Cost balance against process order.

Hi Guru,
1)I have one error in  process order , in that user has reverse order, all material movements has  correctly reversed.
But there is still cost balance in that particular order which is due to price difference.  How can I post this difference ?
2)Again in certain  process order which is cancelled(cors).  by mistake, user has  reversed settlement through ko88 , due to this order having cost balance.
When I going to do ko88, system gives message u201C there is no accured amount,settlment is not possibleu201D.  How can remove this cost balance?
you reply is valuable.
Regards
Sanjay.

Hi,
           But there is still cost balance in that particular order which is due to price difference. How can I post this difference ?
Error : Balance of order xxxxxx is not zero
issue is due to Goods movements were posted even after the variance was posted , thus balance is not ZERO.here goodsmovents should be reversed & should run the varinace calculation again.To run the vaiance calcualtion (KKS2), order should have the status of DLV or TECO.
When I going to do ko88, system gives message u201C there is no accured amount,settlment is not possibleu201D. How can remove this cost balance?
You can NOT settle the order unless order have the status DLV or TECO.
You can remove the cost balace by running the variance calcualtion( KKS2)
Thaks,
Rajanikanth

Similar Messages

  • Goods Receipt against Process order mvt 262

    Hi,
    Is it possible to not to receive material against process order (262 mvt) if it is not issued using process order using 261.
    Do the needful.
    Regards
    Mohan

    261 and 262 are two different movement types INDEPENDENT of each other. I definitely know for the fact that SAP allows you to create a 262 without a 261. if you were to restrict it... you can disable access through a tcode for that mov. type 262 and ask users to use MBST to cancel any material documents created via 261 movt type.. that would ensure a smooth process

  • Goods receipt against process order with inbound idoc

    Hi Experts,
    We need to post good receipt against process order with movement type 101 and for By-product 531.
    Can we use inbound idoc-WMMBID02,with message type WMMBXY to achieve this functionality?
    Or please advise if we can achieve this  from any other Idoc type.
    We are getting below field values for external system
    1. process order number
    2.plant
    3.material
    4.quantity in unit of entry
    5.unit of measure
    6.storage location
    7. movement type
    8.Batch
    Kindly advise how can we achieve this.
    Best Regards
    CS

    261 and 262 are two different movement types INDEPENDENT of each other. I definitely know for the fact that SAP allows you to create a 262 without a 261. if you were to restrict it... you can disable access through a tcode for that mov. type 262 and ask users to use MBST to cancel any material documents created via 261 movt type.. that would ensure a smooth process

  • Goods Return to Store against Process Order

    Hi,
    Tell me how to do Goods Return to Store against Process Order
    For E.g.
    Process Order X having Material M1 with Requirement Qty 100 Kg as per BOM specification and Issue Qty using COR6 is also 100 Kg but due to less Consumption 20 Kg is required to be returned to store
    So how to have effect of returned 20 KG against Process Order
    Note : I have used MB1C option for Goods Receipt but it won't make any effect in Process Order
    i.e. Requirement Qty  -   100 KG
         Withdrawn Qty     -    100 KG
    But in MMBE it shows 20 KG after receipt from MB1C
    Kunal

    Hi Vivek,
    I tried as per your given direction but it won't worked
    What I required is for E.g.
    Process Order No 11111
    Material No           Mat-A   
    Batch No              Bat-A
    Storage Loc          PM01
    Requirement Qty which is coming from BOM                        120 KG
    Withdrawl Qty either using COR6 or MB1A (261 mov type)     120 KG
    Consider that Process Order is already confirmed and due to some reason All the materials issued against Process Order has to be returned to Store for another Process Order
    When I used MB1A and entered movement type 262 with storage location PM01 then click on To Order Button to enter Reference : Order and click on Tick Button
    It then displayed only those materials which is not yet issued and required to be issued and automatically Movement Type changed to 261
    Please guide
    Kunal

  • During GR against Process Order Storage loc. not appearing

    He Experts,
    I am trying to do goods receipt against process order for bulk material using MIGO.
    But under where tab in MIGO storage loc field is not appearing. For this material production storage location is maintained in MRP2 view & in material type customizing both quantity & value field is selected for a given plant.
    Can you please explain why this field is not appearing? Is there any other customizing behind this? During migo 101 movement type (GR for acct. assgt.) is appearing in moveent type field.
    Thanks in advance,
    Vijay.

