Unit Costing in Material components

Dear Experts,
I have come across a requirement where dummy materials are to be used for cost planning. These materials wonu2019t be processed any further. The planned cost for these materials is project specific ie. Material A in Project 001 costs 1 $ while same material in Project 002 costs 5$.
We are planning to use unit costing to cater this requirement. Unit costing works for Item category L.
The planned cost from Unit costing for material is considered when we create u201Creservation + purchaser requisitionu201D for WBS element for the material.
On Creating u201Creservationu201D for WBS element, the planned cost from Unit costing is ignored and the planned price is calculated as per the valuation strategy maintained in the Network costing variant (valaution variant). However it is intended that the cost for unit costing is to be considered for reservation for WBS.
We are using std. costing variant PS04 for material costing.
Is there something I am missing so that the planned cost for material from Unit costing is considered in case of reservation for WBS?
Regards
Sejo

Phoenixcfa & Ahmed,
Thanks for ur inputs.
I had already thought of the option you have suggested. In the currect process, the "Res / Purc. req." is maintained as "Immediate" at network header level. So the activity also inherits the same reservation relevance & it cannot be changed from "immediate" to "Never".
As suggested by Phoenixcfa it has some thing to do with split valuation. I could carry out the unit costing for a material with "res. for WBS" in IDES.
Hope, I will figure why it doesnot work our Dev system, soon.
Regards
Sejo

Similar Messages

  • Unit cost of material from the PO for a specific time

    Hi gurus,
    is there a report that can give us what the unit cost of a material was during a given time frame. The cost we are looking at is the PO price. For example we would want to be able to see OK what was the cost of Part A from 03/01/09 to 03/31/2009 or on 3/1/2009.
    Thanks
    Anusha

    hi,
    For material group / vendor you get the purchasing values..
    for that check: MC$4 : for vendor..
    MC$< : for material group
    But material price can;t be taken out directly, just because material master data is independent of vendor master data...and both together comes into picture when they are procured from the given vendor...
    Regards
    Priyanka.P

  • Unit costing for materials assigned to activity - for material cost plannin

    The requirement is that material cost to the company will vary depending upon the project/customer. Eg.: Material cost = basic material cost + a % for P&F + 2 % for Clearance + a % for excise + 2 % for insurance + a % for Customs
    It can be a % or a lump-sum value. It can be all the components listed or part of them. This will be project specific.
    Hence the following preference for material cost planning is required:
    1. Material cost based on quotation or Purchase order - If quote/PO is not available, then
    2.Material cost based on unit costing done for the material in the project - If this is not available, then
    3. material cost from material master depending on price indicator i.e. Std cost or Moving average price
    We are working with valuated project stock.
    SAP Help says"
    "Prices are calculated in one of the following ways:
    u2022     Using the strategy in the valuation variant
    u2022     Manually, using the invoicing plan
    u2022     Using unit costing"
    But how to get the cost as per the priority required when these three options are there is not clear.
    I have tried to work with valuation variant in the costing variant assigned to Network. No valuation strategy explicitly refers to unit costing of material.
    During various testings, at times, unit costing of material gets updated as planned cost; at times not. What triggers in also not clear.
    Pl. clarify
    Thanks and regards
    A.Saravanan

    Hi All
    I have psoted to service market place and got the reply; we have implemented also.
    there were 2 suggestiosn:
    1. Valuation price with user exit - (EXIT_SAPLCK21_002) - This user exit has to be implemented; we have implemented - it is working. But this is taking effect when overhead calculation is done - this we rae managing that way now
    2. Alternatively you can try to use BAdI VALUATION_CK.: This BADI is not editable by us now; SAP has not released for our editing!
    The problem is solved although
    There is one more clarification  required:
    As SAP Help documentation: -> Unit costing is used instead of strategy sequence, but not in between steps of strategy.
    How to get this done ? right now we are using the strategy - inbetween steps of strategy with user exit
    Thanks and regards
    A.Saravanan

  • Unit Cost of non stock material - Hubwoo Catalogue

    Hi Team,
    There is one requirement to transfer the the cost of matrial from SAP PM to ArcFM. Here the materials are assigned to the operations in the PM order. Here we want to transfer the service cost and material cost of the particular operation to the ArcFM ( ie an external design tool) to estmate the total cost involved for the particular operation.
    Here the unit cost of the stock material can be get from the material master. But for nonstock material, a hubwoo catalogue is maitained. How do we get the unit cost for the this material?
    There is an interfece we have to develop to transfer the service cost and material cost from the SAP to ArcFM. Hence we have to get the unit cost of the non stock material here.
    Thanks in advance.
    Regards,
    Shyjith

    Hi,
    Yes, you are right but in material master price is not updating, many times I have been assigned the same material as a non stock and at every time I have maintained the planned price on order level but it is still maintained as "0" value in material master,
    what is the standard process?
    what settings need to be made to get automatically planned price or last purchased price for a non stock material?

