Accounting entries after PGI for STO Within same Plant

Dear Members,
We have activated STO within same plant in OLME->PO->Setup STO -> Set up stock transfers between Storage locations
Cycle is PO ->VL10B->VL02N ->PGI ->GR
We are using newly created delivery type ZNL ( copying NL ,Using 641 )
Which is working fine
Now the thing I am observing here is this
a > When we have not assigned any pricing procedure  in  Determine Schema for Stock Transport Orders
after PGI no accounting document was generated
But our requirement is to add freight cost that is why we added a pricing procedure ZRM200 (copying RM2000)
Here we are observing after PGI accounting document is generated
Postings are ( Material cost 500 Eur i.e 100 Kg @ 5.00 Eur in PGI )
RM stock a/c       500 Cr.
RM stock a/c       800 Dr.
Freight clearing   300 Cr
And it does not matter whether P101 is in ZRM200 or not (Same posting with or without P101)
Now my question is it correct system behavior ?
And requirement is postings should only be like this ( i.e without including transfer posting price)
RM stock a/c       300 Dr
Freight clearing   300 Cr
Can it be possible to achieve ?
Many thanks in advance
Edited by: redriver on Dec 29, 2011 2:35 PM

Not necessary to activate Purchase account
Even for STO we use FRE. It is only a name and called as Purchasing freight account
So check the pricing procedure at M/08 for freight condition and account key. I think it is FRE
Check which GL account assigned at OBYC/Purchasing freight account(FRE).
if the GL is same as your RM and if your need mainatain separate GL enter that GL here.
Let us know result
Srinivas

Similar Messages

  • STO-Within same company code and same sales organisation

    hi freinds
    i need steps for STO Within same company code and same sales organisation "xyz" with different plant "X " and  " Y"
    with regards
    dinesh

    Hi,
    Sales organization is linked to sending plant. It does not matter if receiving plant is using the same or different sales organization. The setup from sending plant is independent from that.
    As for the STO standard setup, I suggest you search SDN first. Below example link.
    STO setup article link:
    http://www.sdn.sap.com/irj/scn/index?rid=/library/uuid/c05e2251-91f0-2c10-4e91-e919468e4687
    Regards,
    Dominik Modrzejewski

  • Release Strategy for inter Storage Loc Material transfer within same Plant

    Hi Guru's
    I hope all are doing good. I gota small concern to share with you. Is it possible to apply Release Strategy between two Storage Locations within same Plant for Material Movement?
    Many Thanks
    SONAL

    Release Strategy cannot be assigned in material document.
    However you can restrict this at authorisation level for T code MIGO_TR.
    Regards
    Bhavesh Mistry

  • Transfer between storage location to storage location within same plant

    Dear Gurus,
    We r doing storage location to storage location transfer within same plant through purchase order.
    Due to excise requirement we have to raise excise invoice for the same for captive consumption purpose.
    Is it possible to make it One step procedure so that GR will take place at same time as GI the way it works for plant to planrt.
    In ECC 6.0 option is there for transfer between storage location. I configured but it is not working.
    Please check the same.
    Rgds,
    Saurabh

    Hi Saurabh,
    The proceedure you are following is a bit wierd. But I think this is as per your business requirements.
    You can continue to follow the same proceedure as this may  not be possible through one step movement type.
    Best Regards,
    Prateksha.

  • Which accounting entries will getupdated in STO and Subcontrtaction?

    Hi
    Can anyone tell me which are the accounting enties will get updated at the time of GR for the below to processes
    1.  For Subconatracting
    2. STO (Plant to Plant transfer)
    Best Regards,
    Sairam.

