Blocking MIRO when the stock is in Quality

Hi all,
We are using mySAP ECC 5.0.We have configured QM for Procurement.
when the materials is received through MIGO, stock is posted to Quality.At this stage, if i am doing the MIRO, system is allowing me to do.But system should not allow me to do this? Can some user exits be used for this?
Alos, based the quality's decision MIRO quantity should come. Suggest some user exit.
Thanks in advance,
Gowtaman

Hi Gowthaman,
The following BADI can be used in your case.INVOICE_UPDATE is the Interface name of the BADI.It provides the following methods ,
CHANGE_AT_SAVE
CHANGE_BEFORE_UPDATE
CHANGE_IN_UPDATE.
Do check out this BADI.
Regards,
Samson

Similar Messages

  • How to block Gr if the stock reaches the maximum limits

    Dear All,
    Is there any way so that the system will automatically Block the GR while doing MIGO when the stock of the given material has crossed the maximum limit.
    Regards
    Om Prakash Gupta

    Hi,
    If you want to restrcit any specific material stock quantity, it means some where you need to maintain the Stock limit for that purpose you will have create a Z table whene in you will maintain sthe maximumstock limit and then with the help of user exit in PO or MIGO you can validate it with the Z Table stock . Z table for stock quantity can consider stock incremental aginst each PO and GR .
    Take ABAPer's help
    Regards,
    Vikas

  • HT4259 I have been trying for hours to extend my Extreme Gen 5 network with an Express Gen 2.  But no matter what I do or try, it doesn't work.  What does happen is my internet gets block somehow when the Express looks like it's set up and 'green' - no in

    I have been trying for hours to extend my Extreme Gen 5 network with an Express Gen 2.  But no matter what I do or try, it doesn't work.  What does happen is my internet gets blocked somehow when the Express is online and looks like it's set up perfect and 'green' - but no internet connection for anything even though the Extreme is green and the modem is good.  Once I disconnect the Express, everything is good again.
    I've tried LAN, WAN, though a switch, direct connect, Extreme set to Extend the network, the Express set to be an extension.  Most of the time I get an error trying to update the Express.  But when it seems to be set up perfect, the entire house can't get to the internet.  Just when it looks right, it is so wrong.
    If anyone can give me exact steps (e.g., "...from the Base Station menu, select the Restore Default Setting option" vice "...just restore the defaults..."), I would greatly appreciate it.  I'm left to the conclusion that the Express is faulty.  I've been using Airport Utility 6.2 from Mountain Lion on one computer and Airport Utility 5.6.1 from Snow Leopard on another computer (the latter give more control while the former just want you to 'forget' the Express).

    I finally got it working.  I was trying to set it up ethernet.  My biggest mistake was when the new Express came on, I did not select 'Continue' - I went straight to manual thinking that I would get the most setup options in manual mode.  So everything I initially tried always resulted in 'wireless'.  Even when I would update or restore default settings, the Express would not completely restart. Or sometimes I would get an error. So most of the time I had to unplug it.  So when it came back up, none of my changes were retained. But there were a lot of times when everything was green and appeared to be fine. But anytime the ethernet cable was plugged in, no more internet.
    So here's the weird part.  When I finally tried 'continue' (vice manual), I would get 4 options.  One would be 'ethernet' extended.  So I would select it, it gave me green lights, all looked good, and still the same problem.  This is when I got frustrated.  I thought I had exhausted all possible combinations.
    But somehow when trying continue again after another restore, I only got 3 options.  One was the same ethernet extended option (can't remember what the missing 4th one was).  And this time it worked - it gave me the big green circle with the checkmark saying it was successful.  I don't know what I did different, but I know now that it won't work if 4 options come up to choose from.  It will work if only 3 options come up.  And success if only verified by the big checkmark.  Had anyone anywhere said the checkmark declaring success is validation, then maybe I wouldn't have gone down so many rabbit holes thinking it should have been successful.
    As for which Airport Utility I prefer, 6.2 looks nice, but it would just ignore the Express and would want me to 'forget' it and would not let me edit it.  Airport Utility 5.6.1 was the one that I ended up using the most and finally had success with.  It still strikes me as odd that there is no manually way to pick ethernet, it can only be choosen following a 'restore defaults', and only from the 3-option list (the 4-option list had the same ethernet choice, but it no worky).
    Thanks for the response.  I really do appreciate it.
    Aiport Extreme Gen5 - internet access and router
    Airport Express Gen2 - connected via ethernet, extending my wireless
    - configured while connect directly to the Extreme, but now on a switch (16-port hub)
    Using Airport 5.6.1
    1) Restore Defaults from Base Station menu
    2) Following restart, Select Continue
    3) Of the 3 option presented, select 'ethernet.... extend network...'
      - if 4 options are present, may not work
    4) Wait for the green circle with the big white checkmark.
    5) Connected Express to the switch where a cable went to other end of house - works.
    Dead-zone went from 2mbps to 24mbps.
    I probably spent 4 hours chasing my tail in anger.  The correct way took about 5 minutes total.
    Thanks again.

