Change cost planning after copying to different CO version

Hi,
I have done network cost planning through project builder, after completing this I copied my cost planning to different CO version. Now I'm not able to change values of second CO version. I can see the figures in reports, but not able to change using CJR2 or CJ40 transactions.
Thanks

Hi,
Full authorization is provided to the user, and the required fiscal year too is configured in second CO version. This is not solved the problem!
If my understanding is correct, only version 0 can have network costing, all others will have either cost element based or WBS element based cost planning.
Now, when a network costing is copied to another CO version, the destination version can't hold cost planning in the form of network costing then what type costing second version would be having and how one can modify the value and quantity in that version?
Thanks

Similar Messages

  • Why capital letters change in lower after copying them from a PDF document, or otherwise, why some uppercase are in fact lowercase when I look in the Text Property in any PDF Reader.

    Why capital letters change in lower after copying them from a PDF document (Made by InDesign), or otherwise, why some uppercase are in fact lowercase when I look in the Text Property in any PDF Reader.

    your home page to get into your Web site should be index.html (for Mac) or index.htm  (on PC)
    You can name it something other than index, but will be harder to find.  when you create the subjects and link to them, they can can be named anything with the html extension  Or if your using PHP end in .php. There is a Microsoft type asp or aspx but your hosting service has to set up using windows server system.
    My hosting service use a Linux server normally but can convert Windows for a Fee.  UNIX Linux has no concept of asp or aspx.
    See this : https://skitch.com/pjonescet/8mnnx/dreamweaver

  • Cost Planning Details not reflecting in new version

    Dear Experts,
                        .  We created the 'NEW' version . But we want to copy cost planning from u201C0u201D version to u201C1u201D version. For
    this we are executing u201CCJ9BSu201D t-code but after executing this, only cost
    are getting copied. Detail Planning is not getting copied.Kindly look into the matter and helpful solutions are

    Dear Experts,
    . We created the 'NEW' version . But we want to copy cost planning from u201C0u201D version to u201C1u201D version. For
    this we are executing u201CCJ9BSu201D t-code but after executing this, only cost
    are getting copied. Detail Planning is not getting copied.Kindly look into the matter and helpful solutions are.
    i.e
    1 I planned material costs in .Cj40 > Primary Cost > Edit >Detailed Planning >Change
       Here we maintain material cost, service cost, BPO etc
    2.When we copy the version from '0' to new version which i have created copying the 1 version.Or say '0' version to '1' version then material cost is not reflecting in new version cost planning after CJ9BS.

  • I want to change my plan from Photoshop to the student version of Creative Cloud - I can't get anyone through live chat and no way of contacting customer support. Help please?

    I want to change my plan from Photoshop to the student version of Creative Cloud - I can't get anyone through live chat and no way of contacting customer support. Does anyone know how to contact adobe?

    Hi Beansy21,
    Please refer to the link below to contact the customer support:
    http://helpx.adobe.com/contact.html
    Regards,
    Sheena

  • Changing cost assignment after posting advance

    Hi Friends,
    I have a problem;
    I create a travel request (TRIP) with some advance request
    Cost is charged to Cost center 100%
    Settle the request, post the adance(PRFI, PRRW)
    Enter expenses,
    Change cost assignment to WBS element in PR05
    Post the trip
    it posts to same cost center, not to WBS element
    Please note that i post the trip in accounts depending upon activity type. For WBS, we have different account
    If there was no advance posted, the WBS change takes place correctly.
    any solution please!
    Thanks and regards!

    Hi,
    Till you create an expense report you will be able to change cost assignment, but once expenses is created no changes can be made to the cost assignment.
    And also, while posting you can change the cost assignment either from cost center --> cost center or WBS --> WBS and not vice versa.
    Hope this helps.
    Regards,
    S.Srikanth

  • PDF comments change to XML after copying and pasting

    Has anyone experienced a problem with comments in mark-ups where they appear as normal text until they have been copied (and pasted into Indesign, though this part is not relevant) but when ticked as completed they change to xml formatted text? See before and after pics below:
    Oops, sorry, cannot load images, must be an error with the upload software. Not accepting TIFF/JPEG or PNG.

    As a follow up to this I have just experienced another similar situation where the the pdf comment changes to Greek text...
    the left hand pic is from the comment window, the right hand pic is from the mark-up in the text. Very odd...

  • Change role name after copying

    I copied a role (Business Explorer) and want to rename the role.
    Changing the name does not help, because only changes to other languages than the original language are taking effect.
    Changing the ID is possible, but there I am not allowed to change the name.
    How can I change the name of the role in the original language?

    I found the solution. I created the role in language "EN".
    I wanted to have the name change in language "DE". Therefore, I had to translate the role name.

  • I am THIS-CLOSE to changing carriers/plans after almost seven years and multiple family accounts

    How do I TALK (Verizon is in the phone business, isn't it?) about accessing part of my account to pay my bill as I used to every month? This is ridiculous. Verizon has received THOUSANDS of dollars from me and my corporate account over the years and I'm so (removed) right now I'm about to nix it all. If anyone at Verizon is scanning these emails, get back to me. My chat feature isn't even working online.
    Comments edited  as required by the Terms of Service.
    Message was edited by: Admin Moderator

    Sorry, gang, this was a family member that is irritated about her account, not me. I'll handle this. Thanks.

