Copy Project to different CO Version down to activity level

We have tried to copy a project from one CO version to another using transaction CJ9B, but it only copies to the WBS element level.  Is there a transaction that will copy a project to a different CO version that included components down to the activity level?
Thanks, Rae

In Cost Planning for CO version 0 (Plan version 0) in CJ40 you are planning costs at WBS level, not at activity level.
So where the question of copying activity cost come?
Activity costs come at activity level planning, not in plan version level.
Which as mentioned can be copied by simulation version, project version.
SSanjay

Similar Messages

  • Data copy to from different scenario, version to one scenario version

    Hi,
    I have this scenario to do.
    Copy data from 3 scenario version to one scenario version.
    Scenario1 -> final to TargetScenario -> working
    Scenario2 -> final to TargetScenario -> working
    Scenario3 -> final to TargetScenario -> working
    Means 3 scenario data into one
    Sum of all three
    I am using Datacopy command to target but this is wiping out previous scenario data
    Any thoughts which command to use or else???

    You cannot use DATACOPY here.
    Create a calculation script which does fix on working
    Target scenario= scenario1->final+scenario2->final+scenario3->final;
    Regards
    Celvin
    http://www.orayplabs.com
    Please mark responses as helpful/correct if applicable

  • Change cost planning after copying to different CO version

    Hi,
    I have done network cost planning through project builder, after completing this I copied my cost planning to different CO version. Now I'm not able to change values of second CO version. I can see the figures in reports, but not able to change using CJR2 or CJ40 transactions.
    Thanks

    Hi,
    Full authorization is provided to the user, and the required fiscal year too is configured in second CO version. This is not solved the problem!
    If my understanding is correct, only version 0 can have network costing, all others will have either cost element based or WBS element based cost planning.
    Now, when a network costing is copied to another CO version, the destination version can't hold cost planning in the form of network costing then what type costing second version would be having and how one can modify the value and quantity in that version?
    Thanks

  • BAPI/FM: Copy Project Version(CJV4)

    Hi All,
    I want to know is there any other way other than doing BDC for copying project version(CJV4 transaction)? I need this information in 4.6c version.
    Any pointers are welcome.
    Thanks and Regards,
    J.Jayanthi

    Hi
    There is no BAPI for CJV4 in 4.6 as well as in ECC 6.
    Regards
    Abhii

  • How to Launch an Integration Builder under two different java versions

    How to Launch an Integration Builder under two different java versions     1
    1. Situation     2
    2. How To Do     2
    2.1 jre preparation     2
    2.2 Put them into the system     2
    2.3 Execute a Java Web Start under jre 1.4.x version     3
    2.4 Change Java Runtime Versions     3
    2.5 Launch an Integration Builder     6
    1. Situation
    OS: windows 2000 pro – English
    Java version: jdk 1.5.x was already installed. (It’s not permitted to change.)
    I don’t have any authorization to install any software on the PC.
    But I need to use an Integration Builder.
    I already knew URLs of an Integration Builder (http://<hostname>:50000/rep/start/repository.jnlp).
    2. How To Do
    At this moment, an Integration Builder (XI 3.0) can be launch under jre 1.4.x environment (on windows).
    2.1 jre preparation
    I download j2re-1_4_2_10-windows-i586-p.exe from http://java.sun.com/j2se/1.4.2/download.html
    I installed it on my home PC and copied all files from C:\Program Files\Java\ j2re1.4.2_10\ into my USB.
    2.2 Put them into the system
    I pasted j2re1.4.2_10 folder from my USB into the windows 2000 pro system.
    Finally, I could list up all of javaws.exe under this system.
    c:\j2re1.4.2_10\javaws\javaws.exe
    c:\Program Files\Java\jdk1.5.0_05\bin\javaws.exe
    c:\Program Files\Java\jdk1.5.0_05\jre\bin\javaws.exe
    c:\Program Files\Java\jre1.5.0_05\bin\javaws.exe
    2.3 Execute a Java Web Start under jre 1.4.x version
    I executed c:\j2re1.4.2_10\javaws\javaws.exe .
    2.4 Change Java Runtime Versions
    Go to File-> Preferences -> Java
    As you can see, it indicates 1.5 version.
    Click [FIND] button.
    Click [NEXT] button.
    Click the j2re1.4.2_10 folder.
    Click [NEXT] button.
    A JRE Finder is able to find javaw.exe automatically. Or you can indicate C:\j2re1.4.2_10\bin\javaw.exe directly.
    Click [NEXT] button.
    Finally, there are two Java Runtime Versions. Now you need to uncheck the Enabled column of 1.5 version and check 1.4 version.
    Click [OK] button.
    Well, in the General tab, I selected None for Proxies.
    2.5 Launch an Integration Builder
    In the Location field, I typed the URL of an Integration Builder jnlp.
    http://<hostname>:50000/rep/start/repository.jnlp
    SAP Integration Builder comes up inside Applications area.
    Select it and click [Start] button.
    If you click Environment-> Integration Builder (Configuration), you can launch Integration Builder: Configuration.
    [PDF file location] with screenshots
    http://SDN.mobilian.org/SDN/How2LaunchIB.rar
    ===================Advertisement==========================
    How do you search SDN?
    What about [<b>SDN Search Widget</b>]?
    SDN Search Widget
    =========================================================

