Hi all,
Can i maintain batchwise prices for Finished Product which is having standard price in material master.
Thanks & regarsd,
Ganesh
Hello Venkata,
In this case, you need to maintain split valuation for material. For all the batch you need to create valuation type (in std SAP valuation category X is avilable). With this you can maintain standard price batchwise in material master.
http://help.sap.com/saphelp_46c/helpdata/en/a5/63314d43a211d189410000e829fbbd/frameset.htm
http://help.sap.com/saphelp_46c/helpdata/en/47/61017149f011d1894c0000e829fbbd/frameset.htm
Hope this helps.
Regards
Arif Mansuri
Similar Messages
-
Production order wise report of all component.
dear all
I want production order wise report of all component.
1) quantity required 2)issue quantity3)currect stock
I got quantity required and issue quantity field in co24 but i didnt get currect stock field(unrestricted stock) in that t-code
Is any t-code is available ?
rgds
SurendraHy Surendra,
In any of the standard SAP reports you will not find the Goods Movements of Particular order along with available Component stock.
Goods movements report of the Production / Process order is static report once the order is close.While Stock report is variable report and may be change Time to Time.
I think if you wish such kind of report then you have to go for Z reorts.
You can find all the Goods Movements of Order in COOISPI/COOIS/IW3M but there is not available stock report.
Regards,
Dhaval -
Report to view Production order wise atcual cost when PO is assigned to PCC
Hi All,
Can anyone help me to get the report for production order wise actual cost incurred when that Production order is assigned to PCC (Product cost collector).
Is it possible through Summarization hierarchy or Product drilldown?
If yes, can u explain the steps.
Regards,
Durga.Hi Bhaskar
You are in Alaska and you wanna eat vegetarian food
You cant get values at Prod order level if you have chosen PCC as cost object.... You will only get Qty at Prod order level
To get a bird's eye view of costs incurred in PCC, execute report MCRY with PCC as the input... MCRX shows only Qty info for components
br, Ajay M -
How to get Production Order wise Actual Values
Dear CO Experts,
How to get Actual Values (Raw Material Issue, Activity Confirmations & OH Calculations & Goods Receipts from Production) each Production Order wise ?
My Scenario is Product Cost Collectors (PCC) with Production Orders.
If we select above scenario Production Order is Statistical and PCC is real cost object.
For PCC is Period wise we can track the cost Periodically in individual Material.
But my client is asking how to see the each Production Order wise Actual values. Is there any T.Code ??
In Production Order I am able to see only Plan values (CO03).
Waiting for your favorable reply.
Regards,
KBR.Hi Bhaskar
You are in Alaska and you wanna eat vegetarian food
You cant get values at Prod order level if you have chosen PCC as cost object.... You will only get Qty at Prod order level
To get a bird's eye view of costs incurred in PCC, execute report MCRY with PCC as the input... MCRX shows only Qty info for components
br, Ajay M -
Dear Experts ,
I have a requirement that i want to check production order wise stock in hand.its a bit urgent.
Can anybody just help me out by some Tcode or some tables by which i can get the required data.
Regards
SarfrazHi,
If the Stock is not referring to any special stock (sales order, Project etc..), it is not possible to get the production Order stock.
This is with referenve to the FG.
If you want to have the Stock for Components of the production order, then with reference to the Reservation no. you can findout the components..
Regards,
siva -
Production Order wise List for Target cost v/s Actual cost
Dear Sir,
We have make to order scenario . We want to have a list giving Production Order wise "Target Cost" and "Actual Cost" . The purpose of list is to analyze the Variances Production Order wise .
I request to kindly guide us , how can the above list be generated please .
Regards
B MittalKKBC_HOE - With Defined Summarization Hierarchy
S_ALR_87013104 - Sales Order Selection
KKAC - For Sales Order with Assigned Orders
KVBI - Actual Costs
KOB3 - Variances -
Report to see the OverHead Posted Production Order wise
Dear SAP Gurus ,
I request you to kindly guide me as what Tcode is available to see the Over-Head Cost booked related details (prefearably along with the Production Order number) .
Regards
B MittalHi,
Transaction CO03
Menu Path: GoTo >Cost > Analysis
Another cost report for production orders is transaction KKBC_ORD
regards,
R.Brahmankar -
Overhead calculation - Production order wise
Dear All,
We have two furnaces for which different production orders (Material code is same) are created every month. Seperate cost centers are also being made for them. We are implementing overhead calculation percentage based.
