Where to Enter the Freight Cost VF02

we are dispatching as per the invoices ( multiple ) in a single Truck with single LR No for single destination.
we are able to enter in VF02 condition as ZFRI.
without entering the LR No and Truck No i cant identify these multiple invoices has dispatched in a particular one truck.
please help us to enter the Truck no and Lr no to identify the multiple invoice dispatch in a single truck.
Note : on the other hand my company strictly told don't enter on the Text TAB.
Regards
Kabil

HI,
In the Node SPRO > IMG > PM and CS module > Master data > Technical object > Serialization procedures > Select Integrated serial number managament and do the following settings.
A serial number profile with the procedure MMSL must be entered in the material master record.
If a stock check is to be performed, the indicator of the same name must be set in the serial number profile.
In order that the individual stocks are recorded correctly, you must define the indicator as follows:
The serial number usage for the procedure MMSL must be 03, meaning that the assignment of serial numbers is obligatory for goods movements.
The stock check must be 2, meaning that if the stock data is inconsistent, the system does not perform the posting and issues a corresponding error message.
In Customizing for inventory management you can sort the different types of goods movements into groups using movement type groups. By assigning movement type groups to a serialization procedure you define for the assigned movements whether:
Serial number requirement exists for the materials assigned to the profile
A serial number including an equipment master record is created in inventory management for a goods movement
Regards,
RitiG

Similar Messages

  • Reducing the Freight cost on material value for undelivered material

    Hi Experts,
    Summary :  The material supplier vendor needs to be paid for full quantity of material. The freight transport is allowed an under tolearance of 0.5% on the material to be supplied. If the delivered material quantity breaches the 0.5% under tolerance then amount at 1.5 times the cost of material for the shortage is to be deducted from the transporter. A dummy GR will have to be prepared for the undelivered quantity for which we do not want the freight cost to be loaded. The details scenario is mentioned below :-
    We have to make a Purchase Order with material code say ABC for procured of some material. Suppose we make a Purchase Order for 100 nos. at a Unit Price of Say Rs. 10/- for Material Code ABC on say Vendor M/s XYZ. A freight condition is maintained in the Conditions Tab and suppose the Freight is Rs. 10 per unit of the material.
    While preparing the Goods Receipt through MIGO, in the Freight Tab we select say freight vendor say M/s PQR against the freight condition and post the goods receipt.
    While doing Invoice Processing in MIRO, when we enter the combination of Purchase Order and Planned Delivery Cost the system will populate the vendor codes of both the supplier of material and the transporter. On selecting the transporter the freight amount will populate against which the invoice of the tranporter can be processed.
    In the Vendor Master of M/s XYZ GR-Based Invoice Verification is activated.
    The vendor is allowed an under tolerance of 0.5% (i.e. the vendor should deliver at least 99.50 nos. of the Purchase Order). If the vendor delivers 99.50 or more then there will be no deduction in the freight charges.
    But suppose the vendor delivers only 99.4 nos. of the quantity. Then we will prepare the GRIR for 99.4 nos.only. But while processing the MIRO we need to deduct 1.5 times the value of the material from the freight amount for the shortshipped quantity, i.e.
    0.1     no (99.5 u2013 99.4) X Rs. 10/- * 1.5 = Rs. 1.5 are to be deducted from the final payment from the freight amount of the transporter.
    The material supplier will have to be paid in full 100 nos. of quantity and will raise an invoice for 100 nos. A dummy GRIR for the 0.6 nos. of undelivered material will have to be prepared for processing the invoice for the 100 nos. of the material supplier and a dummy issue for 0.6 nos. of undelivered material will be prepared to remove them from the system.
    Hence the freight cost for this 0.6 nos. of undelivered material will also go into the cost of the material and increase the MAP by that amount. Also the goods issue Cost will also have the effect of the freight cost.
    We do not want to load the freight cost for the undelivered material in the value of the material.
    Can any one please suggest a solution for the same.
    Thanks in advance.
    AJ.

    Hi
    A PO Will be raised for full quantity of material say 100 nos.
    The material supplier vendor needs to be paid for full quantity of material.
    A freight vendor is maintained at the time of GR for material against the freight condition maintained in the Po.
    The freight vendor facilitates the delivery of the material from the vendor to the purchaser for which he is given an under tolerance limit of 0.5%. Any delivery below this tolerance limit, freight amount to the effect of 1.5 times the per unit rate of material x short fall below 0.5% tolerance will be deducted from the freight amount.
    A dummy grir will have to be prepared for the short delivered quantity for processing the invoice for the full quantity of the purchase order, as the vendor is going to raise the invoice for full purchase order quantity. The client does not want to load the freight cost of the undelivered quantity on the material value as it will wrongly show the MAP of the material. This shortshipped material will be issued to remove it from the system and the stock will remain for the delivered quantity only. The vendor is subject to gr based invoice verification.
    Please suggest a solution.
    Thanks in advance.
    AJ
    The freight transport is allowed an under tolearance of 0.5% on the material to be supplied. If the delivered material quantity breaches the 0.5% under tolerance then amount at 1.5 times the cost of material for the shortage is to be deducted from the transporter. A dummy GR will have to be prepared for the undelivered quantity for which we do not want the freight cost to be loaded.

