When we try to do a GR against a process order (MIGO), and we use a quantity more than the process order, then the system is issuing an 'error' message.
Say process order is for 37000L, confirmation is done for 39000L (COR6): works
But when we try the MIGO or MB31, for the GR, then the system issues error as M7022: 'quantity exceeded by 2000L'.
Checked: 1) OMCQ and the message  M7/ 022 is set as 'w', warning.
               2) Also, the permissible batch size is 35000L  - 39700L
Please advice.
Thnx!

Hi
you need to have an overdelivery tolerance (i.e 10%) in the process order header - goods receipt tab.
The tolerance should be maintained in the work scheduling view of the material. Then it is copied into the process order automatically.
BR
Eivind

Similar Messages

  • Order recommendation must be extra than the sales order quantity

    Hi Expert,
                   My client is using the MRP wizard to generate the Purchase and Production order once a sales order comes from customer than MRP create the production order for parent item and purchase order for chilld items with required quantity but there is a possibility of rejection which comes to know at the end of production and to complete the quantity required some time.
                                                                                    Is there any possibility that MRP generate the recommendation 10%(for example) extra than the sales order quantity.So that it will full fill the rejected quantity at the end of production.
    Thanks

    Hi,
    MRP in B1 designed in a way that you don't need to enter many choices to select from.  To fulfill your goal, I think it is not that difficult because you could export recommended order and calculate the new total by a formula like New Qty = Recommend Qty * 1.1 in Excel and DTW the production orders using the calculated results.
    Thanks,
    Gordon

  • Gross price of Service entry Sheet more than the value ordered in PO

    Hi all!!
    I have a PO that were created and changed by the following way:
    The user created the PO of service with the quantity = 1 and the price = 50.000,00
    Than he made the service entry sheet of this PO and MIRO normally.
    As the fields on service tab wasn't blocked, the user changed the quantity to 105.000,00 and the price to 1.
    After that, he made 3 services entry sheet to complete 105.000,00 quantities.
    With this, the value delivered became bigger than the value ordered in the PO.
    if I make a service entry sheet with a quantity of 200.000,00 for example, the message SE363 will be shown to me with a message that the "quantity entered exceeds quantity in purchase order".
    I'd like to know if there's a way by customizing of control the price on Service entry sheet based on the value ordered in PO instead of quantity.
    Can anybody help me?
    Thanks in advance,
    Cris

    Hi Ajit and Rajesh
    Thanks for the response.
    The user made a PO with one line with quantity 1 and net price 50.000,00.
    In the services tab, he put a sevice with quantitiy 1 and gross price 50.000,00, and than made the service sheet entry, and MIRO.
    After this he changed in the services tab the quantity to 105.000,00 and the gross price to 1 (with the objective of making more than one service entry sheet by quantity).
    With this, the system let the user make many entries of service allowing the user to make entries os sheet more than the net price that is in the line of PO.
    I'd like to know if there's a way configure the system to make a compare between the gross price and the net price when i'm doing the service entry sheet, because now when I change a line of service tab, the system is not considering that other service entry sheet were made.
    So that, i'm having the value of ordered bigger than the value delivered.
    Nowadays, the block is made by quantity as I said, but i'd like to block by price too.
    Sorry about the bad explanation before, I hope that now i explained better.
    Thanks
    Cris

  • How to pack the More than one sales order delivery qty in one packing

    Hi Folks,
    How to pack the more than one sales order quantity combinely during packing?
    Thansk in advance and points wil be rewarded for the reply.
    Best Regards
    Srinivas

    Packing is done during Delivery.
    In Sales order also Packing function is available but as a Packing proposal.
    So actual packing is done in Delivery.
    When you process several sales orders together, the sales order items having same Ship-to-party, Shipping point, Route, Delivery due date & Incoterm are combined into one Delivery in the standard system.
    In the delivery overview screen,do the picking by subsequent function rom the menu bar, you will get a button "PACK", click on this system will take you to the packing screen.
    In the packing screen, give the packaging mterial number, select the materials to be packed, select the packaging material also and the click on the "PACK" button.

