Costing a Phantom
We are implementing WIP and BOM with the use of phantoms.
At the moment can not configure the system to show the costs of
the phantoms at previous levels at the subassembly or finish
good, somebody handle phantoms in previous levels and how made
the configurarion to make the cost roll up at the last level.
Regards from Mexico.
Not sure if i understand the question, however if the question
is
"Can i roll up the costs of phantom items by rolling up the cost
of it's components and routing for phantom"
Yes you can do this in 11i, by setting up parameters in BOM.
Similar Messages
-
Hi all
I'm trying to cost a material which has a phantom component in the BOM.
Can someone clarify if the phantom needs to be costed at all..? I mean, does "no costing" indicator need to be set in costing 1 tab of material master..?
Can someone explain this please?
Thanks very muchHello -
A phantom material does not need to have a standard cost becuase the costing program will ignore that particular material when calculating for the upperl level item. Instead, the cost of the components that make up the phantom assembly are taken into consideration. Any labor that is stored in the routing for the phantom assembly is also ignored if one exists.
Hope that helps. -
Having problems with an update that keeps showing up on my User's App Store Adminitrator account that is for a program that is only on another Standard user's account. When I attempt to download the update from the App Store, a Fly-Down window appears instructing me to log on to the Standard User's account in order to download the update. But when I log on to the Standard User's account, there are NO App Store updates. I have logged on to both App Store accounts and reset all notifications on both accounts, but I keep getting the update notification on my Admin account's App Store.
There is no "ignore this update" option on App Store of which I am aware.
Please help!
BrianRoutings for phantom items are just for costing purposes, and not for production. A>B1>B2>C1>C2 --> D is the right structure for a production order for finished goods A, so components B1,B2,C1,C2 will be assigned to operation steps of material A. You will notice operations to build B and C do not appear in production order for A, so routing for material A should somehow include operations of B and C for actual costing.
Phantom items by definition are entities that cannot be placed on stock, so if you "un-phantomize" B and C, you will get planned orders for them and you will have to GR them into stock once done! If B and C are physical items that can be placed in stock, then you can un-phantomize them.
Hope this helps. We use lot of phantom items at our divisions, and SAP functionality for this is standard and works well. -
Hi,
Can you please help me answer:
Which possibilities are there to use bills of material (BOMs) in SAP SRM 5.0 or beyond? We are using Material Master data replicated from MM in SRM Extended Classic Scenario?
Is there any documentation available? I have not been able to find any.
Thanks.
Best regards,
JohanHi
Please go through the pointers below ->
BOM DAta Access in SRM
Can we maintain the BOM for the trading(HAWA) material
Costing of phantom in a BOM
Re: Account assignments
Re: Contract Upload Issue
Re: block materials in R3
bid invitation
Do let me know.
Regards
- Atul -
Can 119 phantom asslys at one bom level create problem in product costing
I am going through a scenario where there r 119 phantom assemlies at one bom level. Can this create problem in product costing? It has been told to me by somebody that there can not be more than 99 phantom asslys at one level of bom? Is that true? My problem is that when i am doing product costing it is showing error-" too many dummies at bom level". Is this related to no. of phantom asslys at one bom level?
HI bala,
all the materials are costing relevent. I thik this problem is releteted with no. of phantom assemlies allowed at one bom level.
I had 119 phantom assemlies at bom level 3 of a varient material. At that time it gives me abap runtime error during product costing.
Now I have removed special procurment key 50 from material master of 20 number of phantom asslys. so now there r now 99 phantom assemlies at bom level 3.
I have taken costing run and its not giving error.
so i reached to conclusion that statndard limit of no. of phantom assemlies at one bom level can not exeed 99.
Now customer requires 119 phantom assleys at this level 3 of bom.
So can u suggest me whether i should contact sap to increase this limit for this perticular case?
will they solve my problem or there is any other solution to this?
please reply.
nitin -
Error in creation of Phantom item bill
Hi Gurus,
We have planned to use phantom item. for that wehave created an item of type: 'option class'. Then created its routing but facing below error when trying to cretae bill for phantom item.
Kindly help me out
Regards,
Ali Raza
APP-FND-01048: Use of this combination restricted by WHERE clause ' ( ((:parameter.query_mode = 2 AND bom_enabled_flag = 'Y') OR (:parameter.query_mode = 1 AND EXISTS (SELECT NULL FROM bom_bill_of_materials bom WHERE bom.organization_id = :parameter.org_id AND bom.assembly_item_id = inventory_item_id AND ((:parameter.bom_or_eng = 1 AND assembly_type = 1) OR :parameter.bom_or_eng = 2) ))) AND (bom_item_type in (:parameter.model_item_access, :parameter.planning_item_access, :parameter.std_item_access, :parameter.oc_item_access) ) AND ((:parameter.bom_or_eng = 1 AND eng_item_flag = 'N' AND NOT EXISTS (SELECT 'X' FROM bom_bill_of_materials bom WHERE bom.organization_id = :parameter.org_id AND bom.assembly_item_id = inventory_item_id AND bom.alternate_bom_designator IS NULL AND bom.assembly_type <> 1) AND (:parameter.eam_type is null OR (:parameter.eam_type in (1, 2, 3)
APP-FND-01388: Cannot read value for profile option FND_INDICATOR_COLORS in routine &ROUTINE.Hi Sandeep,
Thanks for your reply.
