Update the expiry date of dunning lock in program

Hi,
I have requirement where I want to update dunning lock expiry date to today's date in the program. Does anybody have idea about FM or BAPI for that.
I have actually used FKK_S_LOCK_DELETE but here i dont want to delete it directly. I have checked other FMs in function group FKLOCK but couldn't find any suitable.
Thanks in advance,
Murtuza

Hi Murtuza,
You can use function module BAPI_ISUACCOUNT_CHANGE.
Pass dunning lock details in parameter TCTRACLOCKDETAIL. This function module only create and delete locks.
So, you need to pass existing lock details (from table DFKKLOCKS) with PROCESSING_MODE = 04 (delete) and append another value with changed expiry date with PROCESSING_MODE = 01 (Create).
This will also help in maintain lock history too.
Hope this helps.
Regards,
Avinash

Similar Messages

  • How to automatically update the Expiry Date's number of days

    My web app input form is an event submission form. Users enter the event title, event date and other details, etc. I've figured out how to get the "expiry days" in the form and it be hidden but i can't figure out how to calculate this:
    (today's date) - (event date) + 1 day = number of days to expire and then set the expiry days to that value upon submission.
    I have tried writing the js but am getting no where, has anyone out there already accomplished this? I've researched and researched and find a million things on calculating the number of days but can't get one of them to work for my situation here... any help would be greatly appreciated!!

    Hi Murtuza,
    You can use function module BAPI_ISUACCOUNT_CHANGE.
    Pass dunning lock details in parameter TCTRACLOCKDETAIL. This function module only create and delete locks.
    So, you need to pass existing lock details (from table DFKKLOCKS) with PROCESSING_MODE = 04 (delete) and append another value with changed expiry date with PROCESSING_MODE = 01 (Create).
    This will also help in maintain lock history too.
    Hope this helps.
    Regards,
    Avinash

  • How to prevent multiple users from updating the same data in coherence

    Hi,
    I have a Java Web Application and for data cache am using coherence 3.5. The same data maybe shared by multiple users which maybe in hundreds. Now how do I prevent multiple users from updating the same data in coherence i.e. is there something in coherence that will only allow one user a time to update. If one user is in a process of updating a data in coherence and some other user also tries to update then the second user should get an error.
    Thanks

    I have a question on the same line. How can I restrict someone from updating a cache value when I a process is already working on it. I tried locking the cache key but it does not stop other process to update it , it only does not allow other process to get lock on it.

  • When and how to update the "saved data" in report ?

    Hi,
    The BO version is "BusinessObjects Enterprise 12.0"
    The case is that, some reports are uploaded withe saved data. while viewing the reports, the reports return the old data.
    How to view the update data while click the "View" in CMC/InfoView ?
    I have tried to schedule it , then can see the update data in "View the latest instance".
    Is there any approach to refresh/update the saved data in the report ?
    Thanks and regards,
    Forest
    Edited by: Forest lin on Dec 5, 2008 12:12 PM

    Hello Forest lin,
    I recommend to post this query to the [BusinessObjects Enterprise Administration|BI Platform; forum.
    This forum is dedicated to topics related to administration and configuration of BusinessObjects Enterprise, BusinessObjects Edge, and Crystal Reports Server.
    It is monitored by qualified technicians and you will get a faster response there.
    Also, all BOE Administration queries remain in one place and thus can be easily searched in one place.
    Best regards,
    Falk

  • Unable to create or update the Custom Data Provider WIS 10853

    Hi,
    I have created the universe in designer then I created QAAWS. In the web intelligence tool, clicked for new document and then chosen web services under other data sources. After giving webservices detailed, I encountered the following error.
    Error from Personal Datasource : Unable to create or update the Custom Data Provider: invalid information retrieved while trying to get the structure. (CDS 105109). (WIS 10853)
    Can anyone help abt this problem? I wud very thankful for them.

