hi to all,
i would just like to ask if its possible for a standard network to be assigned to several WBS elements? this is because i have a Standard WBS structure with elements having similar activities, i wonder if i could just create a single network then assign them to SEVERAL WBS elements and not just one.
Hi,
To assign the standard network Activities to multiple standard WBS elements please follow the procedure below:
1. Go to Tcode :CN02 (If the network is already created with CN01 or else create with Tcode CN01)
2. Select the Network in question.
3. hit F5, this will take you to the standard network Header.
Assign the WBS Element where this network header should be asisgned.
4. Hit Shift+F1, this will take you to the screen where internal, external activities can be entered. Please select the relevent tab. And enter all the activities.
5. By default all the activities are assigned to the WBS element mentioned in the Network header, this can be seen by scrolling little right in the same screen under the column standard WBS Element.
6. Pick the column Standard WBS element and drop it next to Operation short text.
7. Now identify the activities to which the different WBS elements need to be assigned. Either select them from the list or you may refer to Tcode. CJ93.
Hope it is clear now.
Reward points if found useful.
Similar Messages
-
Attach Network to a WBS Element
Hi,
I have created a network having activity and its milestone using BAPI bapi_network_maintain, and a project and its wbs elements using bapi_project_maintain. Now i've to attach the network to the wbs element using a bapi.How to achieve this??I dont know which version you are using. But, it is there since release 4.0A. Go to t.code BAPI > click on Alahabetical tab ? Network > Maintain > INetwork Update. that is BAPI_NETWORK_UPDATE
-
Assignment of networks / activities and WBS elements
hi experts,
I have some basic doubts... can any ony clarify these:
1.can a WBS element be assigned to several Projects.
2. can a network be assigned to several WBS elements.
3. can an activity be assigned to several networks
4. can an activity element be assigned to several network activities.
thanking in advance.
regards,
priyanka
Edited by: priyanka on Jun 29, 2008 10:54 PMHi Priyanka,
Yes, Iam sure that a single network can be assigned to more than 1 WBS at a same time.
A WBS can be assigned several activities even different networks also if required, but an activity can be assigned to one WBS element only. Once activities are assigned to WBS elements, you can exchange data between activities and networks. For example activities can inherit statuses from the WBS elements they are assigned to. Conversely you can total up project activity dates to WBS elements or can check funds allotted to activities against WBS.
A single or several networks can be used in the project structure, to map individual aspects of the project such as activities that are linked to each other via relationships. The relationships between two activities define the logical sequence of the activities (predecessor u2013 successor relationship) as well as their time dependencies. Activities of different networks can also be linked to one another. Advantage of network technique is that, system can automatically determine planned dates for each activity and entire network on the basis of duration of individual activities and their chronological sequence.
Priyanka, I hope this may clear your doubt . .
reward points required please . . .
Regards,
Dhruv Kumar Malhotra -
Standard network assigning various WBS Elements
Hi,
I am using Standard network and Stand WBS Element for creating actual project.
There are Std WBS Elements, using the same Standard network. As i know, we can assign Std WBS Element in Std network. How can i make it using same std network for various Std wbs element to create actual project as Std network is same for most of the WBS Elements.
I donot want to copy Std network for actual project once we create copying Std Project in CJ20N.
Regards
N.Rajucreate more standard wbs - there is no other way
-
Hello ABAPers,
I have been using BAPI_PROJECT_MAINTAIN to create Project and WBS elements and I have done them without any errors.
Now I need help on how to create network activities.
Can anyone share on how to pass data to I_NETWORK table and I_ACTIVITY table and a brief description on what they are ?
Thanks in advance,
KiranHi Kiran,
Do the following steps
1.pass the following to i_method_project
method_project-refnumber = lv_refnum.
method_project-objecttype = 'NETWORK-ACTIVITY'.
method_project-method = 'UPDATE'.
concatenate aufnr(network nr) vornr(activity) into method_project-objectkey.
