Hi SDN Network,
We use the made to order setup so run MRP with the Sales Order as the basis of the demand. After that, we avail the services of a subcontractor to assemble the finished goods although we supply the subassembly and raw matls.
The PR generated during the MRP run has an account assignment of either M or E depending on the Item Cat in the sales order. From that PR, we create a subcon PO (item cat L). Problem is the PO generated is not showing up on the ME2O transaction. Does this mean that POs whose GR goes directly to Sales Order stock are not allowed in the system? I am able to post
We would still want to retain the 'reservation' of the materials using the Sales Order stock. But does it follow that you cannot use Sales Order Stock with subcontracting?
Did I miss out anything in the config? Is there another way to do this?
Thanks in advance!

Hi
Subcontracting issue to subcontractor (special stock O) and sales order stock (special stock E) both have special stock indicators and hence not possible.
The process can be done as explained in the link below:
http://help.sap.com/saphelp_erp2005vp/helpdata/en/4d/2b90b043ad11d189410000e829fbbd/frameset.htm
Best regards
Ramki

Similar Messages

  • Subcontracting for Sales Order Stock and collective Transfer Posting

    Dear Expert,
    We have a scenario in subcontracting wherein the sales order the customer also wants to see the components and as such along with the Header item of subcontracting ,we also mention the components as another line item in the sane Sales Order.
    Now from the sale sorder two Po's are created onr for the subcontractor and one for the compnens to be procured.
    Since the components are procured on sales order stock there is noway we can issue it to the Vendor stock through Movt .Type 541.
    As per SAP AG WE CAN:
    "ubcontracting is also possible in conjunction with sales order stocks and project stocks. The subcontracting orders are account-assigned to a sales order or a WBS element. Thus, the components are not transferred (using a transfer posting) to the u201Cstock of material provided to vendoru201D but are directly withdrawn from the sales order stock or the project stock at the time of the goods receipt. The material manufactured is also posted to the sales order stock or to the project stock. The cost of subcontracting is then debited to the sales order or WBS element.Since the components are not transferred to the u201Cstock of material provided to vendoru201D, we recommend that you use a transfer posting to transfer the provided components to a new storage location (for example, 9999). This enables you to obtain an overview of those stocks that are physically located at the subcontractor.This information is particularly important when you carry out a physical inventory of the sales order stocks and project stocks."
    But my query is that how many such storage locations will be created for the subcontracting vendors.
    Secondly for the stock transfer from sales to storage location , we have lots of sales order, is dera way through which we can do bulk transfer rathar than clicking at new item everytime and then doing the transfer posting.
    your expert advice shallbe helpful in resolving a longtime pending issue , waiting for the response.
    Regards
    Jabeen

    This is a known issue, the system doesnt allow stock to have two special stock statuses at the same time.
    Your concern of having to make multiple storage locations is valid (since this is a configuration).
    I suggest you do the following
    - Configure a warehouse and a single storage type (say 001). Allow mixing of materials in a single bin
    - Assign this warehouse to a new storage location.
    - Create a bin for every sales order number in the warehouse.
    - When goods are moved to subcontractor, perform a transfer posting to the storage location, and perform a putaway to the respective bin. The putaway strategy can be tweaked using a user exit to go to the relevant bin. This way you do not have to enter the WM transaction for putaway.
    - To consume the stocks, you can use 231E movement (MB1A). On the WM side, the picking strategy can be enhanced so that the picking TO is generated with the correct source bin. Make sure the GL account and CO objects are as per FICO requirements.
    This way you can track the stocks binwise (bin level reports are available in WM), perform physical inventory and also consume the stocks from the relevant bin automatically.
    We had faced the same situation, and we ended up not having sales order stock at all.
    Hope this helps.
    Regards,
    Aroop

  • Goods valuation with sale order stock

    use S price valuation material, goods have production order ,with sale order stock, when the produciton order have GR, the goods stock value do not use standard price for material accounting view,why ? what problem? use standard price valuation sale order stock is standard program for the SAP system ? this is very touchy problem.

    make sure that for the final product manufactured in accounting view u have maintinaed the price contrlo indicator as S
    and if still error comes then let me know system would be showing the  actual cost and planeed cost
    if there is variance then system is goingto post that to the cost difference account

