BOM change with history requirement

hello,
requirement: CS02  must input Change Number
configuration:OS25: BOM Usage-BOM status -history requirement flag selected
issue: CS02 change BOM, only warning message: Enter change number -BOM has history requirement
how to meet my demand? any other configuration?
pls give me some help, thanks
best regards
lee

Hello check this SPRO settings ;
Engineering Change Management Setup
This are the basic IMG settings in order to used the engineering change management
features.
x refers to a tick.
First setup the control data in OS54.
Revision sections
Fields :-
Revision level active            x
Ext. revision level              x
Higher revision level            x
Object Management Record sections
Fields :-
Object maintenance               x
Assign alternative date          x
Overide value/assignment date sections
Fields :-
Only with leading change mst.    x
Setting the Revision level active is to activate the engineering change management for
material master.  If you do not want the engineering change management for materials,
remove the tick.
With a tick in "Higher revision level", the new revision level has to be always higher
than the old revision.
Secondly, setup the external number range in OS53.
If you use the internal number range, then remove the external number range.
Third, define the status for the change master records in transaction SM30 - V_T419S.
Change No.     Chg        Date Chg     Dist. Lock      Description
Status         Poss
  1             x            x             ' '         Active
  2            ' '          ' '            ' '         Inactive
  3            ' '          ' '             x          Locked
Fourth, define modification parameters for the BOM in OS27.
Fields :-
BOM Validty Maint.               x
EC Management Active             x
History Requirement             ' '
Unit Piece                      PC
The rest of the fields are blank.
If the History Requirement is tick, every time during creation of the BOM, SAP will
prompt your for an ECN number as is compulsory.
Lastly, define fields selection for routing in OP5A.
PP task lists: initial screen -> Change number -> Transaction code -> Tick Req.
Setting the Transaction code fields Required indicate that you have make the ECN number
compulsory when changing the routing.
Finally, do a test by making changes to the Material Master, BOM and Routing.
Regards,
jaya Vimal

Similar Messages

  • Authorization to change BOM with history requirements

    Hi Techies,
    I m facing an issue now with respect to authorisation of changing BOM with history requirements. Our quality system was a copy from a production server which was used for CRM before. Usually in SAP when we change a BOM with a change number we cant again change it back without a change number.
    In our case it is not providing an error but it is providing a warning. Now my requirement is to change this warning message to error message. So that people wont change BOM without a change number.
    I tried to enter the transaction SU24 and found the authorizaton C_STUE_NOH with proposal YS. Then i tried to change the filed value to ' ' (NO) and saved it.
    But still i m not able to change the warning message to error message.
    Is there any other setting i need to carry out for this.
    Please help me with this issue.
    Thanking you in advance.
    Regards,
    Kris.S

    Dear Krishu,
    Below has been mentioned in OSS note: 420878. Check once again you have save as NO. Then go to tcode SU03 Object Class PP/ C_STUE_ROH
    Summary
    Symptom
    In Customizing of the BOM, the history requirement is set or a BOM requires a history. Despite this, it is possible to process BOMS without engineering change management. The system only processes a warning message (29 045) which can be skipped.
    Additional key words
    CS02, change number, OS27, W045(29)
    Cause and prerequisites
    Authorization profile
    Solution
    Check the authorization profile of the respective user.
    Example:
             C_STUE_NOH <OBJ>
                &_SAP_ALL    <AUT>
                    NOHIS      <FLD>
    would have the authorization to process BOMs requiring history without a change number. In this case, if you change '*' to ' ' in NOHIS, you will no longer receive a warning, but rather an error message.
    Regards / US

  • BOM changes(Not creation) with EC Number

    Hi
    I want to make the ECN as mandatory while changing the BOM,not for creation.
    I tried by setting OS27,OS25 settings for BOM. I tried BOM creation with status 3(With history requirement). System gives only warning message,not the error message.(Message no. 29045)
    I tried to make the Change number field as mandatory,but it applies it to CS01 & CS02. I want only in CS02.
    Plse help me out if any knows the soultion.

    Dear Sudhar,
    1.Please check in OS27 - Tick mark is included for EC Management Active &
    BOM validity manitained and History Requirement.
    2.In OS25 - For History Requirement.
    3.Get the help from ABAP consultant,to make use of field exit for the particular
    screen CS02 ,which has got a screen number.The system will not allow the user
    to enter into the next screen unless that field is not filled.
    4.Check for the Auth.Object C_STUE_NOH
    With this Logic only we are using in my present project.
    Check & reply.
    Regards
    Mangal

  • Bom Revision Changes with Same Day

    I have and issue when BOM items are changed using ECR control within the same day. ECR 5xxx001 is used to change item 0010 from part SKY123-A to SKY123-B. Later that same day, ECR 5xxx002 is used to change item 0010 from part SKY123-B to SKY123-C. When displaying BOM after ECR 5xxx002 change has been complete, I am unable to see all the changes. I typically only see the change from SKY123-A to SKY123-C. Has anyone ever seen this issue before? I suspect the issue is because table STAS and STPO allow for change on date only, without time stamp.

