Capitalization of Asset Under Conustruction(Investement Measure)

Hi Gurus.
I have created a Internal Order for AUC and  posted expenses to that order. At the end of the period, i have settled the order using T.Code KO88.
How to capitalize part of the amount from that AUC to main asset. When i am trying to transfer to the amount using T.Code ABUMN, system is not allowing.
Please suggest me in this regard.
Thanks in Advance,
Ganesh

Hi,
Have you checked in the AUC asset class as Investment measures?
If it is Investment measures, you need to give second settlement rule for the same Internal order for transfering the value from AUC asset to main asset. Then do settlement again.
Regards,
Murali
Assign points if useful.

Similar Messages

  • Creation of Assets for Capital Investment Measure

    Hi,
    Can some please tell me how to create an Asset for Capital Investment Measure.

    Hi,
    First you have to create master data using asset class AuC.
    You have define asset class for Capital Investment Measure (AuC class) in t-code : OAOA. And still in the same t-code (OAOA), you choose "investment Measure" in box "Status of Auc".
    If you choose "Investment Measure", the assets under construction in this asset class can be created solely in relation to capital investment measures (internal orders or WBS elements).  So you cannot create and post in Asset Accounting directly (Example post using t-code : F-90).
    If you use WBS Elements then you can post to the asset for Cap Invest Measure using t-code : CJ8G or CJ88.
    Hope it can help.

  • Capitalization of Assets under construction

    Hi Gurus,
    Can anyone assist with the procedure and considerations for the capitalization of assets under construction?
    Regards

    Hi,
    To Capitalize AUC go to T.code : AIAB then define settlement rule then go to AIBU and Settled  AUC cost to main Assets. 
    Thanks
    Javed

  • How to post the Down payment for assets using the investment measure?

    Hi,
    We want to post the down payment using the investment measure for some of the assets. Please tell me how to post it and how to clear it.
    I have searched the net but till now I am unable to find something with which I can do that.
    Thanks in advance...
    Regards
    Nitin

    Hi,
    Please reply as I am facing problems with posting the down payments using the investment measure and I have tried and read alot but nothing as such I have been able to found.
    Thanks and Reply
    Nitin

  • Change of Cost Center in Asset Master for Investment measure (AuC) Assets.

    Hi,
    We have an asset class 4001 which has been maintained as an investment measure for AuC. I want to change cost center for all the assets that are maintained in the asset class 4001. The system is showing cost center field in display mode in change transaction of the asset AS02 for all the assets in the asset class. I want to replace the old cost center with new cost center in the asset master record. How can I make the cost center field changeable ? 
    Can anyone help me ?
    Regards,
    K.S.K

    Hi Kattula,
    We can change the cost center for AUC with Investment Measure. To do this you need to identify the relevant WBS element assigned to your asset. You can find the WBSE in Origin tab of your asset master record.
    Then go to the change WBS element Transaction CJ12 and change the cost center. Once you change the cost center of the WBSE, the change would automatically get reflected in the correspondind asset master record.
    This would solve your issue.
    Thanks & Regards
    FICO GSupport team.
    RK & IK.

  • Asset Under Conustruction

    Hi Gurus,
    Our project has gone live on 31.01.2007, Client has given balances of AUC upto 31.01.2007. In case of normal assets, i have done it in Tcode AS91 using LSMW.
    How to upload the balances of AUC as We have special asset classes for AUC.
    Please advice me, either  i have to create internal order or asset master record.
    Regards,
    Ganesh

    The following link may be of help to you
    http://help.sap.com/saphelp_47x200/helpdata/en/4f/71e327448011d189f00000e81ddfac/frameset.htm
    Assign points if useful
    Regards
    Aravind

  • Asset under Construction for Investment Measures

    Hi all
    This is my client requirement
    how to do asset under Construction for Investment Measures
    configration
    pls send configration

    Hi
    These are the steps to be followed:
    1. Create a asset class for CWIP (Auc) - OAOA: In this select Investment Measure under Status of AuC.
    2. Define Investment Profile (OITA) - Give AuC Asset class as invest measure asset class.
    3. Create Internal Order Type for Investments: Normally standard 0650 order type will take care of the requirement.  We need not to create anything.
    4. Create Asset (AS01) under normal asset class i.e., buildings or vehicles etc... (You cannot create under AuC Asset Class)
    5. Create Internal Order (KO01): Give Object class as investment and under Investments tab give investment profile created in step 2.
       Go to settlement profile tab and give category as FXA and settlement receiver the asset no. and give 100%.
    6. Change asset master to incorporate the internal order number under Origin Tab.  Give no. in Investment order field.
    7. Release the Internal Order (KO02)
    8. Post the transactions through different T.Codes by referring Internal Order as account assignment.
    9. Go to Internal Order through KO02 and complete TECO under control data.
    10. Go to T.Code KO88 (internal order settlement) and settle the order.
    Hope this will help you.

