Charging Porposnate dep to the cost centes based on the Interval Assigned

Hi,
I have scenario were asste is being transferred from one cost center to another and depreciation needs to be charged on proposnate basis between the old and new cost center.
I have changed the interval in the aaset master (T-Code AS02) for transfer, but when I am posting depreciation system is chaging 100% dep. to new cost center irrespective of the date of changes.
Regads,
AB

Hi,
I tested it, made some research and found note 29947:
When posting depreciation with RABUCH00, with account assignment to cost
center, depreciation is always posted to the cost center assigned at the
end of the posting period in which depreciation is being posted.        
Depreciation is not distributed for a proportionate period of time (by  
date) to the time-dependent cost centers assigned in table ANLZ.        
This note speaks about RABUCH00 but is is release independend and still valid.
Have you made another experience?
( Time independent organization unit is not relevant in that case)
regards
Bernhard
Edited by: Bernhard Kirchner on Nov 16, 2010 12:31 PM

Similar Messages

  • MIGO - Goods issue to determine cost center based on storage location

    Hi Experts,
    Any idea how to determine the cost center based on the storage location instead of from tcode - OKB9 when creating Good Issue via MIGO_GI?
    Points will be awarded for useful solutions. Thanks.

    Hey Janet,
    A Cost center cannot be determined from an SLOC..it si always at the company code and valuation aea level

  • How to capitalise cost center based purchase

    Hi Friends ,
    Presently we are buying all plant and machine and Building related on cost center based purchase with GL accounts . We want to capitalise these once project compleate , how to capitalise material with cost center based purchases .
    Raghu

    Hi,
    This as a manual posting in FI from your cost center to the asset.
    TC like FB01
    Use for the asset posting key 70  asset number TTtype 100 fill in the information
    Credit you cost center with posting key 50 GL accounts.
    Wy you don't use Internal orders or projects? From there you can settle your investment to AUC and the final asset.
    Paul

  • How to capitalise cost center based purchases

    Hi Friends ,
    Presently we are buying all plant and machine and Building related on cost center based purchase with GL accounts . We want to capitalise these once project compleate , how to capitalise material with cost center based purchases .
    Raghu

    Hi,
    This as a manual posting in FI from your cost center to the asset.
    TC like FB01
    Use for the asset posting key 70  asset number TTtype 100 fill in the information
    Credit you cost center with posting key 50 GL accounts.
    Wy you don't use Internal orders or projects? From there you can settle your investment to AUC and the final asset.
    Paul

  • Cost center based release strategy.

    Hi Gurus,
    Could anyone explain about cost center based release strategy?. Thanks.

    Hi,
    There are two options i have mentioned below.
    Option-1:
    You can create release characteristics with field KOSTL and add this characteristic with release class with other release characteristics. And you can design your release strategy based on requirement & then limit the cost center via authorization object K_REPO_CCA
    Option-2:
    Create Purchasing Group (OME4) as Department & assign the department to Cost center(KS02/KS01). Now create purchasing group as release characteristics with field EKGRP add this characteristic with release class with other release characteristics. And now you can design your release strategy based on requirement.
    Regards
    Siva

  • Material cost charge to Production Order from Cost Center / Work Center.

    In Production Order Environment, is it possible that goods are issued from Storage location to Cost Center / Work Center, and in turn charged to Production Orders.
    Scenario. Transformer Manufacturing.
    Production Order size : 100 Units
    Steel (Kgs) per Transformer : 3 Kgs
    Total Steel required for Production Order: 300 Kgs (100x3)
    In the process of manufacturing of a Transformer Steel or Core winding is the first process step.
    Even though the Steel required for above said Production Order is 300 Kgs, the minimum issuable lot size from stores is 2000 Kgs.
    Is it possible in SAP ECC 6.0 that the Steel of 2000 Kgs is issued to a Cost Center / Work Center, and later charged to production order based on actual Consumption in the said Cost Center / Work Center.
    Regards, Replies and Sugestions shall be appreciated
    Madhu