  • MTL MATERIAL TRANSACTIONS having zero unit cost

    Hi All,
    For some of the POs, we are getting zero unit cost in the Receiving Account, but rest of the POs are working fine and correct data is populated.
    This is not with any particular Org as well. Any idea what can be the reason so that the cost will be zero in there.
    I am new to costing/Finance module, so please let me know if I am not making sense or missing any information that will be important to get the solution.
    Thanks,

    Amit
    What is your costing method in that organization? Can you please check the price in the PO for that item which is giving you this issue?
    This can happen: If your price in the PO is Zero and you are using any costing method when you receive this is what happens:
    Cr Accrual Account @Po Price
    Dr Receiving Account @Po Price (could be Zero)
    When you deliver to Inventory depending on the costing method value will change:
    In std costing
    Cr Receiving @ po price (zero)
    Cr Purchase Price Variance @st cost
    Dr Inventory @ std cost
    In avg costing
    Cr Receiving cost @ Po Price
    Dr Inventory @ po price
    But the cost will be recalculated as
    (onhand qty*current cost+po qty*po_price)/(onhand_qty+po_qty). So if the cost was 100 and onhand was 1 and if the po qty is 1 and po price is Zero cost will become 50.
    Thanks
    Nagamohan

  • How to get unit cost for finished goods in prod order

    HI all,
    IN a production order of type PP04, there is cost analysis you can get from CO03.  This shows the cost for finished goods and BOM components.  Would anyone know how the cost for finished goods are calculated ?  The issue i have is that the unit cost of the finished goods is not correct.  It is higher than what it should be.  I looked at the moving avg price at material master but the cost used in calculation is different than in material master.   Can anyone shed light how finished goods are calculated and why it is picking up a higher unit cost ?  Where is the higher cost coming from  for finished goods material as shown in CO03 ?  The BOM materials are picking unit cost correctly.  Would this have anything to do with cost settlement ?
    thank you.
    joyce

    Hi,
    Finished goods price will depend on BOM componenet price,  activity price and overhead price. Check whether this prices are picking correctly or not.
    Regards,
    Sreekanth

  • Posting Actual Costs at Material Level

    Hi All
    For our standard costs we will have BOM Components, Activities from Routings and additive costs. We also have activated Material Ledger and will use it for Actual Costing, the objective being that each and every actual cost will be brought to the SKU level. For BOM components and activities that is no problem since it will be done through settlement.
    However for cost components that have additive costs how do we settle them to the material ledger? Do we need to do MR22 for difference between standard and actual? Is there a way to do this through a template allocation or some other allocation method?
    Thank you

    Hi
    Lets assume, you have Std cost of 100 USD involving Material + Labor and an additive cost of 10 USD entered manually from CK74N...
    During production order processing - You would issue material components and confirm Labor hrs... Say, this amounts to 120 USD as against the std cost of 100 USD...
    However, in prod orders, there will be nothing posted against the additive std cost of 10 USD... If you wish, you need to post it either through template allocation from some cost centers or use some assessment cycle or transfer manually from KB11N or use a costing sheet
    Regards
    Ajay M