    Hi
    My further investigation has confirmed, BOM changes with ECR/Revision completed within the same working day cannot be separated in CS03 (display BOM) by date / time. For example, If you change something with ECN1 then you will see this
    changes valid also with ECN2 (same valid from date), because the changes are valid exactly from the same day.
    Entering the revision level in CS03/CS14 does not mean to have a different version of the BOM, but forcing the system to take the valid from date of the corresponding ECN.
    So to sum up: for one date there can be only one version of the BOM.
    Thank you everyone for you responses to the string, you have all been extremely helpful.

  • BOM Change Number

    How to make change no mandatory for BOM creation and change?
    The required config should not impact any other objects except BOM Creation & Change.

    Dear Venkat,
    In case of CS01/CS02 to make the change number as mandatory,follow this steps,
    1.In OS27 - Check box included for BOM validity maintained,EC Management active,History Requirement.
    2.In OS25 - BOM usage 1 & BOM status 1 - History Requirement check box is included.
    3.Authorization object C_STUE_NOH is with No.For this you should take the help from your BASIS
    consultant,while creating a new role in PFCG for this Authorization object C_STUE_NOH the value must
    be set as No.
    In most of the cases consultants peform the first 2 step alone,in that case only a warning message is displayed,only if step 3 is
    done ,an error message gets displayed and the user cannot enter or make any changes for the BOM without any change
    number.
    Regards
    Mangalraj.S

  • Bom Change Authorization (CS02,CS62)

    Hi all
    I am tring to block users from changing Material Bom usage 1 without ECM
    but allowed them to change Order Bom any usage without ECM
    I used c_stue_ber and c_stue_noh for tring block them
    also i couldn't find any user exit that i can used for this validation.
    Please Help

    Hello Kobi,
    In exceptional cases you can allow a BOM change without a change number
    using the authorization object C_STUE_NOH for BOMs with history
    requirements.
    Hope it works...
    Cheers, Dudle.
    PS: Plz Do not forget to give rewards

  • Bom Changing Authorization (cs02,cs62)

    Hi all
    I am tring to block users from changing Material Bom usage 1 without ECM
    but allowed them to change Order Bom any usage without ECM
    I used c_stue_ber and c_stue_noh for tring block them
    also i couldn't find any user exit that i can used for this validation.
    there is any way for block material bom usage 1 only from changing without ECM
    Please Help Thank

    Hello Kobi,
    In exceptional cases you can allow a BOM change without a change number
    using the authorization object C_STUE_NOH for BOMs with history
    requirements.
    Hope it works...
    Cheers, Dudle.
    PS: Plz Do not forget to give rewards

  • BOM changes inputting the BOM component -reg

    Hi Friends,
    we would like to know the BOM quantity changes happened for a particular BOm component .
    Using CS80 we have to input BOM header to know BOm changes , but our requirement is for a BOM component what changes are made and when they are made .
    Our BOM component say a paint part number is used in many BOM headers
    it is not possible to see CS80 by inputting one by one  BOm header and check whether the BOM component quantity changes are there .
    instead we would like to input BOM component and know when and what changes are made to its quantity (menge) in what BOM header by which use
    please help
    regards,
    madhu Kiran

    Dear Madhu Kiran,
    This is possible only if you are using ECM - Engineering Change number and you can obtain the details
    from the tables STAS,STKO,MAST &STPO.
    Without ECM I dont think its traceable.
    Check & revert back.
    Regards
    Mangalraj.S

  • Authorization to change BOM without history requirements

    Hi Techies,
    We are checking the design and validation of few scenarios in the testing server. During the testing we found that we are able to change the BOM which we have already changed with Change number without change number. Instead of an error message we are only getting a warning message stating the BOM has history requirements.
    I found that we could do that only if we had the authorisation C_STUE_NOH assigned to the user profile.
    I checked the transaction SU24 and for the transaction CS02 i found the authorisation C_STUE_NOH assigned and the authorisation proposal was YS.
    I m a functional consultant and hence i m not able to come to a conclusion on this to know if this the reason which is allowing us to change the BOM without history and just providing an warning message instead of error message.
    Thanking you in advance.
    Kris.S

    Dear Krishu,
    Below has been mentioned in OSS note: 420878. Check once again you have save as NO. Then go to tcode SU03 Object Class PP/ C_STUE_ROH
    Summary
    Symptom
    In Customizing of the BOM, the history requirement is set or a BOM requires a history. Despite this, it is possible to process BOMS without engineering change management. The system only processes a warning message (29 045) which can be skipped.
    Additional key words
    CS02, change number, OS27, W045(29)
    Cause and prerequisites
    Authorization profile
    Solution
    Check the authorization profile of the respective user.
    Example:
             C_STUE_NOH <OBJ>
                &_SAP_ALL    <AUT>
                    NOHIS      <FLD>
    would have the authorization to process BOMs requiring history without a change number. In this case, if you change '*' to ' ' in NOHIS, you will no longer receive a warning, but rather an error message.
    Regards / US