  • Easy Cost Planning -Costing has already been completed. No changes possible

    Hi,
    I am in Easy Cost Planning tool and i would like to remove some items or add in some items.
    The system is giving a message that "Costing has already been completed. No changes possible"
    May i know where did we complete the costing(Transaction code?) such that no changes are possible on East Cost Planning tool anymore?
    Thank you.

    Hi,
    Check the Costing Model in CKCM and do changes as per your requirement.
    Now Use this costing Model in CJ20N while cost planning for wbse. you can change cost plan here also as per wbse specific requirement.
    regards,
    Hari

  • Tcode : CJ40 - Cost Planning

    Hi,
    I would like to confirm <b>'BAPI_BUS2054_CHANGE_MULTI'</b> Bapi can be used to change cost planning? plese let me know any function module or BAPI to simulate(testing) the Cost Planning.
    Regards, Suresh

    no prob cool
    see if it is used anywhere
    else search in se37 with *
    regards

  • Clarification on Cost planning version

    Hi Gurus,
    I need a clarification... as per the client's business requirements, cost planning is to be executed in various versions before it is finally approved. As of now it is decided to copy  this into zero version (approved version). What will happen if components & services are assigned to network when real execution starts ?
    Let me give an example, Unit cost planning is executed for $1000. This cost plan is copied into zero version. when the user start executing the project, they assigned components & service in the network amounting to $800. As system takes this planning directly to zero version, will the total planned cost will become  $1800 ? If so, should i not take the approved cost plan into zero version instead to copy into some other version and only use Plan 1/Plan 2/ Actual Report to see the comparison ?
    Whether my understanding is correct ?
    Regards,
    Vinodh

    Hi Vinod,
    Goto OPSV ( Define Order Value Updating for Orders for Projects ), remove the Check box "addit" for Order category - 20.
    You can copy the Planned cost from other versions to active version - "0" but you can keep order settings to avoid appending planned cost to WBS Element Level. So, even though user do network costing, network planned cost not appended to WBS Element. Hence your initial approved planned cost remains same and you can see in all reports.
    Hope this clears you !!
    Br,
    Hari.

  • Can I get single line plan after just upgrading?

    I just upgraded to a smartphone plan with a renewed 2 yr contract from a basic plan, but now I see the Single Line Plan for smartphones.  Is it possible to change plans since I renewed my contract?

        hellgirl We're glad to hear that you just upgraded to a new device. It is possible to change your plan after extending your contract. First, we need a few more details. What price plan do you have now? Are you on a family share plan?
    SheritaH_vzw
    Follow us on Twitter
    @VZWSupport

  • Missing iviews for Personnel Cost Planning and Simulation

    Hi,  We are implementing "Personnel Cost Planning and Simulation" in R/3 version 5(mySAP ERP). At present we have the following Business packs in our Enterprise Portal Server. 60.1.5 and 60.1.1(mySAP ERP 2004). We uploaded both the BP's in our test environment to make sure we get all the iveiws that we need.
    SAP presentation has all the iviews, But we are unable to locate/identify under MSS the iviews for "Web Based Detail Planning for Line Managers",  "Detail Planning:  Detail Costs per Cost Object" and so forth for Personnel Cost Planning and Simulation component.
    We researched other BP's such as 50.4.5 and 50.3.9 but in vain.
    We truly appreciate if some can guide us to get these iviews.

    Finally I got the answer and thought I can share this with you all.....
    For Personnel Cost Planning and Simulation, SAP has not delivered mss iViews, but SAP has realized the detail planning pages for the line manager and the personnel cost planner by using the Business Server Page (BSP) "hrhcp_planning".
    You can find the description of it's usage in the online documentation under the following path:
    Human Resources>Personnel Management>Personnel Cost Planning and Simulation-->Personnel Cost Planning and Simulation Flow -->Creating Personnel Cost Plans
    --> Providing Detail Planning for Line Managers
    --> Detail Planning by Line Managers
    --> Detail Planning by the Personnel Cost Planner
    If you wish to use the detail planning page in an mss environment, you can integrate the BSP as an external service into the manager's portal. Otherwise, you can also use it, by providing the URL to the managers.

  • Easy cost Planning & Network Costing

    Dear All
    In one Project can we use both Easy cost Planning & Network Costing. Easy cost planning is generally used when you have structure with WBS only. Network cost planning is a combination of group of activities, all these having their relevant cost elements/ work center combination. can we manage both this in one project. If it possible please explain in detail.
    Regards
    Nivrutti

    What is your business requirement ? It depends on that. Yes your understanding is quite correct. We use easy cost planning in the initial phase of project. Easy cost planning can be done in various versions including  0 plan / actaul version.  If you does easy cost planning in 0 along with network costin you will double up lannning cost.
    Network costing can only be done in plan / actual version 0 only.
    Best approach is to use easy cost plnnaing as rough cut level apart from 0 version. And use network costing. However it may very a/c to business requirement.
    With Regards
    Nitin P.

  • Hierarchical Cost planning in CJ40 not updating in CNS41

    Hello Experts,
    When i am planning cost using cj40 than checking report cns41 so this is not showing cost planned via cj40.
    what will be reason of not showing this cost plan. Please guide.
    thanks
    Sunil

    Hello Abdul,
    Please check massage given when choosing version 0
    You must not use version 0
    Message no. BP067
    Diagnosis
    Version 0 is not intended for cost planning or flagged as a delta version.
    System Response
    Processing stopped.
    Procedure
    Choose a version which allows cost planning or
    Notify your system manager.
    Action by system manager
    Release version 0 for cost planning.