I have checked all three possibilities. Item is not Engineering item and already assigned to Org. Also the BOM doesnot exist. Kindly note that I donot have any issue in creating bill of a standard item. We are using phantom item for the first time so tell me if phantom item need some special setup or some profile option to be active etc? I am using below attributes in inventory. Kindly go through it and suggest.
Deviation Factor + 0
Deviation Factor - 0
Shelf Life Days 0
Price Tolerance % 0
Acceptable Rate - 0
Acceptable Rate + 0
Postprocessing Lead Time 0
Planning Time Fence Days 1
Lead Time Lot Size 1
Descriptive Flexfield ---------
Item Status Active
Conversions Both standard and item specific
Forecast Control Consume Forecast
Effectivity Control Date
Service Request Enabled
RMA Inspection Required Inspection not required
Default SO Source Type Internal
Restrict Locators Locators restricted to pre-defined list
Make or Buy Make
Billing Type Material
Cycle Count Enabled No
Check Material Shortage No
Lot Split Enabled No
Lot Merge Enabled No
Lot Translate Enabled No
Lot Substitution Enabled No
Bulk Picked No
Engineering Item No
EAM Notification Required No
Use Approved Supplier No
Taxable No
Allow Description Update No
RFQ Required No
Outside Processing Item No
Equipment No
Planned Inventory Point No
Repetitive Planning No
Build in WIP No
Customer Ordered No
Customer Orders Enabled No
Internal Ordered No
Internal Orders Enabled No
OE Transactable No
Assemble to Order No
Ship Model Complete No
Financing Allowed No
Invoiceable Item No
Invoice Enabled No
Enable Contract Coverage No
Enable Defect Tracking No
Lot Control No lot control
Serial Number Generation No serial number control
Lot Expiration No shelf life control
End Assembly Pegging None
Check ATP None
ATP Components None
Safety Stock Non-MRP planned
Inventory Planning Method Not planned
MRP Planning Method Not planned
Primary Unit of Measure NUMBER
BOM Item Type Option class
WIP Supply Type Phantom
User Item Type Phantom item
Locator Control Prespecified locator control
Tracking UOM Indicator Primary
Pricing UOM Indicator Primary
Reservable Reservable
Restrict Subinventories Subinventories restricted to pre-defined list
Description TEST FG
Revision Control Under revision quantity control
Planning Time Fence User-defined time fence
Inventory Item Yes
Stockable Yes
Transactable Yes
BOM Allowed Yes
Costing Enabled Yes
Inventory Asset Value Yes
Include in Rollup Yes
Purchased Yes
Purchasable Yes
Receipt Required Yes
Create Supply Yes
Shippable Yes
Pick Components Yes
Returnable Yes
Enable Service Billing Yes
Regards,
Ali Raza -
Issue with Phantom Material in PCE
Hi,
While creating the PCE for one of the finished materials, in the PCE, the phantom material is not getting selected.
There is no issue with the production version or BOM or Master recipe since in the process order after the BOM explosion the phantom material is being picked up.
The costing date of the PCE is also as per the production version validity date. In the BOM & master the phantom item is maintained for costing.
Let me know what else could be missing.
Thanks in advance,
Regards,
AbhijitThere is no problem with the costing run. If a material is marked as a phantom assembly (that is, it has a special procurement type with procurement type: In-house production and special procurement: Phantom assembly ), costing directly explodes the BOM and calculates the planned costs for all material components in the phantom assembly. These material components are displayed and updated in the cost estimate of the higher-level material, but not in the phantom assembly. The idea is, phantom assemblies are not needed to be costed as they are not valuated and neither stock is maintained for them. But their cost structure is exploded properly for the costing run.
-
http://sportsraxco.com
I'm creating sports related 3D products using illustrator to create the original art. You can see them at the website above
The art is outlined exported as dxf and sent to a metal fabricator to laser cut the art.
Multiple phantom outlines of the drawing appear in the dxf complicating the cad work and adding cost to production.
We've found that the phantoms actually are in the illustrator file. Exact images of what i'm drawing but assigned no color.
Why is that happening. How do I stop it from happening?
Thanks four your help
Larry Raymond -
Does the AC adapter pull a "phantom load" when not actively charging?
