Confirmation of activity on material GR (MIGO for PO)

Hello Friends,
For non stock items, I am generating material requirement in network with item category "N".  Based on my project requirement, I am putting requirement date for the material on "General Data" tab of component overview. I want my activity to be confirmed as and when I am making GR for this material.  Please assume that there is single component planned for each of the activity.
Can anybody help me ? 
Thanks and best regards
Bharat Parikh

Hi,
As per std SAP activity confirmation is a manual activity.
For this kind of scenario you need to go for development !!
Regards
Abhinay Gautam

Similar Messages

  • SLoc disabled in MIGO for Material in MIGO for a PO

    I am trying to create a MIGO for a PO and one of my materials is disabled and hence am not able to enter the SLoc for that material.
    When I SAVE the transaction, I get an error to maintain the SLoc.
    How can I maintain the SLoc for my first material now?
    Thanks,
    Kiran

    Hi,
    Can you check if the Material Master is set and a Sloc specific view and Plant specific view extist for that material.
    Also, check if there are other PO with this material as Line Item and they aleast have the sloc populated in the PO..
    You can try to edit the PO to append the sloc.
    I have not faced this situation but of the view that  , this PO might have got created with incomplete Material Master setup.,  if the Material Master sloc view is in place and if PO is having Sloc then this issue will not happen.
    Hope this help.
    Tnx
    MJ

  • How to change component / actual used material during MIGO for Suncontract

    Hi
    We have below scenario, need your expert help...
    1) As per BoM Material A- is produced from Mat B.
    2) Sub-contact Order is created with Mat A and Mat B is sent to Vendor with Mov type 541.
    3) In few cases Mat A can be produced with Mat C / mat D etc
    4) Now at the time of MIGO..we will come to know that which mat is used .
    Question: -  Can I change component material at the time of MIGO. I mean can change component material from Mat-B  to Mat C etc.

    Hello Rajesh,
    You need to change the component in Purchase order (ME22N). there is not separate table for this.
    - Go to ME22N transaction
    - Select the line item for final product
    - Go to Material tab and click on "Component" at rightside
    - Add new material number here
    - You can keep old material or delete it.
    Hope this helps.
    Regards
    Arif Mansuri
    Reward if answer is helpful

  • Issue to make mandatory field(SELD/BBD and Date of manufactor)in migo for particular Material type and material Number starting with'1' series.

    Hi friend,
    i have issue regarding mandatory  self life field (SELD/BBD and Date of manufactor)in migo for Batch Tab for particular Material start with '1' Series and material type.
    i want to make mandatory above field during GR from migo..any one let me know exit or badi for that to full fill this goal..
    Regard's,
    shaikh Khalid.

    Hi Shaikh
    First of all Thread is not closed seconldy as a good practice if you have resolved your issue kindly document it here so that it may help someone in future
    Nabheet

  • Migo for subcontracting po- Excise invoice is posted later to material docu

    Dear all,
    While we are doing migo for sub-contracting PO we are getting an error like this  Excise invoice is posted later to material document.
    process
    1. Create subcontracting PO.
    2. Issue material 541 MVT.
    3. Create sub-contracting challan- dated 8-8-2010.
    4. Migo date 8-8-2010.
    while entering subcontracting challan no & year, error messege  is coming as Excise invoice is posted later to material document.
    Pls give solution.
    Thnaks & regards
    madhu

    Hi,
    You will have to post the MIGO at least one day after the creation of Excise Challan.
    Regards,
    Prashant Kolhatkar

  • Goods Receipt is allowed through MIGO  for PO's though they hav the confirm

    Goods Receipt is allowed through MIGO  for PO's though they hav the confirmation control key. where as its should allow based on ASN(inbound Delivery).
    Not sure if any system changes has to be made or anything else. please suggest.
    Thanks

    Hi Dear <
      You can also recived the goods  with reference to inbound Delevery,
    1  Select  In Confirmation  Tab Con con key while in  Creating PO
    2  Create a Inbound delevry from T.code: VL31n
    3 Once you create the Inbound delevery wth reference to PO, The inbound delevery no will be propulated in  Confirmation Tab of PO
    4 you can Do the mIGO  with reference to that Inbound delevery

  • Blocking print out put for a material in MIGO with reservation

    Dear Gents
    How can we block printing a particular material of a storage type from MIGO for reservation
    regards
    anant

    hi ashok,
    what is the output type you have assigned for the printing.
    in mn21 you create a output  type we03 with tr.event as we and print version as 3(collective slip ) at the time of Migo.
    print indicator as 1.
    you can also take the print in MB90.IN THIS you give the document no and processing mode as2 for reprinting and then execute.
    Regards,
    velu

  • While doing MIGO for a material we getting error as?