  • ECM - History Requirement for BOM status not activated

    Hello,
    He have an issue with the warning message  displayed when we are trying to modificate an BOM (transaction CS02).
    In OS25 transaction we defined that only BOMs with "usage = 1" and "status = 3" have history requirement.
    The parameters of OS27 transaction are OK too.
    The problem is that the warning message 045 is displayed when we execute CS02 for every kind of BOM usage and status.
    We must substitute the warning message by an error message. To do that, we must disable the field NOHIS in C_STUE_NOH object, in the user profile. But, when we do that, the error message is displayed to all kind of BOMs status, blocking the process (following the warning message, which is displayed to all kind of BOM status)
    This is an issue of SAP_APPL 470 system.
    We tested the similar procedure in an SAP_APPL 603 system, and the results were OK, in other words, the warning message is only displayed for the BOM usage and BOM status defined in OS25 transaction.
    Thank's in advance

    When the BOM with usage 1 and status 3, by example, is changed with a modification number (following OS25 parameters), the field STZU-HISTK is activated.
    Then, if the status of the BOM is changed to 2, the modification number is required, because the STZU-HISTK is activated.
    In OS25 transaction only the BOm usage = 1 and BOM status = 3 has the history requirement flag, but after the modification with the mod. number, all the status of the BOM now has the modification number requirement.
    How can I allow the modification of the BOM without modification number (other status not flagged in OS25), if this BOM hal already been changed with an modification number (by the status flagged in OS25)?
    Thank's in advance

  • How to get bom changed history?

    somtimes bom is changed with ECN , and sometimes without ECN, how to get all bom changed history?
    it appears that 'cdhdr' and 'cdcls' is the reference table, but some fields is implicit.  can you give me some idear?

    Hi,
    Kindly go through this link below,
    Previous Version of Bill of Material
    Hope it helps
    Regrds
    Mansi

  • BOM change history

    Dear all
    We are using change number to chang BOM. We want to develop a report for all BOM change history. Is there any function module can use? From table CDPOS is difficult to know what have been changed.
    Thanks
    Hailiang

    Hi,
    As others have questioned Why CS80 is not suitable ??
    Other possibility would be:
    Make a work instruction or mandatory to maintain the description and details of the change in the "BOM Long text".
    U can see the long text indicator in BOM,if checked than u will come to know the details.
    Caution: Works fine only if everyone follows maintaining the long text for any changes.
    Regards,
    Prakash

  • Tracking Data Changes with Record History (WHO)

    Hi all ,
    I've a custom form & i need to Tracking Data Changes with Record History (WHO) will anyone show me example of how it's done because i tried to go through the application developer guide but unfortunatelly this part isnot tht clear with me
    waiting your reply
    thanks

    Hi,
    Good question, a colleague asked me the same yesterday - i will find out officially for you.
    Regards,
    H

  • Function module required for BOM Changes

    Dear SAP Guru
    I need the function module which gives me the details of changes done in the BOM.
    Scenario: Need to develop the report which gives only the details of BOM changed on the given date. The BOM level might vary.
    Regards
    Rahul

    Dear
    I think you should have ECM in place to have tracability for any changes carried out in BOM .
    Refer earlier posting : Re: ECM ECR
    If the ECM is in place , then you can see what changes has been done in CC02/03 Environmnet - > Reporting -> Bill of Material.
    Otherwise please try the following Functinal Module : You can also try CEWB and CS80
    1. CSAP_BOM_ITEM_MAINTAIN
    2.CS_BOM_EXPL_MAT_V2
    3.CHANGEDOCUMENT_READ  and CDHDR
    Refer : http://help.sap.com/saphelp_40b/helpdata/en/92/58b521417011d189ec0000e81ddfac/content.htm
    Regards
    JH

  • BOM change track report.

    Hello All,
    I have a requirement where I need to develop a report that represent following fields of BOM change history.
    1. Material (Along with description if possible)
    2. Changed By
    3. Change On
    4. Change Details (Entry, Delete, and replacement data for the item)
    5. Header level change (Change in Base quantity, from to lot size, Bom activation/deactivation)
    6. Plant (Most Important)
    I have checked to get it through CS80  Change Documents for Material BOMm but it'svery lengthy task and can't do it one by one.
    I have gone through these tables
    STKO --- BOM - header 
    STPO --- BOM - item 
    STAS --- BOMs - Item Selection 
    STPN --- BOMs - follow-up control 
    STPU --- BOM - sub-item 
    STZU --- Permanent BOM data
    But not getting any clue.
    NOTE:- I have not implemented the Change document mgmt system (CC01,CC02) and if I do such so then what about the existing changes already done in the system. So, I know it can be achieved by implementing Change mgmt but practically it's not possible for me.
    kindly help!!!!!!!!!
    -- Jimmy

    Dear Jimmy,
    I dont think it's possible to prepare a report using the tables or CS80 for the same,without having Engineering Change
    Management.
    Check and revert back.
    Regards
    Mangalraj.S

Maybe you are looking for