    Hi,
    OK,You are trying to do GR for a materisl which is defined as Bulk Material (Can be done in BOM or Material master).
    You said , there is no stock appearing for this material in this Storage location.
    Check one thing,
    go to MMSC and find out whether the storage location is maintained for the material or not?
    if your Storage location is not appearing in the list, maintain it there.
    Create a new Process order/productrion order  and check
    Regards
    Ratan

  • Costing varients in process order

    Dear Gurus
    Can u tell where we r assigning costing varients in process order cofiguration side (Planned & Actual)
    Thanks & Regards
    Ragesh

    You have to assign these costing variants in COR4 transaction in controlling tab for process orders.
    Regards
    TAJUDDIN

  • Target cost calculation in Process Order based on Variance Calculation

    Hi all,
    I have a question on Target cost calculation in Process Order. My understanding is, the Target Costs gets calculated when the confirmation and GR is made for the Process Order.
    But if the confirmation/GR is not done, whether the target costs gets calculated for only the activity types after the Variance Calculation (KKS2).
    I have two scenarios. In one, the target costs got calculated for the activity types without the confirmation/GR after the Variance calculation.
    In another scenario, the target costs are not getting calculated for the activity types without the confirmation/GR if I try to do the variance calculation in KKS2.
    SO i want to know which scenario is correct?
    Can anyone answer this question?
    Thanks and Regards,
    Brijesh

    Hi,
    In general, the target costs are calculated once you deliver the order.
    Target costs for the components and the activities are updated only once you deliver the order and the target cost for the finished product gets updated when you do the variance calculation.
    Consider your scenario number 1 - you said the target costs got calculated for activity types without confirmation / GR after variance calculation.
    Now, if the order is not having any status like PDLV, DLV or TECO it will not calculate the variances in the first place.
    Your second scenario is correct - without GR the system does not calculate any target costs. Also it will not calculate any variances because the order status is still not DLV.
    Best Regards,
    Sameer

  • COGI against process order

    Dear all,
    After receiving stock,from COGI how to post the stock against process order.
    Regards
    Rajasekaran

    Hi,
    In the COGI enter the details like qty and batch then select the row for which you want process the record and click on save on top....check the below screenshot...
    Thanks
    Kumar

  • Return against Process Order

    Hi Gurus
    I have a problem while posting a return against process order. When I am returning the process order the order quantity is not coming into the unrestricted area and it is showing in the reserved area. Because of this other process orders are not picking the right batch. The process order is not closed.
    Early response is highly appreciated.

    I check the problem and found that the process order line has reopen once we post the return. I don't know why this is happening. Could anyone tell me the standard practise and process flow of process order return.

  • PLANNED AND ACTUAL COST IN A PROCESS ORDER

    From where the planned cost of material and activity types in cost itemizationafter creation flow ?From where the actual cost of a material and activity types in  cost analysis of process order after confirmation flow?

    You may be knowing you give Costing Variants ( Both actual as well as Planned ) in Order type. These Costing variants contains Valuation variants which says which costs are to be taken while creation ( for Planned Cost ) and Actual cost ( while confirming and Moving Goods) to be calculate. These Variants decides mode of Cost Flows.
    Now, Data in Planned costs are Standard Cost figures or Current prices for material or Planned Prices of Activities.
    As far as Actual costs are considered it may be the price for the consumed quantity @ the moving average price of the day or activity price for the qty. consumed which include up planned consumption too.....
    Reward if you find useful

  • Rserved materials deatils against process order

    Dear Gurus
    How can i view reserved materials deatils against process order's. hrough change or display mode of process order it is possible, but i want collective deatils for more than one process order is it possible?..pls help
    Regards
    Ragesh

    Ragesh,
    With <b>COID transaction choose Materials radio button</b>. You can view the materials assigned to the order along with the reservation details.
    Regards
    Ram

  • Regarding goods issue (reversal) against process order

    Dear friends,
    Recently i have noticed one strange thing in SAP.I have created one process order and against it i have done the confirmation.Now when i go to Transaction code mb1a and select movement type 262 (Goods Issue to process order-reversal) and give the storage location and in next screen i gave order number,material code and its qty.These material code is not maintained in the bom of order header material.And even in process order in material tab we haven't maintained this material.Also while doing the confirmation in goods movement we haven't maintained this material.Then also system allows me to do so.Which means material which i haven't issued against the process order, system is allowing me to do its reversal i.e (262).because of which system is creating the stock for that material, which is not correct.
    Can we control this behaviour of system.
    Thanking you guys in advance.

