All activity prices are manually entered (Message no. KP211 )
Dear All,
I have maintained Activity Rates through KP26. On Activity Master I have set Act. price indicator = 5.
Now when i am executing KSII it is giving me error message as :
All activity prices are manually entered
Message no. KP211
Diagnosis
All activity prices in controlling area FLGP, fiscal year 2011, and version 0 were determined and set as manually entered prices.
In actual price calculation, all plan activity prices, meaning those calculated automatically (activity price indicator 1 and 2) and those set manually (activity price indicator 3), are treated as if they have been set manually.
System Response
The SAP System cannot calculate activity prices automatically.
Processing is cancelled.
Procedure
Check your activity type planning. To calculate the activity price automatically, you must set the activity price indicator accordingly.
Proceed
Please let me know if I need to done any additional settings.
Br, Vivek Srivastava
Hi Vivek,
"The error message KP211 is display by the system due
to the SAP System cannot calculate activity prices automatically.
(can you review the settings in the system).
The procedure that you have to follow is to review transaction code
KP26 and your activity types.
From viewpoint of actual price iteration all plan prices are political
in the sense that 'prices does not change during actual price
iteration'. If all activity types have indicator 1 then everything
will be evaluated with plan price in actual. So actual price iteration
has nothing to compute because no price will be changed. You have to
set price indicator to 5 or 6 in actual price indicator for at least
one activity type in order to calculate the actual activity price.
When you change some activity type master data in transaction KL02,
these changes take effect in all relevant tables, BUT please notice
that the values of TARKZ, TARKZ_I etc. are only DEFAULT values for
activity planning and therefore ONLY READ ONCE when the relevant
planning set is created. Subsequent changes to the master data (default
value) take not effect in the planning sets. You have to change the
values in every single planning set manually."
You indicates that for the activity types you have set in the master data
actual price indicator to 5 (Actual price, automatically based on
on activity). But this is only a default value and can be overwritten
for example during planning.
Please see table COKL for cost center / activity type if have an empty field for
the actual price indicator. Thus the system only finds the plan price
indicators during price calculation and message KP 211 is justified if
you consider the following part of the long text:
In actual price calculation, all plan activity prices, meaning those
calculated automatically (activity price indicator 1 and 2) and
those set manually (activity price indicator 3), are treated as if they
have been set manually.
In order to run KSII as expected by you, you have to execute trans.
KP26 for the cost center and activity type using layout 1-204
(Activity Types: Indicators).
Here you can set the actual price indicator to 5.
Afterwards there should be no further problem with KSII.
I hope helps,
Regards,
MLM
Similar Messages
-
Activity prices maintained manually..Is KSII/MFN1 possible?
Hi Experts,
We have this scenario:
1. Activity prices are entered manually in KP26.
2. All Costs are maintained as Activity independent costs.
3. For Production Cost centers, some costs (primary costs) are Activity relevant and others not relevant at all for Activity.
4. No Splitting structure maintained so far.
Now, we are considering calculating Actual Activity prices through KSII and then MFN1 for revaluating Process orders.
I tried KSII in our test system, where I got the following error message # KP211. I even tried by maintaining the Actual Activity type category '01' and Actual price indicator '05' in AT master, but no luck.
Short Text
All activity prices are manually entered
Diagnosis
All activity prices in controlling area , fiscal year , and version were determined and set as manually entered prices.
In actual price calculation, all plan activity prices, meaning those calculated automatically (activity price indicator 1 and 2) and those set manually (activity price indicator 3), are treated as if they have been set manually.
System Response
The SAP System cannot calculate activity prices automatically.
Processing is cancelled.
Procedure
Check your activity type planning. To calculate the activity price automatically, you must set the activity price indicator accordingly.
Proceed
Questions:
1.Given our case, is it possible to do KSII/MFN1? If yes, what configuration and master setup is required?
2. What accounting/CO entry posted MFN1. Especially, want to know if value also posted to CO-PA?
Thanks much for your time.