    Thank you for the reply,
    However, the scenario that i had in mind was a bit different from what you had conceptualized.
    Scenario - These transformers are basically for loading on to Inverters & UPS, The max weight of the transformer range from 15-30 Kgs. and they dont have an external casing of steel as seen on Indian Electricity Board transformers. Multiple production orders are processed at a single time in the Plant as per Customer specifications.
    The general process followed for manufacture is as follows:
    1. Core Winding u2013 This process takes place in the core winding department. Steel reels are loaded on to Winders and individual cores of approx 5 u2013 30 Cm Diameter are produced. (Multiple reels of Steel are stacked one on top of the other onto a pallet.) Usually issue of steel from stores happens pallet wise. The pallets of steel generally weigh in excess of 2 tons.
    In the present situation (Non SAP Environment) the entire pallet of Steel is issued to the Core winding department and later the Output is charged to multiple Production Orders, based on the records of the Core winding dept. Since in general the steel content in the FG ranges from 3- 25 Kgs multiple Production Orders can be catered to from one Pallet of Steel.
    2. Core Laithing. The wound cores are laithed so as to make the sides smooth.
    3. Core Annealing u2013 Heat treatment process.
    4. Core Insulation. u2013 Insulation of the annealed cores with insulating material.
    5. Primary Winding. u2013 Copper is wound as per the BOM Specification. The issue like that of Steel also arises in the Copper winding process. Here also the Cooper comes in Spools which far exceed the requirement for any Production Order. The minimum issueable lot for Copper from Stores is one Spool. The current practice followed is that the Cooper is taken in the name of the Copper winding department and later charged to individual Production Orders.
    6. Primary Soldering.
    7. Mid Insulation.
    8. Secondary Winding
    9. Secondary Soldering
    10. Shielding
    11. Final Insulation u2013 Same issue with insulation too, since the insulating material comes in rolls.
    12. Testing.
    13. Potting & Drilling - Process of pouring a chemical compound in the center of the transformer, which helps the transformer to later be loaded on an Inverter. The same issue with like of Steel, Copper & Insulation arises here too, since the chemical compound comes in big containers capable of meeting production requirement for a week.
    14. Packing
    15. Transfer to FG Inventory.
    One of the suggestions was to issue the entire 2000 Kgs to the Production Order and then return 1700 kgs after completion of the Production Order based on actual usage. However, in my opinion this option might not be practicable because, assuming that I get another / multiple Production orders in between the issue of 2000 Kgs and return of 1700 Kgs, issue to the new Production order will not be possible if the stock in stores was only 2000 Kgs initially. In case assuming that the material is available in stores for the next production order, the situation could worsen in case of receipt of multiple production orders.
    Hope, I have explained the scenario & issue being faced.
    Regards
    Madhu

  • CATS Time Entry - Charging time to a different cost center

    We are looking at using CATS for time entry for our salaried non-exempt employees.  Some of these employees charge their overtime to a different cost center.  For example, normally their overtime is charged to their own cost center but periodically they help another group and need to charge the overtime to the other group's cost center.  In the CATS profile where you select the fields you want to be available for input, display, etc., I see cost center as an option.  However, when I select it as a field for input, it does not appear on the timesheet.  I see there are other cost center fields (receiver cost center, sender cost center) but I thought these had more to do with work orders (not sure of that, though) and work orders are not used for this group of people.  Currently, the time is being charged to an alternate cost center when the time administrator enters the overtime via PA30 and then selects the 'Cost assignment' button to record the appropriate cost center. I would appreciate any information/guidance you can provide.  Thank you.

    Hi Kathleen,
    We are trying to do the same thing so I understand exactly what you are asking.  We made the sender cost center field an input field via the IMG - Cross-Applications Components> Time Sheet> Time Recording> Choose fields> - select data entry section and look for sender cost centre - field name CATSD-SKOSTL - ensure "input" is selected.
    Eventhough we have been able to enter an alternative cost center with an attendance (i.e., different from the employee's cost center saved on IT0001), it is not being transferrred to HR (does not appear on attendance infotype) therefore payroll does not pick-up the cost center with the attendance hours and it is not posted to FI.  Payroll continues to use the employee's home cost center.
    Have you been able to get any further with this issue?
    You can contact me directly if you like - 1-613-599-8600 - ext 243.
    Catherine Maunder
    Calian
    340 Legget Drive, Suite 101
    Ottawa, ON, K2K 1Y6