Now the requirement is user wants to capture overhead cost of furnace 1 cost center to be absorbed on production order of furnace 1 and furnace 2 cost center cost on production order of furnace 2.
How to achieve this when material code for which the production orders is being created is same.
Regards
DivrajHi Divraj,
I can suggest for one approach which you can think over.
You can absorb the overhead cost of these two furnaces through activity rates. Just work on the extra cost you want to absorb as overhead on individual cost center. Increase the activity rates to the extent of this overhead.
So, eventhough material code of the production order is same you can book the actual activity on the orders and the production order will bear the cost accordingly
regards,
Makrand -
In Production Return & Rejected Qty Prod Order wise required
Hi Experts,
In Production, Parent Item to be produced 100. Two Child items are there for the parent Item.
Parent Item A- 100 Qty
Child Item A1- 100 Qty -- Issue method Back flush
Child ItemA2 -100 Qty -- issue method Manual
Child Item A2 Issued Manually. Production Completed........
In the receipt from Production
Parent Item A -90 Qty completed
Child Item A1- 8 Qty Returned (Good Raw Material Returned)
Child Item A2- 3 Qty Returned (Good Raw Material Returned)
Child Item A1 -2 Qty rejected (To be scraped)
Child Item A2 - 7 Qty rejected (To be scraped)
We would like to take query/Report......... Production Order Wise, Child Item Issued, Component Returned, Component Rejected.
Plz Guide Me,
Thanks and Regards,
ManikandanHi,
In SAP, for items defined as Back-flush, you cannot change the issue qty of Raw Material components. This will always correspond exactly to the qty of Finished Goods and the relation between the FG qty and the component qty in BOM. In you example, the RM Item A will be issued as 100 qty as the FG produced is 100 qty.
Or if you are recording 90 qty then RM Item A will be consumed automatically equal to 90 qty.
In SAP, the FG reject is prodcued only for numerical record and is recorded in the Receipt from Production screen. Total prodcued qty will be reject qty + completed qty.
The scrap of FG item is not possible as FG item. Fixed qty of Scrap can be defined in the BOM or the production order as a row with negative qty. This will be prodcued automatically based on the qty relationship between Scrap item and the FG item.
Say if in the Production Order for a FG of 100 qty, scrap is produced equal to 20 qty, then this srap item will be entered in the Production Order as a row of -20 qty. When production of X qty is recorded, scrap will be prodcued in the following ratio:
Scrap produced = X * (20/100)
Regards -
Use of Planning Table (MF50) in Capacity Levelling with Production Order
Hello Experts
I wish to know that is it possible to perform Capacity Levelling in planning table (tcode MF50) with respect to a Production Order ? It is known that MF50 is used in Repetitive manufacuring to do the capacity levelling with respect to Planned orders. But in our discrete manufacturing scenario we want to use planning table to the capacity levelling with respect toa Production order.
Any clue or help pertaining to this will be highly appreciated.
Thanks in advance
Regards
JayantaDear ,
MF50 is does the cacapcity leveling based on mateail -run schedule order (planned order ) where as in discrete manufacturing , when you run the MRP , MRP system assume Infinite Capacity and schedule the order as per your selection in MD02(2,1,3,3,2) and then you convert those planned order to Production order .Here you checkied the Capacity in Production Order level .
In stanadrd SAP , it is not possible to use MF50 for discrete production order.
In discrete order or process order , do the caapcity leveling , there are seperate planning table available based on Over all Capacity Profile and Schedule type .This can be done in following way :
1.CM31-Production Order Wise -Tabular
2.CM23-PO wise -Graphical
3.MC88: Ruf Cut Planning
Work Centre Wise : CM21 -Graphical , CM22-Tabular Planning Table .
Make sure the below set up before you carry on the Capacity leveling :
.Define time profile in OPD2.
Define the strategy profile in OPDB
Define the Overall profiles in OPD0.
In OPJK maintained check capacity with SAPSFCG013 profile for your production order type
In OPU3 , scheduleing parametre s: Generate Capacity , Scheduling Type , Automatic Log ,Start date in Past as per your req.
In OPJU , chekc the contol tab of the scheduleing as per OPU3
In OPKP- Production scheduling paranmeters assing the overall capacity profile -SAPSFCG013 with finte scheduling tick.