    I am not getting anywhere with deploying my application or
    applet.
    I have set up my bc4j project. It contains all my VO info,
    links, application module. (proj a)
    I then have another project with DbInfo in it(has all my rowset
    info), Multiple Frames, and my Applet.java file.
    Actually I have an Applet.java file and a Application.java file
    because I was seeing if both/either worked. Anyway they seem the
    same, except for that extra window that comes up when you run the
    applet.
    I follow the steps in the oracle directions (from earlier post).
    And all seems ok. But at ---->
    [*] Select the subdirectory under myhtml where your applet's HTML
    file
    is located, and enter the directory path of the 'staging'
    directory you
    created in step 3 above, if different from the default.</li>
    [*]Select the HTML files that JDeveloper created to run your
    applet.</li>
    [*]Select all of the Java source files in your project that make
    up the
    applet.</li>
    I have no HTML file associated with my applet, at least that I
    know of.
    So do I need to create one, or should it of been done
    automatically.
    Also, I trying to figure out what will be the best way to deploy
    my project. Applet or stand alone application is what my first
    choices have been so far. I have read that there is some issues
    with applets being served from a different server than the
    database. So a stand alone application was my front runner, but
    I haven't gotten either way to work yet.

  • Problems using projects created in older versions of iMovie

    I have a few projects created in older versions of iMovie, as far back as version 2 as well as more recent versions. Most of those projects are finished and I want to burn them to DVD again, but a couple of them could bear a little touch up editing. These projects are precious movies of our kids and hard to replace. Although I could probably find the original video, I put many hours of work into creating these projects.
    In any case, when I open up an old project, I get a warning that goes something like this: "The project was saved with an older version of iMovie. Opening it in this version will cause it to be upgraded, which will make it unreadable by older versions. Are you sure you want to open it?"
    I clicked okay, thinking "sure, I don't need to play it in an older version. I have iMovie HD."
    However, now when I play my old iMovie project, there are a few problems. For example, one original movie's title was over black. When I play the movie, I get a completely white screen and no title. Also, in another movie, when viewing the movie in full screen, the transitions were replaced by a black screen (although the transitions were there when I viewed the movie in the iMovie window). Basically, there are problems cropping up here and there.
    I need to do some more experimenting with all this to more fully understand how many problems there are. I don't know if the projects I opened in iMovie HD are now "broken" since I "upgraded" them with iMovie HD (when prompted to save the project's changes when quitting, I said NO, don't save changes).
    I don't know if I should use older versions of iMovie to view and burn to DVD these projects. (I still have iMovie 2 and 3, but not 4 or 5. I don't know if older versions would even work on my Quad G5 with OS 10.4.7.) I also don't know if the older versions of iMovie would work with the current version of iDVD. How can I tell which version of iMovie was originally used for a given project? How can I find iMovie 4 or 5 if I need it?
    I also wonder if projects I make with iMovie HD can be opened by future versions of iMovie, or if I should export them as Quicktime or something to be safe.
    As I start to look into this further, I would appreciate any comments, suggestions, and experiences that you may be able to offer. I need to get these movies back to their former selves, when they looked good!
    Message was edited by: Anthony M Kassir MD