  • Where to enter the SL. No. of the material issued

    Dear friends I have created a material and serialised.When GR is done Serial numbers are entered for the 10 items purchased. But Where to enter the sl. no. of the item issued to a particular cost centre/work centre. I am not finding any provision in MB1B/MB1A.
    Pl. guide me how to maintain the sl.Nos of the issues/postings made.
    Thnaks in advance
    Rddha

    HI,
    In the Node SPRO > IMG > PM and CS module > Master data > Technical object > Serialization procedures > Select Integrated serial number managament and do the following settings.
    A serial number profile with the procedure MMSL must be entered in the material master record.
    If a stock check is to be performed, the indicator of the same name must be set in the serial number profile.
    In order that the individual stocks are recorded correctly, you must define the indicator as follows:
    The serial number usage for the procedure MMSL must be 03, meaning that the assignment of serial numbers is obligatory for goods movements.
    The stock check must be 2, meaning that if the stock data is inconsistent, the system does not perform the posting and issues a corresponding error message.
    In Customizing for inventory management you can sort the different types of goods movements into groups using movement type groups. By assigning movement type groups to a serialization procedure you define for the assigned movements whether:
    Serial number requirement exists for the materials assigned to the profile
    A serial number including an equipment master record is created in inventory management for a goods movement
    Regards,
    RitiG

  • How to allocate the freight cost when providing free shipping

    We do not charge our customers freight cost.  We would like to allocate our freight cost to the product cost of each item sold.  Can we allocate our freight cost in the delivery note, then copy the delivery note to the customer invoice and remove the freight?  Will this process allocate the freight cost to each item cost on the delivery note, and at the same time not charge the customer for freight?  If this process will not work, is there another way to allocate the freight cost to each item on an customer invoice, without charging the customer for freight?
    Regards,
    Wayne

    Hi,
    It is not possible to post the freight charge to item cost while booking delivery.
    Freight value will be posted to the Revenue account defined in the Freight set up.
    Material need to be re-valuated by selecting the Freight revenue account, so that freight value will be debited to stock and credited to Freight Revenue account.
    After doing this you can book delivery and Invoice.
    Regards
    Ravindran Srinivasan

  • How the freight cost are transferred from condition type of shipment cost document to service entry sheet and collected in service PO item

    Dear Experts:
    could you please share with me the knowledge for below topic:
    How the freight cost are transferred from condition type of shipment cost document to service entry sheet and collected in service PO item, because these three objects use three different pricing procedures, and different condition type.
    how did the condition type of service entry sheet know to copy the value of whcih condition type in the pricing procedure of shipment cost document?
    Is this SAP standard function OR there need an enhancement to do that?
    I didn’t find related condition value copy setting in background, could you please share related setting with me? Thank you very much for your kind help!
    Best regards,
    Andy

    Hi, Gopi,
    Glad to see your feedback, but i still have question on your feedback:
    which condition type in the pricing procedure of service entry sheet should know to capture the net value of shipment cost doc? becasue there are so many condition types,
    And i have checked the corresponding condition type (PRSX) of service entry sheet pricing procedure in my SAP system, this is a self-defined condition type, but NO any calculation routine maintained for the condition type (PRSX), how did the condition type (PRSX) know to copy the total cost of shipment cost document?
    Below is the example and another question:
    what the relationship between the pricing procedures at service PO item level and service line item level?
    1. The freight cost in shipment cost document—including used condition type and pricing procedure
    The pricing procedure of shipment cost document
    2. The freight cost in service entry sheet—including used condition type and pricing procedure
    The pricing procedure of service entry sheet--the pricing procedure at service line item level
    3. The freight cost in service PO item—including used condition type and pricing procedure:

  • IDoc segment to capture the freight cost (XML/EDI invoice)

    Folks,
    How to capture the freight cost on an EDI incoming invoice. Any idea which IDoc segment can be useful in this regard.
    Any thoughts/suggestions/comments would be deelply appreciated.

    Hope you have not read the Invoice Idoc type whcih is used for EDI invoice.
    The Invoice idoc type does not support the functionality of Planned delivery costs ( Freight )
    Please go through the link
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/44/f50abcea3b11d194dc0000e83dd751/content.htm

  • My visa ends soon how and where to enter the new

    my visa ended soon how and where to enter the new

    Welcome to Apple Communities
    http://support.apple.com/kb/HT1918?viewlocale=en_US&locale=en_US

  • When i switch on my macbook its icon first appears smallers then gets bigger and the place where we enter the password.......that page looks like over zoomed. Please help tell what to do????

    when i switch on my macbook its icon first appears smallers then gets bigger and the place where we enter the password.......that page looks like over zoomed. Please help tell what to do????