    Hi,
    You check an invoice for a subcontract order in the same way as for a standard purchase order. Additional account postings do, however, occur if a price variance has occurred. These postings are shown in the following example.
    Postings for a Subcontract Order
    In this example, a subcontract order was created for the end product "ASSEM-1". The components COMP-1 and COMP-2 were provided to the subcontractor.
    Purchase order
    50 pieces of material ASSEM-1 were ordered. The subcontract price is $10/piece (total value = $500).
    The following components were provided to the subcontractor:
    15 kg of the component COMP-1
    5 pcs of the component COMP-2
    Goods receipt
    The subcontractor delivers 50 pieces of material ASSEM-1.
    At goods receipt, a consumption posting for the components provided to the subcontractor is automatically made. It is valuated at the price from the material master record, for example:
    15 kg of the component COMP-1 at $20/kg = $300
    5 pcs of the component COMP-2 at $30/pc = $150
    The goods receipt is valuated with $950. This is calculated as follows:
    The subcontract price (50 pcs * $10/pc = $500) and
    Value of the components ($300 + $150).
    Invoice receipt
    The vendor (subcontractor) sends you an invoice for the subcontract work. However, the price is $10.50/pc. Therefore the invoice is 50 pieces ASSEM-1 * $10.50/pc = $525.
    Posting Schema for Moving Average Price Control
    In this example, the following postings are made at goods receipt and invoice receipt, if the material (end product) is valuated at moving average price.
    Postings
    At goods receipt
    At invoice receipt
    Vendor account
       525 -
    GR/IR clearing account
    500 -
    500 +
    External service account
    500 +
    25 +
    Stock account: end product
    950 +
    25 +
    Change involving stocks
    950 -
    25 -
    Stock account: comp.
    450 -
    Consumption account
    450 +
    Posting Schema for Standard Price Control Without Price Differences
    For materials (end products) with standard price control also note that
    No price differences are posted if the total of the external service value (for example, $500) plus the "material to be provided" value (for example, $450) varies from the value at standard price (for example, $1000). Posting of a price difference is not required because each posting line has its own offsetting entry.
    No posting lines are created on the stock account or on the stock change account when an invoice is received.
    In the above example, the following postings are made for a material with a standard price of $20.
    Postings
    At goods receipt
    At invoice receipt
    Vendor account
       525 -
    GR/IR clearing account
    500 -
    500 +
    External service account
    500 +
    25 +
    Stock account: end product
    1000 +
    Change involving stocks
    1000 -
    Stock account: comp.
    450 -
    Consumption account
    450 +
    Posting Schema for Standard Price Control With Price Differences
    However, if you wish to generate a price difference posting in those cases where the manufactured material is managed at standard price and the standard price varies from the receipt value (externally performed service + value of components + delivery costs), you can configure this in the Customizing system of Inventory Management.
    In the above example, the following postings (including price differences) are made for a material with a standard price of $20.
    Postings
    At goods receipt
    At invoice receipt
    Vendor account
       525 -
    GR/IR clearing account
    500 -
    500 +
    External service account
    500 +
    25 +
    Stock account: end product
    1000 +
    Change involving stocks
    950 -
    Price difference
    50 +
    Stock account: comp.
    450 -
    Consumption account
    450 +
    Reg STO please inform in details entries in case plant to plant or between co-codes?
    BR
    Diwakar

  • More than one PGI for STO/Sale order

    Dear All,
             When doing PGI for a STO or Sales order that having many no.of items, more than one PGI is created for the same STO
    or Sale order. My doubt is How the system takes the material in each PGI whether there is any logic behind this or it takes in
    random manner. This happens while creating billing doument also.
    Could anybody help me to find the reason ?
    Regards,
    S Sridhar

    Dear Suresh,
              Thanks for your response.
              Please let me know, why  the system creates more than one outbound delivery for a single STO that contains many items.
    In my case, I have 8 items in a STO. When I create a Outbound dely,in VL10B, the system created 4 outbound dely.documents.
    my question is,
    1. Why the system creates 4 Outbound Dely.documents for a single STO that having 8 items ?
    2. By which logic the system decides the material in outbound dely ?
    My requirement is to create a single outbound dely for a single STO or otherwise I have to control the outbound dely.creation (more than one Outbound dely.document for a single STO)
    Regards,
    S Sridhar

  • Accounts updated after PGI and release to accounting

    Hi All,
    Could you pls tell me,
    1.Which documents documents are updated after billing(release to accounting?
    2.After PGI what documents will be updated and which accounts?
    Hope this is clear
    regards,
    James

    Hi,
    The following updations take place on PGI:
    1. Warehouse stock of the material is reduced by the delivery quantity
    2. Value changes are posted to the balance sheet account in inventory accounting
    3. Requirements are reduced by the delivery quantity
    4. The serial number status is updated
    5. Goods issue posting is automatically recorded in the document flow
    6. Stock determination is executed for the vendor's consignment stock
    7. A worklist for the proof of delivery is generated
    8. A worklist for the proof of delivery is generated
    After goods issue is posted for an outbound delivery, the scope for changing the delivery document becomes very limited. This prevents there being any discrepancies between the goods issue document and the outbound delivery.
    Cheerzz..
    Subbz..