  • System is allowing to post the Adv Pmt amount more than the PO Value

    Hi Experts,
    I am FICO Consultant. I facing one problem regarding Advance Payment. We have a process to for making advance payment with reference to Purchase Order and Purchase Order Line Item. But system is allowing to post the advance payment amount more than the Purchase Order Value. I want to prevent this to happen. The system should not allow to make advance payment more than the Purchase Order value.
    Please help me on this issue.
    Thanks in Advance and Regards,
    Alkesh Mistry

    HI
    Please create the Advance payment request with PO number using sp gl indicator as F and then make the advance payment using the request.
    Regds
    Rajiv

  • How to block invoice posting more than the GR quantity

    Dear Experts,
    While trying to do MIRO with more than the PO/GR quantity system is accepting both increase in qty and value with out any tolerance limit.
    How to block, so that system should not allow to do MIRO more than the GR quantity.
    Regards,
    Alok

    Hi,
    System will by default block the payment, when it is not matching with the PO/GR value.
    then you have to go transcation code MRBR - Release Blocked Invoices. so that you can make the payment for these invoices.
    system will give you the message before saving, if you want an error message then go to oba5 tcode and change the message in to error, then if the Amount is not matching with the PO/GR value then the system will through error.
    Regards,
    Padma

  • Confirmed quantity more than the ordered quantity in sales order.

    Hi All,
    We have a situation wherein the confirmed quantity is more than the ordered quantity.
    a.) SO was created for qty1.Two schedule lines were proposed as stock was not available.
    b.) When stock came in and most probablly, when the rescheduling job calling tcode  V_V2 was run, both the schedule lines were confirmed.
    c.) As a result, further processing  is not done by system as confirmed quantity is more than ordered quantity.
    Also we noticed that double schedule line was confirmed for a another order even without the rescheduling job is run.
    Can you please suggest as to why this is scenario is occuring and how we can avoid the reoccurence? Thanks in advance!!
        Regards,
    Jeevan Penumatsa

    Hi  Jeevan Penumatsa
    Welcome to SDN forum
    Generally two schedule lines will take place if stock is not available in your plant or if open orders are there for that material also. So check the stock in MMBE
    .If there are any backorders then it might be getting added in the created sales order and then you might be getting in two schedule lines
    Regards
    Srinath

  • More than one process bind() to a multicast port.

    Hi,
    I found one strange behavior when there are more than one process bind() to the same multicast port. The problem is as the following:
    If there is a process bind to a port, say 2000 and joined a multicast group. This process did not do a SO_REUSEADDR,
    before bind() and join the multicast group. Later on, I have another program in the same host joining the same multicast group with the same port number (with SO_REUSEADDR), the second process will not be able to receive any data from the multicast group (with the same port number) eventhough the second process can join the multicast group successfully.
    However, if both process call setsockop with SO_REUSEADDR, both process can receive multicast data from the multicast group. The simplest fix is to have both set SO_REUSEADDR. But the problem is, the first application is an off-the-shelf software and we do not have source code to it.
    I wonder if this is a problem with Solaris. Any thoughts?
    Thanks,
    Shao

    Hi,
    I found the answer to this question. Basically, according to the source code (Solaris 8 Foundation Source), ip6.c, line #2510, multicast data is forwarded to all "listeners" only if the first "binder" has a SO_REUSEADDR set. What that mean is, if the first "binder" does not set SO_REUSEADDR before bind(), any subsequent bind() with SO_REUSEADDR is meaningless (in practical terms).
    My question is, is this behavior correct? I think it's much better to allow subsequent listeners (successfully bind and joined the multicast group) to be able to receive data. The reason is that if the first binder does not set SO_REUSEADDR before bind() the port and joined the multicast group should not deny any "late comers" to join in and participate in the multicast group. "Fixing the code" is not always practical especially if one of the application is a third-party application. Or reject bind() if the first "binder" does not allow SO_REUSEADDR.
    Any comment?
    Regards,
    Shao

  • HT1212 How do I perform step 5 in the Recovery Mode when an iPad minnie has been disabled for having more than the allowable entry attemps?

    How do I perform step 5 in the Recovery Mode when an iPad minnie has been disabled for having more than the allowable entry attemps ?

    FORCE IPAD INTO RECOVERY MODE
    1. Turn off iPad
    2. Turn on computer and launch iTunes (make sure you have the latest version of iTune)
    3. Plug USB cable into computer's USB port
    4. Hold Home button down and plug the other end of cable into docking port.
    DO NOT RELEASE BUTTON until you see picture of iTunes and plug
    5. Release Home button.
    ON COMPUTER
    6. iTunes has detected iPad in recovery mode. You must restore this iPad before it can be used with iTunes.
    7. Select "Restore iPad"...
    Note:
    1. Data will be lost if you do not have backup
    2. You must follow step 1 to step 4 VERY CLOSELY.
    3. Repeat the process if necessary.

