Cost center in functional location

Dear all,
In functional location and in equipements it is possible to add a cost center.
Could you please tell me how this cost center is used (on creating orders and/ or notifications)? Is the cost center copied into the order? As the cost center of the workcenter/ activity type is used for the costs of an order, is there a need of this cost center in the master datas?
Thank you.
Best regards,
Thomas

Hi Thomas,
     The Cost Center from the Work Center will be used for the calculation of the actual cost incurred for that Maintenance. Based on the cost center selected in Equipment & Functional Location, settlement rule will be defined in case you want to change it, do it manually as per your wish. The costs incurred will be posted in the cost centers based on equipment or settlement rule & not based on work center cost center.
Regards,
Maheswaran.

Similar Messages

  • Can I do plant maintenance cost planning in functional location wise?

    Dear Experts,
    My customer plans to prepare annual plant maintenance cost planning in "functional location" wise.
    Can this be done?
    If yes, what are the steps?
    regards,
    Abraham

    Abraham,
    You could do it indirectly in ECC using a cost centre for each FLoc. You can then plan the costs in the cost centre
    PeteA

  • Material Transfer from cost center to storage location

    Dear Experts,
    Can anyone please tell me what is the movement type for transfer posting of material from Cost center to storage location?
    We have bought materials for certain cost centers, but we didn't use all our materials and we would like to put it again in our stock.
    Can anyone help me for this issue?
    thanks in advance,
    regards,
    Ahmed.

    Hi,
    1. If you bought the goods with "K" account assignment PO, you should cancel the GR (MBST or MIGO). After that you can receive the parts as stock items and post GI (MIGO + 201 / MB1A + 201) against cost center with the quantity you really used from them.
    2. If you received the goods into unrestricted stock (GR against PO with no account assignment, MIGO + 101 ) and later you posted GI for cost center (MIGO + 201 / MB1A + 201), you can do the reverse movement (no cancellation!; MIGO + 202 / MB1A + 202) and this way receive the remaining goods into stock.
    You can also use MIGO + 202 in case of point "1", but cancellation and after that GI with already consumed qty would be the exact solution I think.
    Regards,
    Csaba

  • Need to find out the Cost center for one location, one cost center

    /* Formatted on 2015/02/27 08:34:29 AM (QP5 v5.215.12089.38647) */
    SELECT DISTINCT cost_centre
      --  INTO l_cost_center
      FROM (  SELECT DISTINCT                                 --pap.name position,
                     haou.organization_id org_id,
                     haou.LOCATION_ID,
                     pcak.concatenated_segments cost_centre
                FROM                              -- per_all_positions         pap
                    per_all_assignments_f pasf,
                     hr_all_organization_units haou,
                     pay_cost_allocation_keyflex pcak,
                     HR_LOCATIONS_ALL_TL l
               WHERE     pasf.organization_id = haou.organization_id
                     AND haou.cost_allocation_keyflex_id =
                            pcak.cost_allocation_keyflex_id
                     -- AND pasf.position_id=pap.position_id
                     -- and pap.primary_position_flag = 'Y'
                     -- AND haou.business_group_id=101
                     AND pasf.LOCATION_ID = l.LOCATION_ID
                     and l.language='US'
                    -- and l.organization_id=haou.organization_id
            GROUP BY haou.organization_id,
                     haou.LOCATION_ID,
                     pcak.concatenated_segments                    --pcak.segment2
                                               ) Pos_cc
    WHERE pos_cc.location_id =
              (SELECT DISTINCT location_id
                 FROM hr_locations_all
                WHERE location_code = 'Pinelands'                  --i.branch_name
                                                 AND ROWNUM = 1)
    Please help me with this query, I am new to HRMS modules. Need to understand that why for one location it is coming multiple cost center.
    Please help me understand this. I need to pass one value in INTO of this query.
    Thanks,
    Syed Hasan

    Cost centre is stored at the Organization level.
    And many Organizations can have the same location, so for a location you can have different cost code combinations.
    If you need just one segment(location segment), then it could be unique.
    So , instead of pcak.concatenated_segments cost_centre use pcak.segmentX  (X could be 1,2,3 etc based on your flexfield definition)

  • PP Work Center ------  PM Functional Location, PM Equipment

    Hi,
    For a given PP Work Center , I want to have the table where details of PM Functional Location & PM Equipment are stored, in which the PP Work Center is used.
    Thnx,
    Shivaa.