Master Data :
1.Materials Master define the Production scheduler and production scheduling profile
2.Work Center - Define the capcity planner group,activate checkbox Relevant for Finite sceduling,on the capacity header define the shift timings,break timings and unit of measure,no of individual capaity, enter formula for scheduling in capacity view.
3.Routing - enter the values for the standard values. Use control key with scheduling.
Hope this will help you .
Regards
JH -
Goods Receipts 101 E from Production Order without valuation
Hi,
we faced a strange issue relating to the final confirmation of production order.
In some cases, the goods receipt of main order, created by the confirmation in CO11N, has value "0".
Taking a look to some production orders for the same product, they have no differences and the valuation is correctly with the plan cost estimate.
The issue is triggered twice:
1- Directly with the first confirmation in random cases;
2- Confirmation with wrong value (higher than Zero), reversal of confirmation and new confirmation without valuation.
Could you please help us?
Thanks.
MCHi
With Valuation Strategy M, a record is created in EBEW for each sales order
1. The first goods receipt results in valuation on the basis of one of the subsequent strategies in the specified sequence. A standard price selected through one of the subsequent strategies is copied into strategy and serves as the valuation basis from this point onwards.
- The system calculates the standard price on the basis of your customer exit COPCP002 Material valuation for valuated sales order stock.
- The system calculates the standard price in a sales order cost estimate. This sales order cost estimate can be based on a unit cost estimate or on a product cost estimate.
- The system determines the standard price using the production order cost estimate or the planned costs for the WBS element. If there are multiple production orders for the same sales order item, the system uses the standard price that results from the production order that delivers first (see strategy 1).
2. If the above price is changed after first delivery, then the difference would be posted as output price variance at month end.
3. Even reversal of first goods receipt does not reverses the standard price. You need to manually change it using MR21..
4. Have you ticked "W/o Val Strategy" in your req class? If yes, it means that inventory is valuated using Std cost from CK11N... In your case, if it is ticked and Std cost is not released, then GR will be valuated at zero price
BR,Ajay M
BR,Ajay M -
Reg :Production order cost report day wise.
Dear Expert,
1.We want a report for a particular Production order cost day wise.
The scenario is like this Production order is Released for 100 Qty.
Today they confirmed only 50 Qty.
Tomorrow they will confirm 50 qty.
Now they want to see the cost for today confirmation and tomorrows confirmation.
Reason being daily the Raw Material cost is changed and they want to track the variance.
Is there any standard report we can achieve this or do we have go for development
2. And also i need to know daily how many production orders have been released.
Thank u in advance.A day is not a controlled cost object. You could write a report to look at costs gathered in a day (by reporting date), but I strongly suggest that if you need to analyze costs per day you switch to daily orders.
You'll find then that all the standard processes work for you. -
Work center wise production order infomation report
Hi all,
i have a requirement that workcenter wise (with date) production order information with quantity details (plan and actual).
Eg: My production order quantity - 40 nos. (it takes 4 days to finish).
i have three operation in production order.
my order scheduled start date - todays date.
In standard, when enter my first operation work center, system showing production order and its quantity (40 nos) . but i need to split that order quantity in report.. means on todays date for particular production order - order quantity = 10 nos.
Clent want like that (with quantity break) report..
Any standard report ???
If customization.... How it can be mapped in SAP.??
Thanks in advanceHi,
You can use the FM COIS_SELECT_ORDER_DATA_READ.
CALL FUNCTION 'COIS_SELECT_ORDER_DATA_READ'
EXPORTING
iv_prod_order_sel = lv_prod_order_sel
iv_proc_order_sel = lv_proc_order_sel
iv_planned_order_sel = lv_planned_order_sel
iv_rem_objects_only_sel = lv_rem_objects_only_sel
is_objects_to_read = ls_objects_to_read
it_parameter = lt_parameter "General Structure for PARAMETERS and SELECT-OPTIONS
it_status_hdr = lt_status_hdr
it_status_opr = lt_status_opr
it_status_cmp = lt_status_cmp
TABLES
ct_ioheader = lt_ioheader
ct_ioitem = lt_ioitem
ct_iodocl = lt_iodocl
ct_ioopdocl = lt_ioopdocl
ct_iomamo = lt_iomamo
ct_ioconf = lt_ioconf
ct_ioopconf = lt_ioopconf
ct_iosoconf = lt_iosoconf
ct_iogomo = lt_iogomo
ct_ioopgomo = lt_ioopgomo
ct_iosogomo = lt_iosogomo
ct_iogmer = lt_iogmer
ct_ioopgmer = lt_ioopgmer
ct_iosogmer = lt_iosogmer
ct_iosequen = lt_iosequen
ct_iooper = lt_iooper
ct_iosoper = lt_iosoper
ct_ioopcomp = lt_ioopcomp
ct_iooppreq = lt_iooppreq
ct_iosopreq = lt_iosopreq
ct_iooppord = lt_iooppord
ct_iosopord = lt_iosopord
ct_ioopmst = lt_ioopmst
ct_ioopprt = lt_ioopprt
ct_ioopcap = lt_ioopcap
ct_ioopscap = lt_ioopscap
ct_iosocap = lt_iosocap
ct_iososcap = lt_iososcap
ct_ioopsccf = lt_ioopsccf
ct_iososccf = lt_iososccf
ct_ioprodlist = lt_ioprodlist
ct_iomatver = lt_iomatver.
