Blocked indicator in purcahse order workflow sap

hi colleagues
I have a purc.order with status blocked at release indicator
I don´t know why is 'blocked , and not released or rejected
the release code says sap workflow
what should I do?
thanks

Hi........
I think you have kept untiked to PO Approved in Administration> System Initialization> Document Setting Per Tab--> Purchase Order.
Put the Purchase Order Approved Ticked........
Regards,
Rahul

Similar Messages

  • How to creat deadlock for the purchase order in SAP Workflow

    How to creat deadlock for the purchase order in SAP Workflow

    Hi Ben,
    Are you using FM "CONVERT_DATE_TO_EXTERNAL" before passing delivery date?  If not, use FM like this, before passing the date to BAPI_PO_CREATE1 and it might work
      DATA: vf_doc_date(10),
                 internal_date TYPE d.
         vf_doc_date = sy-datum.              "Document date.
         internal_date = vf_doc_date.
      CALL FUNCTION 'CONVERT_DATE_TO_EXTERNAL'
        EXPORTING
          date_internal            = internal_date
        IMPORTING
          date_external            = vf_doc_date
        EXCEPTIONS
          date_internal_is_invalid = 1
          OTHERS                   = 2.
    Regards,
    Vivek

  • Block Creation of Production order Unless released in Order.

    Hi Experts.
    we have a requirement where we want to block the creation of production order inless it is confirmed. Is there any User exit / or anyother indicator where i can define or configure so that the MRP run and also the Creation of the production order can be block for a sales order.
    Plz advice.
    Thanks in Advance
    Rishi

    Hi
    But Manually it does allow the user to create Production order .
    I want unless, Say the delivey block at item level is removed , User should not be allowed to create the production order for the relevant line item of the sales order.
    Any more suggestion
    Thanks
    Rishi

  • Steps to create a purchase order in SAP r/3

    Hi All,
        I need to create a purchase order in SAP R/3,I am very new to SAP R/3 just started using material managements module in R/3.Could any one please help me to know what all steps i need to take for creating a PO.Do i require some pre-requisite data in R/3?
    Waiting for your reply!
    Thanking you.
    Regards,
    Namrata.

