CA96 update of in-house production time

Dear PP Gurus ,
I want to update material master for in-house production time with Routings lead times.
The system update processing time (lot dependent) but I want to update the in-house production time (MRP2 view).
Can you help me ?
Thanks in advance

I am confused.
Routing is required for production order right. Why do you need this data for reorder point planning?\
Are you producing this material depending on the reorder point planning?
If so whether your production rate is independent of lot size? like you need 100 to or 1000 to, the time taken is same? is it true?
Kinldy let us know your business scenario...looks to be intersting.

Similar Messages

  • Updating in-house production time in mat master

    Hi, we have not maintained in-house prod days in material master for all materiasl. pls advise do we need to run ca97 t-code after uploading all fert materials in production server? is there any other method.

    Hi,
      For updating in house production time in material master you have to follow the procedure,
    1. Maintain Processing time in Routing Operation details screen.
    2. Then go to Operation overview screen in Routing, In menu go to Extras -- >Scheduling ---> Choose Schedule. Scheduling   
        pop up screen will appear.
    3.Enter the scheduling type, lot size and dates for the corresponding scheduling type.choose continue, on the next pop up 
         enter the overview variant and choose continue.
    4. In scheduling Overview screen choose the operation and select Scheduling result tab on the next pop up choose Update
         material master tab.
    5. Choose continue and save the routing.
    6.Then go to CA96 enter the plant and choose continue, on the next screen select the scheduling result and choose Update
       material master tab.
    7. Go to Material master ---> Work scheduling view you can see the In house production is updated.
    Regards,
    Muthamil

  • In house production time: Routing/ Material Master.

    Hello All,
    For a semifinished product with procurement type as "E", thr is a tab for entering in house production time (lot size independent). While creating the material master, i leave it blank. Also, i create a routing for the material.
    Please tell me how can i get the in house production time in work scheduling view, updated from Routing.?
    Regards,
    Chetan.

    hi chetan,
        if you want to update the lotsize dependent inhouse production times, below is the steps for execution.
    1. Maintain Processing time in Routing Operation details screen.
    2. Then go to Operation overview screen in Routing, In menu go to Extras -- >Scheduling ---> Choose Schedule. Scheduling
    pop up screen will appear.
    3.Enter the scheduling type, lot size and dates for the corresponding scheduling type.choose continue, on the next pop up
    enter the overview variant and choose continue.
    4. In scheduling Overview screen choose the operation and select Scheduling result tab on the next pop up choose Update
    material master tab.
    5. Choose continue and save the routing.
    6.Then go to CA96 enter the plant and choose continue, on the next screen select the scheduling result and choose Update
    material master tab.
    7. Go to Material master ---> Work scheduling view you can see the In house production is updated.
    regards,
    sree

  • In house production time in material master .

    Dear All ,
    What will happen if i do not enter ( keep blank ) the inhouse production time in MRP 2 view ?
    Where i am using routing for all inhouse produced material . all the scheduling parameter are correct as per routing considered .
    i have checked the scheduling in routing for these material , scheduling appearing correctly . So this is supposed to be copied as it is in the planned order --> prodn order ( it is happening ) .
    So if i do not use in house production time field in MRP2 what will happen ?
    Pl guide

    Hi,
    It is the time to produce a product in a plant in no.of days.
    In-house production time:
    Specifies the time in workdays needed to produce the material in-house.
    In-house production time is independent of the order quantity.
    Use:
    The system requires the in-house production time to determine the planned dates for planned orders in materials planning.
    Procedure
    You can define work scheduling times in the material master record in one of two ways:
    Either you enter the in-house production time. If required, you can get the system to update this value from the routing.
    Or you enter the setup, tear down, processing, and inter operation times. If you maintain these values, the system determines the in-house production time on the basis of lot size.
    Production Planning and Control (PP)
    The time required to produce the material in your plant.
    You can enter the in-house production time depending on the order quantity or independent of the order quantity. It is calculated by adding the lead times of all operations, the float before production, and the float after production.
    I hope it helps you. Any queries please revert me back.
    Regards,
    Madhu.G

  • Process order scheduling based on in-house production time.