  • Reducing the Freight cost on material value for undelivered material

    Hi Experts,
    Summary :  The material supplier vendor needs to be paid for full quantity of material. The freight transport is allowed an under tolearance of 0.5% on the material to be supplied. If the delivered material quantity breaches the 0.5% under tolerance then amount at 1.5 times the cost of material for the shortage is to be deducted from the transporter. A dummy GR will have to be prepared for the undelivered quantity for which we do not want the freight cost to be loaded. The details scenario is mentioned below :-
    We have to make a Purchase Order with material code say ABC for procured of some material. Suppose we make a Purchase Order for 100 nos. at a Unit Price of Say Rs. 10/- for Material Code ABC on say Vendor M/s XYZ. A freight condition is maintained in the Conditions Tab and suppose the Freight is Rs. 10 per unit of the material.
    While preparing the Goods Receipt through MIGO, in the Freight Tab we select say freight vendor say M/s PQR against the freight condition and post the goods receipt.
    While doing Invoice Processing in MIRO, when we enter the combination of Purchase Order and Planned Delivery Cost the system will populate the vendor codes of both the supplier of material and the transporter. On selecting the transporter the freight amount will populate against which the invoice of the tranporter can be processed.
    In the Vendor Master of M/s XYZ GR-Based Invoice Verification is activated.
    The vendor is allowed an under tolerance of 0.5% (i.e. the vendor should deliver at least 99.50 nos. of the Purchase Order). If the vendor delivers 99.50 or more then there will be no deduction in the freight charges.
    But suppose the vendor delivers only 99.4 nos. of the quantity. Then we will prepare the GRIR for 99.4 nos.only. But while processing the MIRO we need to deduct 1.5 times the value of the material from the freight amount for the shortshipped quantity, i.e.
    0.1     no (99.5 u2013 99.4) X Rs. 10/- * 1.5 = Rs. 1.5 are to be deducted from the final payment from the freight amount of the transporter.
    The material supplier will have to be paid in full 100 nos. of quantity and will raise an invoice for 100 nos. A dummy GRIR for the 0.6 nos. of undelivered material will have to be prepared for processing the invoice for the 100 nos. of the material supplier and a dummy issue for 0.6 nos. of undelivered material will be prepared to remove them from the system.
    Hence the freight cost for this 0.6 nos. of undelivered material will also go into the cost of the material and increase the MAP by that amount. Also the goods issue Cost will also have the effect of the freight cost.
    We do not want to load the freight cost for the undelivered material in the value of the material.
    Can any one please suggest a solution for the same.
    Thanks in advance.
    AJ.

    Hi
    A PO Will be raised for full quantity of material say 100 nos.
    The material supplier vendor needs to be paid for full quantity of material.
    A freight vendor is maintained at the time of GR for material against the freight condition maintained in the Po.
    The freight vendor facilitates the delivery of the material from the vendor to the purchaser for which he is given an under tolerance limit of 0.5%. Any delivery below this tolerance limit, freight amount to the effect of 1.5 times the per unit rate of material x short fall below 0.5% tolerance will be deducted from the freight amount.
    A dummy grir will have to be prepared for the short delivered quantity for processing the invoice for the full quantity of the purchase order, as the vendor is going to raise the invoice for full purchase order quantity. The client does not want to load the freight cost of the undelivered quantity on the material value as it will wrongly show the MAP of the material. This shortshipped material will be issued to remove it from the system and the stock will remain for the delivered quantity only. The vendor is subject to gr based invoice verification.
    Please suggest a solution.
    Thanks in advance.
    AJ
    The freight transport is allowed an under tolearance of 0.5% on the material to be supplied. If the delivered material quantity breaches the 0.5% under tolerance then amount at 1.5 times the cost of material for the shortage is to be deducted from the transporter. A dummy GR will have to be prepared for the undelivered quantity for which we do not want the freight cost to be loaded.

  • Detailed Report on Unit Cost Planning.

    Hi friends,
    I am doing Unit Costing in my Project in Version 1.
    Is there any standard report where I can get a display of all the Materials & services or (say) any Misc cost obtained thru Arithmatic Operation in the Unit Costing?
    That is to say the detailed report of whatever is done in the Unit Cost Planning.
    I am only getting the report of Planned Cost on Overall Basis.
    Secondly, in Unit Costing if I do any arithmatic Operation on the total value or on a particular row, then the value obtained from the arithmatic operation is not getting displayed in the cost Planning report.
    Thanks in advance.
    Regards,
    Abhra Bose.