  • Transfer Posting problem with "sales order stock type" status

    Hello, i have this problem, i spend 2 days looking in the forum, but
    nothing, the question is:
    The SD users sell an item, and the item get the status of "sales order
    stock type" in the MMBE, but at the same time, the MM user made a
    trasfer posting in two steps, he take out material with transaction
    MIGO, mvt 351, to another plant, but the materail was already
    compromised with SD; now he cant sell the items, because he dont
    realize that the material was in sales order stock type, and he already
    transfer it to another plant. how can i block this? if a material in
    MMBE is with "sales order stock type" status, he CANT transfer it with
    351 mvt type, what config i have to make?  thanks a lot!!!!
    now the quantity of the unrestict use
    stock is lower than the sales order, we dont want to have this issue,
    thanks again
    Edited by: Alex Arti on Aug 6, 2008 7:14 PM
    Edited by: Alex Arti on Aug 6, 2008 7:16 PM

    Hi!
    Have you recently upgraded to EHP4? In this case, please, check the note 1441195. This note should solve the issue that you are reporting.
    I hope this helps,
    Esther.

  • Issue with sales order stock that is referencing a non-existing sales order

    We have an issue with sale order stock.
    Due to user error we have ended up with a negative quant of sales order stock in a bin. Further the error was due to mis-keying of sales order number. Hence this negative quant is referencing a sales order that does not exist.
    We need to get rid of this quant.
    I thought of cycling this quant off as a solution. And hence replicated the scenario in the test system. I was able to create a TO to cycle it off but cannot clear the differences from 999 . The error I get while trying to do this is "SD document not in database or has been archived" . This error is true since the sales order actually does not exist. So cycling it off did not work.
    Can anyone suggest how we can get rid of this negative quant of sales order stock ?
    Thanks

    Hi,
    You said that your user mistyped the SO number and it resulted in a -quant. In which transaction was it possible? If I give a non existing no. SAP doesn't allow me to book.
    If I were you I would check both in WM & IM what the user had done...step-by-step...
    Negative quant comes to existance in interim storage type if we book e.g. a GI. It should have started in IM...how was your user be able to do that??? If it was possible cannot you reverse the IM booking?
    (...if all else fails...cannot you create a SO document with external number assignment with the same number?...)
    BR
    Csaba
    Edited by: Csaba Szommer on Jun 24, 2008 8:31 PM

  • PReqs with sales order stock couldn't be adpoted by PO with acc. assignmnt

    I use MD50 to generate PReqs for MTO, these PReqs couldn't be adpoted by ME21N with message 06251:
    Requisition &, item & , assigned to other order account
    but if I use ME21, it's ok. I find the following notes. But I don't understand in my case I don't want change PReqs account assignment, but adpotion is also failed to get account assignment from PReqs.
    Refer to  Note 632573 - ME2xN: 06259 if different account assignment in PReq
    Summary
    Symptom
    In Transactions ME21 and ME22, you can change the account assignments for purchase order items with reference to purchase requisitions with sales order special stock or project special stock. This option no longer exists in the EnjoySAP purchase order transactions, the system generates error message 06251:
               Requisition &, item & , assigned to other order account
    Other terms
    ME21N, ME22N, ME23N, 06251, sobkz,
    Reason and Prerequisites
    The purchase requisitions were not generated from sales and distribution but created for sales order special stock or project special stock.
    Solution
    In the EnjoySAP purchase order transaction, you cannot enter an account assignment different from the purchase requisition for sales order special stock or project special stock if you reference to a purchase requisition. You must first change the purchase requisition correspondingly and then call the purchase order again.
    Under the above mentioned conditions, also in Transactions ME21 and ME22, the account assignment of the purchase order must correspond to the purchase requisition if the reference to the purchase requisition is created in a schedule line. Unlike in Transactions ME2xN, you can change the account assignment in the purchase order at a later stage.
    It is not planned to change the system response