    (when prompted to save the project's changes when
    quitting, I said NO, don't save changes).
    Excellent! That should leave you in pretty good shape. More below.
    I don't know if I should use older versions of iMovie
    to view and burn to DVD these projects. (I still have
    iMovie 2 and 3, but not 4 or 5. I don't know if older
    versions would even work on my Quad G5 with OS
    10.4.7.)
    The old versions of iMovie will run just fine in today's OSX. (But not iMovie 2 if it was the version that ran in Classic instead of Mac OSX.)
    I run versions 2,3,4,5 and 6 today. Problems are minimal.
    I also don't know if the older versions of
    iMovie would work with the current version of iDVD.
    That's not a problem unless your old iMovie projects contain chapters. If you tell iMovie 3 to create a new iDVD project, it might not work. You might not be able to transfer the chapter information to the newer version of iDVD.
    (I just tested iMovie 3 to iDVD 6 and everything worked just fine.)
    Except for iMovie 2, all old versions of iMovie stored a small QuickTime reference movie in the project folder. If you can't get an old version of iMovie to play nice with iDVD, drag that movie into the iDVD window.
    How can I tell which version of iMovie was originally
    used for a given project?
    Drop the project file (discussed below) onto the TextEdit icon in the Dock. The version of iMovie that last saved the project is shown in the first few lines of the project file.
    iMovie 5 used an entirely different project file format, the pList format. The top of the project file will look like this in TextEdit:
    <?xml version="1.0" encoding="UTF-8"?>
    <!DOCTYPE plist PUBLIC "-//Apple Computer//DTD PLIST 1.0//EN" "http://www.apple.com/DTDs/PropertyList-1.0.dtd">
    <plist version="1.0">
    <dict>
    How can I find iMovie 4 or
    5 if I need it?
    eBay?
    I also wonder if projects I make with iMovie HD can
    be opened by future versions of iMovie, or if I
    should export them as Quicktime or something to be
    safe.
    We can never assume any new version of iMovie will be able to understand all features of a older project. It's always smart to make a backup.
    There can be problems Apple can't anticipate. There may be third-party software used to create titles, transitions and special effects, plug-ins not installed with the new version or (more often, incompatible). The fonts installed on our Mac may have changed too. There's lots of features that can't be anticipated. I've never had a problem converting projects, but I never use third-party add-ons and special fonts.
    As I start to look into this further, I would
    appreciate any comments, suggestions, and experiences
    that you may be able to offer. I need to get these
    movies back to their former selves, when they looked
    good!
    My guess is it should be possible to restore the projects back to their original state.
    Note that when imovie 5/6 converts an older project, it does NOT create a true iMovie HD project. Instead of creating an iMovie package, it retains the project FOLDER format. It places new iMovie HD elements inside the old project folder instead of converting it to a package.
    When converting the project it changes the old project file name to "Sample Project Name.iMovie2Project", then creates a NEW project file with the plist format, having the name "Sample Project Name.iMovieProj". (There may NOT be the .iMovieProj extension.) When you save the new project, it adds a new project file "Sample Project Name.~iMovieProj". Note the tilde. The tilde file is a backup of the project file as it was when last saved in iMovie HD.
    For our purposes, ignore the iMovie HD project files. We'll use the file ".iMovie2Project" to restore the project. (The extension is the same for all old versions of iMovie, not just iMovie 2.)
    • In the Finder, Duplicate the entire project folder. Work on the copy.
    • Open the project folder in the Finder.
    • Discard the "Cache" folder, the "Shared Movies" folder, the "Audio Waveforms" folder and the two iMovie HD project files. (Some of those items may not yet exist yet because you didn't save the converted project.)
    • Drop the "Sample Project Name.iMovie2Project" file onto the TextEdit icon in the Dock to get the version. Close it.
    • Remove the ".iMovie2Project" extension, if you want.
    • Launch that version of iMovie. Drop the "Sample Project Name.iMovie2Project" file icon on the iMovie icon in the Dock. With luck, the project should open normally. It's possible any third-party plug-ins used to create the project may not be available. If they aren't available, there might still be problems.
    • Move your unconverted projects to folders that say which version of iMovie created them. To open them in the future, drop the project icon on the appropriate version of iMovie.
    If all this fails, there is another way to do the editing you want. That is to import the project.mov file that's inside the converted project folder to a new iMovie HD project. That will deliver the video and audio of the original project as a single clip. Use that to re-edit the project. The name of the movie is "Sample Project Name.mov".
    (The movie is a QuickTime reference movie, with no video and audio of its own, just pointers to the files in the Media folder. So long as the Media folder hasn't changed, it can play the original project as last saved.)
    Importing the project.mov won't work with iMovie 2 projects, however, for iMovie 2 didn't store a project.mov file in the project folder.
    Even if you end up importing the project.mov, you still may want to "unconvert" the project as described above.
    Hope I haven't skipped a step. Let me know if you bump your head on something.
    Karl

  • FCP 10.1: "Copy Project to Library" does nothing?