    Hi Abhra,
    UC Method is only to plan the project cost estimates. There is no such standard report to get the detailed plan report in terms of material, resources and Miscellaneous (tru Arithmatic calculations) except cost element report ( that to interms of cost only). 
    As you said, you can only get the Overall Planned total in Hierarchical report (i.e like S_ALR_87013532 - Plan/Actual/Variance ) including arithmatic calculations. but If you check in Cost element report ( i.e like S_ALR_87013542 - Actual/Commitment/Total/Plan in CO Area Currency ) you can get all planned cost that is planned against specific cost element, since it is a cost elements based report only.) If you want the planned cost tru arithmatic calculations also, you need to specify a cost element against that line item either in BPO or at WBS level.
    Hope this will help you some extent.
    Appreciated for giving points.
    Regards,
    Hari Krishna.K

  • Weighted avg Unit Cost calculation for COGS

    Hi friends,
    Has any body done weighted avg unit cost calculation for inventory valuation and COGS calculation. In a way we need to mirror ECC material ledger functionality based on the APO data in side the planning tool.
    Any ideas on the above!!!
    Kind Regards,
    Krish

    Hi Jerry,
    Thanks for the tip. I actually needed to clean the spreadsheet up and put bogus values in to comply with company policy. Anyhow, here is a sample of the spreadsheet
    http://dl.dropbox.com/u/7499586/junk.png
    Just imagine about 100 products and several hundred raw materials, a dozen types of labor and about 30 types of packaging. It's a monster spreadsheet.
    The "units" under each product is the number of units per batch. You can see each product has two columns. One where you put in how much of a raw material, package type, and labor type go into each batch, the next calculates the cost for each item. Then it gets summed at the top for the total unit cost for that product.
    Let me know if you have any other questions about it. Thanks so much for your help!

  • Unit Cost Calculation

    Hi Folks,
    We have a unit cost spreadsheet that was built in openoffice. I'd like to convert it to numbers and clean it up to be "numbers style" (i.e. not one gigantic table with a bunch of different sections). I'm having some trouble organizing this though. Here is what we have right now:
    Row a contains things like the names of raw materials, types of packaging, & labor.
    The first couple of column contain calculations on these like cost per KG of raw materials, cost per unit for packaging, etc).
    The following columns contain each product. So each product has a column where you can enter in how much of each raw material, packaging, & labor are required to make it. The next column displays the cost for all of these things. At the bottom of this column is a summation of the total cost for this product. Then there is another spreadsheet that pulls these numbers to calculate margins and things of that nature.
    I can accomplish all of this in numbers, separating all of the functional sections into different tables, but the problem is this: Say I go to add a new raw material or a new type of packaging, when I add a row, the rows in all the other tables become "off" by a row. That is, if I add a new raw material, then the table that has the product formulas no longer reflects the right amounts of each raw material because it's been thrown off by that row. Am I approaching this wrong, or is there some way to make numbers keep track of row/column additions & deletions across tables that reference each other? Thanks.

    Hi Jerry,
    Thanks for the tip. I actually needed to clean the spreadsheet up and put bogus values in to comply with company policy. Anyhow, here is a sample of the spreadsheet
    http://dl.dropbox.com/u/7499586/junk.png
    Just imagine about 100 products and several hundred raw materials, a dozen types of labor and about 30 types of packaging. It's a monster spreadsheet.
    The "units" under each product is the number of units per batch. You can see each product has two columns. One where you put in how much of a raw material, package type, and labor type go into each batch, the next calculates the cost for each item. Then it gets summed at the top for the total unit cost for that product.
    Let me know if you have any other questions about it. Thanks so much for your help!

  • How to change price total for "Change Unit Cost Estimate Screen" for KKE1 Tcode ?

    There is a requirement of bringing the Material Price in KKE1 while entering the Item Catogory M ( M for Material) from the Gross Price in the condition type (P001) that is entered in the Purchase order.Currently systems brings the material value from MAP(Moving average Price) in the Material Master data.
    I have looked into the user exit 1) EXIT_SAPLKKEC_001 2) EXIT_SAPLKKEC_002  available in this T code KKE1.When I put break-point in these user-exit,it is not going in debugging mode while fetching the price value in Price total column  for "Change Unit Cost Estimate" screen in KKE1.
    How will change pricing condition for material in KKE1?
    I want to change price condition for material  as marked in red as shown in the screen-shot.
      Where will write the code such that I will bring Price Total based on material number as shown in the image?

    Hi Ram,
    I think you can do the same in thei manner.
    Go to program SAPMV45A.
    use menu GOTO -
    > Text Elements----
    >Text Symbols
    Here make change of Text-002 Sold-To Party as saleable .
    Regards,
    Pravin

  • Custom SAP report used to display an average standard cost per material.

