Change Work Center on a Prod. Order

Hi,
I have been searching through the archives and found a lot of maybe, but no final ideas.
How do you change a Work Center on a Prod Order?
Anybody has a suggesfull way of doing it?
Thanks
Andy

Andy,
Try using BAPI_ALM_ORDER_MAINTAIN. The documentation states this BAPI is for maintenance orders, but we have used it to change the bill of materials and other parts of the production order.
Glenn

Similar Messages

  • Change work center

    Hi all,
    Please excuse my ignorance in what is probably an easy operation.
    What is the transaction code for changing a work center that a production order is setup default to be completed in?
    For example if i have product 'A' that is usually completed in work center '1' but I want to change the data so that next time and every other time I create this product it identifies work center '2' on the production order.

    Hi Gman,
       For producing "Product A" currently you are using work center 1. Instead of using this work center 1 you want to use work center 2. To change the work center, you need to change the routing for the "Product A". Go to CA02  and enter the material and select the routing and press operation, in the operation you will see the work center 1. Change the WC1 to WC2 and save it.
      After changing this, when ever you want to produce "Product A", system will select WC2.
    Hope it clears your doubt. Revert back if you have any questions.
    BR / US

  • Bapi for change work center data

    HIi All
                    I need BAPI to change work center data for all categories and work center change transactions .....IR02 ,CNR2,CR02.
    Thanks in advance .

    Hai,
    Try the fm CRAP_WORKCENTER_CREATE
    BAPI_BUS2054_CHANGE_MULTI
    CRAP_WORKCENTER_CREATE
    Regards,
    Venkat

  • PM Order - Change "Work Center" on operations to "Main Work Center"

    Hi Experts,
    We have prepared a tool for client, which create Maintenance Plan and order in the background.
    The order created is having "Main Work Center" defined at header and "Work Center" at the operations level. In the current scenario the "Main Work Center" and "Work Center" are different say 'ABC' & u2018XYZu2019.
    Client has the requirement that work center maintained at operations should be same as the main work center.
    We need to implement the solution to take care of work center to be same as main work center while creation of the order in the background.
    Has anyone worked on the similar requirement before?
    I checked for existing USER EXITS for IW31/32/33 and found only one IWO10012. This doesnu2019t seem to be much useful.
    Please suggest any possible solution.
    Thanks,
    Ankur Sharma

    Hi Tilak,
    Thanks for the response. The current situation is that we are creating the order in background using the Z-program. The scenario is creating order with operation entries having work center not equal to the main work center.
    I am not functional, so just talking in terms of technical terms.
    Is there a way the work center at operation level can be changed to main work center in background?
    Thanks,
    Ankur Sharma

  • Change Work Center during production order confirmation

    Dear All,
    I must to modeling this situation:
    I created an production order. In routing I used an work center A.
    After I confirmed a half of quantity, the work center A was damaged and I must to change it, with the work center B.
    The system allow this change, but when I checked the costing, the situation isn't real. The system counted the costs just for the work center A, and no for work center B.
    My question is: it's possible to change the work center, during production order confirmation and the costs updated with new cost?
    Thank you for your answer!
    Regards,
    Marian

    once a Order is released, the Process order detaisl for that order is frozen.
    however if you want to do it, change the order status to CRTD after reversing the Movements done.
    Do READ MAster data , this will copy the new Work center , redo the previously done Moevements.
    if the change is long term.
    or
    Just manually add the new work center and do the processing. if the change is temporary.