    Hello!
    I have following problem. My SAP system is configured in that way that process oedrs are schedulled based on times saved in master recipies. When I input data to in-house production time in master data for materials and make new process order, this time is not
    taken into account.
    Where I have to change configuration to use in-house production time from material master data to make scheduling process orders.
    Regards
    Bogdan

    Dear
    Process Order /Production Order scheduling ( Lead Time Scheduling )  based on the Operation timings in the routing not based on the Material Master In house Production Time in Work Scheduling View .
    If you are loking for Basic Date Scheduling then it will happend based on material master , scheduling margin key  at material master level .
    It depends the selection of Schedueling indicator while excetion of MRP in MD02 .
    In case of Process order specifically , you need  to schedule the Master Recipe and check whether operations are getting scheduled, if it is not then you need to first the problem, which may be because of wrong "Forumla" or paramater assigned in resource or the resource is not maintained for Finite scheduling (capacity header).
    Master reciepe can be schedule in the change transaction C202, and from menu you would find the option to schedule the recipe .
    Also  check the OPU3/OPU5-Define scheduling parametres wether scheuling , adjust scheduling , scheuling type , logs all are in place .
    Check and revert
    Regards
    JH

  • In house production time and delivery date on PO

    Hi Gurus,
    Can anybody please calrify the following for me? Plant A is procuring material X from PlantB via STO. The planned delivery time for the material in plant A is 21 days. The in house production time of the material in plant B is 3 days. When the STO is created, with a delivery date of 04/26/2010, based on the planned delivery time of 21 days, the material has to leave the plant B by 04/05/2010. But what what about the considertation of 3 days of inhouse production tiume in plantB. How does the inhouse production time play in picture?
    Thanks
    Anusha

    Hi
    Inhouse production time in Plant B is considered if there is a planned order or production order is created for material in plant B. If a STO is created in plant A, then system will check only planned delivery time in Plant A only. If you want some buffer, you need to use GR processing time in plant B.
    Regards
    Antony

  • In-house production time not considered in scheduling

    i have a material, with an in-house production time of 7. requirements date is today, May 23. as a sap standard, using backward scheduling, it shall see that the start day lies in the past, and should switch to forward scheduling, with May 23 as the start date, and may 30 as the finish date. however, the system only proposes a finish date of may 27. why is the system behaving this way?

    Hi,
    Please let us explain, where u have carried out  scheduling  ie  during the MRP or in Production order.
    I hope ur asking about Production order scheduling , inthat case system will not consider the Inhouse production time. Because lead time scheduling is carried in production order.
    Scheduling will be done for routing times not for In-house  production time.
    Pradeep

  • In house production time & MRP

    Dear All,
    What is in house production time? How it function during MRP run?
    Please provide some example against explanation.

    Hi,
    In house production time is a time in workdays (maintained in MRP2 view of MMR)  needed to produce the material in house. This time is either dependent / independent of the order quantity / lot size. This time is used to determine the planned dates of the planned orders in material planning. 
    The basic dates are determined only by the lot size independent in-house production time and independently from the order quantity.
    The floats are not included in the calculation of in house production time but actually form the part of in house production time.(The total floats are maintained through the inter operation time).
    Hope this will clear your doubt.
    Pavan

  • Mass change in In house Production Time in Material master

    Hello Frinds,
    I am dooing mass change in Inhouse Production time in material master By using MM17
    field is MARC-DZEIT
    i am putting Material ,Plant & in house Production time & after execution it shows following MSG.
    No data meet the selection criteria
    Message no. M&107
    Where i m wrong weather my Varient is not created Properly  ,Pour some light on it ,if i m wrong tell me the way of dooing mass change in ECC6.0 ,LSMW & DBC is next Option ,i want to do it with MM17
    Regards ,
    Girish

    Dear Girish,
    Goto MM17--->click on Fields tab page,select the field MARC-DZEIT and then clcik on execute button.
    In the next screen,either input the material ,plant combination or else input the plant and click on
    execute button.
    Now enter the inhouse production time in the new values say 2 days,Either select the materials for
    which this new change has to be made or else select all the list of materials and click on mass change
    icon and check the results and save the datas.
    Regards
    Mangalraj.S

  • In-house production time in MRP2 View

    Hi, Please advise what to mention in in-house production days field in mrp2 view, whether we need to mention the time required to  produce 1 part or any qty? please advise.

