Delivery Costs into SO

Hi all,
I have below scenario.
Let's say i have a material X, this material X which will be procured through Purchase Order (PO). The delivery costs for this material until our warehouse will be issued with another PO. So, in short, we will use 2 POs until this material is completely procured into our warehouse.
This material X will be used in 2 scenarios:
1. It will be used in production order
2. It will be sold to customer through SO
If the delivery cost is received into cost center, how can we include the costs into production order or SO?
For Production Order, i am thinking of using manual cost allocation instead of costing sheet, because only 1-2% of the material X will be treated this way.
I have no idea how to include this delivery cost into SO (not the delivery cost to customer, but the one into our warehouse) if the SO is not a cost object..
Please kindly suggest, any help is greatly appreciated...
Regards, Erwin

Hi,
I see, then i have to use assessment from cost center to COPA value field, while asking the SD guy to maintain a statistical condition type which should consist of estimated value, right?
But why should it be after billing was done?
what if the delivery cost is already known at the time of SO creation?
Because in the 2nd case of that material X, it is already in our warehouse, waiting to be sold..
But, that kinda makes sense, since not all SO can 100% be processed to billing...
Thank you
Regards, Erwin
Edited by: Erwin Hartono on Nov 1, 2010 3:25 PM
Edited by: Erwin Hartono on Nov 1, 2010 3:26 PM

Similar Messages

  • Distribute planned delivery cost into all open POs when post FI vendor invo

    Hi,
    We planned transport cost in PO usning condition type but we post the freight invoice monthly for freight vendor using F-43 with out refernce to POs.
    So POs always expect a freight invoce,ends up with GR/IR clearing balance and so we can't archive these POs now.
    Now we are looking for a new solution that to distribute monthly freight invoice amt into all those open invoices when we post a FI freight invoice for vendor (F-43).
    Please do suggest any user exit or BADI to check for open POs for that vendor when post F-43.
    hope to hear your reply soon. Thanks in Advance
    Regards,
    Jagadheshwar

    Hi
    Since it is planned delivery cost, I belive the Freight posting would have happened at MIGO itself.... i.e. the Freight amount would have been inventorized or posted into consumption account in the case of account assigned PO... Is this understandng correct?
    If yes, then ideally you should be passing entry using F-02, Dr the GR/IR account and Crediting the Vendor account... Allow manual posting for GR/IR in FS00... populate the PO No in GR/IR account while doing the posting.... Then you can clear them...
    Ideally, you should not have had planned delvery cost, if you are not booking the invoice PO wise....
    If you are getting the freight invoice for each PO separately, you can do ERS (Evaluated Receipt Settlement)... Which means system would automatically Dr the Gr/IR and Credit the vendor.... You dont need to wait for the invoice.... This is usually done for trusted vendors
    Br, Ajay M

  • Message no. V1631-You cannot enter new delivery costs

    Hi All,
    before posting this issue i have searched and could not found the correct thread.
    system: ECC: 6.0
    Scenario1: Inter company STO with import process
    PO created and delivery created and TO created and confirmed and PGI done.and SD invoice done
    After this foreign trade module process starts and creating shipment and entering delivery import costs and releasing import costs from the custom transaction which will update the delivery costs into PO through BAPI_PO_CHNAGE
    here i am getting the above error Message no. V1631-You cannot enter new delivery costs
    but when i am adding delivery conditions manually in ME22N system accepting
    scenario2:
    PO created and delivery created and TO created and confirmed
    foreign trade module process starts and creating shipment and entering delivery import costs and releasing import costs from the custom transaction
    successfully updating delivery conditions  in PO
    scenario 3:
    PO created and delivery created and TO created and confirmed
    Foreign trade module process starts and creating shipment and entering delivery import costs and releasing import costs from the custom transaction
    successfully updating delivery conditions  in PO
    PGI done and SD invoce done and GR completed
    After that trying to add delivery conditions and getting the same error
    Question: why i am not able to update the conditions through BAPI and i am able to update conditions in ME22N manually in scenario1??
    Thanks
    Kiran

    Hi ajit,
    Getting issue after PGI. no GR done.