  • Transfer investment measure asset to other compnay code

    Dear All,
    This is required to my client , we have two company codes. Right now we are purchasing assests under capital investment measures in one co.code , from this one of the equipment to be transfered to another compnay code.
    when I am trying to transfer ABT1N systme throughing the following error message
    "Asset A001 17000011-0  that is to be posted is an investment measure.You are not allowed to post transactions that affect acquisition value using the current transaction.
    Check the asset and transaction type 320."
    May i request you kindly advise me.
    thanks & regards

    Hi,
    We have also faced a similar issue. The solution we thought and implemented is
    1. Settle the Internal order ( KO88) with Final settlement. So that the values will move from the AUC to the Final asset.
    2. Now the Final asset value can be moved to the Other company code.
    Due to the Internal controls, system will not allow you to settle or transfer the values on the AUC created through the Investment Measure.
    Thanks
    Siva

  • Error while creating PO for Asset is investment measure

    Hi All,
    I am getting error when I try to create PO for Asset which is investment measure.
    Error is as below:-
    Asset is investment measure, transaction type not allowed
    Message no. AK005
    Diagnosis
    Asset 305000003 0 that is to be posted is an investment measure. You are not allowed to post transactions that affect acquisition value using the current transaction.
    Procedure
    Check the asset and transaction type 120.
    I am using account assigment catergory 'A' in PO. I have checked Allowed transaction type for Acquisition and 120 is already allowed.
    Please guide.

    Hi,
    Try to create PO with account assignment category as P/N for project related ones.
    If the related asset is related to Investment Measure we need to settle transactions to WBS element and from WBS element to AUC. We cannot directly post to AUC.
    Thanks and Regards,
    padmaja

  • Message no. AK005 - Asset is investment measure, transaction type not allow

    Dear All,
    I am getting following error while transfering Investment AuC to Main Asset.
    Message no. AK005 - Asset is investment measure, transaction type not allow
    I searched the Forum and got some input.., but in that I have a clarification.
    Please see my doubt and the forum input.
    Internal Order as Investment Measure:
    Can you explain me Step 10. Settle the amounts to Main Asset from AuC(Prcg type: Full) - KO88 once again.
    How we can give the Receiver Main Asset master in KO88. In KO88 we can only provide the Internal Order. But that Internal Order is already settled to AuC in Step 8.
    Please guide me.
    Thanks.
    Regards,
    nms
    Re: Settlement of cost center to final asset ?
    Posted: Oct 27, 2009 11:40 AM
    Hi,
    Are you doing any settlement using the AUC asset ?
    Normal practice is to Create an Auc Asset and settle cost to Auc. Once the asset is ready for use, finally settle the Auc to final asset.
    This can be done in two ways like - line item settlement / investment measure.
    Below are steps in two scenarios :
    Internal Order as Investment Measure:
    1. Define the AuC Asset Class (with investment measure) - OAOA
    2. Define the Asset Class u2013 for Main Asset - OAOA
    3. Define Investment Profile - OITA
    a. Assign the AuC Asset Class (Step-1) in the investment profile
    4. Assign Investment Profile to Model Order - OITA
    5. Define Order Type (Investment) - KOT2
    a. Settlement Profile - OKO7
    b. Maintain Allocation Structures - OKO6
    c. Planning Profile - OKOS
    d. Budget Profile - OKOB
    6. Create an Internal Order - KO01
    a. With the Investment Profile (Step-2)
    b. AuC automatically created by the system using Asset Class given in the Investment Profile
    7. Post the amounts to IO - FB01
    8. Settle the amounts to AuC from IO (Prcg type: Automatic) - KO88
    9. Create the Main Asset - AS01
    10. Settle the amounts to Main Asset from AuC(Prcg type: Full) - KO88
    AuC using Line Item Settlement:
    1. Define the AuC Asset Class (with Line Item Settlement) - OAOA
    2. Define the Asset Class u2013 for Main Asset - OAOA
    3. Define Order Type (Overhead) - KOT2
    4. Create an AuC-Asset (using Step-1 Asset Class) - AS01
    5. Create an Internal Order - KO01
    a. Assign the AuC u2013 Asset in Settlement Rule in IO
    6. Post the amounts to IO - FB01
    7. Settle the amounts to AuC from IO - KO88
    8. Create Main Asset (using Step-2 Asset Class) - AS01
    9. Assign the Main Asset in IO (Step-5) - KO02
    10. Settlement AuC u2013 Line Item List - AIAB
    11. Settlement AuC - Receiver - AIBU
    VVR