    Trigger
    A purchase order needs to be created, and the vendor is known
    Business Process Description Overview
    A purchase order is a legal document issued by the buyer to the vendor to supply materials or service at the agreed price, terms and conditions. The Purchase Order forms the basis for all follow-on activities like Goods Receipt, Invoice Verification, etc. The Purchase Orders can be created directly by entering all the required data, copying already created purchase order, with reference to an RFQ/Contract or with reference to a PR.
    Purchase Order creation is possible only if sufficient budget allocation is there for the Fund Centers. It is not possible to create Purchase Orders for a Vendor who is blocked for procurement or not maintained in source list for that item. Also it is not possible to create PO for Quantity more than the PR quantity.
    All the price components which are to be paid to vendors and requires to be inventoried has to be included in PO.It is possible to add different vendors for delivery costs. The tax codes should be correctly maintained in PO for the purpose of Cenvat availment etc.
    The payment term defaulted from Vendor Master or RFQ has to be verified and changed if required.
    The incomplete Purchase Orders can be saved as HOLD document and later completed and saved thru Change PO menu
    Input - Required Fields     Field Value/Comments
    Vendor     Vendor number
    Purchasing Organization     1000
    Purchasing Group     Purchasing Group code
    Date     Purchase order date
    Account assignment category     Where costs will be allocated
    Delivery Date     Anticipated Delivery Date
    Plant     For which plant we are buying the material
    Output - Results     Comments
    Purchase order document     Can be changed, displayed or printed which can then be mailed to vendor
    Tips and Tricks
    The Purchase Orders can be created directly by entering all data required for creating PO or by copying another PO or with reference to RFQ/Contract/PR.To create a purchase order by copying existing document (PO/RFQ/PR), you can either select the desired document in the document overview   .and adopt it in the current purchase order in the right-hand area of the screen using the ADOPT button   .In addition you can drag it onto the shopping basket symbol   with the left-hand mouse button. 
    Click the Personal Settings button on the tool bar, this function is for default information for purchase order header data and also purchase order item data.  This will reduce the amount of redundancy in the data entry, i.e. plant, company code.
    One Purchase Order may be created for several purchase requisitions
    Procedural Steps
    1.1.     Access transaction by:
    Via Menus     Logistics èMaterials ManagementèPurchasingèPurchase OrderèCreateèVendor/Supplying Plant Known.
    Via Transaction Code     ME21N
    1.2.     Double-click   
    On screen “Create Purchase order”
    On screen select Domestic Purchase order in this screen . You can also select other document if you want to create other. Here drop down menu is available.
    Click   to enter the organization data.
    Screen will change in the header; enter data as given in the table below:
    Field Name     R/O/C     Description
    Purchasing Org.     R     Enter the purchasing organization code.
    Example: 1000
    Purch. Group     R     Enter the purchasing Group which is procuring the material
    Example: P01
    Company Code     R     Enter the company code under which above purchasing
    Organization is.
    Example: 1000
    After entering the organization data enter the vendor or material supplier in the field    here drop down is available.click   to see the drop down.
    Field Name     R/O/C     Description
    Search term     O     Text that describes the vendor in more detail.
    Example:     MICON
    Vendor     O     Description of the vendor.
    Example:     100008
    Click   .
    System displays all possible entries available as per data entered
    Restrict value range (1)   1 Entries found
    To select required Vendor Click   .
    Click   .
    Vendor selected
    Now go to   ,here the system will pick up the data automatically from the vendor master but if you want to chane the data you can change the data. Here drop down menu is available.
    Now go to   to mainatin the text.
    After maintaining the text if you want to see or change the vendor address click   and do the amendments.
    Now Go to   and click to enter the Items and other data as per the table given below:
    Field Name     R/O/C     Description
    Account Assignement     R     Key that identifies specific settlement receiver types such as cost centers, internal orders, work orders, asset accounts, or project WBS elements.Example: K
    drop down menu is available here.
    Item Cateogry     O     How the procurement of a material is controlled.
    Drop down menu is available here.Example: Standard
    Material     R     Here you will enter the material to be purchased from the
    Vendor.
    Here also drop down menu is available. Use the following
    to select the material. Example ZROH-DEMO
    In the figure above enter the search cretira for the material for example ZROH-DEMO and click
      . The follwing result will appear on the screen select the line item and click   to select
    the material.
    Short Text     R     Enter here short description about the material,if the text is not
    automatically picked up from the material master.
    PO Quantity     R     Enter here quantity to be ordered.
    Example 10
    Order unit     R     Here we enter the order unit’s of measurement.
    Here also drop down menu is available.
    Example : KG
    Category of delivery date     O     Here you can enter deleviery date format.
    Here also drop down menu is available.
    Example : Day format
    Delivery date     R     Enter the delivery date. You can use the calender provided by
    the system.
    Example : 28.02.2006
    Net price     R     Enter the net price of the material here
    Example : 1000 INR
    Material group     R     Enter the material group to which that material belongs.Here
    also drop down menu is available. This field is also automatic
    picked up field.
    Example : M10001
    Plant     R     Enter the plant code for which you are purchasing the material
    Here also drop down menu is available.
    Example : 1100
    Storage location     O     Here you will enter where the material is to be stored. Drop
    Down menu is available here.
    Example WH01
    Click Enter and system will give you message  
    You will now see the screen
    Field Name     R/O/C     Description
    Cost Centre     R     The purchase is done for which purpose. Here also drop down
    Menu is available.
    Example: 11050 for CDU/VDU /SGU OP
    G/L Account     R     G/L account from which payment will be done.
    It will be automatically be picked up from the material group
    You can change it also.
    Unloading Point     O     Specifies the point at which the material is to be unloaded.
    Recipient     O     Specifies the recipient for whom the material is destined.
    Click   to see and to change the Tax Code at item level.
    Select    to view the taxes applied on the line item.
    click   to go back to the previous screen .
    On the main screen in the same tab if you want to change the taxe select the tax code from the drop down available
    After selection again, Select    to view the taxes applied on the line item.
    If you want to add more conditions click   tab and enter the conditions from the drop down
    You can also maintain the text at item level by clicking   tab.
    After completeing this all click   to check wether here is any error in the purchase order , If there will not
                             ↓
    any error then on the screen following line will appear.
    If there will be some error the system will throw the message on the screen
    select the line item and click   to see the detail of the error.
    close this window now and goto main screen to rectify the error.
    After rectifying the error again click   to check wether here is any error in the purchase order.
    Now click   to save the purchase order, after clicking the button the following message will appear

