We are trying to carry out credit checking at the line item level. Standard SD only has credit checking at the document level.
Does anyone know of any enhancements or notes we can apply to achieve this.
Thanks Steve

Hi Steve,
The field VBAP-CMGST is only at the header level that is the credit      
status is only available at the header. So when you release a            
sales order the entire order is released. It cannot be maintained        
at the  item level.                                                                               
Note 60672 explains that placing a delivery block on the schedule line   
level will have this affect on credit management.  Credit bases things   
on what can be delivered. Please check in the tranx OVZ7                                                                               
In block quantity confirmation in delivery blocks there is a blocking    
reason setup (ZI) which blocks confirmation if an item is incomplete.    
Please see configuration in transaction OVZ7.                                                                               
Unfortunately, in standard SAP, credit block is applicable to the        
whole S/O document.                                                                               
In general, credit is applicable to the customer [soldto/billto/payer].  
In SAP, this 'customer' is part of header/document level, and not        
item level.                                                                               
You can not change this behaviour in IMG or userexit.  
I hope those information can be useful
regards
Ruy Castro

Similar Messages

  • Default profit center in sales order line item level

    Hi Experts,
    In creation of a sales order, I want to default the profit center for every line item in the order depending on some logic. How do I go about it.
    Warm Regards,
    Abdullah Ismail

    Hi,
    You would need to implement a user exit:
    try this user exit :
    USEREXIT_MOVE_FIELD_TO_VBAP
    Use this user exit to assign values to new fields at sales document item level. It is described in the section "Copy customer master fields into the sales document".
    regards,
    Advait

  • IDOC(ORDERS05) - Pass payment method on sales order line item level

    Hi
    We have requirement here to pass payment type(VBKD-ZLSCH) on each line item of the sales order from IDOC. But, IDOC structrure ORDERS05 doesn't have provision to handle this data. Is there any other way to pass this information, except extending the IDOC and handling in the user exit(002) for the same. Please advice.
    thank you very much in advance.
    Thanks
    Lakshman

    I was able to fill the event container creating a new FM based on the template FB SWE_CD_TEMPLATE_CONTAINER_FB_2.  At that point, you have access to all of the Change Document information (i.e. CDHDR and CDPOS).  I was able to take the line item affected and set the Event parameter for line item and then pass it through my workflow. 
    As I was testing I realized that if I made multiple line item changes, they are tagged with the same Change document number during the same update in the sales order.  As a result, I had to make the Event parameter a multiline parameter.  Now I was trying to set the Event parameter, but I think I was using the Methods SWC_SET_ELEMENT for the multiline parameter.  It wasn't setting it properly.  I think I need to use SWC_SET_TABLE and pass it the whole table. 
    I will let you know if this works.

  • Sales order line item check based on material status

    Hi
    I have the following requirement
    There are Distribution chain specific material status maintained in the material master ( Sales Org1 View). Now for some of these statuses we need to reject these items in the sales order @ line item level. A reason for rejection needs to be assigned for these line items.
    Is there any standard setting or a user exit is required. I believe user exit save_document_prepare could be used to carry out these checks & assign a reason for rejection. Pls suggest asap
    Thanks
    Ramesh

    Dear Ankit,
    The difference between reason for rejection and delivery block is,
    Reason for rejection you can find this field at header level and line item level, the use of this is once you mention any reason for rejection the TOR or Schedule line not been confirmed for that material,so that the material can be confirmed to another customer.
    If you set delivery block the material for sale order in case if the material not available it will rise TOR or if available it will confirm the schedule line and block the material for that customer or sale order.
    This is the major difference between two.
    Regards
    Ram

  • Third Party GRN Posting Date to be Copied to Sales Order Line item Billing Date

    Hello Experts
    I have a client requirement where in they want to bill line items in the sales order ( third party process ) to the end customer in sync with the GRN posting dates happened in the PO
    For EG if GRN happened on 1st July 2014 then Billing Date should come in as 31st July 2014 so when they execute VF04 giving from and to dates as 1st july to 31st corresponding sales order can be invoiced
    Actual problem is for suppose if i create a sales order in the month of june say 26th basing on the factory calendar setting and invoicing list maintained in the customer master system defaults the billing date to 30th June 2014 , and the same when user runs VF04 from 1st June to 30th June this sales order shows as due and mistakenly end user invoices the customer ( whereas logical GR would have only received in July 1st )
    My requirement is similar to below threads but i am unable to find answer how to copy GR Posting date to Billing Date of the sales order line item
    use GR Doc date as billing date
    3rd party sales process (w/o ship notif) - Billing

    Hi Lakshmipathi ji,
    As my requirement is to update the billing date at the sales order line item level , As a process user goes in executes VF04
    For Ex
    Sales Order Created Date is 1st June 2014 then System Defaults Billing Date at line item to 30th June 2014
    Now when i do GRN suppose on 1st July 2014 for that line item , system should trigger a code where in check the posting date of the GRN and override the same in the Biiling Date field of the sales order line item
    So when VF04 is run for a month All the GRN which are recieved in the month of July are invoiced in July
    Please share me your thoughts do we need to check any userexits from MM side which reads the posting date of GRN and then copies in to my third party sales order
    Regards
    Hiba

  • Sales order line item user exit?