    nms,
    Your message is not very clear - while you have mentioned at what stage are you getting the above-mentioned error message, you haven't mentioned exactly what you were trying to do. The fact that you are getting this error is a straight-forward indication that you are attempting to do something that SAP does expect.
    However, answering your query about how to use KO88, you have to settle the AuC to a FA (fixed asset, with asset class other than AuC ), as that will close the open AuC, transfer the value from the AuC to the FA and from this point onwards, all transactions will happen to this FA. Your statement "in KO88, we can only provide the Internal Order" is incorrect.
    Hope this helps.
    Regards
    Gulshan

  • Posting a credit to an Asset created by a project i.e Investment measure

    Can anyone help with this.  i am trying to post a credit to an Investment measure using f-02.  I want to create a transaction type that will work but I am not sure what the entries in this transaction type should be.  Any ideas?

    That's exactly what I am trying to do in f-02 with ttype 100 but I get the message, asset is an investment measure, transaction type not allowed.  Am I using the wrong t- code or the wrong transaction type?

  • Asset Under Construction Expenses

    Dear Friends,
    My Client is in the process of construction of building.He is incurring expenses like labour charges, cement and other building material.
    For Construction of building, creation of assets under consutrction is necessary
    How to account for expenses incurred in construction of a building.
    What is the process and what t.codes have to used.
    All the help will be greatly appreciated.
    Regards
    Sridhar

    HI
    You can capture the AuC Cost using any of the below procedure :
    "IO as IM" section in the step - 9 create desired asset master (plant)
    "AuC using line item settlement" section in the step - 8 create desired asset master (plant)
    Internal Order as Investment Measure:
    1. Define the AuC Asset Class (with investment measure) - OAOA
    2. Define the Asset Class u2013 for Main Asset - OAOA
    3. Define Investment Profile - OITA
    a. Assign the AuC Asset Class (Step-1) in the investment profile
    4. Assign Investment Profile to Model Order - OITA
    5. Define Order Type (Investment) - KOT2
    a. Settlement Profile - OKO7
    b. Maintain Allocation Structures - OKO6
    c. Planning Profile - OKOS
    d. Budget Profile - OKOB
    6. Create an Internal Order - KO01
    a. With the Investment Profile (Step-2)
    b. AuC automatically created by the system using Asset Class given in the Investment Profile
    7. Post the amounts to IO - FB01
    8. Settle the amounts to AuC from IO (Prcg type: Automatic) - KO88
    9. Create the Main Asset - AS01
    10. Settle the amounts to Main Asset from AuC(Prcg type: Full) - KO88
    AuC using Line Item Settlement:
    1. Define the AuC Asset Class (with Line Item Settlement) - OAOA
    2. Define the Asset Class u2013 for Main Asset - OAOA
    3. Define Order Type (Overhead) - KOT2
    4. Create an AuC-Asset (using Step-1 Asset Class) - AS01
    5. Create an Internal Order - KO01
    a. Assign the AuC u2013 Asset in Settlement Rule in IO
    6. Post the amounts to IO - FB01
    7. Settle the amounts to AuC from IO - KO88
    8. Create Main Asset (using Step-2 Asset Class) - AS01
    9. Assign the Main Asset in IO (Step-5) - KO02
    10. Settlement AuC u2013 Line Item List - AIAB
    11. Settlement AuC - Receiver - AIBU
    SKS

  • Capitalization of  AUC investment  measure  to asset

    Hi,
    I created a project and then settled corresponding WBS elements to AUC investment measure using CJ88.After that i am not able to capitalize to final asset.Please help me in procedure  as I am not able to settle using normal line item settlement AUC as this is investment measure.