    Hi,
    While doing a MIGO for a material we are getting a error as ''special stock o of a vendor doesnot exists"
    Thanks
    KK

    if you are following subcontracting process then do following
    Transfer material to vendor by Mb1B or MiGO transaction with movement type 541 ( you can also use ME2O)
    Then do GR, This error will get solved

  • MIGO for pipeline material

    Hi,
    I am trying to post MIGO for pipeline material, while at the same time I am facing following problem while executing:
    1. At the time of the Goods Issue of the Pipeline material, the error ocured: Account determination for entry INT GBB _____ VBR not possible.
    So maintained an enntry for the same in the OBYC setting, but received a new error: period 001/2005 is not open for a/c type S & G/l A/c 790000
    Thus tried to solve it by going in FS00, but change authorisation was not available.
    Please help me in coming out of this
    Thanks 
    Ritesh

    Hi,
    Now Use t.code: OB52 and open current period in Account Types  S and specially Account Type “+” which stands for valid for all accounts type and save( also can check A, K, D,M,). Better consult FICO consultant for OB52 step.
    Also Check in T.code: MMRV and see which period is open for ur Co.Codeand back posting is allowed or not.In MMPV close the period last period and automatically system open the new one.
    Regards,
    Biju K

  • Enter chapter id for material during MIGO

    Hi,
    While doing MIGO for STO  system is giving following error.
    Enter chapter id for material during MIGO.But i have maintained chapter id and material combination in J1ID and also Excise duty
    rates but when i enter excise invoice no in header only for one particular item chapter id is missing and some times chapter id is coming but AED, BED and SED (duties) are not being calculated.
    Please do needful ASAP.
    Thanks,
    Santosh.

    Hi
    1) Check your chapter ID for supplying Plant It should be same as receiving plant in J1ID
    2) I think at the time of outgoing excise invoice you have  not maintain chapter Id for material of supplying plant  ,later you maintain at time of MIGo thats why error is coming even you have maintain chapter Id in J1ID now
    3) check your outgoing excise invoice document in table J_1IEXCHDR in t-code se16n
    Regards
    kailas Ugale

  • Interlock for confirmation of activity

    Dear Gurus,
    My scenario is as follows -
    I have created project structure, It has single network and activities looped into.
    Activities are spread across several WBS elements.
    I have done scheduling of netwok by linking all activities and defined relationship (FS) in network graphics.
    The finish to start sequence is like this
    10 - 20 - 30 - 40 - 50 and so on
    Problem - After releasing the project and network, I am able to confirm any activity in above sequence.
    Requirement - system should not allow me to confirm activity 30 before confirmation of activity 10 and 20.
    But I am able to confirm activity 30 before confirming 10 & 20.
    Pl suggest me which settings I may need to do. Useful answer will be blessed with full marks.
    Thanks and Regards
    Parimal

    Dear Parimal,
    Please go to the T-code OPSU and find the control key used in your network profile. Now change the confirmation indicator to "2 - Confirmation Required".
    This will solve your requirement
    Regards,
    Uddhab Paul
    Edited by: Uddhab Paul on Feb 12, 2009 7:29 AM

  • Updating Batch classification data from MIGO for Purchase order

    Hi,
    I need to update batch classification data (in MSC3n) from MIGO for purchase order. The logic needed for this is as below,
    1) Pass material and batch to MCH1 table to get CUOBJ_BM.
    2) Pass CUOBJ_BM to INOB table to get INOB-OBJEK.
    3) Pass INOB-OBJEK to CLAF_CLASSIFICATION_OF_OBJECTS to get class name & characteristic name.
    4) Pass INOB-OBJEK, CLASS name and characteristic name to BAPI_OBJCL_CHANGE to update batch classification data.
    I created implicit enhancement at the bottom of FM "CLVF_VB_INSERT_CLASSIFICATION". But the problem is, the return parameter of BAPI_OBJCL_CHANGE is giving the following error.
    Class type 023, object type MCH1, object RAW-6             0000001151
    Object is currently locked by user
    The assignment was not changed
    Please let me know how to do it. Is there any BADI or User Exit?

    Hi,
    As you said the break point is not triggering did you activate your exit and activated even the project to which your exit is assigned.
    I hope you missed activating your project in CMOD transaction. Please verify it once and if it is not activated then immediately activate it and try debugging again.
    Regards,
    Rafi

  • Single time receiving material from stores for diff process order.