    I have a Project I'm working on that I need to transfer to an FCP user at a different location. I would like to transfer the job to an external HD to send to them. I thought I could just select the Project and then File > Copy Project to Library and copy it to a new Library (aka a "transfer" library), but when I do this, nothing is copied. In fact, the new Library that I try and create isn't even created. Something doesn't seem right...? Any advice would be appreciated.
    Thanks,
    Kristin.

    Yea, that's one of the things I've tried. I've tried both...
    1. File > New > Library (then File > Copy Project to Libray, attempting to copy to the new Library just created)
    2. File > Copy Project to Library > New Library
    With both attempts, the Project isn't copied (I've also tried to Move the project as well, with nothing happening). With #1, the Library is created, but nothing copied to it. With #2, the Library isn't even created (even though I go through the whole process of naming the new Library, choosing where to save it, etc.—but, when I click Save, nothing happens (the Library isn't even created).
    Now, I've attempted doing the same with other Projects within the same Library, and they'll copy over fine, so I've at least narrowed it down to the individial Project I'm working with. I've consolidated the files (so they're not residing in external folders, etc.), I'm able to Duplicate the Project (within the same Library), I just can't Copy or Move it to a new Library.
    Is it possible for a Project to become corrupt? Is there any way to repair a Library?
    I've considered moving the whole event (as yes, I do want the associated media to be copied/transfered with the Project itself), but there are multiple projects within the event and so there would be a lot of "extra" media files that would go with it, which aren't part at that Project itself. As well, this problem, I assume, would persist on the recipients end, passing the problem on to them (which would become apparent when they need to transfer it back to us). So, I'd really like to "fix" the Project itself, so it can be copied to a new Library and transfered.
    One other thing I tried was to "select all" from the Project's timeline and copy all the elements and paste into a new Project's timeline, but nothing happens that way, either, when I tried to paste (and this method works fine with other Projects' timelines).
    So, there's defintely an issue with this one Project but not really sure how to fix it?
    Any further advice would be appreciated.
    Thanks,
    Kristin.

  • Oracle Sql Query issue Running on Different DB Version

    Hello All,
    I have come into situation where we are pruning sql queries on different DB version of Oracle and have performance issue. Let me tell you in brief and i really appreciate for your prompt response as its very imperative stuff.
    I have a query which is running on a DB of version 7.3.4 and it takes around 30 mins where as the same query when run on 8i it takes 15sec., its a huge difference. I have run the statistics to analyze on 7.3 and its comparatively very high. Question here is, the sql query trys to select data from same schema table and 2 tables from another DB using DB link and 2 other tables from another DB using DB link.So,how can we optimize this stuff and achieve this run as same time as 8i DB in 7.3. Hope i am clear about my question, Eagerly waiting for your replies.
    Thanks in Advance.
    Message was edited by:
    Ram8

    Difficult to be sure without any more detailed information, but I suspect that O7 is in effect copying the remote tables to local temp space, then joining; 8i is factoring out a better query to send to the remote DBs, which does as much work as possible on the remote DB before shipping remaining rows back to local.
    You should be able to use EXPLAIN PLAN to identify what SQL is being shipped to the remote DB, If you can't (and it's been quite a while since I tried DB links or O7) then get the remote DBs to yourself, and set SQL_TRACE on for the remote instances. Execute the query and then examine the remote trace files, And don't forget to turn off the tracing when you're done.
    Of course it could just be that the CBO got better,,,
    HTH - if not, post your query and plans for the local db, and the remote queries.
    Regards Nigel

  • In P6 version7 not able to copy project with the baseline.

    Hi,
    In P6 version 7 it is not able to copy project with the baseline. It copies only the schedule.
    Please help.
    regards,
    Baber.