Got notice today that our electric bills are going to be "around $44/bill" higher starting June 1st, according to Austin Energy. Their "suggestions" for less power use (which are really pointless in view of how much Air Conditioning costs) are to "elminate phantom loads" such as battery chargers, etc.
I'm wondering if the AC adapters for laptops (and iPods and the like) pull a "phantom load" if left plugged into the wall, but not plugged into the laptop?
I've always just left the adapters plugged into the wall, 24/7, even if the laptop isn't charging. Same with the iPod charger...it stays plugged in whether the iPod is plugged in or not.
Anybody know the answer to this? If they DO, then I've got to start playing "plug nanny" with even those adapters.
Thanks, "City of Austin", greedy, money-hungry entity that you are.You can get a definitive answer for anything in your home by getting a device like the Kill A Watt which is a meter you plug something into and it tells you how much power it uses. You can set it to calculate how much money a particular device or appliance is costing you.
You can get versions that are much cheaper than the fancy model I linked to. Also, regardless of electrical rates I already plug a lot of adapters into power strips so that I can throw one switch to shut off the whole strip and ensure nothing is drawing power. -
Finished Goods BOM Semi finished goods costs
Dears
We have Product Costing by order where we have multi level BOM with Phantom Assembly. When we run the costing CK11N we unable to see the cost break at semi finished goods level rather we can only see the cost details by raw material level. We think something wrong with the BOM but unable to find out the reason. Can some one help us in this regard
Thanks
Farhan QaiserHi Ajay,
I need your help, in the CO03 the production order the GR shows (finished goods) negative value? will it be correct or anything else , i want to confirm to my client.
one more year end activity,while KKAO we run successfully, but the accounting entry is not generated?will generate accounting entry or not .please explain us. I have posted in forum but not got the correct answer.
Edited by: arjooo on Apr 11, 2011 6:23 AM -
Costs of components and activities not incorporated in costs of FG
Dear experts,
I am setting up discrete manufacturing in a warehouse with Handling units. The process I follow:
1. Crate handling unit with COWBPACK
2. Do goods receipt with COWBHUWE
3. Consume components with COWBHUWA
When looking at the financial documents behind the goods receipt of the finished product, I notice that the only costs that are booked are the costs of the actual finished product to inventory, but not the activities or the costs of the components...
What am I doing wrong or what configuration is missing?
Thanks. MHi Pankaj,
When generating PPM/
PDS, the system checks whether the components of the bill of material exist in an active integration model. If not, the corresponding components are not transferred to the PPM.
Compenet will not transfer if :
-Components that have the phantom item indicator are not transferred.
-Components that have the bulk issue indicator are not transferred.
-If the leading material already exists in APO but this leading material is no longer in an active integration model, no data is sent to APO.
If all are fine, will suggest you to to do initial tranfer again.
Manish -
Phantom with Outside processing
Hi all,
pls help me.
I have an assy with a routing with outside processing but I often need to change to phantom this assy. So this assy result phanto for a BOM and non Phantom for another BOM.
I need also to count the time of resources used for phantom items so I enable the flag in BOM parameter "Use Phantom Routings".
The problem is that: for Jobs in whitch the subassy is phantom I need all its resources that go up to the parent but NOT the Outside processing.
for jobs in whitch the subassy is NOT phantom the outside processing is correct.
Is there any way to solve this request? I try to use alternates bills and routing but WIP consider only the alternative BOM and/or routing of the parent and not even of the phantom subassy.
is there someone who can help me?
really really thanks
AlexHello Rafik ,
Hope this will give you an idea about Subcontracting Operation :
Subcontracting Steps:
1. Define all the materials in your plant (subcontracting and packaging etc).
2. In the material master MRP 4 view there is one field in which you can mention that this material is not relevant to MRP planning, use this field for subcontracting material so that it will not be planned in MRP runs ( generally use this field for re-order point planning).
3. In the BOM for the subcontracting material put the special procurement key as Subcontracting and do not keep relevance for costing.
4. If you're using packaging material of your company and want to capture the cost of these materials in the subcontracting production order then put relevance for cost.
5. Define alternate BOMs for each customer.
6. Generally the routing will be the same but materials will change, define different prodcution versions for each alternate BOM and assign to the routing.
7. Define the activite types for packing and mixing in the work center and assign them to the cost center, use these for your routing.
8. Whenever you recive a sub-contracting order, use the relevant production version depending on the customer.
9.Please use control key PP02 (customizing in OP00)in routing and maintain
info record for subcontracting vendor
In my place all the palnts belong to the same client in sap and they want to use the same material code in both plants, so I think my subcontracting scenario might be different from yours but it give you some ideas to go about it.
Regards
Jia -
Repeated entry of same material during costing of header
Hi ,
during costing run of a header material, a component assigned only once in BOM is comming in multiple line items with different qty.
what may be the reason?