    Hi Jitendra,
    This is fact and there is no standard Control available for the same.Only thing you can do is put control over Movement type 262 or try it by implementing User Exit.
    I am not sure but you can use Enhancement CCOWB001 - Customer exit for modifying menu entries.
    Include is LXCOWBF01.
    Regards,
    Dhaval

  • No cost booking against sales order+line item once accontng release is done

    Dear all,
    I want to stop all cost bookings against a sales order + line item once the accounting release for that item has been done.
    By cost booking i mean, all such transactions that are done for a sales order + line item that involve cost booking. Like, MB1A should not allow any goods issue against that sales order + item once accounting release is done.
    Is it possible to that in sales order? Like by using any status at item level.
    Please guide.
    regards
    SAPshed

    Hi Ajay,
    We have not kept automatic cost estimate marking during saving of sales order as costing dept wants  to confirm whether costing for the SO is correct or not.
    Hence we have to use CK51N.
    Now the problem is for any change in any line item of a sales order is changing the costing status from "VO" to "KA" for all line items of the given sales order in table KEKO.
    This is causing measure problem as production people are facing problem while making any change in production order as already there is a check put in CO02 that if cost estimate does not exist for underlying sales order, then change in production order should not be allowed.
    Similarly production order creation (converting planned order to production order) is getting held up.
    Costing user has to repeated run CK51N for all line items of a single sales order if there is any change in any single line item of the sales order.
    Hence pl. help and suggest as to what is to be done now.
    Regards
    Ratna

  • Actual Cost Calculation in Process Order

    Hi All,
    I updated Standard cost of a raw material through a cost estimate and also ran cost estimate of the FIN that is using this raw material but when I am creating a Process order, it is taking the cost of this particular raw material from the previous estimate not the recent one to calculate the target cost. Can any body help me with this.
    Thanks
    MKR

    Hi Ashok,
    My Valuation variants for the Costing Variant of Cost Estimate and Production order (Actual/Plan) cost calculation are in Sync to get the prices according to the price indicator in material master. But when it calculates cost for a production order, it is picking up cost from the previous period for that particular raw material. I have updated the standard cost by running the cost estimate but still its not working.
    Any lead on this. This will be really appreciated.
    Thanks
    MKR

  • Costing issue in process order

    Hi everybody,
    We are facing a problem now like... for a FG material we have changed the BOM, updated recipe but costing release was not done before that a process order had been created, material release carried out, process order confirmation made, GR made and the stock is there in FG location, In the cost analysis it shown Rs. 1.14 lakh as variance in FG consumption G/L.
    Now we reversed the stock from FG location, canceled the confirmation and changed the order qty to 1nos, to make the order dummy, but still cost analysis shows Rs. 1.14 lakh variance in FG consumption G/L
    Help us to resolve this.

    Hi,
    Now for the finished good  create material cost estimate with quantity structure
    Create standard cost estimate (marking and release to be carried out)
    now for the same old process order in the cost analysis u can see different value for  total target cost
    carry out confirmation  and u will get the total actual costs based on the activity types u have assigned
    -Variance=(difference between  total target cost and total actual cost)
    Variance related settings are done in consultation with Controlling people.
    Regards,
    Raj

Maybe you are looking for

  • No longer able to capture screenshots on iPad Air? (iOS 8.2)

    I've tried several hard resets (by holding down Sleep + Home buttons to turn iPad on & off), and I've also tried resetting all device settings - but I'm still unable to capture a screenshot on my iPad Air. The camera doesn't even click/flash or ackno

  • Encore cs6 preview out of sync but DVD fine

    Hello, Blu-ray project in Encore, exported audio and video from AME using the blu-ray h264 preset. When I preview in Encore the sync is off but once I create the dvd and play it back, the sync is fine.

  • Text review nightmare

    Hi guys, Just a quick niggling operational question I wondered someone would know the answer to.. When creating scrolling text inside FCP, is it possible to stop the cursor moving back to the top of the page everytime I go to review how the text is l

  • Compressor 4 Clustering

    I am looking to find out if since QMaster has been built into the same interface as Compressor, has anything changed in its stability? In the past I have spent several hours trying to get Compressor to cluster multiple computers together to render ou

  • Forms 6i - menu disable

    Hi! I cleared "Menu Module" property (DEFAULT&SMARTBAR) in my form module, but I still have "Window" menu. Is there way to disable menu at all? Thank you.