  • MRN9 How it will work when the stock is negative qty

    Hi,
    We have facing one problem while doing inventory valuation.
    when we running the program MRN9 it will determine the balance sheet value from comparition of lowest price then it will update.
    But the stock in negativeside like -1000kg qty and the NRV price is 50 and FIFO price is 60.
    When running the program it has determine lowest value.But in negative side it is showing the price as  -60000 is the lowest value. As a mathmedical it is correct. But when you see the other side (50000) compare with (60000)  the value (50000) is the lowest price.
    could you any one help to explain or any notes are available to rectify the issue.
    this is happening only for negative stock. Positive stock it is working fine.
    Thanks in advance.
    Regards
    Gopal

    Here are a couple of Adobe encoder activation links, maybe one of them is what you need:
    Adobe encoder activation
    Adobe MPEG Encoder activation
    And an offline product activation link: Offline Activation
    Cheers,
    Neale
    Insanity is hereditary, you get it from your children

  • I cannot display the block diagram when the VI is running

    It is not possible to show the block diagram while the VI is runs. The frontpannel remains on the screen. When the VI is started from the block diagram, the frontpannel pops up and stays  on the screen

    Are the VI Properties >> Window Appearance... set to dialog or modal? That could keep the front panel on top.
    Lynn

  • Linkage of inspection lot when the stock is posted to new material in UD.

    Dear QM Gurus,
        My client has the following requirement.
       The stock is sometimes posted to the new material whle Usage decision(Partially or completely)
        In this case the target  material has no linkage with the inspection lot of the material for which the Usage decision is done.
       The user has to manually create the inspection lot for the target material and record the same results once again for the record purpose.
       The requirement is to establish a link between the inspection lot original material and the target material  so that the additional step of creating the manual inspection lot and result recording  can be avoided.
      Is there any standard functionality through which I can link the inspection lot/result recorded to the target material or can it be acieved through some enhance ments.
      Please help.
      Regards
      Ankush

    Hi Ankush,
    I am not aware about the standard functionality for this link. But following work around may work for you. Possibly you may have to develop the ABAP report for this linkage. Try this if works.
    1.     When you do material to material transfer in QA11 it generates a movement in background with material document generation.
    2.     Pass the inspection lot through QAMB table and fetch all material documents
    3.     Pass these material documents in MSEG table and get the material
    4.     You may put several conditions for fetching these details.
    Best Regards,
    Anand Rao

  • Unable to restrict the Release of order when the Stocks are deficit.

    Hi gurus,
    i have a packing material for which the stocks are deficit when i checked in MMBE.
    While releasing the order the material is picking the stock from some where and is not restricting the Release of order. The same case is working fine with other materials as well.i.e when there is a deficit of stock then the release is Rejecting for all the materials except for this packing material.
    Thanks for your understanding.
    Naveen.A

    Hi,
    Please check the below mentioned points
    1.Material Master  MRP View : (View 2 or 3, i dont remember) You had maintained the proper Checking Group (Say 02)
    2. OPJJ: If you are using standard Checking Rule "PP" for the combination of the Checking Group and Checking Rule PP, make sure that scope is defined properly. Generally receipts from PR would be out of scope.
    3. OPJK : Make sure "you had NOT checked "No Check" for Material Availability.
    4.OPJK: The checking Rule is the right one (PP in Standard)
    5. OPJK : For the order type you use, the Plant  and business function 2combination check if you had set "3 -  No release if Parts are missing"  for the  field "Release Material"
    Thanks
    Bala