  • Third Party Order Delivery Costs(COGS in Purchasing)

    Hello MM/SD Gurus,
    We have a Scenario where in its a 3rd Party Order direct shipment Process where the Shipping is done by a Logistics Vendor!
    So->PR>PO>Inbound Del->GR->IR>Goods Issue-->Customer Invoice.
    Now the Issue we have is Delivery Costs(Freight,Insurance,Duty etc) raised by Logistics vendor are taken as estimated costs during the PO creation with appropriate Condition Types but when at the end of the Month when Actual bill is sent the Prices are to be settled and paid back!!
    2)Assuming vendor invoice of $100 and Freight invoice of $10. The accounting entries aare as follows:
    Vendor 100-
    GIT(Goods in Transit) 100
    Fright Forwarder 10-
    GIT 10
    Since the Stock is Non Valuated here how can Account postings from PO/GR is shown for COGS in SAP.
    Understood that COGS is hit when Goods Issue(GI) is done but our need is to account COGS in Purchasing.
    Can anybody throw some idea of how to Capture the COGS in PO and post then individually with different G/L accts for Freight,Insurance etc.
    Full points guaranteed heheheh! Pls help me with your expert suggestions.
    Regards,
    Hari'
    Singapore

    Hi Suraj,
    Thankx for your reply and sorry for my delayed reply.
    Well your answer is too immature for me to apply since I have already done all those and surpassed those things.
    Well to make my question simple I need to account Delivery Costs(Freight,Insurance etc) during GR.Although I have setup all the COnd types in PO Pricing.Now I need to know since GR is Statistical and Goods are in Transit can I account the Delivery Costs into seperate G/L acounts??
    It would be great if any of the Forum ppl have already setup capturing of the Delivery Costs in PURCHASING and accounting them into Sepate a/c's. I feel this is Common Scenario in most of the Mfg Org. So knowledge transfer is higly appreciated!!
    Rgds,
    Hari

  • Third Party Order Delivery Costs ( COGS for Purchasing)

    Hello Experts
    We have a Scenario where in its a 3rd Party Order direct shipment Process where the Shipping is done by a Logistics Vendor!
    So->PR>PO>Inbound Del->GR->IR>Goods Issue-->Customer Invoice.
    Now the Issue we have is Delivery Costs(Freight,Insurance,Duty etc) raised by Logistics vendor are taken as estimated costs during the PO creation with appropriate Condition Types but when at the end of the Month when Actual bill is sent the Prices are to be settled and paid back!!
    2)Assuming vendor invoice of $100 and Freight invoice of $10. The accounting entries aare as follows:
    Vendor 100-
    GIT(Goods in Transit) 100
    Fright Forwarder 10-
    GIT 10
    Since the Stock is Non Valuated here how can Account postings from PO/GR is shown for COGS in SAP.
    Understood that COGS is hit when Goods Issue(GI) is done but our need is to account COGS in Purchasing.
    Can anybody throw some idea of how to Capture the COGS in PO and post then individually with different G/L accts for Freight,Insurance etc.
    Full points guaranteed heheheh! Pls help me with your expert suggestions.
    Regards,
    Hari'
    Singapore

    Hi Suraj,
    Thankx for your reply and sorry for my delayed reply.
    Well your answer is too immature for me to apply since I have already done all those and surpassed those things.
    Well to make my question simple I need to account Delivery Costs(Freight,Insurance etc) during GR.Although I have setup all the COnd types in PO Pricing.Now I need to know since GR is Statistical and Goods are in Transit can I account the Delivery Costs into seperate G/L acounts??
    It would be great if any of the Forum ppl have already setup capturing of the Delivery Costs in PURCHASING and accounting them into Sepate a/c's. I feel this is Common Scenario in most of the Mfg Org. So knowledge transfer is higly appreciated!!
    Rgds,
    Hari

  • Planned Delivery Cost is changed during GR

    Hi Experts,
    PO is created with Planned Delivery Cost. When GR is created, the costs will be distributed to material cost.
    However, delivery costs can be changed for each delivery.
    How does SAP handle or distribute actual delivery costs into the received materials for each delivery? Where do I enter actual delivery costs with GR.
    Thanks,
    Sukhbold

    Hi,
    one option is availabe in SAP to post the unplanned delivery costs apart from the planned delivery costs,
    we can post the unplanned delivery costs to material 'or' separate G/L account also,
    pls check the fallowing path,
    IMG-Materials Management-Logistics Invoice Verification-Incoming Invoice-Configure How Unplanned Delivery Costs Are Posted,
    pls note that the above costs can post while doing invoice posting only
    chenna kesava reddy

  • Planned delivery costs (Freight) vendor into an access sequence

    Hello,
    Our MM users want to maintain a price condition record where they would be able to maintain a cost/ton based on effective dates.
    The objective is to maintain a price condition record based on the following criteria: PO header vendor, material, and planned delivery costs (freight) vendor so that they would not have to maintain prices manually in the PO (this price would come directly from the condition record).
    However, there is no standard field available to create an access sequence in which the freight vendor (KOMV-LIFNR) could be included. Indeed the field LIFNR is available but I guess it refers to the PO header vendor.
    Is it still possible to create such an access sequence? What do you think of this requirement?
    Thanks,
    Annabelle R.