    Hi,
    Can you post the wsdl URL. It would be of great help if we could have a look at the wsdl schema. Not all schemas are supported at the moment and hence the error. You can have a look at the limitations section in the documentation guide.
    Regards
    Rahul

  • Please enter the expiry date in dd.mm.yyyy format

    Dear All,
    I have configured SAP AA in Dev. Now I want to craete asset master. But it is showing the following error, when I am going to save:
    Please enter the expiry date in dd.mm.yyyy format
    Can anyone tell me the solution?
    Thanks
    Azimul

    Thanks Jigar for your reply.
    My company is using SAP last 2.5 years. During SAP Implementation, Consultants configured SAP AA, but during testing it showed error in Asset Accounting. That is why, we donu2019t use SAP AA.
    Now we want to use Asset Accounting in SAP. I have configured SAP AA in Development. Then I try to Create Asset Master, But it is showing Error:
    Please enter the expiry date in dd.mm.yyyy format
    I cannot get Error message no also. If I double click on error, it is not opening.
    I donu2019t know about Validations. Can u please guide me?
    Thanks,
    Azimul
    Edited by: Azimul on Oct 1, 2011 7:58 AM

  • How we can update the  System Date,in java

    Hi guys,
    can U pls help me...
    How we can update the System Date,in java
    I need to get the System Date and time continuosly thruogh threads concept.kindly help me
    Thanking u in Advance

    System.currentTimeMillis() will give you the current
    system date and time as a long value.
    ~I think the OP wants to change the system time not just get the system time.

  • Error 4 when updating the text data

    When i am trying to load the data  using IP i am facing the issue Error 4 when updating the text data.Please suggest me
    Edited by: srikanth reddy612 on Dec 15, 2011 12:45 PM

    hi srikanth,
    you might have selected given lowercase data
    and please check in the Infoobject the lowercase Checkbox is unchecked then it will allow you to update from IP.
    also check in the Datasource fields tab whether particular field is unchecked with lowercase.
    if checked all records you are pushing will have to be in uppercase.
    thanks
    Sankaresh S

  • CJR2-The plan data transfer is locked

    Hi,
    I am planning costs by CJR2 on a WBS element for a certain period and version by cost element.When I execute CJR2,it allows me to enter the values against periods but when I try to save ,system gives error message-The plan data transfer is locked for fiscal year 2009 and version F06 in controlling area 1000.
    I have checked in OKP1 and also in CO versions,this version is not locked for any transactions and Fiscal year 2009.Has anyone come accross similar situation and how was it resolved.
    Its matter of urgency,any help will be highly appreciated.
    Regards,
    MTH

    Hi Ravi,
    Thanks for your answer.I have checked the statuses and there are no status hampering the Plan primary cost or Periodic reposting Plan data.I guess its more related to the version used.Any other thoughts?Anyone.....
    Regards,
    MTH

  • I have recieved back to school card with my mbp what is the expiry date

    what is the expiry date of the back to school card..??

    If it has no expiration date on it, or doesn't mention anything about how long it is valid for, then it never expires.

  • Could I update the schedule date by the add-in software OpenPS?

    I create the R/3 PS WBS using the add-in software OpenPS from MS Project at the beginning. But according to  our company working business , I can't update the WBS schedule date by  updating the activity schedule date under the WBS, i can only update the WBS schedule. (so I have done some set-up and set the duration of every activity is zero).  I hope I can update the schedule date by the add-in software OpenPS from MS Project during the R/3 system is online running(NOT the beginning). 
    We know the adjustment of schedule in MS Project is very easy and convinent.  So if I adjust the schedule  in MS Project, and I update the schedule in R/3 PS by the add-in software, then everything will be good.
    But  maybe this operation will have a bad effect on the running R/3 system.
    Please give me some advice and practice experience.

    Hi Sanjay,
    You really MUST try things BEFORE saying that they are wrong.
    The CDHDR table DOES store the creation date AND time because the system treats the creation as a Change.
    If you simply enter ME51N as the transaction code in SE16N for table CDHDR you will see that it is YOU that is wrong.
    Please do try to verify your comments before challenging Seema in this way, who has provided a good and workable solution.
    Steve B

  • After the last iPhone 5 update, the calendar date do not match the respective weekday. i.e. November 1st 2013 is marked as Saturday on the iphone.

    After the last iPhone 5 update, the calendar date do not match the respective weekday. i.e. November 1st 2013 is marked as Saturday on the iphone.

