Cash Purchases

Hello experts ,
I have a scenario in which basically two types of purchases are made in cash  .
As the purchases are high in volume , we need to capture this in PO . Also as we need to have a control over inventory , we dont want to use 501. Hence 501 is totally blocked .
I basically have two kinds of cash purchases .
1. Material bought from local vendors
2. Frieght given to the transporter for the credit material purchased from some other vendor.
In case 1
I need to make a PO .
do a GR
update inventory & value .
book an invoice
But how do I settle the cash payment already made ? All the above activities are booked in SAP after having actually completed.
In case 2
I have certain factory cashier giving cash to the transporter immediately after the GR .
The material invoice is booked as usual .
The friegt invoice also is booked as usual as i need to valuate the inventory with the amount of frieght incurred .
I book  a material invoice & a frieght  invoice as usual .
Pleas tell me , how can I settle the frieght invoice booked for which i have already made a payment .
Is there any std procedure in the system to denote a cash/credit purchases in the invoice document ? Also any link to settle the payments already made ?
Regards
Anis

Hi,
In SAP standard procedure, any procurement (by cash) and related activities (freight,insurance,p&f charges) payment made before making purchase order and then created purchase order all payment included in the PO value.
After that MIGO posting the related payment activities(freight,p&f,insurance)  cost added to the material actual cost.
If not require to added the related activities(freight,insurance,p&f) cost to material actual cost, you have to book directly through FBCJ T-code for the payment made.
Hope, it is very useful for you.
Regards,
K.Rajendran

Similar Messages

  • Confirmation for  Cash Purchases in SRM

    Hello All,
        We are running on SRM 4.0(Classic Scenario) wherein the PR,PO and Invoice is done in R/3 and the SC  creation & Confirmation in SRM.The prob we are facing is that for cash Purchases,once the Purchase requisition is closed in R/3,the status of the SC is to be updated automatically as closed in SRM or is there any provision wherein we can confirm  the SC?
    Regards,
    Disha.

    Hi Disha,
    This is not a common scenario...
    However, you have to update PR status (manually or automatically via a custom report) and check that SRM report BBP_GET_STATUS_2 is reading PR and correctly updates SC history else you will have to enhance standard behaviour (PR status management and BBP_GET_STATUS_2 report) to match your requirements.
    As i do not have a R/3 system right now, i am not able to check PR status possibility...
    Regards,
    Yann

  • Cash Purchase in Maintenance

    Dear Gurus;
    In one of the scenarios, my client wants to have cash purchase in regular maintenance order as well as preventive maintenance order.
    So there is no PR & hence no PO.
    How it can be mapped in SAP?
    Thanks & Regards
    Hemant

    Hemant:
    I've been in this situation before. There are some customers that don't want to create orders for every single spare (in particular, consumible). So, it's possible to register the cost of a vendor invoice directly trough. For example, you can use FB60 or FV60, selecting as imputation object the Maintenance Order (preaviously created). There are some companys that create one of this order per equipament and nenver close then, running the settlement process every month.
    The problem is that this cost will not appear in the order as plannified ones, but it will certanly impact in the "Cost" tab. You must understand that's not a very "clean" process, becouse you are allowing the user to put cost directly, without planing and you miss the techincal data, relevant for maintenance
    For electricity and water charges you have several options. You may create an preventive maintenance, that every month genereat and PR and then a Service entry or directly the Service order (this is know as accelerated processes, see <a href="http://help.sap.com/saphelp_470/helpdata/en/09/363fd3051311d2a3c10000e8a522f1/frameset.htm">http://help.sap.com/saphelp_470/helpdata/en/09/363fd3051311d2a3c10000e8a522f1/frameset.htm</a>). This is usefull for this kind of repetitive  Other option it's to register this cost directly trough FI as i told you before.
    Hope this help
    Ezequiel

  • Cash Purchase

    Dear All,
    How do we map cash purchase in SAP,How do we make GR.
    Plz explain me in detail

    Hi,
    for cash purchase do GR with 501 movement.
    for excise duty capturing
    in J1IEX select option 'capture excise invoice' & ' without purchase order'
    Regards
    Prakash

  • How to verify a Creative Suite as valid (cash purchase)

    I am going to purchase CS4 Design Standard for Mac as a cash deal (from Craig's list). All my "antenna" say that this is a good deal, it is from someone who validly does have an extra, shrink-wrapped, version for sale.
    My questions
    1) If it is shrink-wrapped, is there any tell-tale icon of authenticity (like a hologram) on the packaging?
    2) If I have any worries, what is the fastest way to install it and get it activated? Do I need to install all of the programs (which would take some time!), or is there a fast way to activation to just prove that it works?
    Please, don't respond telling me that I am a fool, I can make up my own mind about that (and will, after I make the purchase!). And I did read (most of) the lengthy discussion of eBay purchases in Photoshop WIndows Forum.
    A