  • MM Purchase order Workflow  links

    Dear friends,
            I was working on MM Purchase order workflows.
            Please specify Links for exploring MM workflows.
    thanks and Regards,

    Hi
    Standard Workflow for Purchase Order is WS20000075(Access it via PFTC_DIS Tcode). The business Object for Purchase order is BUS2012(access it via SWO1 Tcode).
    http://help.sap.com/saphelp_47x200/helpdata/en/75/ee153f55c811d189900000e8322d00/frameset.htm
    <b>Reward points if useful</b>

  • Activating conditions for Purchase Order workflows in EBP

    Dear SRMer's,
    I am facing the following problem:
    System Info :SRM Server 5.5, ECC 6.0
    Scenario 1:
    All start conditions for Purchase Order in SAP Business Workflow are activated.
    I created a direct procurement shopping cart (DP)  in SRM browser and ordered it, then I logged in as proffessional purchaser, changed the Price and processed the DP PO.
    When Ordering, the follow on Documents are created, but says the PO is waiting for approval.  When I check for this PO in the Backend R/3 system in the Me22n (Display PO changes), I don't see the PO.
    Scenario 2:
    All Start conditions for Purchase Order in SAP Business Workflow are de-activated
    I created  another direct procurement shopping cart (DP2)  in SRM browser and ordered it, then I logged in as proffessional purchaser, changed the Price and processed the DP2 PO (Status is held). 
    When Ordering, I get the Warning message, no workflow found, contact system administrator.
    Please advice what needs to be configured for the PO to be ordered successfully.
    Thanks in advance
    Raj

    Hi,
    In your scenario 1, if system is saying that there the PO has to be approved, it means that you have managed the user that will receive the workitem..
    Activating all PO WF is not a solution as in standard there are two many cases activated (amount, role, limit...)
    I propose you to first activate only the 0 step WF and to overwrite the code inside
    Just code that every PO modification should trigger O step WF thus it will be more simple to test it.
    Later on, if you want to implement more complex starting conditions, you just have to modify the WF content...
    Kind regards,
    Yann

  • "Delivery Completed" Indicator in Purchase Order

    Hi,
    While doing GR, we want to check the "Delivery Completed" on the Goods Receipt Screen if we are expecting no future receipt against the Purchase Order.
    On SDN & SAP Note, I got to know that we canu2019t tick the "Delivery Completed" Check Box while doing Goods Receipt.
    We have implemented the Release Strategy on the Purchase Order. To tick the "Delivery Completed" Check Box, we need to cancel the Release Strategy.
    Is there any other way (T Codes) to achieve the same?
    Regards,

    Even you flag Delivery Completed" Indicator in Purchase Order, system still allows GRN for open Qty.
    Use MEMASSPO trxn & Put Deletion indicator for the PO Line Item. So that you can not do GRN for the open Qty of PO line item.
    Check
    mass setting of delivery completed indicator

  • How to Make MRBR to show the Customised Payment Block Indicator (MIRO) ?