SCHi SC,<br>
<br>
sorry for my delay.<br>
<br>
Yes, you can process KSII even if you maintained planned activity prices manually. For this, the Activity type master should be activity price indicator "5" for Actual, hoever it's defalt value for planning (KP26).<br>
Could you check activity planning value in your period as follows;<br>
<br>
1. Go to transaction KP26<br>
2. Selection screen;<br>
Set your version and year/period and also cost center/activity types in problem.<br>
Push Next Layout button (Ctrl + F8) and set layout 1-204 (named "Control indicators").<br>
3. Push "Overview screen" (F5)<br>
<br>
You can see plan price indicator and also ACTUAL price indicator, so you have to check if actual price indicator is not "7" or "Blank". If not, please set it with value "5" or "6".<br>
Hope you can understand what I wrote above, but if you have any queries, please feel free to ask me.<br>
<br><br>
Additonaly about your question regarding "activity independent" cost planning<br><br>
In F1 help document for field "Equivalence Numbers", there're useful description how activity-independent costs allocates activity type and activity prices calculates. If you do not use cost split or activity-depend planning, you can process activity price calculation by "Equivalence Numbers". it's easy-way to allocate cost to each activity type. you can see this field also in KP26 with layout 1-201 (sample)<br><br>
the following passage from field "Equivalence Numbers" F1 document.<br>
<br><br>
- Equivalence Numbers<br>
Weighting factor for distribution of activity-independent plan costs of a cost center onto the available activity types.<br><br>
- Use<br>
This field group serves to weight the activity types created in a cost center. After weighting, the activity-independent plan costs of a cost center are distributed onto the available activity types.<br><br>
-Procedure<br>
If you want to change or create equivalence numbers in planning, this field must be defined in the planning layout. If this field is not defined, any existing equivalence numbers will be displayed, but they cannot be changed.<br><br>
Examples<br>
You have planned the following activity types for cost center 4420:<br>
Activ. type Plan quantity Equiv. nr.<br>
<br>
FST 400 hrs 3<br>
REP 50 hrs 1<br>
RST 20 hrs 1<br>
<br>
Total: 5<br><br>
This cost center has planned activity-independent costs worth $20,000 . These costs are distributed according to activity price calculation onto the iteratively calculated activity prices (cost rates) of the activity types:<br>
ATyp Fixed costs Fixed portion of activ. price<br>
<br>
FST 20,000 X 3/5 = 12,000 $12,000 / 400 hrs = 30 $/hr<br>
REP 20,000 X 1/5 = 4,000 $4,000 / 50 hrs = 80 $/hr<br>
RST 20,000 X 1/5 = 4,000 $4,000 / 20 hrs = 200 $/hr<br><br>
Edited by: Takashi Kotani on Feb 9, 2010 7:55 PM -
Activity prices are not matching compare to previous year
Dear Sap Guru's,
Activity prices are not matching for the year 09 compare to 08.But standard cost estimation is correct.how it is possible.can you guide me how system calculates activity prices.
Ex: My client having business in egypt.Last year they started thier business at this time activity prices are maintained for INDO OH :13.81, Labur 0.44 per Min plan price 1.It is common for whole year -08.
Now I copied the same activity prices for this year through kp97 by selecting object currency for both plan and cost.under planning currency tab.
Activity prices are showing for IND oh is 17.14 ; instead of 13.81 and labour it is showing 0.55 instead of 0.44.
Pls guide me.
Regards
KUMAR.Hi,
guess you are using a controlling area currency (A) thats different from company code currency (B).
First check if the prerequisites within KP97 / button "planning currencies" are met when ticking "object currency" and using the F1-help especially the point
"It only makes sense to activate this indicator if you have activated all
currencies
1. when copying: in the source and target versions".
Whatever the reason is, your KP97 copy did the following thing:
For each CO area and plan version there are settings for each fiscal year to be made (IMG: Controlling / General Controlling / Organization / maintain versions, mark the relevant version choose "Controlling area settings", mark it again and choose "settings for ecah fiscal year".
Compare your 2 fiscal years, which exchange rate type (can be different, normally its "P") and value date (its often the first day of the new FY) is used?
If you have a difference in minimum one of the mentioned settings in CO version you might have different act. prices in comp. code currency.
Your KP97 process copied the values in controlling area currency (A) and converted this numbers to comp. code currency (B) based on your CO-version settings.
Best regards, Christian -
I have just rceived an upgrade to an iPhone 3GS. Now, when I visit the Store all the prices are in US dollars, not a big problem but I cannot edit my card details or contact to a UK address. I cannot see how to change this.
Hi Roger
Thank you for your reply.
My original feed is: http://casa-egypt.com/feed/
However, because I modified the feed http://feeds.feedburner.com/imananddinasbroadcast and nothing changed, I redirected it to another feed and then I deleted this feed.