    I use MD50 to generate PReqs for MTO, these PReqs couldn't be adpoted by ME21N with message 06251:
    Requisition &, item & , assigned to other order account
    but if I use ME21, it's ok. I find the following notes. But I don't understand in my case I don't want change PReqs account assignment, but adpotion is also failed to get account assignment from PReqs.
    Refer to  Note 632573 - ME2xN: 06259 if different account assignment in PReq
    Summary
    Symptom
    In Transactions ME21 and ME22, you can change the account assignments for purchase order items with reference to purchase requisitions with sales order special stock or project special stock. This option no longer exists in the EnjoySAP purchase order transactions, the system generates error message 06251:
               Requisition &, item & , assigned to other order account
    Other terms
    ME21N, ME22N, ME23N, 06251, sobkz,
    Reason and Prerequisites
    The purchase requisitions were not generated from sales and distribution but created for sales order special stock or project special stock.
    Solution
    In the EnjoySAP purchase order transaction, you cannot enter an account assignment different from the purchase requisition for sales order special stock or project special stock if you reference to a purchase requisition. You must first change the purchase requisition correspondingly and then call the purchase order again.
    Under the above mentioned conditions, also in Transactions ME21 and ME22, the account assignment of the purchase order must correspond to the purchase requisition if the reference to the purchase requisition is created in a schedule line. Unlike in Transactions ME2xN, you can change the account assignment in the purchase order at a later stage.
    It is not planned to change the system response

  • Billing with Sales Order Stock

    I created an invoice, with a delivery that has sa sales order stock "E" item... I got an error message saying the GL account should have an assigned cost center.. why is this? we don't want to put cost center to the Sales GL account..

    Hi,
    You have to define your account in T-code OKB9 with the relevant company code. You should make an entry for Company Code, GL account and then tick the box Prf Seg (Profitability Segment).
    By doing this, you can make sure that this entry goes into CO-PA. or if you do not want it to go to CO-PA, then assign a cost centre directly or based on profit centre.
    Regards,
    MT

  • Account Determination with Sales Order Stock

    Hi, Guys
    Does anybody know how (and WHY) SAP makes (or doesn't make) account determination of material movements from or to Sales Order Stock???
    I have found that, for example, an Accounting Document is generated when transferring to or from Customer Stock (411E and 413 mvt) and that no Accounting Document is generated when processing GI from Customer Stock (601E mvt) or GR against Production Order (101E to Customer Stock)....
    There are also NO Accounting Documents when inventory differences occur (701E or 702E)...
    It's pretty strange I think....Sure there is some logic  put into the process of managing Sales Order Stock but I don't get it...
    Of course, reward points are guaranteed for helpful answers!

    Automatic Accounet determination is done in MM. In this for some of the movement types there is no need to enter the G/L account every time.
    All are customized in  Automatic Account determination.(AAA)
    Go to SE16 enter the Table name T156 and press F4 you can see the movement types where G/L account are customized in  (AAA)
    you can check the movement types
    G.Ganesh Kumar

  • Problem with sales order stock.

    Hi all,
    I have stuck in one problem, please help.
    We created one sales order A and after production stock is moved to that sales order.But then we created sales order B and moved stock of A to sales order B(By 413 E?). system created materail document for stock movement but stock was not transfered. we can see that stock is against sales order A only. But material document shows that stock is moved to B. then we deleted Sales order B.
    Now the stck is against sales order A. when we try to do shipment systen gives error ' VALUATED STOCK BECOMES NEGATIVE.' Message No. M7 314. We have to.ship this material.
    When I see the value of this stock it is showing zero.
    Please advice what to do.
    Thanks.
    Edited by: s j on May 10, 2010 3:25 PM

    Hi!
    Have you recently upgraded to EHP4? In this case, please, check the note 1441195. This note should solve the issue that you are reporting.
    I hope this helps,
    Esther.

  • Working With Sales Order Stock - Sales (SD-SLS) - SAP Library

    To add a comment, please log in or register on the top of this page and choose Reply. Please write your comment in English.
    You can also go back to the SAP help page.