2.Into i_activity
activity-network = aufnr.
activity-activity = vornr.
3.i_activity_update
activity_update-network = 'X'.
activity_update-activity = 'X'.
It should work.If not let me know.
Rgds,
K.S. -
1 project definition with several wbs elements or several project definitin
Hello
I need projects as account assignment elements in CO (when entering vendor invoices for costs). Should I have 1 project definition with all projects /wbs elements underneath, or should I have 1 project definition uniquely defined for each project/wbs element? Some projects are not settled to assets und construction, some projects are settled to assets und construction.
kind regards
ArjanArjan
I don't think you can have Projects as account assignment objects. You can have WBS element as account assignment object.
One alternative I can suggest, if you want to see project costs at higher level instead of breaking down the project into many WBS elements. Create a project with one WBS element only and use that WBS element as account assignment object.
It is only possible to have a project with one or more WBS elements. I don't think you can define projects within projects.
letus put it this way assume WBS elements are projects within a project. But make sure all the WBS elements are related to one project
Hope you are clear now.
Thanks
Prasad -
Mail on when attaching BOM to particular Project/WBS element
Hi gurus,
I have following requirement,
1. Design department attaching a Bill of Material in particular Project / WBS. To convey this activity to other departments (i.e. Procurement / Sales / Project / Production Department), they need an system generated email/message.
2. Some time due to changes in Customer requirement, Design department will add/change/delete the attached material components in particular Project / WBS. In such changes Client need an Email/message to generated informing about such changes to respective departments.
Please help me with proper documentation.
Thank &Check in SWEL whether any event is getting triggered if not you can use this following Business Object.
Check this two Business Object
BUS2054 Work breakdown structure
BUS2054001 Extended WBS in Plug-In
You can also go for user Exit and status management to trigger the workflow,
Thanks
Arghadip -
How to attaching the documents to WBS element in projects .
Hi Friends,
Can any one explain me how to attaching the documents in project WBS element. We have u201CDMSu201D server. But I donu2019t know the process. Please explain me step by step the entire process of attaching documents to WBS elements in project.
Regards,
Hari KrishanHi...
Im adding to Expert..Venkats reply.
Plz see this link
http://help.sap.com/saphelp_45b/helpdata/en/95/5fdf348840ee64e10000009b38f83b/frameset.htm
Regards
Chandra -
CJ20N: handle Z table's related to project and wbs element
Hi there,
The requirement is to handle Z table for project and wbs element.
Example:
ZTAB1 has fields: pspnr | field1 | field2 (for projects)
ZTAB2 has fields: pspnr | field3 | field4 (for wbs element)
I found an enhancement that can read z table into internal table, i read it into screen and no problem.
I use it for wbs element too.
The problem is when the project has several wbs element's in tree, and the user navigate and change them.
I can't control the data in internal tables, since the user is swithcing.
How does the standard sap control the memory from each wbs element and project?
How can i read and save it separatelly?
Thanks in advance,
Edited by: orgasmics on Nov 22, 2010 9:37 PMHi,
try table <b>jest</b> with key = prps-objnr
Andreas -
Not allowing to create wbs element
Hi Experts,
It would be really kind of you to Help me out of the situation,
Iam trying to Add one more wbs element .The system was throwing error.
and Iwant to consider activity dates at the time of caliculating wbs date How to do this.
Thanks
Athidi.Hi Dear ,
Iam getting Error::
"Several WBS elements on level 1 not allowed
you cannot save the wbs if there are several wbs elements at level 1."
Thanks,
Atidi -
Copy partner function from sales order to WBS element
Hello
Does someone know if it is possible to copy the partner function and its assignment from the sales order to the WBS element?
In our project, we create sales order with article having a strategy group (85) view MRP3. Thanks to that a network and a WBS element is created in background based on template. In the template a partner determination procedure is maintained => partner tab in the WBS element is displayed (CJ20N) but the partners maintained in the sales order are not populated.
Is something missing in the customizing?
Is it possible to do it in standard?