    Hi Folks,
    Can any one of you suggest me an user exit in sales order line item level?
    I want something which stops before/ or just after entering the quantity in the item level.
    We wanted to set up a issue which deals with rounding profile comming from CMIR record to take from Ship-to rather than standard Sold-to party functionality.
    Thanks a TON in advance.
    Praveen.

    Praveen,
    Check this post
    https://forums.sdn.sap.com/click.jspa?searchID=7098802&messageID=1674246
    Regards,
    Satish

  • Sales Order Line item category not getting Re detemining Correctly

    Dear all,
                I need  help regarding the Sales order item category redetermination.
                we are having two item categories YNAE and YNAG and it contains schedule  line categories CP and CB ( i.e for item         category  YNAE schedule line category is CP and for item category YNAG schedule line category is CB),
    for YNAG Purchase Requisition is automatically created becz of functional setting on save and it is working fine.
    For every line item in sales order line item level item category YNAE will be determined by default as per functional settings.
             Now my requirement is that, if sales order line item doesn't contain 100% confirmed quantity, than i needs to change the default line item category YNAE to YNAG which i am trying to do it in USEREXIT_PRICING_PREPARE_TKOMP becz in this exit i am getting the values in XVBAP and XVBEP and  it is working fine .
             But schedule line category is not getting redetermined automatically what i mean is, if i change the item category to YNAG from YNAE in user exit corresponding schedule line category CB of YNAG is getting determined automatically at the schedule line level and if ichange the schedule line categories in XVBEP in exit USEREXIT_PRICING_PREPARE_TKOMP, changes are reflecting at the schedule line level but Purchase requisation is not getting created for schedule line on SAVE and its delivary dates are also not getting determined properly. If i press the option ATP check at the schedule line level than very things will getting corrected.
       I feel that i am not doing this in proper way, do u have any idea about how to redetermine item category. please let me know if u have any idea .
    Regards,
    Vaddepally Manoj

    USEREXIT_PRICING_PREPARE_TKOMP is the wrong location - that exit is for pricing communication preparation only.  Your primary location for item category determination is USEREXIT_SOURCE_DETERMINATION (MV45AFZB).  In your simple scenario, you could consider making an availability check at this point with some assumptions and then assign the item category accordingly.  Otherwise, you can re-assign item category and schedule line category in USEREXIT_MOVE_FIELD_TO_VBEP.  The exit is called once before ATP (for ATP-relevant schedule line categories) and once afterwards.  The call is recursive if you re-assign another ATP-relevant category.

  • Sales order line item conditin type

    hi experts
      in pricing procedure determination we  at lost we are giving condition type. it was displayed in sales order line item level
    what is the purpose of this condition type.
                                   thanks to every buddy who are trying to give answer this question.
                                        narasimha
                                        [email protected]

    Hi,
    This is to avoid going into the line item and entering the value in the amount field.
    When u assign it there in your pricing procedure determination you can enter the amount in the amount field for each line item and avoid drilling down to conditions tab for each item
    Hope you find this helpful.
    If you, please reward points for contribution.
    Regards
    Ravi

  • Credit check at sales order level?

    Dear experts
    I want to set credit check at sale order level with following conditions
    consider open deliveries for credit exposure
    consider billing documents for creadit exposure
    do not consider any open orders
    Also if oldest items are open for more than 7days then block the sale order creation
    e.g suppose customer is having credit limit Rs.100000/- and open deliveries against this customer is having the value Rs.50000/- i.e. credit exposure is Rs.50000/-. In this case system should block the new sale order created of value more than Rs.50000/-
    plz suggest the configuration steps
    regards
    kailash

    dear friend
    For i am already having the same setting but still my scenario is not working. i will explain my scenario again
    suppose customer is having credit limit Rs.100000/- and open deliveries against this customer is having the value Rs.50000/- i.e. credit exposure is Rs.50000/-.
    In this case system should block the new sale order created of value more than Rs.50000/-
    But with the said settings purpose is not getting solved.
    my settings are;
    In OVA8 ;
    Update: 000015
    Static check: TICK
    Status: TICK
    open deliveries: TICK
    Plz suggest
    kailash

  • Custom program for availability check and update for existing sale order at Item level(VA02)