    Hi
    Currently, from what I know of, MRBR only showing Log Payment Block as follows:
    A     Automatically blocked due to existence of blocking reasons
    S     Stochastically blocked
    M     Manual payment block set in header - no blocking reasons
    W     Automatically blocked due to entry via Web Invoice
    However during the manual MIRO creation, I put in customised Payment Block G (Block due to XX) in the Payment Tab of MIRO. This G does not get shown up in MRBR.
    How to make it possible in MRBR as I have configured a few customised Payment Block such as G (Block due to XX) and H (Block due to YY).
    I would like MRBR to show up the exact Payment Block indicators as those in the MIRO.
    Please help.
    Thanks

    Hi Nick.
    I just found out that Payment Block Indicator shown in MIRO will appear in MRBR. The reason that it was not shown in MRBR because during MIRO creation, it was set BLANK and then user went to FB02 to change it with other customised Payment Block Value, thus when we run MRBR, it was showing blank under Payment Block column. Thus, we had to resort to LOG Payment Block which gave rise to this thread.
    Having understand the importance of how FB02 changing  payment block will affect MRBR, we have decided not to let user change the payment block in FB02.
    SAP note: 394370 has explained everything:
    "A document generated with MIRO was blocked for payment. You cancel the payment block from the vendor line item in the FI follow-up document. Transaction MRBR then displays the invoice document nevertheless. Why?
    The invoice document itself cannot be changed by changes to the follow-up documents; this is not programmed. Transaction MRBR therefore continues to display the document as blocked. If this document is released from an MM point of view, the FI follow-up document remains released. Thus the damage caused is restricted to unnecessary work by the user. SAP recommends that you only use the release transactions for releasing invoices."
    Thanks a lot!

  • RE: During MIRO payment block indicator piks up automatically

    Hi All,
    Can anyone tell me about this issue:
    My user is doing MIRO at that time Payment block indicator picks up automatically for some invoices randomly what could be the reason.
    1) there is price differences MIGO and MIRO the same
    Pleas let me know the possible reasons to check in my case.
    points will be assigned.

    Hi,
    When you enter an invoice, the system suggests the values that it expects an invoice to contain as a result of the purchase order or goods receipt. If the invoice item differs from the default values, you must determine the reason for the variance by contacting the purchasing or goods receiving department or the vendor.
    If a tolerance limit is exceeded, you receive a system message. You can post the invoice in the system, but it is automatically blocked for payment if an upper tolerance limit is exceeded.
    An invoice can be blocked for payment due to one of the following reasons:
    u2022     Variance in an Invoice Item
    u2022     Amount of an Invoice Item
    u2022     Stochastic Block
    u2022     Manual Block
    When an invoice is blocked, Vendor cannot be paid. Invoices can be blocked either automatically or manually. You can block an item by selecting the Ma (manual blocking reason) field in the item list.
    When you post an invoice, two things happen:
    u2022     The account postings resulting from the invoice are made.
    u2022     In the vendor line of the accounting document, the system enters an u201CRu201D in the field Payment block so that Financial Accounting cannot make payment for the invoice.
    I hope this will solve your doubt.
    Regards,
    Kapil

  • Removal of deletion indicator in Production order

    Hi,
    Can any one explain me how to remove the deletion indicator in production order.
    thanks and regards
    Murugesan

    As I know we have delition flag status and delition flag in the control data tab page.
    both are related, whenever you set the status as delition flag set, this indicator will come automatically, and visa versa. I am not sill clear which you are refering as delition indicator?
    Is it some thing different from what I am talking about?
    If so what is the significance of this indicator and why you are using this?
    Form dlition  inicator many of he fuctions can be blocked. Is there any function which can be blocked after delition indicator than delition flag indicator what I am refferring?