  • How to manipulate the profit center in the prod order within an mto-flow

    Hello,
    It is allowed in the sales order to change the profit center. I want to copy the entered profit center from my sales order to the profit center of my linked production order which has been created automatically.
    I tried already some user-exits (enhancements PPCO000?) but it doesn't work. Who can help me solving this problem?
    Many thanks for helping,
    Bart

    Dear,
    Maintain the Profit Centre in Costing 1 View of Material Master.
    Then it will be defaulted into the Production Order.
    Profit center can be entered at the item level in the sales order T.Code: VA01, in the Account Assignment Section.
    If Profit Centre is maintained in Material Master Data, in Sales: General / Plant data, then the same will default in sales order.
    Regards,
    R.Brahmankar

  • Dyanmic work center selection in production order based on material

    Hi ALL,
    We’ve a business requirement to support the following functionality.
    There are four similar type of milling machines say MILL1 MILL2, MILL3, MILL4, we create a single work center called MILLMC by specifying total capacity of four milling machines in the capacity header screen of work center with 4 individual capacities. And we mention work center MILLMC in the operation of routings for respective materials.
    However, during production order creation, there needs to be provision for detailed planning of work centers as per the following requirements
    In production order, some operations can be performed on any one of the machines MILL1 MILL2, MILL3, MILL4, so provision needs to be there to enter exact machine on which it is performed in the production order operation after the details are copied from respective routing during production order creation.
    In production order, some operations can be performed on only MILL3, so system should select only MILL3 in the respective operation of the production order
    In production order, some operations can be performed on either MILL1 or MILL2 or MILL4 and not on MILL3, so system should not select MILL3 in the respective operation of the production order.
    Please provide your valuable feedback to support the above requirements.
    Regards,
    Satya.

    Hi Satyanarayan,
      Please do refer to the below document. I think the same concept can be used for work centers as it is used for resources in PI industry.
    Resource Classification in Master Recipe for Planning
    Regards
    Kalyan

  • Work Center Mandatory  in PM Order

    Hi Experts,
    May i know how can i make Mandatory, both  Work center (Mn.wk.ctr) Under Person Responsible sub screen and the work center ( WkCtr/Plnt ) under first Operation sub screen  of the Header TAB in PM Order.
    Regards,
    Kavvya

    Hi,
    The Work Center (CAUFVD-VAPLZ) field under 'Person Responsible' should always be mandatory as it is hardcoded.
    The Work Center (AFVGD-ARBPL) of operation can be set with transaction OIOPD. If the 'work center' field is not available in OIOPD, then see the correction from note [1282463|https://service.sap.com/sap/support/notes/1282463].
    -Paul

  • Read Routing and work center details from transfer order

    Hello
    I am using transaction LT31 to print a form for the transfer order.
    The customer wants me to print a field that is in the work center details of the routing for this material and plant.
    I can see this data with transaction CA02 where i enter material and plant,and then the work centers are beeing displayed.From here i can double click on the work center and see the field Supply area that i have to print.
    My answer now is,how to read details on the work center starting from my transfer order number.Which is the table connection between transfer order table LTAK and the tables where i can find the work center details.
    Thank you

    I have found the solution:
    ltak-tanum = mseg-tbnum
    read aufnr from mseg and go to afko
    mseg-aufnr = afko-aufnr
    read plnnr from afko and go to plpo
    afko-plnnr = plpo-plnnr
    from plpo read arbid and go to crhd
    plpo-arbid = crhd-objid
    from here,we can find the arbpl and the field that i was looking for PRVBE

  • Require help on coast center and work center tables through sales order

    dear experts
    my requirement is to report the cm05(capacity planning ) transaction.
    The original capacity planning consists of workcenter details.
    but my client needs the report as follows
    on which sales order and on which work center we require the capacity of materials.
    any tables and fields for this report please.
    help needed.
    kindly update me.

    hi,
    Please explore table CAUFV View "Order Headers PP/CO" ,here you will find the relationships between the three.
    Regards,
    Neha

  • Changing Profit Center in PartiallyDelevered Sales Order

    Dear Experts,
    Can anybody tell me how we can Change Profit Center in Partially Delivered Sales Order?. in Standard, System allows to change  PC in open sales Order without any subsequent documents.
    There is business requirement to change PC in all Open Sales Orders.
    br,
    vgl.