This FM get data from the report used by transaction COOIS. If you needed the header data then you can use lt_ioheader table and seperate the data with the date. If you need at operation basis the you can use lt_iosoper table. You can use this FM to create custom report even with the checks like material availability, PRT availability, capacity requirement etc.
Thanks and regards,
Pradip
Edited by: Pradip Ray on Aug 26, 2009 8:26 AM
Edited by: Pradip Ray on Aug 26, 2009 8:26 AM
Edited by: Pradip Ray on Aug 26, 2009 8:26 AM
Edited by: Pradip Ray on Aug 26, 2009 8:27 AM -
How to get Operation wise Time for a list of Production Orders
Dear Sir,
We have a list of Production Orders numbers and need to know the operation wise time duration for these production orers (off course the desired time is same as mentioned in the routing for the relevant component)
Kindly guide us as how can we get these timing details .
Rgds
Sonia agarwalSonia,
I hope your are refering to setup time, process time, teardown time in the production order.
use report COOIS for it.
In the 'List choose operation.
Give input for the production orders in the slection scren. Execute.
In the report select the columns as per your requirement.
Hope this helps you.
SmanS -
How to get open production orders by plant wise
Hi,
How to get open production orders by plant wise.
i know from tcode COOIS, is it possible to get from this. if so what are the parameters we have to give to get open production orders by plant wise.
is there any tcode or tables available , please provide details .
regards,
Hari priyaHi,
What is your definition of Open Production Orders?
Definetly you will get the report from COOIS for Plant wise.
Whther you want to consider all the Orders having the Status REL but not DLV?
Then there is a chance of having the Orders, still with PDLV status but GR is done for the full Qty. May be you don't want to consider the TECO status, eventhough the Order is short closed??
Better to ommit the Orders with CRTD status also..
So, based on this which status to consider and which status not to consider..
You can define the "Selection profile status" in BS42.
Use this selection profile in COOIS, so that the rsults will be accurate..
Best Regards,
Siva
Maybe you are looking for
-
Flat file to Oracle: Dynamic flat file name
Hi, I am doing a transformation from flat file to oracle. At one place there is requirement like flat file name is dynamic. *eg. D:\ Flat DB\ Sample<Date>.txt examples may be like Sample09012012,Sample08012012 * As in physical schema we specify na
-
Problem in Using Log4J with Weblogic 9.2
I am using Weblogic 9.2 and Log4j. By using Admin console I set the Severity Level to WARNING and inside my java code is given below: Logger logger = Log4jLoggingHelper.getLog4jServerLogger(); if (logger.isEnabledFor(Priority.DEBUG)){ logger.debug("D
-
How to make File Dialog in different color
Hi to all, How to make File Dialog to appear in orange color. Regards khiz_eng
-
Import/export--need help gurus!!!!!!
C:\DOCUME~1\ADMINI~1>set oracle_sid=orcl C:\DOCUME~1\ADMINI~1>expdp scott/tiger directory=orcl_exp_datapump schemas=scott Export: Release 10.2.0.1.0 - Production on Tuesday, 12 February, 2008 19:35:34 Copyright (c) 2003, 2005, Oracle. All rights rese
-
Making AS3 code backward compatible to Flash 8?
So I made a slideshow swf in AS3 only to later find out it needs to be compatible with Flash 8...and in my estimation AS3 cannot publish back to a Flash 8 swf without it being AS2...is there anyway I can do this without rewriting the code? I'm fairly