Is there any way to change the feed in itunes? The only feed I have now is http://feeds.feedburner.com/CasaEgyptStation
I tried to restore the feed http://feeds.feedburner.com/imananddinasbroadcast but feedburner refused.
I know that I missed things up but I still have hope in working things out.
Thanks is advance.
Dina
Message was edited by: dinadik -
Does anyone know how to update OSX Mountain Lion 10.8.1. to 10.8.2. on a late 2012 Mac mini. All I get are 'not compatible' messages even using supplementary updates etc?
It appears that many of the problems with the HDMI are the "monitors" that are being used. Samsung and Vizeo both DO NOT support a computer input on HDMI only VGA. There probably are others, manuals must be read to confirm compatability.
I strongly believe that the reason the 10.8.2 update was pulled is due to the fact (it happened to me) that the new Disk Utility creates a Fusion drive if aftermarket SSDs are added to the system. I think Apple wants this propriatary Fusion Drive to be something you buy from them not a "homebrew" for lots less money. -
Windows Live Hotmail: every time I log on to this site for my emails, I have to manually type in my password, instead of Firefox automatically doing it.The tools box for saved passwords shows the right password in the list of saved passwords, so why is this particular password not entered automatically? All other saved passwords are entered automatically in the appropriate website logins. Puzzling!
Are you referring to the SAME computer/login?
If not, he likely has auto-complete (or similar) enabled and you probably do not. -
KSII activity prices not calculation (actual)
Hi
During Actual Price calculation KSII following is error message :
All activity prices are manually entered
Message no. KP211
Diagnosis
All activity prices in controlling area HGC, fiscal year 2011, and version 0 were determined and set as manually entered prices.
In actual price calculation, all plan activity prices, meaning those calculated automatically (activity price indicator 1 and 2) and those set manually (activity price indicator 3), are treated as if they have been set manually.
System Response
The SAP System cannot calculate activity prices automatically.
Processing is cancelled.
Procedure
Check your activity type planning. To calculate the activity price automatically, you must set the activity price indicator accordingly.
Regards
ImdadHi Imdad
Go to KL02 and set your Actual Price Indicator so that it allows to calculate Actual Price through system
There are 2 such fields - Plan Price Indicator and Actual Price Indicator... I think you have presently chosen MANUAL price indicator
Regards
Ajay M -
Hi, This is my first time I hope someone can help.
I am working with numbers and I have a large number of products in one column and the relevent prices in another. All the prices are different and I want to increase the price of everything by 5% or 10% etc. Is this possible?
Thanks in advance
Stiffy123Ad a new, temporary column (or one you can hide when not using). Let's say the current Prices are in column C and the new column is D.
you can inflate the prices in column C by 5% by entering the formula in the first cell of column D as:
=C2*105%
likes this:
to fill down, select D2, then copy, then select the D3 thru the end of the column, then paste. Now select C2 thru the end of column C, now paste over the existing values using the menu item "Edit > Paste Values"
you can now hide column D until you need to use it again. -
Planning activity price in various currency
Hi,
I have controlling area with currency EUR and two company code linked to it:
Company code A with currency EUR
Company code B with currency MXN
Is there any way to plan activity price in USD?
Thanks in advance
RegardsHi ,
THere are 3 currencies which are available in CO. One is the CO Area currency ( the currency maintained in the CO Area ) , Second is the Object currency ( the currency maintained in the Object , if it is a Cost Center , then the Object currency will be the Company code currency to which the CC belongs to ) and Third is the Transaction currency ( the currency in which a transaction is posted , be it Plan transaction or Actual transactions ) .
You can enter cost element planning using any of those currencies ( by creating user defined layouts if std layouts do not suffice requirements ).
Activity output has to be planned in terms of quantities in Cost Centers.
Activity price is to be computed automatically in the system ( recommended ) . Activity prices are always maintained in only two currencies , Object currency and Co Area currency. All activity transactions will happen using the Object currency so that the absorption on Cost Centers is always proper.
We cannot have activity prices maintained in transaction currencies. Is there a real justification and a business reason to have the price to be maintained in USD ? Please let me know.
Regards,
Venkat. -
CK11n with activity prices from different plan versions
Hello,
We are looking for a simple & practical way to calculate a standard cost estimate for a material using activity prices from different CO plan version.
In the valuation variant of the costing variant the CO plan version is determined from where the activity prices are taken, eg version 0
So, we want to cost the same material using the activity prices of a different plan version, eg 90, or 91 ... but without using a different costing variant per CO plan version(so without having to create/customize a separate costing variant per CO plan version)
Is this possible?