  • Reg.Initially post the stock in quality

    HI
    i want to post the stocks directly in quality.how its possible if i use MB1C-563 mvt.system
    shows error
    "Change the inspection stock of material FT1611R1 in QM only"
    Pl give me some ides to post the stock in quality
    thanks
    selva

    Hi
    In the materialmaster select quality management view for all the material which u want to send to quality Stock
    For raw material maintain inspection type=01
    for sfg and Fg select inspection type=03
    And inspection type 04 for final inspection
    Once you go GR for raw material it will automatically come under quality stock
    and when you confirm production order and do GR for Production order the material will automatically come under quality stock
    once material comes under quality stock
    carry out results recording and do the usage decision
    Regards,
    Raj

  • Stock lying in Quality from LQUA

    Hi All,
       How  do  i determine the  Stock lying in Quality/Returns/Blocked from LQUA  ....? I mean among  the below set of fields  which can give me Q- stock , Blocked , return stock etc (for WM)
    LQUA-BESTQ  =
    space   available stock
    Q     Stock in quality control
    R     Returns stock
    S     Blocked stock
        GESME
        VERME
        EINME
        AUSME
    Any other improvement tips ..
    Regards
    Jaman
    Message was edited by:
            ABAP Techie
    Message was edited by:
            ABAP Techie
    Message was edited by:
            ABAP Techie
    Message was edited by:
            ABAP Techie

    Hello ABAP techie,
    Do you want to use this information in Report or some business transaction? What you are trying to achieve with this. This will help us to give better input.
    Regards
    Arif Mansuri

  • Block UD saving, If stock posting is not done

    Dear Experts,
    My requirement is to block UD when a stock posting activity not completed. In standard setting, the system allows to save UD without stock posting completion.
    Is there any customization is possible to do this activity?
    So that, the system should not allow UD saving without stock posting completion.
    VRMP.

    Hi VRMP,
    Gajesh is guiding you in 100% correct way. Status Profile will work for you exactly as per your requirement.
    You will be in need to use the STD Profile "QM_L_001 - Inspection Lot Profile 1" will surely work for you. Herewith attaching some guiding links that are prepared to establish the control to prevent UD if RR is not done. Similarly look into for some business transaction that prevent UD before Stock posting.
    [Thread - 1 |Re: User Profile created to block the UD, if RR is not done.]
    [Thread - 2|Re: Result recording mandatory before UD]
    [Thread - 3|Re: How to prevent UD when Result Recording is not carried out]
    Or the at the other hand you can do it smarter way also.
    Make the Posting proposal for UD code in Back ground in QS51 for each UD code. By doing this if the user will perform UD and save, system will; perform the Stock posting in background automatically.
    Reagrds,
    Shyamal

  • Moving Stock out of Quality Inspection

    Hi Guys,
    I have a slight issue that I need help with.
    First, let me explain the situation.
    I have a client that wants to use a 3rd party for their Inventory postings. They DO NOT want SAP Quality to move stock. Currently they have an Interface in place that sends the Stock postings via EDI. They never had Quality Management in place until now.
    So, now when they do a MIGO Goods Receipt on a Purchase Order it generates an 01 type inspection lot. I have turned off the movement on the Usage Decision so that SAP can't move the stock out of Quality when they close the lot. They want the Interface to move the stock from Quality to Unrestricted. Currently it errors out and says "can't move stock need to use QM only"....
    My question is......Besides updating the Inspection Lot via QA12. Is there ANY configuration settings I can work with to fix this? or Allow the "321" movement?
    Thanks so much

    No.  Stock must be moved via the inspection lot.  For a third party interface like that you'll have probably look at building something using the FM used by the external interfaces to SAP QM such as LIMS.
    This PDF file might help you.
    http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/1ebb1361-0b01-0010-56aa-c780c5446963?quicklink=index&overridelayout=true
    FF