    Hi All,
    I need to implement a report with the following functionality,
    This is a custom SAP report used to display an average standard cost per material.  Standard cost data is stored in SAP at the Material/Plant level.  This report will gather the individual Standard Costs at each applicable plant (restricted by selection screen input and additional logic specified in more detail in the u201CReport Fieldsu201D section) for applicable Materials (restricted by selection screen input; if not specified all materials should be returned) and calculate an average standard cost for each material.  The corresponding Currency and Base Unit of Measure will also be displayed.
    Additionally the relevant u201CCommodity Code/Import Codeu201D information should be displayed for each material returned.  This attribute is also stored at the Material/Plant level.  To determine the value of this field for each relevant material, the report logic must retrieve the values stored for each plant.  If all values are the same, the value can be output to the report.  If not all values are equal, a message u201CNot Consistentu201D should be output.  It should be noted that if all values are u201Cnull,u201D a null value should be returned in the report.
    Can any one provide me with sample code for the same??
    Thanks Debrup.

    Hello,
    Also refer this [ THREAD|Re: error in Fleet management customising] and [link|Error when recording measurements in IFCU]
    Regards
    Nav
    Edited by: Desire_Naveen on Nov 4, 2009 12:35 PM

  • Unit Costing / simulation Costing( Prduct Estimation )

    Hi;
    Can somebody tell me more about unit costing i.e. estimation ??
    Process is as follows;
    Creation of quotation -
      Create BOM according to customer specifications--attach it to material for which quotation created--take costing rungo to unit costing---- all data will be copied to unit cost estimate------change manually in estimation sheet as per estimator requirement- save it. -
    cost will  update pricing of quotation.
    But now my problem is BOM explosion at unit costing sheet is first level only but I need all materials of every level of BOM.
    How to get all materials in unit costing sheet Pl. let me know?????????
    Thanks in advance!!!
    Avinash
    9822136556

    Dear,
            Go to the link
            Re: Difference between ECP and UC
            It wil make you clear all thing about costing.
    Regards.

  • Production costs for material with price control V

    Dear all,
    Can anyone pls tell me, how will the costing occur for a material produced in-house and having price control 'V' ? I am not able to see the target costs.
    Also kindly tell me the settings to be done in CO, like target cost version, valuation variant, costing variant, etc.
    Thank you,
    Shrenik