Kind regards
ChrisHello Tison.
I guess you have the Project created with a BAPI in your system in background. As far as I have seen I'd try the following in ABAP to create Partners in the Project Definition: BAPI_BUS2001_PARTNER_CREATE_M or the corresponding method ProjectDefinitionPI.PartnerCreateMultiple. This should happen in background when the Project is created also.
Best regards.
Jens Schmid -
Project/WBS element documents - in CJ20N
Hello everybody,
I have a requirement to implement documents into PS module.
The tasks are:
1) attach document to proj. definitioon/wbs element
2) select the right document from list of templates
3) automatically fill in the data
4) possibility od manual change - mainly in CJ20N
5) verisons & statuses
I have in my mind three possible solutions, but as I've never done that before, I can't decide which one will satisfy my needs.
a) Documents assigned to WBS element (cv01n can create such a document - I don't know how to maintein them)
b) Somehow connect documents from Business document navigator (OAOR transaction)
c) Somehow connect Smartforms to definition/wbs element
Can anyone give me an overview and/or the way how to accomplish this task?
Thanks for any suggestions.
PetrHi, Thanks for your reply.
Two questions:
1) How do I connect it to the CJ20N (project Builder) to be able to change the document over there
2) Can I put there fields of the generated document, which I must fill manually (keyboard) - because the information can't be retrieved from the system
Thanks
Petr -
Internal processing Vs external processing with in the networks under a WBS
Dear Gurus,
please give an over view about internal processing Vs external processing with in the networks under a WBS element ,
is there any different process for creating reservatios & PRs in both the above ?
rgdsI think for internal processing the procurement indicator willbe 140 (when PR is not required) & for external processing the procurement indicator willbe 130 (when PR is required)
Regards,
Indranil -
Down payment request concept, Network or WBS element is mandatory?
Dear All,
To use down payment request concept, Network or WBS element is mandatory? And without milestone billing can't use down payment?
Regards,
Srikanthrajdear
it is not mandatory to have the Network or WBS for the billing plan .
we will use Billing plan manually in the sales order with relevent Billing rule 4 /5 for milestone.
regards -
How to view history status of a Network activity of a WBS element
Hi,
Which transaction can I use to view history of a Network Activity on a WBS element? I want to know when were changes made on an activity, e.g. when it was REL or TECO etc, and by whom.
Thanks.
PS_PS01YOu can get the same in all the PS Transaction where you can get the disply of user & system status. The prerequisite as Ahmed Pointed out you must have ticked on change document and atleast ordstatchange and opstatchange ticket ( for the ordertype and Plant combination )
If the same is done than you can check as below,
check in CJ20n > Click on any of activity> click on Blue ( Status Icon )>Extra>Change Document -->All.
System will disply the status( User & System ) change history of that activity.
With Regards
Nitin P.
Maybe you are looking for
-
Ipod touch's battery won't charge... see red battery
My ipod touch won't charge or turn on. I have tried charging it for more then 10 hours but it still won't charge. All i see is the red battery sign. I have the right charger and i plug it into the wall. Any help?
-
Lync login issue with one domain but started working when domain is changed.
we have two domains in lync 2013 infra.i have enabled user id with one domain but its not allowing user to login.If we change user id to other domain it start working. it seems user id already existed somewhere in lync or active directory database. c
-
Web service client stubs generation
Hi, I try to generated model for WebDynpro application based on Web service (deprecated). WSDL file is valid. Stub classes generation is completed with compilation error. I found that the generator builds strange method for CMapLayerField complex typ
-
IMac Hangs at loading screen or loads into os but crashes alot
I have had my iMac for 7 months now. This is the 1st problem I have had. Sometimes it will hang on the loading screen with the apple logo and the spinning cursor. Sometime's it would load into the OS but once I start doing anything on it like using f
-
I am writing my first book--fiction no graphics. What template works a best for this?
I am writing a fiction book, no graphics. What template works best with this? Is ibooks author the best option?