  • Accounting Entries during MIRO for a WBS Purchase order - reg

    Hi,
    I have created a Purchase order with account assignment as Project and attached a WBS element in the Account assignment tab. There is no GR involved in this PO.
    When  i am trying to do the Invoice verification, it generates the accounting entries as follows
    Vendor G/L account Credited
    GR/IR account with Zero value
    G/L account assigned to WBS element Debited.
    In actual i dont want to see the GR/IR account with zero values  as an additional entry as it does not makes sense to have an entry with a zero value.
    Please expedite with your valuable suggestions to eradicate the unnecessary entry of GR/IR during invoice posting.
    Regards,
    RitiG

    HI,
    I hope so ,there might be a problem at the PO creation Level.
    an Account assigned PO can be Payed directly by MIRO.
    But the folloeing setting has to be Made .
    IN the Delivery Tab,uncheck the GR Tick Mak
    and in the Invoice Tab GR IV tick Mark.
    if these Ticks are unchecked ,then it would be a pure PO based IV and the posting should be in the Following Manner
    Vendor
    GL -- COnsumption..WHich is maintained in PO
    + any TAX related GLS that are affects do due to TDS(withholding ) or TAXINN
    HOpe so it helps
    Regards
    Anjanna

  • Which accounting entries will update in STO?

    Hi,
    Can anyone explain me which are all the accounting entries will get updated from SD point of view.in Stock tranport order.
    Best Regards,
    sairam.

    hi
    in the delivering company these will get updated:
    sales account
    receivables
    Cost accounting
    Profitabilty accounting
    Customer accounts
    in the receiving company:
    purchase accouting
    payables
    vendor accouts
    reward points if helpful
    suresh

  • Donot want Planned Order to be created for STO in supplying Plant

    Hi Gurus,
    We have material A which in being produced in Plant 1000. This Material A is being used as a Component for a product in plant 2000. By Using Stock Transport order we get the material from supplying plant 1000.
    when we run MRP for the plant 2000, schedule line is generated for the plant 2000. at the same time planned order is generated for the Material A in plant 1000.
    My requirement is i dont want planned order to be created in supplying plant i.e plant 1000.
    Afzal

    Hi,
    Let me Clarify my requirement again.
    Material A is being Produced in plant 1000(supply). The same Material A is being used as Input material in plant 2000(Demand) for product B.
    <b>Master Maintained.</b>
    <b>Material Master</b>
    I maintained Procurement type as F and Special Procurement as 40 in Plant 2000 for Material A.
    I maintained Procurement type as E for Material A in Plant 1000.
    <b>Schedule Agreement</b>
    Schedule Agreement created in Plant 2000 referring plant 1000 as supplying plant and agreement type as LU.
    <b>Source List</b>
    Source List Created based on the schedule agreement and maintained MRP indicator as 2.
    <b>MRP Run</b>
    During MRP run for Product B in plant 2000, It creates schedule line for the Material A in plant 2000. At the same time it creates planned Order for material A in the supplying plant 1000.
    My Requirement is we don't want the planned order in supplying plant 1000. The reason behind is that we want to run MRP in plant 1000 seperately at a different frequency.
    Running MRP in plant 2000 should limit the requirements raising in plant 2000 only and the MRP run for 1000 should limit to plant 1000 only.
    Message was edited by:
            afzal ahmed

  • PGI for STO movement type error Message no. L9005

    Hi Gurus,
    I have created an STO.Created delivery and confirmed TO.
    Now while doing PGI,single step only(647 movement type),
    system throws the following message,
    "" Error during search for WM movement type (641 1 L K  )
       Message no. L9005 "".
    As per my checking for both IM movement types 641 and 647, ' 641 ' has been assigned as
    Ref movement type and " 601"  has been assigned as WM movement type.
    601 is maintained in WM.Should I maintain 641 in WM?That case I have to change SAP std settings..
    If so pls provide me the details for 641 K.
    Kindly help.
    Best Regards

    Hi Kumar,
    Try the following:
    Maintain an entry for your warehouse with movement type 641 SpStIn and Movment Indicator l combination in transaction OMLR.
    And also ,
    Check in IMG Path - Enterprise Structure --> Assignment --> Logistis Execution --> Assign warehouse number to plant/storage location.
    Here check whether the warehouse number is assigned to your plant and storage location.
    Thanks!
    Preethi
    Edited by: preethi R on Dec 2, 2008 10:50 AM
    Edited by: preethi R on Dec 2, 2008 10:50 AM

  • Inspection lot PGI for STO-Quality management

    Sirs,
    I have a query. I have an FG where i am using an STO to transfer the material from 1 plant to another. Here i have inspection type 08 assigned in the master. I have assigned the origin 08 to the delivery type NL hence when i save the OBD (not post PGI) the inspection lot is generated. But even though the inspection lot is generated the system is allowing me to post the Goods Issue for the material. How do i bring the lock in invoicing so that if the lot is generated the PGI of the OBD is not allowed and system should give the message 'status of the inspection lot does not allow goods movement'..
    Waiting for your replies,
    Ariel.