    As a reply to my own post, I made a cash transaction for what appeared to be an unopened copy of CS4 Design Standard. My was I surprised at the lack of packaging now offered by Adobe (I haven't seen a physical CS box for a while now--they used to be huge!).
    Anyway, I had a problem with activation when I installed it on my second computer, which first made worry that the seller had activated one copy, and sold me the box. But, after a 60 minute wait on hold with Adobe Customer Service, I now have both copies activated. I suspect that there was an interaction with a previous unactivated copy of Photoshop CS4 that caused the activation problem, but of course I can't really know. Maybe the seller has a deactivated copy on her computer? There is no way to tell, since Adobe won't let you examine your licenses.
    As an aside, I was tried to purchase CS4 Design Standard from Adobe directly at a discount, offering them the following reasoning. I already own various versions of Photoshop, In Design, Illustrator, and Acrobat Pro, each of which qualifies me for a discount for the CS4 version of that product. So I asked sales to combine these, and apply them jointly as a discount so I could purchase the same apps as CS4 Creative Suite Design Standard. Sales declined to do so, and now I have been able to purchase the product at less than the upgrade price. And, when CS5 comes out, I should have 2 possible upgrade paths--upgrade individual apps, or upgrade the package, which is nice. Or I can sell my CS4 licenses to others.
    Here's hoping your luck is as good as mine if you do the same.
    A

  • Purchase Voucher

    What is the exactly a purchase voucher?
    regards
    VS

    Hello VS,
    To my knowledge it is a Voucher against which Vendor is paid amount for supply the material or giving service. In this voucher Vendor details are mentioned along with PO number, PO line item, Amount to pay or paid.
    This is mainly used for Cash purchase or small value purchase.
    Hope this helps.
    Regards
    Arif Mansuri

  • Cash Disbursement report in SAP

    Is there a report in SAP that shows the actual cash disbursement by category. Some of the categories that we report cash disbursement incluse inventory, fixed assets, inter-company, royalties and payroll.
    Thanks

    Please check this answered link:
    Cash Purchase
    cash purchase
    Edited by: Afshad Irani on Jun 18, 2010 10:27 AM

  • Purchase order scenario ------Pls clarify about the scenarios in SAP

    Hi MM Gurus all,
    pls clarify the following:
    1.Purchase Order given to a vendor & material received from multiple vendors i.e. B or C or D with payment to A.
    2.Purchase order to  vendor A & B vendor & other vendoru2019s material received from either A, Bu2026n. Shah Alloys want to make payment to all vendors.
    3 In my client Cash purchase cycle is there for which they will do PO and GR  and payment is made.
    Edited by: Girish  CM on May 31, 2008 2:52 PM

    just try with the partner fucntions

  • Cash payment to vendor?

    hi,
    Please tell me how to pay vendor for cash purchases through FBCJ?
    please tell me whether it is possible to see the line items? how we can know about the amount?
    thanks
    Shraddha

    Dear Shraddha,
    when you are doing cash payment transaction means you are paying the amount against to purchages. you can post the JV though FBCJ under case payment tab
    you can't see the line items before payment why because there is no open items for this transactions.( you are doing this transaction at time means purchase and payment)
    if you want to see after payment there is an option print cash journal click on this and you can find the all line items 
    Regards
    radha

  • Cash Purcahse process in SAP

    Hi SAP Gurus,
    Can y help how we can best way handle cash purchase case where total
    purchase value is very less and our concern purchase section don't want to
    create order. My requirement is that stock updation as well as vendor
    payments should be done without creating any purchase orders. It should be
    linked document as per standard practices.
    Any help or suggestion will be highly appreciated.
    Regards
    Shyam

    Please check this answered link:
    Cash Purchase
    cash purchase
    Edited by: Afshad Irani on Jun 18, 2010 10:27 AM

  • Juniper 90 Days Same as Cash...

    My Macbook Pro was purchased using the Juniper 90 days same as cash purchase plan offered by the
    apple store and while all payments were made well in advance of the due date including the final payment unfortunately the final statement did not arrive until a week or so after the 90 day period
    had passed, thus a finance charge of $50 appeared on the next statement.
    A little sneaky on the part of Juniper to move the due date a week or so later than the 90 day period IMO but i guess i should have caught this before it was too late.
    Just a heads up for anyone else who may have or may purchase using the Juniper 90 day same as cash purchase plan. Make sure your final payment falls within 90 days of your purchase date.

    Since the amount you earn in 90 days is a pittance it hardly seems worth the hassle and intrusion and such to even try to save the opportunity cost of this type of deal.