    Hi,
      I think note 580216 should solve your problem. Please read this note carefully
    regards
    Waman

  • Operations Executed at a Particular Work Center for a Sales Order

    Hi All,
    We are using a MTO scenario. I have to get a report in which I have to list work center wise operations (and the corresponding material) which are carried out for a particular sales order.
    User will create a sales order, and then do Sales Order based MRP in MD50. System will do a BOM explosion for the header material and will generate planned orders for the production relevant materials. User will then convert all these sales order specific planned orders to production orders. For a particular sales order these would be many operations (at different BOM levels may be ) that would be carried out at a particular work center. I need to get a logic for generating this report. Is there any FM etc or table table-field fetchig logic....
    Regards

    hi,
    maintain initial screen entry as sale order.
    Pass values to AFPO table. Identify all AFPO-AUFNR values which satisfies AFPO-DAUTY = 10
    Transfer AUFNR values to AFKO and check AUFPL (Routing number of operations in the order)
    Transfer AUFPL  to AFVC and check the value of AFVC-ARBID (Object ID of the resource)
    Transfer ARBID to CRHD and check value of ARBPL (Work Center)
    Regards,
    Pavan

  • Changing Work Center in PM Order Operations

    Hi PM Experts,
    We got two companies operating in the same SAP client. But user are properly restricted with Authorizations in terms of company codes, maintenance panning plant, maintenance plants etc, etc,
    But I noticed that in IW32, in  work order operations users belonging on to one company can select(F4) work centers/maintenance plant  from the other company and save orders.
    I was under the impression that org level authorizations block this. Is there a way to stop this? provision of the the relevant authorization object in  this regard will be a great help.
    thanks in advance,
    Cheers
    Deepal

    Hi
    Please check the below link. may useful
    [http://help.sap.com/saphelp_470/helpdata/fr/a5/3eca044ac011d1894e0000e829fbbd/content.htm|http://help.sap.com/saphelp_470/helpdata/fr/a5/3eca044ac011d1894e0000e829fbbd/content.htm]
    Regards
    Seenu

  • Modify/Change the center cost in purcharse order

    Hi Gurus,
    For this year I have changed the cost center for G/L Account number 600000 (Old cost center: CMERC / new cost center: 1017). Now I have a purchases order that created the year before and these have the cost center old assign.
    When I try doing the goods receipt for purchase order, the system produces the following error: u201CCost Center FDB/CMERC does no exist on 08.01.2010u201D
    Anybody know if you can change the cost center for purchasing order last year, with cost center old, to account pending the goods receipt?
    Thanks for your help.
    Xevi Gràcia.

    Hi,
    Two options:
    Change the PO before to do the PGI.
    If you use MIGO to de the goods inbound, try with the BADI MB_MIGO_BADI (I suggest method LINE_MODIFY, you have GOITEM-KOSTL that you can change). So, set the hardcode (period, relation between old cost center and new cost center, and so on) with ABAP.
    If you use other tcodes (eg: MB01, MB1B and so on), check these notes:
    Note 1284654 - Caution with implementations of the BAdI: MB_DOCUMENT_BADI
    Note 92550 - Stock inconsistency due to customer enhancement (exit, BAdI)
    I hope this helps you
    Regards,
    Eduardo

  • Change cost center in statistic internal order

    Hello all,
    I have got a problem with the master data of our internal orders. We´ve defined them as statistic objects, and the information of the cost center is an obligatory input within the master data of each internal order. After the first entry has been done the cost center can not be changed anymore. Now we have the necessity to change the cost center in all our internal orders once. Could you help me to find a solution how the cost center remains a changeable input in the master data of a statistic internal order? Or how I may change the cost center just once?
    Thanks for your help.
    Best regards,
    Bettina

    Dear Sir,
    The field is greyed off if the following is applicable:
    -> the order has planned or posted entries
    -> you have created a settlement rule on it.
    If you want to have the field to be changable, please apply the modification note 198036
    regards
    Waman