    I have this exact same issue!
    I was on 2.0.1 running fine until late last week, noticed emails would not show up unless I had opened them in outlook. I thought I ran into a bug so I upgraded to 2.0.2. Now I can sync my email if outlook had them opened previously, but no calendar or contacts at all. I don't think my exchange admins will move me to another server, any other ideas?
    I love my iphone but if these features don't work I can't use it. I would appreciate any ideas.

  • Using BAPI_SALESORDER_CHANGE to update the delivery date

    Hi All-
    I am using BAPI_SALESORDER_CHANGE, to update the delivery date on the schedule lines...If I have 2 lines of schedule, needs to be updated the second one ETENR '0002'...
    Bapi returns message that successfully processed, when I go back and look at Sales order, I don't se any changes on schedule line..
    I am pssing into BAPI, sales doc and schedule line with the delivery date and the flag 'U'..and also I am using BAPI commit...
    But, let me know if I am missing something and also let me know is it possible to change schedule delivery date or not?
    Thanks,
    Sony
    Please try to use a meaningful subject.
    Edited by: Rob Burbank on Feb 25, 2009 2:08 PM

    give a meaningful title to ur thread, so that, people get u back quickly. Just tip that, try to do ur requirement online, then Observe How the system is behaving....thanq

  • HT2736 Where is the expiry date, code and card number on my iTunes gift card if i want to create and Apple ID??? Please really need help.....

    I am creating an Apple ID and i can't seem to get the payment method right!
    I need to know where the expiry date, code and card number is on my $30 iTunes Gift Card because i have no idea where it is.....
    Anyways please help me!?!
    Thanks.....

    Welcome to Apple Support Communities
    iTunes cards don't expire, so don't worry about that. To know where the code you have to type is, read > http://support.apple.com/kb/ht1574

  • How to regularly update the Master data/Text/ Hierarchy for BW DEV?- Urgent

    Hi Experts,
    Can anyone help me to understand how to update the Master data/Text/ Hierarchy regularly for BW DEV.
    Since all the new query developments are taking place in DEV, users are not finding the latest Masterdata/ Texts /Hierarchy in the DEV system.
    I have searched in SDN and got a document "HOW TO DOWNLOAD A HIERARCHY TO A FLAT FILE". However, is there any other way to upload the master data automatically on periodical basis.
    Please help urgently.
    Advance Thanks,
    BW USA

    If you want to extract master data from PRD in order to load in DEV, i suggest to do this (its a tricky thing):
    For example, you want to download 0EMPLOYEE
    1-In PRD, transaction RSD1
    2-Enter 0EMPLOYEE
    3-Copy the Master table for 0EMPLOYEE (/BI0/MEMPLOYEE)
    4-transaction SE16
    5-Enter the table name /BI0/MEMPLOYEE
    6-in the selection screen, go to "Options" Menu and select "User parameters", and now select "Standard List SE16"
    7-Execute
    8-Now its show's up the 0employee data, go to "System" menu - List - Save - Local File
    9-After you have the flat file, only rest create Infopackae in DEV Env. and load it from the flat file.
    Asigns points if useful.
    Regards

Maybe you are looking for

  • Avoid online device trade in, GO TO THE STORE.

    This has been posted about numerous times already but I feel the need to add more information to what seems to be happening with these device trade in issues.  specifically, the claim that the power supply has an error and the phone wont power on. I

  • Customer number in GL line items

    Hello All, I have loaded the GL line items data and created a report on customers. i am getting the report like this. Doc no--Item NoCustomer NoAccount typequantity-- balance 400001--13001D #-- 4000 400001--2#S80-- (-3000) 400001--3#S20-- (-1000) 400

  • Help on adding a node to a tree

    Hi All, I need help on hierarchical trees. I am running forms 6i on oracle 9i. I am trying to create an organizational chart using the hierarchical tree. I create an initial tree based on a record group, with two . I want to add a node to the last no

  • RFC-XI-SOAP scenario

    Hi friends, I m doing a RFC-XI-SOAP scenario. I m getting an error when tried to run this. soap fault: Server was unable to read request. ---> There is an error in XML document (1, 297). ---> Input string was not in a correct format. Is this because

  • Can't connect to WebDAV server via Go:Connect to Server

    Setting up remote access on a ReadyNAS duo (posted over in NetGear's forums, too, but this seems more like an Apple issue), using WebDAV. I can connect via a browser, but can't connect from the finder. I'm using an address in the format https://0.0.0