  • Sender Cost center based allocation

    Hi All,
    This is unique scenario as per my knowledge.
    Actually we have same cost centers present in two (rather more) different buildings in the company. And as per cost center design each building has been created as a cost center. And the building costs are getting allocated based on SQM (square meters) as SKF.
    Problem: In KP46 where we enter the SKF, we can enter one total value for one cost center. So in SKF if I enter one total value (for all buildings) in the cost center then from all cost centers it will take more than its proportionate share of costs.
    <b>Can you help me in solving this issue?</b>
    I have already ruled out following options:
    1. Creation of multiple SKFs
    2. Creation of individual cost centers per building.
    Because we may have 40-50 buildings in the design. And that will increase the data maintenance efforts many times.
    Waiting for your replies.
    Please post in case of any queries.
    Rgds,
    Manish Gupta

    Hi,
    no this is not causing the issue. It means that after the first internal allocation cycle  run, the results are checked and if there are senders that still have values a second internal allocation cycle is porcessed (based on the results of the first one), this goes on and on till every sender is (nearly) allocated to zero (or the sender % it should be).
    But again: Try to eliminate sending/receiving values within 1 segment for the same CO-object (cost center) to avoid situations like the one you've described.
    Best regards, Christian

  • Default employee cost center based on work center

    Greetings,
    How can I default an employee's home cost center in IT0001 based on their work center assignment?
    I've tried linking both the employee's position and their org unit to the work center via CR02. This did create the IT1001 records. The work center does have a corresponding HR work center. I've even tried attaching a cost center to the HR work center with the IT1001-A011 relationship. No luck.
    Seems like OM side is doing what it should, but we want to get the work center's cost center in the costing tab over to the employee.
    Maybe there's an integration switch that I'm missing somewhere?
    Thank you!

    Thank you both for your thoughts. We have tried the ZXPADU0x exits, but it appears that SAP will not allow us to change an existing cost center value in IT0001 via defaults. I think this is because SAP wants to always keep OM and PA in sync, based on the A011 relationships in IT1001 on the position or org unit.
    In terms of OP42, yes, we have tried adding relationships between the work center and position/org unit and also employee. And also have the cost center linked to the work center on the costing tab. But we're still not able to get that cost center to pull into IT0001.
    I'm wondering if the integration between work centers and HCM is limited to relationship links on the OM side?

  • How to determine a cost center based on a storage location

    Hi all,
    During material movement or stocked purchase, I need to determine different cost center by storage location. Therefore, i can't use OKB9 because the plant criteria is not enough.
    Is there any user-exit or another solution i can implement to solve this problem?
    Thank you for your answers.

    Hi
    As i said earlier, you can use MSEG itself in your substitution rule.
    For  Ex:
    Pre- requisite
    BKPF-BUKRS = 'XXXX' AND BKPF-AWTYP = 'MKPF' (and anyother criteria that needs to be applied)
    Substitute
    Field - Material (MATNR)
    is substituted by "EXIT"
    Create your own exit here & give your logic like
    If MSEG-LGORT = '0001'(your storage location values)
    then BSEG-KOSTL = 'CCTR1'.
    Let me know if you need any further details.
    Thanks
    Kalyan

  • Cost Center based Release Strategy for PR's

    System :4.6c
    At this time, we have PR release strategy with classification configured for over all release.
    Created a new characteristic for cost center , assigned the values for the cost center characteristic, with zeros at the beiginnig.
    Now when I create a PR with multiple line items and with multiple cost centers, the system is not deriving the release strategy defined. But if I create multiple line items with the same cost center, the system is able to find the right release strategy.
    Does it have to be the same cost center in all the line items to trigger the right release strategy?
    Thanks.