    Hi,
    You said that your user mistyped the SO number and it resulted in a -quant. In which transaction was it possible? If I give a non existing no. SAP doesn't allow me to book.
    If I were you I would check both in WM & IM what the user had done...step-by-step...
    Negative quant comes to existance in interim storage type if we book e.g. a GI. It should have started in IM...how was your user be able to do that??? If it was possible cannot you reverse the IM booking?
    (...if all else fails...cannot you create a SO document with external number assignment with the same number?...)
    BR
    Csaba
    Edited by: Csaba Szommer on Jun 24, 2008 8:31 PM

  • Material Ledger Functionality with Non Valuated Sales Order Stock

    We are in the process of setting up Make To Order (MTO) with Non Valuated Sales Order Stock. We currently use the Material Ledger in our other businesses that use Process Orders.
    Does the Material Ledger functionality support MTO with Non Valuated Sales Order Stock? I have been testing this and have not yet figured out how to get ML postings. We are using production orders that settle to sales orders. We do not bring this into inventory, the costs reside on the sales order.
    If this functionality does exist, I would assume I need to configure the Material Update Structure but I cannot find any documentation on this.
    Any help would be appreciated.
    Regards,
    Greg

    Hi Greg,
    no, material ledger will not be able to calculate and allocate actual costs for the sales order in the scenario you describe. It would of course, if you used the valuated sales order stock.
    Generally SAP sees in the valuated sales order stocks (avaliable since 3,1 or something) a great improvement and no real reason to use still the non-valuated scenario.
    best regards,
                          Udo

  • External Procurement with a Valuated Sales Order Stock

    Hi Experts,
    I read the following in SAP Help,
    For external procurement with a Valuated Sales Order Stock, system generates a purchase requisition from the sales order.
    If you are using a valuated sales order stock, the externally procured material is assigned to inventory at the time of the goods receipt. If the sales order item is flagged as carrying costs and revenues, then when the goods issue for delivery to the customer takes place, the sales order item is debited with the costs of the externally procured material.
    My question is - it says costs of external procurement is debited to sales order item when " goods issue for delivery to the customer takes place"
           - but in my case, when I made the GR for purchase order (created automatically by sales order), system directly posted the procurement cost as actual costs to the sales order item. There is no delivery for sales order done still.
    So actually, when should the external procurement cost be debited to sales order item -- when GR for purchase order is done (or) when  goods issue for delivery to the customer takes place?
    Thanks,
    GAN

    Hi Rafi,
    Thanks for your reply. I understand the problem now.
    Material which comes from prod order is posted statistically (value type 11) to sales order when GR for prod order is done.
    Here, the issue is about a GR for purchase order (assigned to sales order). This material purchased is not used in any production process. Its a material which is supplied to customer along with main material produced in house.
    In purchase order, I have given the consumption account (which is cost element 1). Entry was Consumption Dr and GR/IR Cr. So, this posted as actual cost to sales order.
    I should have given inventory account in purchase order (with cost element 90).
    Its a mistake of using consumption account in purchase order.
    Thanks.
    GAN.

  • Subcontracting with slaes order

    hi i want to know
    how can we do the subcontracting with sales order
    i got a process using 311 e movemnt when i search on SDN
    plz let me know if this process is correct how can i  have subcon challan
    Subcontracting scenario(Sale Order wise)
    Subcontracting For Sales order.
    Subcontract Account assigned PO
    how can i create storage loc as vendor
    plz help
    regards
    raj