    Hi,
    I came to know Bapi_Saleorder_Simulate can be used for availability check and update an existing sale order.but there is no sample program explaining the process.I have tried this by passing parameters ORDER_HEADER_IN , ORDER_ITEMS_IN  ,ORDER_PARTNERS and ORDER_SCHEDULE_EX(for getting details),also i have assigned the sale document number ,custom document type(ZSO) in ORDER_HEADER_IN . while executing the BAPI I am getting the error external number range is not assigned for the document type ZSO . I am confused on seeing this error. It is possible to do availability check for existing sale order using this BAPI. Please explain how to achieve this.It will be really helpful if it is expalained with an example.   
    Regards,
    Shanmuga

    Hello, I think you may have been misinformed about this BAPI updating a sales order at item level. As far as I understand it this BAPI can be used to simulate the creation of a sales order which obviously would include and ATP check. This is why it is giving the error because it is simulating creation but you are entering a value in a field that should be automatically generated (i.e. the sales order number). For change the sales order at item level have you looked at BAPI_SALESORDER_CHANGE? I pretty sure this BAPI both updates sales order (header or item level) and can do an ATP first.
    Points are always welcome if you feel an answer has been helpful.

  • Implications of changing credit check from sales order level to delivery

    Currently the credit check is availbale at the sales order level in the system and if I want to change the credit management settings so that credit check will be available at the delivery level.
    What are the implications of changing credit check from sales order level to delivery

    >
    Mangesh Desai wrote:
    > Currently the credit check is availbale at the sales order level in the system and if I want to change the credit management settings so that credit check will be available at the delivery level.
    >
    >
    > What are the implications of changing credit check from sales order level to delivery
    Hi,
    No Implications simple credit check will not happen order level it will happen delivery level .
    *system will not conceded at order level open order will not be calculated
    Best Regards,
    venkataswamy.

  • I have a problem regarding sales order line item with confimed quanity

    Hi Experts,
    I have a problem regarding sales order line item with confimed quanity with '0'  with delivery block but confirming the sales order quantity once the order is released from credit check.
    The situation arises as per the below scenarios.
    Scenario - 1 -  When the sales order has two line item - one line item with confirmed qunaity in the schedule line and for the 2nd line item there is no available stock for the Material xxxxxx.
    Initially the sales order is created for the line item 2 with confirmed quantity = 0, and having the delivery block = 01 for the Material xxxxxx  and the order is set with credit check.  Once the order is relased from the credit check.  The quanity for the item 2 where the confirmed quantity will be = 0 ( Where it is not changing the confirmed quantity)
    Scenario -2-  Updating the order qunaity for the line item 2 as (9Pcs) it will goes to credit check and save the order.
    Maintain the stock for the line item 2 ( 5 Pcs).
    Once the order is released from the credit check.  Then  for the line item 2 the confirm quanity will be seting to 5 Pcs with Delivery blcok 01.
    This should not happen, When the credit check is released even though if it has stock based on the delivery blockl it should set the confirmed quanity to Zero.
    Can you please help me how to solve this issue.
    Looking forward for your reply.
    Thanks and Regards,

    Hi,
    I agree with your point.  In the sales order When the complete delivery check box is enabled where the confimed qty is set to zero, it is fine but when we save the orderr it goes to credit check.  Once we release the order using VKM3 where in the sales order the confimed quantity is setting to 5,  But it should set to Zero quantity.  Quatity should not be get confirmed it should be Zero Quantity. 
    Further in SPRO - customizing in the deliveries blocking reasons - It has a tick mark in the confirmation blcok.  But we dont want to remove the - Confirmation Block tick mark
    Please any one can help me if you have any solution to solve this problem.
    Thanks and Regards.

  • Credit check at sales order

    Hello Experts,
    I have few questions regarding the credit check in FI-AR credit mgmt and SD.
    Currently we have a credit check in AR credit mgmt during the delivery order creation. But the management has decided to crap this and to put a credit check at sales order level.
    Can someone tell me if there is any business process change in doing this?
    Whats the concept of Horizon in dynamic check?
    Can someone clarify the concept of Business Partner in SAP FSCM credit mgmt?
    Any help in this regard is highly appreciated and duly rewarded.
    Regards,
    Sriram

    hi,
    pl check this :
    [Credit management|http://www.sap-img.com/sap-sd/credit-management.htm]
    Dynamic Credit Limit Check with Credit Horizon
    The customer's credit exposure is split into a static part; open items, open billing, and delivery values (see above), and a dynamic part, the open order value. The open order value includes all undelivered or only partially delivered orders. The value is calculated on the shipping date and stored in an information structure according to a time period that you specify (days, weeks, or months). When you define the credit check, you can then specify a particular horizon date in the future (for example: 10 days or 2 months, depending on the periods you specify). For the purposes of evaluating credit, you want the system to ignore all open orders that are due for delivery after the horizon date. The sum of the static and dynamic parts of the check may not exceed the credit limit.
    regards
    sadhu kishore