    Hi,
    Looking at your question it seems you are using overall release strategy. If the characteristic value is not same for all line items then during overall release strategy determination, the system uses "BLANK" value for this characteristic.
    In order for a release strategy to be found, when you have different
    cost center in different PR items you need to add a blank value to your allowed characteristic value for the cost center in your release strategy. Also use Account Assignment Category (KNTTP) as one of your characteristics and define K as an entry, so that release is triggered only when it determines cost center blank with account assignment K.
    But if for diff cost centers there is diff strategy then you better opt for Item level Release.
    Please give this a Try.
    Regards
    Chandra Shekhar

  • Cost Center Errors for new Account Assignment "P"

    Hi Friends ,
                       We are implement PS for our client , and we are facing some issues with Cost Centers when trying to creating a PO with reference to a PR with the new account assignement "P" -Project .
    Currently our client is using "K" as account assignment  for the doc type which we are using above . The error we get is "Please use cost center 400100 not cost centeru201D. And we get this error randomly , and doesn't seem to occur for all the plants .
    Has anyone come across some thing like this ?
    Please let me know if you need any additional details .
    Thank you ,

    I feel that your message type ZX000 is custom message.  you have to take inputs from your ABAP that in which situation this type of error comes perticularly debuggin scenario.
    Virendra sir, please add on.
    Regards
    Nitin

  • Inactive cost center is able to be assigned to a vacant position or Org uni

    Hi,
    Is there a config that can be turned on which prevent inactive cost centre, ie cost centre which has been blocked to be assigned to a vacant position or a Org Unit?
    Thanks
    Regards,
    HR team

    sounds straightforward...
    just supply a simple report screen with cost centre parameter and employee select options.
    Loop through all the employees in the selection option ITAB
    apply the cost centre parameter to each
    remember this info in a suitable internal table you have declared
    process that itab
    update the infotype 0001 as suggested by Kumar by HR Maintain BAPI, or BDC  to PA30-IT0001 or HR INFOTYPE Operation function - whatever is preferable your end.
    2 hours coding - (optional - pass the results in a simple SALV for completeness)
    Your over thinking it - you just want a simple utility to manipulate the cost centre in the employee infotype

  • ME21N: COST CENTER DETERMINATION BASED ON STORAGE LOCATION

    Hi,
    When creating a purchase order (ME21N) I need to determine the cost center based on storage location. How can I solve this problem?
    If the solution goes through creating an USER EXIT, please, have in mind that my knowledge about ABAP is really poor.
    Thanks in advance.
    Luis Álvarez.

    Hello Priyanka,
    first of all, thanks for your quick response.  By COA I suppose you mean Controlling Area.
    Secondly, isn't possible to implement something like this for purchase orders?:
    https://forums.sdn.sap.com/click.jspa?searchID=18930382&messageID=6494959
    Regards,
    Luis.
    Edited by: LUIS ÁLVAREZ on Nov 20, 2008 8:28 AM

  • How to Override Cost Center in IT 1 based on certain conditions

    Hi,
    I have a pretty good understanding on how Cost Center gets defaulted based on Org Structure.  The standard SAP solution for Cost Center will not work for my client and I need to determine the cost center based on certain conditions. I understand that I have to write custom code in some user exit or badi. I tried user exit EXIT_SAPFP50M_001, but it did not work.
    Here is my code:
    DATA: I0001 LIKE P0001.
    CASE INNNN-INFTY.
        WHEN '0001'.
          CALL METHOD CL_HR_PNNNN_TYPE_CAST=>PRELP_TO_PNNNN
            EXPORTING
              PRELP = INNNN
            IMPORTING
              PNNNN = I0001.
    This is just an example to test the concept
    I0001-kostl = 'COST_CENTER'.
         CALL METHOD cl_hr_pnnnn_type_cast=>pnnnn_to_prelp
            EXPORTING
              pnnnn = i0001
            IMPORTING
              prelp = innnn.
    endcase.
    When I change IT 1 record and hit enter, I can see that my code is being executed. I can see cost center being updated on the screen, but when I save it, its not able to retain that new cost center value. This might be because cost center is not an open field.
    How can I change my code so it retains its value after saving?.
    Thanks!

    Contd to manoj
    Cost Center will be a Open feild when the value of   the  switch PLOGI ORGA  should be balnk if it is haveing 1 than it will not default the value kindly check

Maybe you are looking for