RegardsHi vivek/ jiaul,
Thanks for reply,
BOM component is not recursive.
component is assgined only once in BOM . I checked CS12 also and its assigned only once in header.
Let me tell the structure of assignment of this raw material which is coming multiple times.
This Raw material is assigned to Phantom material and the phantom is assigned to header material and we are running the costing run of the header material.
In costing run This raw material is coming multiple times with diffrent qtd. out of which only one lineitem is correct and other lineitems are coming of same material with diffrent qtd.(nowhere in BOM this diffrent qtd which is coming is maintained)
what else to be checked, please advice.
Regards,
Edited by: pp savvy on Jul 3, 2010 3:18 PM -
if I have an Product, and in its BOM there is a phantom assembly item which has its own routing. Question is, can i confirm also the operations for that phantom assembly? How is confirmation done, when there is only one production order (which is for the Product itself)
Hello,
Yes it's same, you have to move all the operations of the phantom material routing to the header material, then only those operations are used for scheduling, costing puposes.
Even in costing system will not consider the phantom routing for the cost calculation when co is doing with qty. struc.
They will encounter problem.
so make sure that there is no routing for the phaantom materials and all the operations are moved to the header material.
Regards,
Manick. -
BAPI_ROUTING_CREATE problems with component allocation of phantom BOMs
I try to create a routing via the BAPI_ROUTING_CREATE and all works fine until I try to do component allocations for phantom BOM lines in the next level.
In my simple BOM I have the following structure:
00004465 (ROOT BOM)
+
+---Phantom_BOM_B (BOM 00004466)
+
+---Material_X
+---Material_Y
I only can allocation Material Y and BOM_B but I am not able to allocate the material X instead of the BOM_B, in that case I always get the message "The component to be assigned has not been completely specified".
My COMPONENTALLOCATION Table Code:
T_COM-SEQUENCE_NO = '000000'.
T_COM-OPERATION_ID = '0010'.
T_COM-BOM_TYPE = 'M'.
T_COM-BOM_NO = '00004466'.
T_COM-ALTERNATIVE_BOM = '01'.
T_COM-ITEM_ID = '00000001'.
T_COM-ITEM_NO = '0010'.
T_COM-BACKFLUSH = 'X'.
T_COM-PLANT = '1000'.
T_COM-MATERIAL = ''.
T_COM-BOM_TYPE_ROOT = 'M'.
T_COM-BOM_NO_ROOT = '00004465'.
T_COM-ALTERNATIVE_BOM_ROOT = '01'.
*T_COM-PATH = '000001'.
I hope some can help me to find me, a solution to solve my problem.
Thanks
JörgDear ,
Phantom BOM means which you want to plan interm of Operation Hrs and Issue Componenets but not intereted to Physically Store rather re-ssiue it to Main FG .
Now ,from your requirement it s clear that BOM : 00004465(ROOT BOM) is for your FG (Let Say A) BOM : 00004466 is a SFG (Let say B) as Root BOM component , which is In House produced .
Bascically , If you do not want to *Store B( Phantom BOM) * but want plan the depedent of B ( X, Y , Z etc ) along with A's dependent and also cost of B ( Phantom BOM ) , then the routing hrs /component along will be issued directly to A( Root BOM) ,
So you do not need to create Routing for Phatom BOM and also no componenet alocation required . Better , you can add that routing operation hrs to main routing of the FG .
Hope this is clear
regards
JH
Maybe you are looking for
-
Install boot camp partition on Mac mini
How to install boot camp on a Mac mini? It ask for a bootable DVD which I have inserted in my Mac book pro, but it does not recognize the DVD. How can I install boot camp on a mini?
-
XSLT mapping error using document function
Hello, We migrated from XI 3.0 to PI 7.1. XSL is made use of for mapping. We are encountering this error of 'File not found' when we use the document funcion to look into an xml file. The xml file along with the xsl map is zipped and uploaded. I am n
-
Adobe Presenter vs. Articulate Presenter
Hello! I previously used Articulate Presenter to develop content. However, due to some major software bugs I was having with Articulate, I switched to using Adobe Captive (and am very happy). Now I just came across Adobe Presenter and it seems exactl
-
Brand new T400 - wont turn on?!
I have a brand new T400 for work. It loads up, goes through the windows screen, briefly goes to the 'cntrl/alt/delete' to log on screen, then goes to a blank blue screen and does nothing else... help! need to access reports on there that I generated
-
Authorization issue using RSECADMIN
Hi, I´ve created an Authorization using the new RSECADMIN tool. I´ve added the 0FUNDS_CTR characteristic filtered with an specific value. I´ve also added the 0TCAACTVT, 0TCAIPROV, 0TCAKYFNM, 0TCAVALID into the authorization. However, after I assing t