Hi,
I have as asset which was capitalized on 2005 with cost center xxx
now requirement is that i need to change cost center to particular asset
Ok it is allowing me to change but these 3 years data will be there in new cost center or old cost centers
when i run a report how can i do it
It is very urgent
I will assigin points
Thanks and Regards
  RAdha

hi Radha
the thing is that now u want to change the cost center for that particular asset but that asset was earlier in differnt cost center so for reporting purpose that data will be there in that cost center only if u dont want that data there in that cost center u can repost it to new cost center

Similar Messages

  • Repeat depreciation run can change cost center in GL a/c or not?

    Hi Gurus,
    I have hit the following issue.
    Fixed Asset 1 originally assigned to CC-01 for month of March.
    And my user has run depreciation for March already.
    Later she changed cost center to CC-02.
    Then she repeat depreciation run for the month of March, from the depreciation result shows the new cost center CC-02.
    But there is no document generated and thus from corresponding GL account, there is no change, still point to CC-01.Which means CC-02 has not been posted to GL account yet.
    May I please know if repeat depreciation run can change cost center in GL a/c or not?
    If cannot, what should be the correct way to post the new cost center in GL?
    Thanks a lot.
    Best Regards
    Li Juan

    Hi, I have tried the method you mentioned.
    I managed to generate the new document (Message shows: Document is posted under number 7500000000).
    So can I say that repeat depreciation run cannot change cost center for corresponding cost element?
    Everytime user has to do manual posting.
    Thanks a lot.
    Rgs
    Lijuan

  • Change cost center in migo

    Hi all!
    I would like to know if it is possible to chage the cost center that was set in the purchase order in the migo transaction. Becuase the view I get from the cost center field is the not changeable view.
    Thanks

    Dear Pablo
    you can change the GL code and cost center through GR but see what the effect is
    1. if the MIRO done throgh GR no. then it will get the effect in your changed Cost center
    2. if MIRO done with PO refecence then the account department didnt get the changed cost center.
    it is good practice not to change the cost and gl account to the existing one because it effect in the account department
    if user mistaken entered the cost center then ask the same to the user to change.
    regds
    dev...!

  • Could not changed cost center field in document type RE - FSG

    Dear Experts,
    I would like to change 'cost center field' in act document type RE (invoice receipt) through transaction FB02
    I have changed the field of 'cost center' in field status group in OBC4 and OB41 (posting key 50 and 86)
    The field staus group both in OB41 and OBC4 are already set as 'optional entry' but field of cost center is still could not be changed/edit (grey area).
    Kindly advice
    Thank you.

    Hi Chandra,
    Can you please details the coding part if you can remember ..so that would be helping me lot...Since it's production issue , we have implement immd.
    Regards,
    Lalit
    Edited by: Lalit  Sharma on Dec 24, 2009 6:45 AM
    =======================
    This problem can be closed. I got the note.
    Edited by: Lalit  Sharma on Jan 12, 2010 12:50 AM

  • Change Cost Center Valid To Date

    Hi,
    I want to change cost center valid To date. Please let me know which t code I use for that. Thanks in advance.
    Thanks & Regards,
    Hemant Maurya

    Hi,
    You can change cost cener validity by creating new cost center through t.code KS01 with reference to same cost center.
    Ex. suppose you have created cost center 5009000000 from 01.07.2005 to 30.06.2006. Now you want the same cost center to be created from 01.07.2006 to 31.12.2009.
    So, Go to KS01 and put this CC code and Valid From to To Date as 01.07.2006 to 31.12.2009. Also put same CC code with CO area in reference. The same CC will be created with all required information. Also If profit center is required field in your CC, then first of all you need to extend your profit center through KE52 t.code.
    Pls get back for further query.
    Thanks & Regards,
    Taral Patel

  • Change cost center in asset master data

    Dear All,
    When I go to change cost center in asset master data by transaction code AS02 it does show gray cost center field and system does not allow to change. I also tried to use time dependent option but field was still gray. Kindly help me in this regard,
    Regards,
    Uddin

    Hi,
    check the accounting object customizing in IMG FI-AA. At the step where you activate the accounting objects you can set a flag "balance sheet relevant" for the accounting objects. If this is checked, then you will not be allowed to change this accounting object in the asset master record after the first posting to the asset.
    Regards,
    Markus

  • Change cost center in AS02-urgent

    Dear All,
    I am running AS02 and want to change cost center. For asset 1200 and sub number 0, the cost center can be changed. But for sub number 3, I can not change the cost center since the cost center field is in grey colour(can not be changed).I have tried with adding new interval but it can not change too.
    Please advice.
    Thank you

    Dear Purti Kristin,
    In IMG under
    Financial Accounting (New) -> Asset Accounting -> Master Data -> Screen Layout -> Define Screen Layout for Asset Master Data -> Choose your Layout-> Double Click on Logical Field Groups option on the left pane of the screen -> Select Time-Dependent Data -> Double click on Field Group Rules on the left pane of the screen -> Make 'Cost Center' Opt or Req as per your requirement
    or
    Financial Accounting -> Asset Accounting -> Master Data -> Screen Layout -> Define Screen Layout for Asset Master Data -> Choose your Layout-> Double Click on Logical Field Groups option on the left pane of the screen -> Select Time-Dependent Data -> Double click on Field Group Rules on the left pane of the screen -> Make 'Cost Center' Opt or Req as per your requirement
    Regards,
    Naveen.