Can we use costing versions in this respect?
Many thanks
AlainHi,
Thanks for quick feedback ... but how do you assign this valuation variant in the costing version... ?
Can you enter is in CK11n? or what transaction needs to be customized?
Thanks, Alain -
Synced phone for the first time, and all my contacts are gone. Please help
I had to upgrade the iOS to 5. And all of the contacts are gone. Is there a way to recover them?
How did you get the contacts loaded onto the iPhone in the first place?
If you used iTunes that would imply the "source" of contacts was either on your computer (e.g. Outlook) or perhaps through a one-time upload from an e-mail service like GMail. In either case, your contacts should (might) still be where they were when you originally put them onto your iPhone.
If all your contacts were manually entered into the iPhone, then you're out of luck since they are not backed up, unless you set iCloud up to sync your contacts (in which case they'd still be in iCloud). -
Lost all contact info. All my Aps are there but all the data/progress is missing. When I plug my iphone into the usb fto synch up with my itunes on the computer a message comes up and says "enter the password to unlock your iphone backup file". This is very frustrating
I suggest trying the update again after an hour or two. Sometimes, the notice that an update is available comes an hour or two before the developers actually sends the revised app out to be downloaded.
-
Import is not available all other actions are active but not import help?
Import is not available all other actions are active but not import help? I wish to import bookmarks from internet explorer, I am using windows 7
Make sure that you do not run Firefox in permanent Private Browsing mode.
*https://support.mozilla.com/kb/Private+Browsing
*You enter Private Browsing mode if you select: Tools > Options > Privacy > History: Firefox will: "Never Remember History"
*To see all History and Cookie settings, choose: Tools > Options > Privacy, choose the setting <b>Firefox will: Use custom settings for history</b>
* Deselect: [ ] "Permanent Private Browsing mode" -
Broadcast message to all active sessions
All,
We have regular nightly restarts for our BO Enterprise ( SIA and tomcat) XI 3.1 SP2 - and it unfortunately is rather abrupt and some-times some users who are working late end up losing some of their work.
I was wondering if there is a way to broadcast a warning message to all active infoview sessions before the system goes down? Can anyone suggest some ideas on how this can be done?
RegardsHi,
There's no way within the BOE system that I can think of, but here's a possibility.
All actions essentially go through your application server so you could parse the last 30 or so minutes of the application servers access logs to get the IP addresses of the clients. From there, you could use a net send or some other kind of utility to let those users know that the system is going offline.
either that or your application server may have a way of sending a message to the client browsers that have open sessions.
Thanks
Jonathan -
I keep getting an error message while trying to setup my imap Gmail and Aol accounts on my new ipad air. The error says user name or password is incorrect but I know for a fact they are correctly entered. How do I correct this?
Hi Allan, thanks for that. I've already set up a log in for my wife and that is all working fine. The problem is that when she logs in and opens iTunes and trys to associate her library with her iTunes account she gets the error message "This computer is already associated with another iTunes account". Whilst this is true, the computer is associated with my iTunes account under my separate log in, which should have nothing to do with hers. If she transfers the association to her account it will lock me out of my content on my log in for 90 days - I'm trying to work out how to associate each of the log in accounts with a separate iTunes account so we can access our music independently of one another without locking each other out. Hope that makes sense!
Maybe you are looking for
-
Function module to find out DATA BASE size, free space, used size
Is there any function module to find out DATA BASE , free space, used size FM that gives all the details of the Date base what data base, what is the size, free space, used space etc... instead of writing case by case for each data base. based on CA
-
Touchpad wont scroll after healthcheck on Equium A80
hello all, my problem is after having a pc world health check done on my A80 i am no longer able to scroll using the touchpad, this happened last year as well and the only way i got it back was to go back to a time when it was scrolling, i mentioned
-
I am trying to view my pay stubs online but nothing happens when I click on the link. Does anyone know why, I never had a problem viewing them with my pc?
-
Maxl script start & Stop application
Hello all- Is there a way to start and stop the application via MAXL script? What command should i use to acheive this? Thanks
-
Why should we using ABAP code in RSQ02
Hi, I want to know why should we using ABAP cobe in RSQ02 , while we creating the infoset we writing code using extras icon . with out abap code we can't creat infoset query in SAPBW? Regards, Goodyear.