  • Block material for sales order entry in specific plants

    Hi Experts,
    I wanted to know if there is a simple way to block material from being ordered in a specific plant other than maintaining exclusions. My situation is one sales org, two plants (A & B). Order entry should be blocked at plant A and not B.
    I tried using the material Cross-distribution-chain material status on Sales org 1, but this blocks across all plants.
    I also tried Plant-Specific Material Status on purchasing view, this blocks the material only if it is being procured (non stock). This does not work for materials that does not require procurement. Setting the material to deletion status in MM06 at the plant level will only give a warning.
    Any ideas or suggestions on how to handle this?
    Thanks,
    Nanda

    Lakshmipathi,
      Thank you. But I don't want to entirely cut off the plant from the sales org. I just don't want to be able to create sales order for a few materials in a specific plant. Ex. Material A should not be allowed on sales orders in plant X but should be allowed in plant Y, both are assigned to the same sales org 1000.
    I did some research and found there is no standard way to handle this in SAP, so I decided to go with a user exit MV45AFZZ. By checking against plant specific status (MARC-MMSTA) and if the value is 'XX' then issue an error message.
    Thanks,
    Nanda

  • Maintenance order workflow (in plant maintenance module)

    Hi,
    I'm looking into implementing maintenance order workflow within PM module. Found the workflow ws2000021, but is this workflow integrated with enterprise portal. That means when a work order is created, can this work order be route to UWL (EP) of another supervisor for release and signoff, instead of going into IW32 and release the work order?
    Is any of the logisitics workflow(like Purchase order) available and can be used in the enterprise portal? Just like leave and overtime application in the HR module which are currently available for use in the portal.

    Hi,
    To get to know info about mySAP ERP 2004 - MM Workflows,please check in this link.
    http://help.sap.com/saphelp_erp2004/helpdata/en/1d/ea9d9c7aca11d194b70000e82dec10/frameset.htm
    Well, if there is a workflow that works with EP, you can find them in the above link itself.
    I dont think Workflows comes with BUSINESS PACK.
    Regards,
    <i><b>Raja Sekhar</b></i>

  • Blocking Quantity in Sales order

    Hi,
    We have a requirement to block Quantity in sales order.
    PP is not integrated with Sales order, its a MTO ( but actually client does not follow MTO in SAP)
    Once the production is completed for that sales order......he want to block the sales order quantity either manually or automatically ( they use a z transaction to declare production complete against sales order ) but this should not stop him doing delivery and billling.
    Please let me know how can we do this.
    Thanks
    Venkata Rama Reddy.K

    Hi,
    The Process goes this Way
    Sales order is created and confirmed ( by mail ) to PP that production should be started.
    PP completes the production and they update the qty against sales order number in a z transaction once production qty matches work order qty. the z transaction stops adding qty in this z t.code.
    What customer wants is once they update this ztransaction with complete Qty ( which equals sales order Qty) , the sales order item quantity should be locked automaticallly so that quantity can not be modified once this z transaction is completed.
    Hope this information provides clarity.
    Please suggest a solution.
    Thanks
    Venkata Rama Reddy.K

  • ME5A: blocking indicator and blocking text

    Hello SAP Guru,
    In ME5A, is it possible to add comments/texts directly for each purchase requisition, such as "not ready to convert", "ready to convert" etc? The requirement from business is that they want to have a PR report with indicator to state: if one PR is ok to convert or not. Since we have not set up PR release strategy, I found "blocking indicator" and "blocking text" in ME5A, but first need to go into each PR to block, then run ME5A to get these info.
    Many thanks in advance for your comments/advice and with best regards-
    Mengyu

    Hi Mengyu,
    ME5A is to List Display PR only. It is in read only mode. You cannot change anything directly form there.
    Thanks,
    Gordon

  • Deactivate WS20000339 - create standard order workflow

    Hi,
    I am facing an issue where in teh WS20000339 - create standard order workflow is applying a block on the customers which prevents me from changing the details of the customers. I want to deactivate this workflow in the system so that the block is not applied on the customer.
    Thanks,
    Prasy

    Hello,
    How does the workflow get started?
    regards
    Rick Bakker
    hanabi technology

Maybe you are looking for