    Dear,
    i have the same question..
    is there any way to generate inspection lot from PS Network activity?
    is there any BADI or Workflow...?
    i hope there would be any solution of this scenerio.

  • Add on Program to generate AP/AR for STO within a company code

    I want to generate the add on Program to Generate the AP with referance to the Material Document.
    Is it Possible to Create it and Update the G/L Automatically?
    If yes , What are BAPI 'S can we use or Shall we use BDC?
    Please share your ideas and Suggestions.

    Assign plants c, d, e to same company code.
    If you want to create a Stock Transfer Order,
    maintain A as supplying plant. (create vendor master linked to purchase org and company code)
    maintain c, d, e as receiving plants. (create customer masters linked to company code)
    Ignore Plant B (if no changes to stock is happening there).
    Do a 2 step stock transfer, when stock is in transit, after 1st step, you can assume stock is moving thru Plant B.
    Settings For Stock Transport Order Without Delivery:
    Order type UB
    Item category U
    GI: 351
    GR: 101
    Delivery type: Blank
    Settings For Stock Transport Order with Delivery:
    Order type UB
    Item category U
    GI: 641
    GR: 101
    Delivery Type: NL
    If STO not needed, use 303 GI from Plant A and 305 GR in Plant C, D, or E thru MIGO.
    If Plant B should be considered in stock transfer,
    Just do a one or two step transfer from A to B, then from B to C, D or E.

  • STO within same co.code

    Dear all
    while doing STO from one manufacturing plant to other plant with in same co.code ( plant1 to plant2)
    I created STO for five line items in receiving plant2, maintained storage location,delivery date etc
    when i go to VL10B,selecting supplying plant1,and execute,select line and click on addl doc data,
    system is showing 2 line items only.for other 3 line items not appearing
    what might be the reason?
    All configuration settings done properly.we are doing well every time.but,only this time system is showing only 2 line items instead of 5 line items in STO
    Please guide me

    Hi
    Check in your STO whether all 5 line items has same delivery date ?
    secondly check whether in CO09 confirmation from supplying plant is ok
    In VL10B go to purchase orders tab and put your PO no. and also see the Deliv.creation date is long enough to cover the delivery date of each line item in your STO
    Please check this.
    Kishor

  • Only on my administrator account firefox will tell me it is already running and to close it or restart my computer. guest account works fine. nothing is running on main account though. after restarting i get the same response.

    when i click on the icon to open mozilla, it shows me this:Firefox is already running, but is not responding. To open a new window, you must first close the existing Firefox process, or restart your system.
    But I do not have anything running?Won't work after restarting, opens just fine on my guest account though?

    Do you still have a [http://kb.mozillazine.org/Profile_folder_-_Firefox Firefox Profile Folder] in that account?
    * [[Firefox is already running but is not responding]]
    * http://kb.mozillazine.org/Recovering_a_missing_profile
    * http://kb.mozillazine.org/Profile_in_use

Maybe you are looking for

  • How to deploy osb projects into managed server in weblogic

    i am new to osb i have a doubt i created a managed server in weblogic admin console, it was running fine ,but i need to know how to deploy my osb projects in that new manged server.As of now it is deployed in http://localhost:7001/sbconsole

  • Applets, URLConnection, IPv6, and Cookies

    The web application I'm working on does part of its cookie authentication by comparing the REMOTE_ADDR header to your cookie, which works fine for browser interaction. But we have a few applets that communicate directly with the server. In mixed IPv4

  • Need to reinstall CS5.5 my serial number wont allow why?

    Need to reinstall CS5.5 my serial number wont allow why?

  • Re-package jinitiator with new certdb.txt

    I understand that with the Oracle Application Suite it is possible to repackage the jinitiator (jinit.exe) in order to include the new certdb.txt file to support SSL Forms. Is it possible to do the same with the Developer Server ? It would also help

  • Security Against ARP Spoofing

    Hi, I  am planning to create two DHCP servers for DHCP load balancing. Since  ARP Spoofing is one of major threats while configuring DHCP, I want to  know what are the ways to prevent ARP spoofing. Regards, Prasad Bait