    Hi Shivaa,
    Go to T.Code : SARA and giving archive object : PM* + press F4 you will get the following
    Try with the following tables:
    PM_EQUI    Equipment
    PM_IBASE   IBase
    PM_IFLOT   Functional Locations
    PM_IMRG    Measurement Documents
    PM_MPLAN   Maintenance Plans
    PM_NET     Object links, master data
    PM_OBJLIST Serial Number History
    PM_ORDER   Service and Maintenance Or
    PM_PLAN    Routings
    PM_QMEL    Maintenance Notifications
    From the above list click the suitable one and press database table tab. You will get all the relevant database tables.
    Here you go...
    If it is useful reward points
    Thanks
    Saravana
    Edited by: K Saravana Kumar on Jul 30, 2008 8:25 PM
    Edited by: K Saravana Kumar on Jul 30, 2008 8:26 PM

  • Assing a cost center to Storage Location.

    Hi experts,
    I need help for assign a cost center to one Storage Location, how I should do???
    Thanks!

    Hi,
    As guys above already wrote - this is not something that you do in SAP. The question to you is: WHY you think you need to do such assignment? What do you want to achieve?
    Regards,
    Tomek

  • How to determine a cost center based on a storage location

    Hi all,
    During material movement or stocked purchase, I need to determine different cost center by storage location. Therefore, i can't use OKB9 because the plant criteria is not enough.
    Is there any user-exit or another solution i can implement to solve this problem?
    Thank you for your answers.

    Hi
    As i said earlier, you can use MSEG itself in your substitution rule.
    For  Ex:
    Pre- requisite
    BKPF-BUKRS = 'XXXX' AND BKPF-AWTYP = 'MKPF' (and anyother criteria that needs to be applied)
    Substitute
    Field - Material (MATNR)
    is substituted by "EXIT"
    Create your own exit here & give your logic like
    If MSEG-LGORT = '0001'(your storage location values)
    then BSEG-KOSTL = 'CCTR1'.
    Let me know if you need any further details.
    Thanks
    Kalyan

  • How can I relate an equipment with the PP Work center & functional location

    Hi,
    I'm trying to relate equipments with their PP work centers (field ITOBATTR-ARBPL listed in the Location tab of the equipment) and the functional location (field ITOB-TPLNR listed in the Structure tab of the equipment) through SQVI.
    The workcenter is in a structure and the functional location relation in table ITOB gives me thousands of results with different functional locations per equipment so I can't tell which one is the propper one.
    Additionally I would like to filter the equipments flagged for deletion, but I also can't find the field of thet flag).
    In resume I need to create a query that gives me all equipments not flagged for deletion with their corresponding PP Work center and functional location.
    Thanks in advance
    JV

    Please check table EQUZ or view V_EQUI.
    In table EQUZ (GEWRK is the work center object number ) -> Use this go to table CRHD and find ARBPL for the correct time slot.
    For fucntional location in EQUZ (ILOAN is the location assignment ) -> go to table ILOA with the ILOAN and fetch TPLNR.
    Please ensure you fetch records which are currently valid from EQUZ (Use the valid to date field compare . Valid to date must be greater than or equal to current date).

  • Function Area derive from cost center

    Hi, here is a question.
    The function area was input in the cost center master data. Cost center A ( Function area 1000), Cost center B (Function area 2000)
    Then creat a PO with Account Assignment Category(K), Item Category (B), input the cost center A in the PO.
    When I do MIRO, I change the cost center (A TO B), but the function is still 1000, not change to 2000. But if I delete the Function area in MIRO first, then change the cost center, the function area update to 2000.
    There is no default function area in GL account and cost element, also no substitution.
    Is it standard in SAP?  I want the Function area can be updated with the cost center. Any method?

    Here is what SAP help says about this.
    Functional area field for postings - ready for input?
    You can enter the functional area directly when entering G/L account postings, provided the "Functional area" field is shown in the field status group of the G/L account.
    SAP recommends that you do not show the "Functional area" field in the field status group of the G/L account, but rather that you have the system determine the functional area of the account assignment. This eliminates the risk of the user entering incorrect functional areas.
    You said you have functional area in cost center master data.  When you post documents, do you get func. area from the cost center automatically or not?

  • PM- Functional location wise cost report

    Hello Friends,
    Does anybody know PM cost report for functional location wise which will consider the all the cost related to PO & internal material procured under the work order?
    Thanks & Regards,
    Vaibhav Gole

    Hi,
    Go to MCI4 analysis report and type your function location in search creteria.You will get all planned cost and actual cost location wise.
    S.S.