    Hello Annabelle,
    Raw material vendor A + Raw material A + Truck company A =» Price A
    Raw material vendor A + Raw material A + Truck company B =» Price B
    can yo please explain the meaning of "Raw material vendor A"  stands for what price?
    As far as i know, freight cost could easily included in the material cost, because in m/06, there are so many cost that are on quantity basis and are included in the material basis, just make a copy of anyone of them and add it to you pricing procedure as well as supplementry pricing procedure, or else you can directly make a condition record in MEK1 for this condition.
    please try it hope it helps
    Regards,
    yk

  • How to get rid of "Delivery costs have not been cleared" status = MM_EKKO

    Hi dear experts,
    During pretreatment of MM_EKKO archiving object (TA: SARA), I get an amazing huge amount of PO position which can not be archived due to "*Delivery costs have not been cleared*".
    I tried several ways to find out how to solve this issue but without any success.
    Point is that we do not clear delivery cost regarding those PO positions, but delivery cost are transfered directly to a global account.
    It means that those PO's won't never be cleared.
    Any ideas about how I can fix this issue?
    Best regards,
    Daniel

    Yep,
    no idea why, but when I uncheck the "Final Invoice" box save and went back into the same PO and check again the same "Final Invoice" box, then, as a miracle, SARA=>MM_EKKO=> Pretreatment knows that this document is cleared and can be archived.
    It is just that for now, really old PO's are located in the present residence time
    I hope this slyness will help someone else one day.
    Regards,
    Daniel
    Edited by: Daniel Putzschler on Jul 28, 2009 2:02 PM

  • LE-TRA Shipment costs as inbound delivery costs, goods receipt

    Hello gurus:
    We are facing the following scenario, regarding inbound transportation.
    We plan our shipment document and shipment  costs, and they feature several items. Each of those items represent a shipping service, which in certain cases be taken on different countries by the same service agent.
    That is, we have a service X on country A, with tax indicator 1, and service Y on country B, with tax indicator 2.
    Both services would need to be transferred as delivery costs to the purchase order.
    According to note 427944, shipment cost value is cumulated by service agent., so that it looks impossible to get the values broken up to the purchase order, which would be the first step to subsequently get the right tax indicators for each item of the shipment.
    Even using different condition types on the shipment cost document, system cumulates by service agent and transfers to the first condition found on the purchase order schema.
    Has any of you faced similar issue? Any workaround possible?.
    Thanks in advance for your valuable help.
    David Ramos.
    PORCELANOSA MM.
    This is the section of note 427944 that indicates the treatment of the shipment costs in the purchase order,
    Transfer the shipment costs into the condition types of the purchase order:
    The shipment cost value (without tax amounts) is cumulated for all relevant shipment cost documents
    for each service agent and transferred to a corresponding condition type of the purchase order item.
    Before cumulation, the amounts are first converted into the purchase order currency.
    1. A transfer of the values for each condition type (similar to the transfer from a shipment
    cost document to the SD billing document) is not supported.
    2. If different service agents exist in the shipment cost documents, a corresponding number of
    condition lines (with value 0) must be specified in the purchase order item. These can always
    belong to the same condition type (in schema 'Manual') or also to different condition types (not
    'Manual'):
    a) Manual condition lines: If the condition type in the schema of the purchase order is
    marked as 'manual', the condition type must be created (with value 0) in the purchase order
    item before the goods receipt. If delivery costs are expected from different service agents,
    several non-valuated entries must be generated for this condition type. If more condition
    lines exist than required, these are then no longer taken into account. If condition lines
    are missing, the last service agents are not settled.
    - Advantage: You only have to define one condition type for the delivery costs.
    - Disadvantage: Each purchase order must be processed manually before the goods receipt.
    b) Automatic condition lines: If the condition lines are to be generated automatically for
    the delivery costs (the condition type is not flagged as 'Manual' in the schema), the schema
    must have enough condition types to settle several service agents. If more condition lines
    exist than required, these are then no longer taken into account. If condition lines are
    missing, the last service agents are not settled.
    - Advantage: The goods receipt can be carried out without manual preparation beforehand in
    the purchase order.
    - Disadvantage: You must define identical condition types with different names.
    Message was edited by: PORCELANOSA MM