    Hi,
    Subcontracting for Project Stock: -
    Purpose: - Subcontracting is also possible in conjunction with Project stocks. The subcontracting orders are account-assigned to a Project. Thus, the components are not transferred (using a transfer posting) to the "stock of material provided to vendor" but are directly withdrawn from the Project stock the time of the goods receipt. The material manufactured is also posted to the Project stock.
    The cost of subcontracting is then debited to the Project.
    Since the components are not transferred to the "stock of material provided to vendor", it is recommended that you use a transfer posting to transfer the provided components to a new storage location (for example, 9999). This enables you to obtain an overview of those stocks that are physically located at the subcontractor. This information is particularly important when you carry out a physical inventory of the Project stocks.
    Features: -
    Withdrawal from Stock of Mat. Provided for Project: -
    For components that are managed in Project stock, you can define whether the components are to be withdrawn directly from each Project or from the stock of material provided to vendor. You manage this via the dependent requirements indicator for individual customer requirements and collective requirements (MARC-SBDKZ).
    You can maintain this indicator in the following places:
    In the MRP view of the material master record (MRP 4)
    In the explosion types for the BOM item (in Customizing for Production in the step Basic Data -> Bill of Material -> Item Data -> Define explosion types)
    Configuring the explosion types has priority over the configuration in Inventory Management.
    If the indicator is set at Collective requirements only (2), the materials are withdrawn from the stock of material provided to vendor. If this indicator is set any other way, the system withdraws materials from Project stock.
    Regarding Subcontracting Challan: -
    Go to OMJJ, select the field "movement type" and press enter
    Enter movement type "311" and double click on "Field selection (Enjoy)" under Dialog Structure on left side.
    here "New Entries" and add field "LIFNR" (Vendor)
    Now in MIGO, at the time of transfer posting of components using movement type "311 Q", specify the vendor code of the Subcontracting PO (i.e. Subcontractor)
    Now create Subcontracting Challan in J1IF01 for material document of 311 Q movement type.
    Also check in SPRO > Logistics - General > Tax on Goods Movements > India > Business Transactions > Subcontracting > Maintain Movement Type Groups > here for Movement Type Group "0001", Movement Type "311 Q" should be maintained.
    Then do GR against PO and refer the Subcontracting Challan here.
    And then do reconciliation in J1IFQ for the GR Document against Subcontracting Challan.
    Also check in SPRO > Logistics - General > Tax on Goods Movements > India > Business Transactions > Subcontracting > Maintain Movement Type Groups > here for Movement Type Group "0002", Movement Type "543 Q" should be maintained.
    Follow the below mentioned process;
    Process Steps: -
    1. OX09 - Create Storage Location as "9999" for Subcontractor Location
    2. MB1B - Do Transfer Posting of material from RM Warehouse to this Storage Location via movement type "311 Q" (Instead of doing 541)
    3. Now go to J1IF01 - here use material document of movement type "311 Q" and create Subcontracting challan. (If required)
    Prerequisite: - In SPRO > Logistics - General > Tax on Goods Movements > India > Business Transactions > Subcontracting > Maintain Movement Type Groups > Here for Movement Type Group "0001" (For issues), maintain movement type "311 Q" also along with 541.
    Rest all, refer subcontracting challan during GR and then reconciliation and completion, etc... will be same as usual.
    Note: - At the time of GR, consume components from storage location "9999" (for 543 movement type)

  • Stock trsp of normal stock to sales order stock

    Dear colleagues,
    I have been working with stock transport of sales order stock before and it worked - I have no issues with it. But this time my client needs to transport normal stock in one plant to sales order stock in another plant. FYI, this is a cross-company STO, i.e. item category "standard" in the PO.
    I thought it was the requirements class in the "Transfer of requirements" function that controled which stock my STO was going to consume, but I am unsure now. I checked the requirement class that SAP assigned to my STO delivery of sales order stock (the one that works - SO stock to SO stock) and it is 041, i.e. the very standard reqmt class that has nothing to do with sales order stock! So how does SAP determines it is the sales order stock that I want to transport?
    The IMG notes for the setting "Determination Of Requirement Types Using Transaction" imply that there can be special rules implied for special stocks:
    Example
    There are business transactions, such as consignment stock processing, in which the material with its planning characteristics is not important, rather the transaction itself. An issue from the customer's consignment stock should not trigger an availability check against planning at the plant as layed down by the planning strategy but rather against special stock.
    How does it work for special stock then?
    TIA for any hints!
    Raf
    Edited by: Rafael Zaragatzky on Feb 23, 2011 8:31 AM

    Thank you, Joshua.
    Yes, it works with M - SO stock is moved from plant to plant. But we need to move normal stock in the source plant to SO stock in the destination plant. Therefore I wonder what is it that tells SAP to do GI from sales order stock. Is it just that the AA category defines the sp. stock indicator both for the issuing plant and the receiving plant? In such case, we are stuck.
    But the comment in the IMG documentation that I cited first implies that there might be other thing that controls the special stock on the delivering plant side.
    BR
    Raf

  • Non valuated sales order stock vs valuated

    When we went live in 1999 we used non-valuated sales order stock for our MTO process.
    I really need to create and save cost estimates for configurable material (an average build) using CK51n. It does not work with non-valuated stock.
    Does any know if I can some new part numbers be valuated while the standard process stays non-valuated? A new material type with new rules??
    I wasn't here in '99 so I don't know what was involved in setting it up, nor in changing it

    Following different option

Maybe you are looking for