  • Settlement Rule based on FL cost center

    Hi Guys,
    My client wants CC to be maintained in the Functional location and they don't want to maintain in the Equipment.
    Their Requirement is, when ever a person creates the Maintenance order for any equipments attached to the Functional location,Settlement rule should gets created automatically based on the CC maintained in the FL.
    But in standard it creates automatically when CC is maintained in the Equipment.
    How to handle this scenario.Is there is any Customer exit to handle this scenario?
    Pl guide me
    Regards
    ISWARI

    Dear Mr Thiyagarajan,
    I really appreciate your immediate response for any threads.
    Here they want to create order based on equipment(for analysis of cost through MO) and want settlement should be on the CC of FL.Hence they don't want to maintain CC in Equipment master and want to maintain CC in FL. 
    As you said ,If I maintain Cost center in FL and not maintain Cost Center in Equipment master,then while MO creation in location tab all data's were copied from equipment and CC field is empty.Hence while releasing the order,system asks for settlement rule.
    How to make the system to copy the FL cost center to the location tab of order.Pl suggest if there is any exit/badi
    Regards
    ISWARI

  • Setup Cost Center hiearachy first, then Profit Center hierachy later?

    Dear Experts,
    Should I setup the cost center hierarchy first, then the profit center hierarchy later? 
    Regards,
    Abraham

    I see.  but if I setup profit center hierachy first, then I got to redo the same for Cost Center.  I thought I could do the Cost center first, then copy them to profit center since there's a "copy cost center group" function in profit center accounting. 
    Can I deactivate the profit center accounting since each time I skip the profit center entry during cost center creation, the following message pop up?
    "Profit Center Accounting active but no profit center specified (CCtr 1110)"
    Regards,
    Abraham

  • Transfering the Cost from Cost center to PM Work order

    Hi all,
    We have a scenario.
    we are doing material consumption from storage locaiton to a cost center using 201.
    when the material requirement comes from work order, we are doing reverse consumption posting from Cost center to storage location using 202. and then issue the material to work order using 261.
    Is there any way, that we can move the cost directly from cost center to work order (skipping the storage location in between).
    Thanks in advance.
    Piyush

    Hi,
    I guess Initially you are transferring material (201 movement) from Central Warehouse to Cost Center assigned to each department. After that, if you get any reservation from the particular department work order, you are issuing the components to work order by doing 202 & 261 movements.
    You can follow either one way.
    1. Without doing 201 movement type, once you create a order, based on reservation you can do 261 movement to order from central warehouse directly.
    OR
    2. Define storage location, do the stock transfer between storage locations. While creating maintenance order, assign the concern storage location in the order. So from that storage location, you can do 261 movement. Also by Material valuation, you can find the value of materials as well.
    Regards,
    Maheswaran.

  • Why we assign cost center while posting to any G/L

    Hi All,
    I need one clarification.
    Why we assign cost center while posting to any G/L, even though we have been assign cost center to the cost element it will post the co entry through cost element.
    Please any one make me understand the internal logic and process of how cost element and cost center works.
    Thanks
    Nandha
    help.sap.com

    Find below your clarification for the points
    Why we assign cost center while posting to any G/L, even though we have been assign cost center to the cost element it will post the co entry through cost element.: Once you have assigned cost center to cost element in T.code OKB9 or KA01, no need of manually entering the cost center for the respecting primary cost GL while passing enteris.
    Please any one make me understand the internal logic and process of how cost element and cost center works.: Whenever you post a cost to primary cost element , you require an object in Controlling , such as cost center to identify the costs. This primary costs are only created when the respective GL exist in the operational chart. Cost center is the location where cost incurs. Thus when you assign the cost to cost center , the cost will be booked against that particular location .

  • Cost Center mapping

    firstly i want to know how do i change how the mapping of a cost center...can a cost center be tied to a storage locatio instead of to a material...so when a stock count is doe the mapping of the cost center will be against the storage location and not the material...

    Cost center and storage location does not come together any one only  has to be used at a given time. If we choose cost center then there will be no storage location asked during GR, and if we do not use Cost center then that indicates Storage location is to be filled in duirng GR.
    Cost center  is for direct consumption  and SLOC is used to store and later issued for consumtion. Accounting entries are different during both the case.