    Hi,
    If you refereed the OSS Note 427944 correctly it explains how the shipment cost can be transferred to delivery cost based on some pre-requisite.
    Like the value for PO should be >0
    Like the service agent is involved during shipment liability, then there should be cumulative transfer for each value which will update based on shipment cost if PO value is "0".
    The shipment cost will be delivered to all delivery items based on weight.
    If you want to enhance this then you need to use the enhancement V54KSFRC to update the values as per your requirement.
    Rgds,

  • Delivery cost in scheduling agreement having time dependent condition

    Hi experts,
    We have one peculiar requirement.
    We have palnt at indonesia.  We are doing import there from india.
    Our requirement is as follows.
    1. We should use scheduling agreement with time dependent conditions.  Because we want to track the price changes and sometimes we want to retro pricing effect and revaluate it.
    2. We want to add importers vat and import tax.
    3. But those tax amount should not get added into inventory
    4. During MIRO it should get accounted to vendor.
    We could succeed this by removing "Time dependend condition" check in document type config.
    But our client is definitely required the point no 1.
    But when we activate time dependent condition check, during MIRO those conditions are not appearing.  But if you remove that check, it is appearing in MIRO accounting.
    Can any one suggest suitable solution?
    Or SAP MIRO will not permit this scenario?
    regards,
    K.Sundaresan.

    delivery cost will not work if u remove the tick Time dependend condition for SA
    SAP MIRO will not permit this scenario
    so u will have to decide what is more important to u and act accordingly
    Solution will be u ask client what is mor imp for there company
    as SAP will not support MIRO for deliver for time dependent condition
    I had a talk with SAP on this and they have told that
    SAP will not support MIRO for deliver for time dependent condition
    AS in Case of imports in india we need to do MIRO before GR
    hope this hel;sp

  • Delivery costs with shipment costs

    Dear Sir,
    I want to capture the delivery costs from shipment cost document.
    I did all bellow mentioned settings:
    For freight cost to be transfered as delivery cost, the Purchase order need to have a freight condition with zero value. Also the freight condition need to have indicator set in config for 'copy shipment cost'. Once this is set up and shipment cost document created, do PGI and it should create a DCGR document in PO History.
    Even after all these settings, i tried but no result. It is not creating ths DCGR in PO History.
    Can any body tell me this bellow setting: Where is this exactly. I tried no field with the name Relevant for costing
    Shipment cost item categories Under the Shipment cost types and item categories activity, set the Relevant for costing field to A = Relevant for calculating delivery costs (Delivery costs). This results in the shipment costs not being transferred directly into accounting. The accounting is done via the purchasing functionality for delivery costs.
    Can any body give me the solution?
    With regards
    Lakshmikanth

    Hi
    I think that you have had your question answered so if you are happy with this can you please award points if you want to but mainly can you please mark your question as answered so that it is easier to navigate around the open questions in the forum as the number of pages are growing and growing and it takes too long to go through everything especially if a satisfactory answer has already been given and people like me who want to help will give up and so some people may not get any help.
    Thanks for this
    Frenchy.

  • Delivery cost in PO

    Hi,
       I have create the PO account assigned to cost centre K and it has multiple account assignment.
    The distribution is on the basis of quantity and in case of partial invoice it is to be distributed proportionally.
    The pricing condition in PO are basic price and freight condition. When I am saving PO the sytem is giving following warning message:
    No delivery costs can be posted in case of multiple account assignment
    Message no. 06356.
    I saved the PO and did GR.As it is multiple account assignment so GR will be non valuated hence no accounting document is generated.
    When I am doing MIRO, I selected option goods/service+planned delivery cost.
    System is not showing the delivery cost. My basic price was 100 and freight cost was 10 say as an example. In MIRO it is showing only 100 not the freight cost 10 though I have selected the goods/service+planned delivery cost.
    When I am simulating the system is showing following warning message:
    No delivery costs selected for invoice document
    Message no. M8599
    Diagnosis
    No delivery costs were selected for the invoice document.
    Procedure
    If delivery costs are contained in the invoice, check that the allocation criteria and invoice type are correct.
    Just to check further , in MIRO I selected only the planned delivery cost , then system is giving the following error message:
    No delivery costs exist for purchase order 4500000596 00000
    Message no. M8014
    Diagnosis
    You have chosen Delivery costs -> Planned -> By purchase order. This function allows you to process delivery costs which were planned in the puchase order. The purchase order which you are currently processing does not contain any planned delivery costs.
    Procedure
    Check the purchase order number. If it is correct, you can only post the delivery costs as unplanned delivery costs.
    Please help how in the case of multiple account assigned PO we can post the delivery cost in MIRO?