  • Settling production variances when the price control of the material is "V

    Hi,
    Scenario: 1) Materials are maintained at moving average price.
                    2) Production variances need to settle to material and MAP need to be adjusted.
    Issue:  When the closing stock of the material is less than the negative variance need to be settled from the production order   the system is giving the message "Moving average price for material is negative"
    Questions: 1) What is the solution for settlement of negative variance to material when there is no stock?
                       2) Is there is any way to settle these variances to price difference account only when the stock is not available. if stock is available the variance has to adjust the stock, if not settle to the price difference account. Is there anys standard settling for this?
    Advance thanks for your help
    Regards
    Koteswararao Padarti

    Hi Rao
    You should never have Price Control V for In House made material...
    That will ruin your inventory valuation forever.. Consider the eg below if your price control is V
    1. Your moving price in mat master is 100 USD
    2. You Mfr on Jan 1 @ Actual cost = 110 in Prod order and Qty = 1.
    Upon GR, GR will happen @ 100 and at period end if Qty is lying in stock, 10 variance will also be inventorized
    BUT, now consider this
    1. 1. Your moving price in mat master is 100 USD
    2. You Mfr on Jan 1 @ Actual cost = 110 in Prod order and Qty = 1.
    Upon GR, GR will happen @ 100 and variance lying is 10 in prod order
    3. You Mfr on Jan 10 @ Actual cost = 110 in Prod order and Qty = 1.
    Upon GR, GR will happen @ 100 and variance lying is 10 in prod order
    4. On jan 15, you consume Qty 1 and qty lying in stock is 1
    5. In period end, when you do settlement, following will happen
    a. For prod order 1: Qty Mfd 1 and Qty lying in stock 1 - Result: variance 10 will be inventorized.
    Mvg Avg price will shoot upto 110
    b. For prod order 2: Qty Mfd 1 and Qty lying in stock 1 - Result: variance 10 will be inventorized.
    Mvg Avg price (MAP) will shoot upto 120
    System wont check whether the qty lying in stock pertains to prod order 1 or 2... It will simply check if the Qty of prod order matches with qty lying in stock. hence, it will keep on inventorizing variance in this case.... and your MAP will touch the sky
    Regards
    Ajay M

  • HOWTO: Avoid go to detail block without fullfill the master block?

    Hi:
    I have a master detail form with 2 blocks. When the user open the form the focus is on the first text item (required = yes) of the master block. If the user tries to get out of that item with keyboard (tab or enter), it gets the correct message saying that the item is required and must be filled. But the problem starts when the user click with the mouse on another item of the detail block. Here, I will have 8 or 9 messages saying that is impossible to create records without a master record. This is really annoying. This message has no ID (FRM-XXXXX), and I really must get a way to forbide users to go to the detail block without filling required items in the master.
    Anyone?
    Best Regards
    Joao

    Hello,
    if there is a relation between the two blocks double click on that rel.and mark the check box property:prevent Masterless operation try this option and tell me what's ur feed back..?
    Regards,
    Abdetu..

  • Cannot save billing, when the sales price is not maintained in VK11

    Dear Expert,
    I want to block billing when the sales price is not maintained in VK11?
    How to block it?
    Thanks
    SAP Support

    Hi,
    We cannot have incompletion procedure at the billing document level.It will be happened at the sales order level.
    But we can control this one either by using the user exit or any ABAP code.
    Goto the T.Code "V/06".Select your condition type.Details.Maintain the value as "A" for the field "Manual entries".
    Goto the T.Code "V/08".Select your pricing procedure.Details.
    Maintain this condition type as required.
    Save.
    This ensures that it should fetch values for this condition type automatically i.e. from condition record.Else it will throw an error message.
    Regards,
    Krishna.

  • Stock Type X Quality Inspection in Production Orders

    Hello,
    I have the material 123EDFXXX that the Production order has set the Stock Type =X (Quality Inspection)...
    We don´t know how was that set!! since that material has not active the QM Views in the material master.
    There is another master data (prod version, route) or something else that is coping that value??

    Hi Marco,
    1.Pl check if QM was active before the creation of order.If so you need to delete all Material and accounting documents
    2. Check in the work scheduling view in material master if the inspection stock is active box is active.then this could be the reason.
    Regards
    George