  • When printing a list in Address Book, how can I select more than the default Attributes and keep them selected when I print again? I want to print ALL information for contacts so I have email address, notes, phone, company, title, etc all on one page.

    When printing a list in Address Book, how can I select more than the default Attributes and keep them selected when I print again? I want to print ALL information for contacts so I have email address, notes, phone, company, title, etc all on one page. I don't want to have to check off an additional 5 or 6 attributes each time I print out contact information. Is there a way to change the default setting for printing lists, so it is not just "phone," "photo," and "job title?"

    I have a user who wants to do this same thing. I did not find any way either to default the attributes to anything other than what you see the first time. Seems like such a trivial thing, hard to believe they do not allow it. I did find a program for this called iDress but I can't seem to download it from any links on the Internet. Not sure if it is free or not, but it was recommended by a link on the Mac support site.

  • I need more than the maximum allowed 30 profiles - how do I change this?

    I need more than the maximum allowed 30 profiles - how do I change this? Once I reach 30 profiles and I try to add one - it just deletes one automatically thus only allowing a maximum of 30. Please help.

    You are talking about 30 Firefox Profiles on the same Windows Logon User Account?
    I never saw that as a limit myself. I had 53 Profiles at one time, although I haven't done that since Firefox 3.0. It was causing an extended launch time and I started using "remote" Profiles that weren't controlled by the Profile Manager and weren't in the '''profiles.ini''' file; launched by command line. Like this in the Target line for the desktop shortcut: <br />
    ''' "C:\Program Files\Firefox_4.0_zip\firefox.exe" -Profile D:\Mozilla\Active-Profiles\4.0_10-15-10-N '''

  • Adding more than the recommenced RAM...

    I have an iMac 17in Flat Panel 800MHz with 256MB of Apple installed RAM (with an open slot for user installed RAM). The maximum recommended total RAM is 1GB. Can you put a 1GB pc133 144pin SODIMM in the user installable slot? Is this a bad idea to have the total RAM (1.25GB) more than the recommended total of 1GB? Thanks your your thoughts and suggestions.

    Is there another way to determine if the memory is really 512 but just not registering correctly with the imac, is it possible the mac doesn't display the correct memory or did I just get taken on ebay?
    Either that device is a 256 MB device or it is incompatible with your iMac and is being incorrectly identified as a 256 MB device.
    Either situation means that you need to return the RAM to the seller.

  • Hi from few days onwards i found one abnormality in my iphone4s .That is if i observe my phone settings screen from right side of the device top navigation appearing rightside height is more than the left side. In reverse manner from the left side.

    Hi from few days onwards i found one abnormality in my iphone4s .That is if i observe my phone settings screen from right side of the device top navigation bar appearing rightside height is more than the left side. In reverse manner from the left side. I dnt know whether it is default feature of iphone or not but i am really disappointed due to this. So please anyone help me in this issue and let me clear my doubt and make me happy. Thanks in advance.

    I believe what you are seeing is an optical illusion when viewing the screen from the side. Try to align one of the one of the options in Settings, like General, with the navigation bar you'll see it does the same thing.
    Hope that helps

  • Returns qty accepting more than the invoice qty

    Hi Experts
    When i am creating a sales order with reference to invoice the system is allowing to enter the quantity more than the invoiced quantity.
    suppose the invoice quantity is 100 when i create a sales returns system is accepting to do returns for 150 also whichshould not be and also it is allowing to do so many times with the same reference document
    i am getting just q warning message that for this invoice reference already returns exists if i bypass the warning message system is allowing to do next time also
    how to do
    any user exits to control which checks the VBRK number and VBRK billed quantity and it should less or equal to VBAK quantity
    regards

    Hi,
    Yes, unfortunately SAP does allow it.
    We are using FORM USEREXIT_MOVE_FIELD_TO_VBKD of MV45AFZZ to have our own validation for the same.
    I hope this helps,
    Regards
    Raju Chitale.

  • Hi, I need help with my iphone four bought in England but I live in Italy, I upgraded IOS six and now I can not read more than the Italian card, how can I contact a service center via email?

    Hi, I need help with my iphone four bought in England but I live in Italy, I upgraded IOS six and now I can not read more than the Italian card, how can I contact a service center via email?

    Only the carrier it is locked to can authorize unlocking it. Sounds like the phone was hacked to unlock it originally. Find out what carrier it is locked to, and look up their contact information using google or the search engine of your choice.

Maybe you are looking for