    Rather than giving my own versions I have compiled here SAP inputs. Pl let me know if you require any clarifications:
    Costing variant has the following components:
    <b>Define Costing Types
    Define Valuation Variants
    Define Date Control
    Define Quantity Structure Control
    Define Transfer Strategy
    Define Reference Variants</b>
    <u>Costing type:</u>
    In the costing type, you define the purpose of a material cost estimate by specifying, for example, which field in the material master record the costing results can be transferred to:
    Update Cost Estimate
    Standard price Standard cost estimate (01)
    Tax-based price Inventory cost estimate
    Commercial price Inventory cost estimate
    Price other than std price Modified standard cost estimate or
    current cost estimate
    No update Any cost estimate
    Define Valuation Variants:
    Define Valuation Variants
    Here you create a valuation variant containing the parameters required for valuation of a cost estimate.
    You also specify which costing sheet should be used to calculate overhead.
    Valuation Strategies
    Material valuation
    Here you define the sequence in which the system searches for prices from the accounting view or costing view of the material master record to valuate materials. You can also access prices from purchasing info records and condition types.
    For material cost estimates, you also specify whether additive costs can be added to the selected price.
    With configurable/configured material components and with procurement alternatives, the sequence defined here is ignored if the strategy "price from purchasing info record" was selected, in which case that strategy is always executed first. For more information, refer to the SAP Library in the component Product Cost Planning under Raw Material Costing or Mixed Costing.
    Activity Types / Processes
    Here you define the sequence in which the system searches for prices in activity type planning or actual activity price calculation in Cost Center Accounting or Activity-Based Costing to valuate the utilized activity types and business processes.
    You also specify which plan/actual version is used.
    Subcontracting
    Here you define the sequence in which the system searches for prices in the purchasing info record. In purchasing, quota arrangements are used to create a mixed price for materials that are manufactured with external vendors with parts provided by the customer. You can specify whether the quota of the individual vendors that are entered in the source list for the material to be processed should be determined through the planned quota arrangement or the actual quota arrangement.
    External processing
    Here you define the sequence in which the system searches for prices in the purchasing info record or routing operation for valuation of the external activities.
    Strategy Sequence
    You define the individual valuation methods for the valuation variant as strategy sequences. For the valuation of the material components you define a strategy sequence that reads the fields of the material master record in a particular sequence such as:
    1. Planned price 1
    2. Standard price
    3. Moving price
    The first price that is not zero is used to valuate the material component.
    Target versions:
    Target cost versions  are used in the following ways:
    In variance calculation:
    To control which variance (total variance, production variances or planning variance) is calculated
    To valuate unplanned scrap( scrap variance)
    Unplanned scrap is valuated in the period-end closing activities when the variances are calculated. You can specify in a valuation variant for WIP and scrap which cost estimate you want to use to calculate the target costs for the valuation of unplanned scrap. You assign the valuation variant to target cost version 0 if you want to include it in the valuation of scrap.
    When you are using a cost object hierarchy with active distribution, you use the target cost version to control which cost estimate the system uses to calculate the target costs, which are used as the basis for determining equivalences for actual cost distribution.
    The actual costs collected at the level of the hierarchy are distributed across the orders in accordance with these equivalences. This distribution is proportional to the target costs for the cost element under which the actual costs are written. Actual costs for material costs are distributed in proportion to the target costs for the origin group, such as for the material, if you have entered an origin group in the costing view of the material master record and have set the indicator Material origin, for example.
    If no target costs were calculated under this cost element, enter a cost element group in the target cost version. The actual costs are distributed in proportion to the target costs for this cost element group. This cost element group should be complete. If costs were updated under a cost element that is not in this cost element group, no distribution is possible.
    You can calculate equivalences on the basis of SAP standard target cost versions 0, 1 and 3.
    The standard system supplies the following target cost versions:
    Target cost version 0 ( total variance)
    The amount of the total variance generates a posting in Financial Accounting during settlement.
    For this version, select actual costs as the control costs and standard cost estimate as the target costs.
    Target cost version 1 ( production variance)
    For this version you choose actual costs as the control costs and planned costs as the target costs.
    Target cost version 2( planning variance)
    With target cost version 2, the costs from the preliminary order cost estimate are interpreted as control costs.
    For this version, select planned costs as the control costs and current cost estimate as the target costs. You cannot calculate planning variances for the product cost collector.
    Target cost version 3 (production variance of the period)
    You compare the planned costs of the period calculated on the basis of an alternative material cost estimate (such as a modified standard cost estimate) with the actual costs of the period on the basis of the yield delivered to stock in the period.
    The base quantity for variance calculation is the yield.
    For this version, you choose the actual costs as the control costs and the alternative material cost estimate as the target costs. To determine the alternative material cost estimate, enter a costing variant and choose a costing version.
    The target cost version specifies which data is to be compared. The target cost version also specifies which variance variant is used and therefore which variance catagories are calculated. You can define a different target cost version for each controlling area

Maybe you are looking for

  • Why does Google voice no longer works in Firefox after adding addtional credit but does in Safari?

    I am using Mac OS 10.10 with FireFox 30.0.2 as my browser. I was making calls OK on Goggle Voice through my G-Mail account. when I ran out of credit. I loaded additional credit and tried to resume calling. However, I kept get getting the following er

  • Silly renaming files question

    Hi, I know this sounds utterly idiotic, but is there a way to rename a photo other than in List View in the Browser View? All I want to do is change the name of a single photo that I imported awhile ago. Thanks. Edit: Especially in full screen. Is it

  • Not all of my iTunes scripts are showing up in iTunes

    My itunes scripts are in Users/Apple/Library/iTunes/Scripts. Some of them show up and work in iTunes and some do not. I was wondering if anyone might know why? I am using iTunes 11. Thanks for any help.

  • When i plug in my 5c overnight to charge, it did not fully charge

    my iPhone 5c has ios 8.1.2  the memory available is 7.8gb storage capacity is12.8gb.  when I plug in the charger to charge overnight, it does not fully charge.  my phone was at 40% power last night and I plugged in the charger and this morning it was

  • Exp_10g

    hi can i use parameter query in command export (exp) to do query for more than one table ..? where my database is oracle database 10g if possible can you provide me any simple command for that? thanks for all