  • How can we change Cost Center in Material document(MIGO).

    Dear Experts,
    Wrong cost center selected in Purchase order, the same copied into" MIGO" document,
    now i need to maintain right cost center .
    please guide me, to change cost center.

    Hi
    If the PO is completely delivered, simply go to KB11N and transfer the value from old cost center to new cost center
    If you are yet to receive the goods, reverse the MIGO, change the PO and do MIGO again
    Regards
    Ajay M

  • Need to change Cost Center Number

    Hi Gurus,
    I have created cost center hierarchy. and now business wants to change cost center no.
    is it possible to change those no.
    If yes then give me a best solutions.

    Hi Tulsim,
    I agree with your answer.
    It is better to go for deletion of that cost center and create new.
    Deletion is possible only when there is no trasactions happen.
    We can always change the description of the cost center at any time but not the cost center number itself.
    Regards,
    Jyoshna

  • Change cost center number in reserve

    Dear All
    is it possible change cost center number  in MB22 (Change reservation)? how can do that?
    best regards
    R.T

    Hi ,
    I have search a lot & conculsion is that ,you cannot change the account assignment data (for example, cost center or order). If the account assignment is incorrect, you must delete the reservation and enter a new reservation.
    You cannot change the material number or the plant for an item. If either of these entries is incorrect, you must delete the item and enter a new item.
    Regards

  • Change cost center in trans.ko02 by function

    Hi  experts,
    i Need to change cost center in transaction ko02.
    Is anyone know wich function/Bapi do i need to use?
    thanks,
    Michal.

    thanks for reply so quikly.
    i need to change cost center for internal order, i dont see where do i fill in the function
    the internal order.
    do you know if it possible?

  • Change Cost center, profit center, BA

    Hi all
    I wonder if there is any way to change Cost center, profit center, BA
    in maintenance order Addit.data Tab according to the WBS element
    ,using user exits IWO10005, IWO10009 and IWO10010.
    The data like business area/ responsible CCtr, Profit Center in
    additional tab are default from the reference object.
    But we need to change these data according to WBS's
    (since WBS has information -Cost center, profit center, BA)
    any help would be appreciated

    Thank you for your reply
    Could you tell me more how to have a look at IWO10010 Maint. order
    (Cust. enhancement for determining WBS element)
    I'm kinda new in ABAP so please help me

  • How to change cost center in asset master data through mass changes

    Hi sap gurus,
    Hi i have 20 assets i have to change the cost center through mass changes provide the solution.
    regards,
    ramanjaneyulu.

    Hi,
    For 20 assets it won't be useful to write a CATT or LSMW. So, either enter it manually or you could correct directly in the tables (ANLZ), though it's generally not recommended.
    Regards,
    Eli

  • Function to change cost center of sales order

    hi guys.
      I would like to know if there is a standard function that change the cost center of a sales order. Could you help me?.
    Thanks in advance.

    Use this FM
    <b>BAPI_SALESORDER_CHANGE</b>
    In the Importing structure <b>ORDER_HEADER_IN</b> you have  the field <b>COSTCENTER</b>.
    Regards
    Kathirvel

  • Using Substitution (GGB1) to change Cost Center assigned in (OKB9)

    Dear all,
    SAP Platform: ECC6
    I've configured both VKOA (GL assignment) and OKB9 (auto acct assignment) for sales billing. In OKB9, I've mapped one cost center to one GL, i.e. GL-123456 = Cost-center-A.
    Alright, now that I've a specific condition that requires to change the cost center at ad-hoc basis, i.e. for material # 2345678 only, I need to assign to GL-123456 but Cost-center-B instead. So, I attempt to use the substitution rule - GGB1 to replace the cost center based on material #. I did the configuration under Cost Accounting | Line Item by creating a new substitution and defaulted the constant to Cost-center-B when material # = 2345678.
    So, I ran the billing in VF01 but the Cost-center-A was pickup instead of Cost-center-B. It appears that the substitution hasn't been triggered. Did I miss a step?
    Thanks.
    Steven

    Hi,
    Have you tried after removing the cost center assignment in OKB9? 
    Thanks,