    Tried the solution from another thread but did not work completely (as warned) - the workaround didn't quite work for me either:
    https://discussions.apple.com/thread/1398462?start=0&tstart=0
    Ended up taking a backup, did a fresh install, created the account as the first one so that it gets the same UID as the other Mac (on which my account was the first) and restored my data - was painful but finally on track.

  • Opening Project First Time from Version Control.  RoboSource Node

    Four writers have upgraded successfully.  My fifth is having issues...
    She has Serena Dimensions SCC installed as well (another source control product - used by Applications, not the authors or Infra.
    Problem: When she is establishing the root path (and the Browse RoboSource Node window opens, but it does not populate, even after 20 minutes.  Reboot did not work, neither did manually removing Serena Dimensions SCC.  I have verified that she has a connection to the database (via RSC Explorer) and can see the project (as well as the RH7 version of the project).  We have
    These are the instructions... (screenshots not included).  She's hanging up on
    1.1    Using a New Project for the First Time
    IMPORTANT NOTE:
    The author must have local administrator rights on the machine.  If the user has a privileged account, they must set up full local control of their work folder (specified in 1.1.2.8).
    1.1.1    Install RoboHelp and RoboSource Control
    1.    Download appropriate software packages, including all patches, from Adobe.
    2.    Launch RoboHelp Installer.  Select the following options for installation:
    o   RoboHelp for HTML
    o   RoboSource Control (Client)
    o   CS4 Script Extender
    INSTALLATION NOTES
    Installation of each component is separate and may take up to 30 minutes.  You do not have to install RoboHelp for Word.
    Only select the Client Install for RoboSource Control.
    3.    Install all patches in the order specified by the vendor.  Check with the technical communicator on which version is currently in use for patching.
    1.1.2    Open the Project
    1.    Launch RoboSource Control.
    2.    Establish a database connection per section 3.3.1.
    3.    Close RoboSource Control.
    4.    Launch RoboHelp 8 for HTML.
    5.    Click Open under Recent Projects under the main frame (do not use title bars).
    6.    Click the Open Project from version control button (shown below).
    7.    Make sure that RoboSource Control 3.1 is highlighted as the Version Control Provider and the checkbox for “Make this my default selection” is checked.  Click OK.
    8.    Configure the Source Control system as follows:
    Connection:  PROD
    Root Path: Click the … button and navigate to the (project name) root in the database and click OK.  This may take several minutes.
    Connection Mode:  Online
    Get to Local Path:  Click the … button and navigate to your Data folder.  Select Make New Folder under Data and give the folder a unique name to help you identify the files as for the Support KB in RoboHelp. 
    9.    Click OK when you have configured source control.  A copy of the database is now being downloaded to the path you specified.  This may take up to 20 minutes. 
    You can verify that installation is proceeding either by watching your local path fill with files or keeping an eye on the CPU usage of the RSO3MiddleTierService and RoboHelpHTML files under Task Manager.
    10.  Once transfer is complete, highlight Tier1KB.xpj and click Open.  It may take several minutes to open the project the first time.  It is typical for the snippet file to check out the first time you open the project and the first time each day that you save all project files.
    11.  Once the project is open, set Version Control properties:
    a.         Select Tools > Options.
    b.         On the Version Control tab, select all options.  This will prompt the user on each version control action they take.
    12.  Test a check out/check in to validate correct installation and source control operation.

    It's the settings in miscproperties in the XPJ and it works in TFS just fine. I'ts as follows:
    <miscproperties>
      <matchedpair>
      <name>vc::provider</name>
      <value>Team Foundation Server MSSCCI Provider</value>
      </matchedpair>
      <matchedpair>
      <name>vc::agent</name>
      <value>MSSCC</value>
      </matchedpair>
      <matchedpair>
      <name>vc::database</name>
      <value>http://ap-gda113-tfs-a:8080/tfs/centric|NB-WWEELDEN|ITS\Wweelden</value> <- Add the TFS URL, your workspace name and your domain name.
      </matchedpair>
      <matchedpair>
      <name>vc::cookie</name>
      <value>$/BV - MVV/Main/Tools/Documentatie/mvv-beheerders</value> <- The location of the project in TFS.
      </matchedpair>
      </miscproperties>