    Hi,
    Nice qns... but the answer would be a simple computation from the system. When it is lot-size independent, system just reads the value from IHPT, there is no calculation as such.
    But when it is lot size dependent, the system will compute the IHPT based on the values populated in the Lot-size dependent section of work-scheduling view.
    I would suggest instead of me writing a whole lot of stuff, take a material in your sandbox & do a simple test with a single operation routing. In the work center maintain formulas for Setup, Operation & in your routing maintain the hours for activities setup & machine. Now in the routing itself click on Extras - Scheduling - Schedule & do the scheduling. Click on Scheduling results you will get the details. Now update the material master.
    Now create the production order for different quantity & notice the difference in dates. This will clarify your doubt as to how system would know.
    Revert if you face any issues.
    Regards,
    Vivek

  • In house production time

    hi folks ,i have a requirement like when a for a sales order qty say 1000 for finished goods product, the required delivery date is say 31.12.2007 , the sales order receiving date is say todays date .
    time required to produce 100 base qty of the finished goods is say 1 day .
    so the toal time required is 10 days from today if i start production today .
    without carrying out MRP can i get how much time required to manufactured the finished goods .
    can we use Inhouse prodn time or lot size independent parameter for the same so that without carrying out the MRP we can calculate production time required for the sales order qty .
    Regards

    Hi,
    goto operation overview , choose extras , schedule and give required qty
    in the lot size.Then choose scheduling results.
      You will get basic start date/ finish date
      scheduled start date / finish date
    Regards,
    nandha

  • In house prod. time for continuous manufacturing

    Hello friends,
    I want to enter in house production time in matarial master for continuous manufacturing process.I am using Base Unit Of Measure "Quintal".It is not possible to calculate In house production time. So how can I define it?
    Thanks!!

    Hi,
    In-house production time is lot size independent it use to schedule the order with basic date only, but when we do the lead time scheduling or create production order then system take the values from routing as it is lot size dependent.
    It is not possible to calculate In house production time?
    So pls maintain the approx time in material master then schedule the routing ca02extrascheduling--schedule after that click on scheduling result and update material master.
    Then go to CA96 and update the result in to material master and check the time in material master--work scheduling view.
    Hope it will clear your doubt.
    Regards,
    R.Brahmnkar

  • One Material with two Different In-House Production Days

    Dear Experts,
    We have 1 semi-finished material (HALB) that is common to two different locations (production version) with two different in-house Production days.  How can we separate the 2 different in- house prod. days for this specific material? Could we setup in the production version? if not, could you give us an advice.
    Ex:
    JDXZ011111 with Prod. version I000 = 3 days
    JDXZ011111 with Prod. version X000 = 1 day
    We are hoping for your help..
    Thank you.
    Regards,
    Marnelli

    Dear Mamelli,
    1.You cannot maintain  the in-house production time in the production version.
    2.In-house production time in days can be maintained in MRP2 view.
    3.If Lead time scheduling is carried out at the time of MRP run then the system uses the in-house time for the calcualtion onf basic
    start and end dates.Based on the routing data the system proposes the production start and end time.
    4.Generally exception messages 64     Production finish after order finish
    63     Production start before order start are  shown after MRP run.
    5.If basic scheduling is carried out then the system proposes only the basic dates.
    Regards
    S Mangalraj

  • MRP - Inhouse production time

    Dear Gurus,
                 In the Mrp 1 View, The In-house production time is in no.of Days format.but my client want's this to be entered in no.of hrs format
    Kindly Advise
    Regards
    Palaniappan Meenakshi Sundaram

    I don't think it is possible, if he want in terms of Hrs format, he is suppose to go for Lead time scheduling instead of Basic Date scheduling.
    The inhouse production time maintain in MRP1 view is independent of Qty and the MRP run result will not be so accurate
    They have suppose to maintain Work center ,Routing Master data, then they can maintain Inhouse processing time interms of  Hrs,min and sec
    K.Prabakaran

  • Kanban: in-house production. relation kanban - replenishment order

    Dear Experts,
    We are investigating the posibilities of using kanban for in-house production. We work with production orders. I have set the test system so it works with classic Kanban and a replenishment strategy that will create PP production ordres.
    The system works OK. When the KANBAn is set to EMPTY (in the kanban board for instance) , a replenishment element is generated. The relation is 1 KANBAN - 1 Production order.
    Is it possible to "assign" two KANBANS to a single replenishment element (productio order in my case)? In some cases two or more kanbans will be emptied at the same time (in the KANBAN board for instance), and this would reduce the "noise" in the system.
    Somehow in the documentation "PP-KANBAN" manual, inside "KANBAN control. in-house production" some other option to reduce the amount of production orders is mentioned, but not very clearly explained how to do this.
    Thanks for your answers,
    Arturo

    Hello,
    Your question is not clear to give correct feedback. Do you want to wprk with multiple KANBANS with production orders?
    I am not understanding about the sentence "reduce the amount of production orders"
    If you want to work work minimum production orders then you can automate the KANBAN replinishment through MRP.
    Raegards
    TAJUDDIN