    Hi Prad,
    I am on 4.6C/D.
    Please check on your settings for Capitalization of AUCs created through Investment Support Measures: -
    1. Go to the IMG, Asset Accounting under Special Valuation and determine the Depreciation Areas you would like your Investment Support Measures to post to.
    2. Still in Special Valuation, define an Investment Support Key and assign it to the relevant depreciation area
    3. Also, define the relevant account determination for such posting under the Special Valuation
    4. Proceed in the same area to define the Transaction type for the Investment Support Measure by changing any of the Standard ones in there in line with your requirements
    5. Now move back to IMG, Asset Accounting then Master Data. Here you go to the screen layout and pick the relevant asset class for AUCs. Get this logical feild group and pick on the item Investment Support. Proceed to define its feild group rule as optional at the required asset maintenance level (Main Asset and/or Sub Level)
    6. Leave the IMG and access the relevant AUC's Master Data from the User Menu. Click the tab Investment Support and insert the Investment Support Key you created in note 2 above
    7. Now capitalise the AUC. Should work

  • Capitalize borrowing costs to asset under construction u2013 IAS23

    Dear experts,
    According to IAS 23 we are required to calculate interest on capital invested in an asset under construction.
    Borrowing costs that are directly attributable to the acquisition, construction or production of a qualifying asset form part of the cost of that asset. Where funds are borrowed specifically, costs eligible for capitalization are the actual costs incurred less any income earned on the temporary investment of such borrowings. Where funds are part of a general pool, the eligible amount is determined by applying a capitalization rate to the expenditure on that asset. The capitalization rate will be the weighted average of the borrowing costs applicable to the general pool. The amount of borrowing costs that an entity capitalizes during a period shall not exceed the amount of borrowing costs it incurred during that period.
    Detail scenario
    The construction of a qualifying asset is controlled by an investment measures that are managed as projects - WBS elements and settled to an asset under construction periodically.  The calculated interest shall update only the determine depreciation area set on the interest profile (OPIB).
    The borrowing operations are managed by money market transaction on TRM (Prod. Category  550  Interest rate instrument).
    Using the interest calculation function (CJZ2 - Individual Processing or CJZ1 - Collective Processing) we encountered several problems/ restrictions.
    1 u2013 When funds are borrowed specifically to a qualifying asset for example, an interest rate instrument as a money market transaction on TRM should be capitalized according to the actual incurred borrowing cost and not by a capitalization rate. How to assign the value to the WBS element?
    2 u2013 When funds are part of a general  pool, although we can calculate and update the effective interest rate for each borrowing transaction (TMEZ) how to determine the weighted average capitalization rate by company code and define it on the Reference Interest Rates (OBAC) to be used in the interest calculation?
    3 u2013 Even if the capitalization rate is defined and updated manually in the reference interest rate for the interest calculation, how to limit the amount of borrowing costs that will be capitalized during the period? The calculated interest in period shall not exceed the amount of borrowing costs it incurred during that period.
    Is there any other functionality to support interest calculation and capitalization of borrowing costs to asset under construction according to IAS23 requirements?
    Please advice.

    Hi,
    The interest rates for capitalization and for appropriation can be collected in separate cost centers and apportioned to WBS . If you incur interests at the group level,then using accrual apportion the relevant portion to the respective C/Codes.
    For arriving the weighted average i assume you take the planned interest.For restricting the planned to the actual ones use the " Budget Manager" functionality,give the actual value,set zero tolerance.This will help restricting  to the actuals.
    Hope this helps.
    Regards
    Ramesh

  • Creation of internal order (investment order- asset under construction)

    I want to capture the cost of asset under construction through internal order (controlling) not throgh Investment Measure module. How i can do this.

    Hi
    It is the same flow as explained by AP above
    If Investment management module is active, then on settlement i believe the AUC asset is automatically generated. Therefore you have to define an asset master and then include this asset in the settlement rule of the IO. Thus on settlement the cost in the IO would flow to the asset
    Thank You,

Maybe you are looking for

  • Airplay to iPad as second monitor

    Is it possible to use Mavericks Airplay to set up an iPad as a secondary display ?

  • User account issues in school please help urgent

    currently have 15 emacs on school network running 10.3.9 and the rest are windows machines the macs are standalone machines yet have the same logins for each. The issue is with setting up accounts for the students I dont want to use simple finder as

  • CS5 - installation problems

    Hi Adobe. I am a happy owner of the CS5-Package. Recently I formatted my PC and I've had serious problems installing the programs. I start out installing Adobe Acrobat. That works just fine.      The other discs are the main problem. They won't insta

  • Axis2 for netbeans

    Hello, This might not be the best place to pose my question but if anyone has any ideas, they will be much appreciated. Is there a tutorial on how to develop web services with the new netbeans 6.1 beta using Axis? I have googled for it but couldn't f

  • Como faço para atualizar a minha versão 10.6.8

    How do I upgrade my macbook version 10.6.8 for a better version, at least for a version that has the look and my mac icloud?