  • Project "Installer Build Product version" vs exe version

    Hi, 
    Can someone help me understand why the "Installer Build" in a project has a "product version", which later shows up in the Windows add/remove programs?  
    I must be missing something because to me it seems very strange that what they call "product version" in the installer is not automatically linked to the compiled exe version that the installer is built for?
    Now I have to try and remember to manually keep these two versions synchronized, and the build 'product version' doesn't even have the same number of fields as the exe version information?!
    It's strange when my program splash screen shows "V1.2.0.8" (read by the app by inspecting its own exe) but in the windows add/remove programs, it could say something totally different, such as 1.0.6...  
    Why is it like this??  How do other people use/handle these various version numbers?  -is there a way for my app exe to find what the installed "product version" is?
    ---Confused...
    -QFang
    QFang
    CLD LabVIEW 7.1 to 2013

    QFang wrote:
    I suppose it helps explain.. Perhaps I just need to think differently about how to name our installers..  Divorce the installer name from the (main) application name, then the difference in version numbers wouldn't be confusing. 
    Ideally the NI builder would be flexible enough that you could have a "Company Name" as the "installer name" and you could add/remove/maintain the whole company's product list with that same installer, similar to the NI installer.. sounds like a lot of work though.
    Thanks for replying!
    It does sound like a ton of work!  I have to belive it is feasable with TKs like VIPM and Deploy on the market. (A few others I am less familliar with come to mind as well)  Niether is exactly what you seem to want but demo that the tech is there!
    Jeff

  • Is there a way I can use a Master with sub-projects on different calendars?

    Wondering if I can get some advice creating a Master Project (MSP2013 Standard, no Project Server software). I have 3 projects of which 2 are utilising a Standard calendar 8:00AM to 5:00PM 8hr day 40hr week, and 1 project (the largest) utilising a Customised
    calendar 7:30AM to 3:30PM  7.5hr day 37.5hr week.
    The dominant project is running on the Customised calendar so I have set the Global Options in the Master to reflect the 7:30AM to 3:30PM  7.5hr day 37.5hr week. Then set the calendar in Master Project Information default to the Customised calendar. 
    Finally, the resource pool for all 3 projects is in the Master.
    No problem when I insert the sub-project into the Master which is using the customised calendar. All data is reflective of the original project.  However, when I insert either of the 2 sub-projects using the 40hr week calendar the Summary Headings for
    the inserted projects are incorrect.  For example, instead of being 2 weeks duration, the summary heading displays 2.13 weeks, and instead of 4 weeks duration, the summary heading displays 4.27 weeks.
    The Global settings appear to be interfering with the projects on the Standard calendars.  I am surprised and extremely frustrated as I thought the settings in the Master would not affect anything?
    Sorry guys, have posted this in 3 different places as it is so important to me!

    Hi Guys, many thanks for your responses, really appreciate your time, however I am finding this much more complex. I have put my original sheets to one side and started again. Once again this is very important hence a lot of detail here. I am hoping something
    will provide a clue where I am going wrong.
    New sheet |save as Master | Change Working Times |copy Standard Calendar and called it 37.5 Hour
    Calendar| No exceptions | Work Weeks tab |Details | Set Monday to Friday 7:30AM to 12:30PM then 1:00PM to 3:30PM. Selected Options | Schedule | Start 7:30AM End 3:30PM |Hours 7.5 | Hours per week 37.5 |Auto Scheduled |Duration Hours|
    Work Hours |Fixed Duration | OK OK. Project | Project Information | Calendar changed to 37.5 Hour Calendar | Save.
    In my previous example I noted that my main project is scheduled 37.5 hours but I will skip inserting it here, the issue is subprojects with different settings to the Global, that is mixing projects with different calendars in a Master.
    New sheet | save as 40 Hour Project |Change Working Times |Standard Calendar | No exceptions | Selected Options | Schedule | Start 8:00AM End 5:00PM |Hours 8 Hours per week 40 |Auto Scheduled |Duration Weeks | Work Hours |Fixed Duration
    | OK OK | Save.
    Entered 5 new Tasks, all 2weeks duration, all linked Finish to Start. Inserted a Summary Heading named 40 Hour Summary | 40 Hour Summary Duration = 10 wks | Start 9 June 1014 8:00 AM | Finish 15 August 2014 5:00 PM |Created 1 Resource called Fred | 100%
    |$100 Standard Rate | Assigned Fred to all tasks 100% | Project | Project Information | Statistics | 10w 400h $40.000 |Save and Close | All correct.
    Back to the Master | Project | Insert Subproject | selected 40 Hour Project |Duration 400 hrs | Start 9 June 2014 8:00AM | Finish 21 August 2014 10:30AM. It appears the Global settings are affecting the inserted subproject note the finish time is now
    10:30AM. Project | Project Information |Statistics |Duration 400h | Work 400h | All correct!
    BUT | select View Outline Show Subtasks |This is where further changes have happened | Project | Project Information |Statistics |Duration is now
    374.5h | Work 400h.
    Besides information being displayed incorrectly these figures will affect all Reports. This example suggests you cannot have subprojects in a Master that are associated with different calendars? Surely not! Please help if you can, I have
    spent hours searching for answers, and I can’t believe I am the only one who has come across this! Many thanks.......

