sync with what is deployed in prd database. Also prd OWB Designer Repository would be like a source safe so we have to always get a mapping from prd designer move it dev designer and when done propagate changes back to prd designer and then deploy to prd database.
    Would this be a good approach?
    Any input on how to handle propagation from development to production environment, and if you are aware of "best practices" when it comes to OWB environment is appreciated.
    Best Regards,
    Vlasta

    Hi,
    Copy whole catalog and rpd from dev to prob.
    If you want to copy specific report go to OracleBIData\web\catalog\samplesales\root\shared\sample+sales(group folder name)
    You can copy reports under folders and dashboards in _portal in Sample sales group folder...both file and .atr file.But you may miss security applied on those dashboards.
    http://www.rittmanmead.com/2008/04/28/migration-obiee-projects-between-dev-and-prod-environments/
    Best practice is to copy whole catalog and rpd (or) Copy shared and system folders and their .atr files from OracleBIData\web\catalog\samplesales\root so that you will not miss security and you will not over ride users folders which may contain some data created by them.
    Thanks,
    Srikanth

Maybe you are looking for