  • Revenue Recognition based on User Status of assigned Sales Order line item

    Dear Community members,
    We have requirement to recognize / de-recognize revenue posted to WBS for calculation of RA, based on the 'User status' of the assigned Sales Order line item.
    To elaborate requirement further -
    1) WBS Element - XXX - 10 ( with operative indicator - Plan/Bill/Account Assign)
    2) Sales Order(SO) Line Items assigned to the above WBS -
    - SO No -  123 Line Item 10 - Actual Rev - $ 300 - User Status - EXE (Meaning this work is in progress , partial payment received thus actual revenue for RA at WBS is 'Zero'
    - SO No -  124 Line Item 20 - Actual Rev - $ 400 - User Status - COMPL(Meaning this work is Complete , all payment received thus actual revenue for RA at WBS is $400
    - SO No -  125 Line Item 10 - Actual Rev - $ 800 - User Status - EXE (Meaning this work is in progress , partial payment received thus actual revenue for RA at WBS is 'Zero'
    As per WBS reports Actual Revenue posted to WBS XXX-10 is $ 1500 ( $300$400$800) , however since two SO line items ( SO 123 /line item 10 and SO 125 / line Item 10 ) are NOT having User status 'COMPLETE', the actual revenue posted by those line items $ 1100/- ($300 + 800)  should not be included as Actual Revenue for RA at WBS level.
    Thus Actual Revenue for RA at WBS XXX-10 should be $ 400 /- ( the revenue posted by SO 124/line item 20 which has user status as 'COMPLETE')
    How do above can be achieved?? Is there any standard solution for this?? Is any SAP Note available for this (I too am looking for one but not found any ) ?? do we need any enhancement , Customer exit etc
    Thanks in advance
    with regards

    Hi,
    Thanks. You are right that the 'Completed Contract Method' would defer revenue recognition. However, the status checked would be of the RA object (WBS Element in this case, as RA key is on WBS and RA is being calculated on the WBS).
    However, our requirement is to check the user status of the Sales Order Line items assigned to the WBS element and filter the revenues posted based on the active user status of individual Sales Order Line item.
    Please give you inputs.
    Thanks in advance
    With regards

  • No cost booking against sales order+line item once accontng release is done

    Dear all,
    I want to stop all cost bookings against a sales order + line item once the accounting release for that item has been done.
    By cost booking i mean, all such transactions that are done for a sales order + line item that involve cost booking. Like, MB1A should not allow any goods issue against that sales order + item once accounting release is done.
    Is it possible to that in sales order? Like by using any status at item level.
    Please guide.
    regards
    SAPshed

    Hi Ajay,
    We have not kept automatic cost estimate marking during saving of sales order as costing dept wants  to confirm whether costing for the SO is correct or not.
    Hence we have to use CK51N.
    Now the problem is for any change in any line item of a sales order is changing the costing status from "VO" to "KA" for all line items of the given sales order in table KEKO.
    This is causing measure problem as production people are facing problem while making any change in production order as already there is a check put in CO02 that if cost estimate does not exist for underlying sales order, then change in production order should not be allowed.
    Similarly production order creation (converting planned order to production order) is getting held up.
    Costing user has to repeated run CK51N for all line items of a single sales order if there is any change in any single line item of the sales order.
    Hence pl. help and suggest as to what is to be done now.
    Regards
    Ratna

Maybe you are looking for

  • Need to e-mail job log after job completes (SM37)

    Greetings! I need to export the results of the Job Log (run SM37, double-click a finished job and then click "Job Log" button at top - this is the list I need).  Obviously, the program has already terminated so it won't be able to initiate it.  Is th

  • IChat status changes to running app!

    Hello all, Suddenly, iChat (v4.0.8 (619), Leopard 10.5.7) has started changing my status to whatever application I run or switch to. It flips between "Finder", "Safari", "iChat", whatever! Has anyone seen this behavior? I didn't "set" it, and can't f

  • Accessing slideshows (which had missing photos) causes iphoto crash

    I have rebuilt the entire library and tried CTRL click and delete. I still can't click or delete about 6 slideshows...any action on or access to these causes iphoto to crash. I lost photo's about 4 months ago.....found them again...but the slideshows

  • Flex GUIs get a bad performance in normal screen mode when switched from full screen mode

    Hi, there : I encountered an odd situation and it is only happens on IE. Our project is a Flash 3D Game using Stage3D, and the Game's GUIs are created by CS6. When our game switch from the full screen( StageDisplayState.FULL_SCREEN_INTERACTIVE or Sta

  • COGI Tcode Express document error

    Hi everyone, when we are trying to run COGI one of our clients are facing the below issue. I googled it and searched also but couldn't find the exact solution our basis team gave this to investigate. "SAP, Express document "Update was terminated" rec