  • How to manage the Cash Customer - creating & using

    Dear all,
    I have a problem with managing the Cash Customers as following,
    the sales departments have the ability to create customers ( group retail, basically sales department is doing so because they want to save customer purchase data to be used later. ) which will be treated as cash customer ( no credit limit, will be used mainly in Sold to & Delivered to, not for the payer ).
    Credit Dept. will have the ability to create the Credit accounts with its approved Credit Limits.
    the issues that we are facing is, we can control creating of Credit Accounts to avoid having any duplicated accounts, to have the full needed details about the customer. But unfortunately we don't have this control of Cash Customers since it will be created by different departments and there is no roles for this at all. even there is no information mostly for this cash accounts created. so there will be a lot of accounts created for same customer.
    So, who we could manage this issue please, I mean, how we could save the customer data for his cash purchase and in same time, to make creating new accounts done through Credit & Collection Department so we will have full control on creating accounts in SAP.
    I need your kind recommendations and advises based on your wide experience please.
    Thanks in advance.

    thanks for answering.
    basicly we are using one account for cash transaction called "Cash Cusotmer", it will be used as payer in the inovice.
    now, you are talling me that I can save the address to the transaction itself, that is find but I am not sure whether it will help me or not becuase I am not sure if this way will give me report ability with filter and subtotal options.
    And, if i use the way you are suggestion, can I later be able to get a report of the total purchased by customer X ( cash or credit )
    waiting for your kind confirmation please.
    thanks.

  • Goods receipt without PO reference

    There is one case....
    Like My client wants to do some cash purchasing... means GR without PO.
    but he need that there should be some restriction on the amount like in this kind of cash purchasing
    they should be allowed only Upto 5000 Rs for cash not much. (means they cant purchase thru cash if the amount is more than 5000)
    so is there any way so that we can restrict the line Item of whole document restricted with respect to limited amount.
    Pls help

    Hi Megha ,
    Is it that per one PO u want it to restrict for Rs 5000 /- or the total purchases from all vendors to be restricted to Rs 5000/-.
    If it is the first case u may try with User Exits . Contact ABAP for the same.
    If it is the second  case contact ur FI consultant , he will do the necessary settings at G/l Account Level.
    Regards
    Ramesh Ch.

  • Scenario of Goods Recipt without P.O

    Hi Experts,
    My Client wants a automatic P.O to be created while doing the Goods Recipt with 101 Movement Type.
    The Scenario is as Follows.
    One of his Vendor has came to show the 20 sample Material But, Infact there is an requirement of these material for production.
    And Out of 20 Materials he require 15 On Spot. And he wants Directly to do GR with 101 Movement Type and Auto-PO Creation in Background. He wants as usual Inventory Stock to Debit and GR/IR to credit asusual.
    As it is not a Cash Purchase with Movement Type 501,  Apart from this he wants to Process MIRO for that Procured material without P.O , and P.O to generate in Background.
    a) Can we Process MIGO with Movement Type 101 without Purchase Order Created ?
    b) Can P.O be created automatically in Background for the recieved goods with 101 Movement Type ?
    c)Background  Automatically Created P.O Number can be Utilised for processing MIRO ?
    Please Help me out with your Valuable advice.
    Best Regards
    Javeed Ahamed

    Hi Javed,
    As i understand your requirement you need to generate a PO while posting GR with Mov type 101.
    For this there is a standard process, Auto PO on GR.
    Certain prerequisites are required
    1. Material has to be valuated, Material number required.
    2. Standard Purchase Organisation has to be assignned to the plant in Customizing.
        (Enterprise Structure->Assignment->Materials Management->Assign standard purchasing organization to plant )
    3. Valid Info record for the materail at std POrg.
    4. Activate Auto PO for Mvnt type 101 in Customizing.
        Materials Management->Inventory Management and Physical Inventory->Goods Receipt->Create Purchase Order Automatically
    5. Flag Autom. PO in Purchasing view of Material Master.
    6. Flag Automatic Purchase Order for Vendor.
    Once the obove settings are completed in MIGo,
    Create Goods Receipt with reference to Purchase Order, enter mvnt type 101,
    Click on the icon NON-Ordered Item just below the Item Overview.
    Make the entries of the material, Quantity, vendor and post.
    Do let me know if you need any further assistance
    Pradeep
    Edited by: Gnana Pradeep.G on Jul 14, 2009 8:19 AM

  • What is best practice for dealing with Engineering Spare Parts?

    Hello All,
    I am after some advice regarding the process for handling engineering spare parts in PM. (We run ECC 5)
    Our current process is as follows:
    All materials are set up as HIBE's
    Each material is batch managed
    The Batch field is used for the Bin location
    We are now looking to role out PM to a site that has in excess of 50,000 spare parts and want to make sure we use best practice for handling the spare parts. We are now considering using a basic WM setup to handle the movement of parts.
    Please can you provide me with some feedback on what you feel the best practice is for dealing with these parts?
    We are looking to set up a solution that will us to generate pick lists etc and implment a scanning solution to move parts in and out of stores.
    Regards
    Chris

    Hi,
    I hope all the 50000 spare parts are maintained as stock items.
    1. Based on the usage of those spare parts, try to define safety stock & define MRP as "Reorder Point Planning". By this, you can avoid petty cash purchase.
    2. By keeping the spare parts (atleast critical components) in stock, Planned Maintenance as well as unplanned maintenance will not get delayed.
    3. By doing GI based on reservation, qty can be tracked against the order & equipment.
    As this question is MM & WM related, they can give better clarity on this.
    Regards,
    Maheswaran.