      Reset PRAM.   http://support.apple.com/kb/PH18761

  • HT201442 My ipod has been disabled for 22,777,704 mintues and when i try to restore it is says it cant be restored because the ipod is locked. there is no where to enter the password. i font have the computer it was originally synced with. help please!!

    My ipod has been disabled for 22,777,704 mintues and when i try to restore it is says it cant be restored because the ipod is locked. there is no where to enter the password. i font have the computer it was originally synced with. help please!!

    Hi saraali,
    Follow the instructions in the support article link below that best apply to your situation:
    http://support.apple.com/kb/HT1212
    Cheers,
    GB

  • Where to enter the Assembly serial number when doing WIP Component ISSUE

    Hello Oracle Guru`s,
    I am performing Kit completion via API`s. I am able to perform Move transaction(have inserted in apps.WIP_MOVE_TXN_INTERFACE) and Completion Transaction(apps.mtl_transactions_interface, apps.mtl_serial_numbers_interface and apps.CST_COMP_SNAP_INTERFACE)
    When doing the Issue(Matreial transaction) , i am inserting in the apps.mtl_transactions_interface and apps.mtl_serial_numbers_interface, where do i enter the Assembly serial number? I would like to know, in what assembly serial number is my component residing.
    Aslo, when doing the issue(inserting in mtl_transactions_interface ), why is it important to enter the operation_seq_num and department_id? and what should be the value in these columns.
    we are using Average Costing.
    TX in advance for you reply.
    Regards,
    K

    Hello KING,
    Did you try doing online transaction for this case.
    I believe that you can enter parent serial number while entering serial number for components during online transaction. With this test, you can check that what column assembly number is going and you can try same in your background processing.
    Thanks,
    Ritesh

  • Just bought an ipad mini.  It recognizes my internet connection but doesn't connect.  It shows a lock.  How do I get to where I enter the password for my connection?

    Just bought an ipad mini.  Trying to set up internet connection.  It recognizes my connection but will not load.  There is a padlock shown.  How do I get to where I need to enter the password for my connection?

    On your router/modem, there will be a Wi-Fi password. If you enter that into your iPad for your connection, then your iPad will have permission to connect to that access point and then you will be able to use your internet.

  • Have firefox 5 install on both my Windows PC and Android(beta5). But I can't find on either device where to enter the three sets of number to sync them. All I can do is get a set of number.

    Installed Firefox 5 on Windows PC. Installed beta5 of Android device. I am trying to sync the two, but all I can do on either device and get the three sets of character to enter on the other device. I can't seem to find the option in either one the enter the number.

    The reason, I included the annotation that I'd upgraded my Itunes, (On my Computer) is B/C in many forums - the very first question, *HELPERS* ask, is. "Do you have the latest version of Itunes downloaded on your computer." I wanted to knock out any obvious replies.
    Now-  "DO YOU have any idea,"... how your UNHELPFUL remarks, do absolutely nothing but hurt others that might not have the EXPERIENCE you have? How do you expect people to know things without asking questions? Whew! RUDE!!
    Message was edited by: Apple I0S Help Team

  • Purchased a prepaid card for photoshop elements 12 and can't find where to enter the redemption code

    Have tried to follow the directions on the box of the prepaid card for Photoshop Elements and on the website but can't find the page to enter the redemption code in order to get the serial number thus being able to download the software??

    Try http://helpx.adobe.com/x-productkb/global/redemption-code-help.html#purchasedproduct

  • Where to enter the base for skf and act type

    Dear Forum,
    1 where can i define the total number of employee for each cost center? i cannot enter in KK01 as in KK01 i only can define the measurement which is number of employee.
    2 where can i define the number of hour spent? cannot be in KL01 as in KL01 only define the measurement which is hour only.
    thanks

    hi,
    1. for SKF its KP46
    2. for activity types it can be eitheir in the KP26 or in the cost object incase if its related to product costing.
    hope this helps.
    regards
    sayeed

  • How to add the shipment costs in to material costs

    Dear friends
    I am implenting the transportation module.
    In purchase process and STO processes, the client requirement is received material cost should be added with shipment cost.
    I mean the material cost is 1000/-
    The shipment cost is 100/-
    Client Requirement: Freight liability should get loaded on the inventory being it is part of purchase cost.
    Now the material cost: 1000+100
    We are not entering the freight costs in PO.
    We are creating the shipment cost documnets for calculating the ship.costs.
    When we do the MIGO/Inbound delivery the system need to capture whole amount as a material cost.
    With regards
    Lakki

    Dear Vinod,
    Already  i created the shipment cost document with reference to inbound delivey document.
    Now the ship.cost value is 100/-
    The material cost is 1000/-
    But i want to show the accounting document for meterial document with 1100/-(Material cost and ship.cost)
    But when we do the PGR, sys will generate the accounting document with material cost only, sys should not add the ship.cost. Because we didnot enter any ship.cost value in PO or delivery.
    We are maintaining the ship.cost in saperate documents.
    How to do that?
    With regards
    lakki