  • Is it possible to open FCE projects in the latest version of FCPX?

    Is it possible to open Final Cut Express 4 projects in the latest version of Final Cut Pro X (10.0.4)?
    I have 18 projects on my hard drive, and I'm concecrned about their compaitibility in the future. Should I leave them as they are, and I'll be able to import them into Final Cut Pro X, or should I first convert them to Final Cut Pro 7 projects?

    You can't open FCE projects in FCPX. If you can open a copy in FCP7 and export an XML file.

  • Costing on Internal Orders with different plan versions

    Hi,
    Is it possible to carry out Costing on Internal Orders using different plan versions?
    I would like to carry out more than one costing on Internal Order so that I could compare different versions. Maybe there are other parameters (other than plan versions) which can be used for executing different parallel costing.
    Best wishes,
    Karol

    Hi Karol,
    In Release 3.0, the following new planning functions are available in order planning:
    <b>Copy plan versions</b>
    In Release 3.0, you can plan order costs for internal orders in different versions. In contrast to earlier releases, you can now
    1. change versions
    2. copy versions
    3. Here you can select :
                                 the planned values to be copied: annual or total values
                                 whether the planned values in the target version are to be retained or overwritten compare versions using the information system
    Planned values are not revaluated in the target version (for example, when you change the value date).
    Overhead and settlements are not copied and, if required, must be repeated in the target version
    Regards,
    Hemachandra K S
    <b>Please, donot forget to mark the answer as Helpful, Very Helpful or Problem solved.</b>

  • I just opened an "old" project in a newer version of iPhoto and the pages in the book doubled in number with the seam in the middle of each page.  Suggestions?

    I just opened an "old" project in a newer version of iPhoto and the pages in the book doubled in number with the seam in the middle of each page.  Suggestions?

    Start with Try the following:
    1 - delete the iPhoto preference file, com.apple.iPhoto.plist, that resides in your
         User/Home/Library/ Preferences folder.
    2 - delete iPhoto's cache file delete the contents the following folder:
    User/Library/Containers/com.apple.iPhoto/
    Data/Library/Caches/com.apple.iPhoto
    3 - reboot, launch iPhoto and try again.
    NOTE: For Mavericks, 10.9,  go to your Home folder and use the View ➙ Show View Options menu to bring the this window:
    where you can check the Show Library Folder checkbox.
    If that doesn't help continue with:
    1 - launch iPhoto with the Command+Option keys held down and rebuild the library.
    2 - Run Option #4, Rebuild Database.
    Happy New Year

Maybe you are looking for

  • Sharing games with different user accounts

    Hello. I've been meaning to ask this for ages and was hoping for some help. There are four user accounts on my mac and my son and daughter love Zoo Tycoon. My question is, how do I share the actual app between the accounts as I can't seem to sort out

  • WCM Error while saving Project

    Hi, I am getting following error while saving new created project in cProject. Saving is not possible because the WFM Core data could not be adjusted Message no. PRP086 Diagnosis When checking the project role or project role staffing, differences to

  • NO RADIO OPTION ON MY IPOD!!

    I have a 30gb 5th gen ipod video and i jus brought the radio remote. after what seemed like a million resets and turnin the option off and on, i still dont see the radio option on the main or in the music screen can some1 tell me what im doin wrong,

  • Maximum size of a compiled JSP page

    Has anybody else come accross a problem with weblogic not displaying .jsp pages greater than           

  • Cannot Activate the Integration Process

    Hi Friend, File Merging: ========== I wonder why the receiver step not taking the " Use Correlation" or "Activate Correlation" value even after creating the correlation list and check(F7) the same. At receivers step in Graphical Definition(BPM) I can