    Dear all,
    I am creating 5 different process order for 5 different FG material.
    But for all 5 fg material one bill of material is common to all.
    While receiving material from stores that particular bom i need to get single time only from stores for all five process order.
    Kindly please let me know how to process.
    Regards
    Rajasekaran

    Hi Raja,
    As replied to your earlier threads, unique reseration is created against each process order. Accordingly issue also takes place againt unique reservation/process order. Use MB1A/MIGO for individual issue or pick list COIK where issue an be done by stores for all process orders in on go.
    In SAP Mill Products once DIMP is activated there is combination order functionallity available where if operations/ BOM of 5 orders are same then combination order (New order) can be created by combining the qty of 5 individual orders. Here Goods issue is done against the new combined order which is single order for total 5 orders qty. This functionality i used in Discrete Maufacturing.
    Have a look.
    Combined Production Order Processing (DIMP)
    http://help.sap.com/saphelp_erp60_sp/helpdata/en/7c/ea814440ce11d385c70000e8200b4c/content.htm
    Thanks & Regards,
    Ramagiri

  • Auto Confirmation of Activity Elements on confirming an Activity

    Hi all,
    When i confirm an activity in CJ2B i.e when i give a percentage of completion to an activity,
    the activity elements under that activity should automatically be overridden by the percentage given...
    irrespective of the earlier percenatge of the elements..
    eg : earlier data
    Activity/Activity Element       percen of completion.
    Excation                                  10%  
           helper                                 2%
           jcb                                      25%
    now when i confirm excavation as 50 % ...it sould auto upadte the activity as
    Activity/Activity Element       percen of completion.
    Excation                                  50%  
           helper                                 50%
           jcb                                      50%
    Is there any setting for such a funtionality or do i have to use some BAPIs ...IF BAPIs then what are the BAPI name.
    plz help,
    Johnson

    Hi Johnson,
    Even I am working on the same scenario.
    The way I handled the scenario is slightly different.
    I havent created them as activity elements as you are aware that there would huge quantum of data.
    In my project, I need to capture labor and material requirements for whole month for all activities.
    So I had created all labor as materials.  I have included them in BOM.  Exploded the BOM thereby genarating hte material and labor requirements.
    Once I get the labor requirements, I have created the same as Serivce PO and created a dummy vendor.  I am doing Service entry but no service acceptance as my scenario doesnt suggest me to capture the actual cost of subcontracting manpower.  They wanna track only Plan Vs Actual.
    Check the report for service entries.  I could able to manage to get Plan Vs actual from different reports.
    Thanks & Regards

  • Confirmation of activity type in Process order -Impact in FI.

    Dear All,
    On doing a confirmation of a activity type for a process/ Production order - values get posted to secondary cost element which has been assigned to a acitivity type.  This means only a impact in controlling but not in FI
    How woould the booking happens in FI ?is it not required to book in FI, if yes, why.
    Please suggest.
    Thanks.

    Hi Daya
    1. You can calculate activity price for plan in KSPI and for actual KSII for respective CCtr and activity type...but some times people manually update price at KP26 directly which in my opinion is not right way because price is either more or less than the real calculation in KSPI and KSII...
    2. However in your case price is directly updated in KP26 against activity type..when confirmation is done in order this rate * activity qty is your value posted in order level and at the same time respective CCtr is also credited by this amount which you can see in CCtr report
       Example:  CCtr  XXXX01
                       Activity type 999999
                       Sec cost Element for activity type 999999 (43 cat)
        Suppose you have booked FI entries for some expenses like Salary in F-02/FB50...against CCtr XXXX01   So your CCtr XXXX01 is debited by Salary amount and this amount will be absorbed in product through activity for which you need  activity price and confirmation.
        FI entry is booked your expense in GL a/c Salary and same time debited your CCtr through CE salary....Now when you charging this expense in product through prod order you are doing it through confirmation of activity qty which in turn calculating value by taking price from KP26 and qty from confirmation.
    Kamal

Maybe you are looking for

  • Creating Condition Table.. Key fields and line items

    dear all I am creating a Condition table and have 6 fields, I want to make 5 of them as key fields and also header line fields. I want my 6th field as line item field but I am unable to do that. My last key field is also shoiwing in line item. Please

  • Want to use touch screen in photoshop. Heard this is supported for new surface 3, is there any way to use it on any touchscreen laptop running windows 8.1?

    Hi, I have the lenvo yoga 2 touch. I run windows 8.1, want to use touh facilities in photoshop. Can I do this yet? Heard surface 3 can due to special deal with adobe, will this be availble to all cc users or will there be extra charge etc. Any info a

  • Audio settings

    How do you make the audio setting work? I cannot change my audio capture setting it is in gray and I cannot access it. HELP. I am running an IMac IC with FCE 4 TIA.

  • IMovie stopped importing video - Why?

    I started importing from a Sony VCR mini DV camera using a FireWire 800/400 Cable 9/4 as recommended by Apple staff. It started importing a video (worked just fine) but stopped when I plugged the camera into a mains supply (probably should've plugged

  • Dblink is creating issue

    Hi We had a dblink at one of client side, they are pushing data throught a dblink since long time. Now they are facing some problem while insert bulk records through application. As a trial basis i tried to pull reccords through dblinks and is workin