    Hello, Anju,
    the systems does (well, in this case does not) exactly what is says: "No delivery costs can be posted in case of multiple account assignment".
    So either you have to split the one items with multiple account assignment into more items with single account assignment, or you have to use unplanned delivery cost in invoice verification.
    If you decide to use the unplanned cost, it can be helpful to activate the "Edit PO Supplement Text in Invoice Verification" function in customizing for LIV, so the buyer can write into defined text in PO "message" for invoicing clerk, that he/she agrees with certain amount of unplanned cost. I know, it's such lousy workaround...
    Kind Regards
    TomT

  • "Reverse" planned delivery costs stated in PO

    Hi,
    In PO, we planned this delivery costs. During Post Goods Receipt, the amount of this delivery costs is debited into stock. So the accounting entries during PGR is Debit Stock, Credit GR/IR
    But later, we discover that this is wrong- there will not be any logistic invoice for this and there will not be such costs. How can we reverse such an entry and close the outstanding PO due to this line? So I want to Credit Stock, Debit GR/IR. If there is no stock, it should be posted to Cost of Goods Sold.
    Your help is much appreciated.
    Thank you.

    Hi,
    Please check transaction-MR11 ,it will post the differences of GR/IR as per your requirement.
    Thanks & regards,
    Sandesh Sawant

  • Shipment costs to appear as delivery costs in Purchase

    Hi,
    we want the shipment costs to appear on the purchase order.
    I have followed the sequence as below
    Created a purchase order
    Created a delivery VL31N
    Created a shipment VT01N
    Created a shipment cost document VI01
    I have goods receipt using VL32N, but the shipment cost did not appear in Purchase Order.
    in configuration i have created a new condition in Purchasing ZFRB which has copy shipment cost slected, and added this to the purchasing schema.
    for the shipment cost item category, i configured the settement to delivery costs and left the generate PO blank.
    i would be grateful if someone could help me with configuration that i've missed,
    thanks in advance
    Shadaab

    Please read OSS note 427944 and check SAP online help:
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/83/218ad1068a11d2bf5d0000e8a7386f/frameset.htm
    Prerequisites
    To add shipment costs to delivery costs in the incoming shipments, you need the following settings in Customizing:
    Shipment cost item categories
    Under the Shipment cost types and item categories activity, set the Relevant for costing field to A = Relevant for calculating delivery costs (Delivery costs). This results in the shipment costs not being transferred directly into accounting. The accounting is done via the purchasing functionality for delivery costs.
    Conditions in the purchase order
    Under the Define condition types activity, set the Condition type field to B = Delivery costs. In addition, select the Transfer shipment costs field. The system only shows this field, if you have chosen delivery costs as condition type. In the purchase order, you have to enter the condition type in the item category section. However, you do not enter a value since this value will be determined by the shipment cost document and will then be automatically transferred to the goods receipt document.
    Goods receipt
    To find the relevant shipment cost documents, you must know the corresponding inbound deliveries. Therefore for incoming goods this must relate to confirmation-related goods receipts. Under the Set up confirmation control activity, select the GR-relevant and GR assignment fields for the appropriate confirmation control key (which is then entered in the purchase order).
    Regards,
    Csaba

  • Issue with reversal of MIRO for Planned Delivery Cost

    Hi Xperts
    We have found out an issue while reversing the MIRO document for Planned Del costs. When we have done the MIRO, the accounting entry got correctly posted with correct account keys.Conditions are not inventoried.
    However, when we had reversed it - the stock account got hit.Do not understand, why that happened.Do you have any clue?
    1. Suppose we have done the MIRO for Del Cost & then performed GR.Now Stock has already consumed & afterwards we have found that the MIRO for Del Cost is wrong & reverse - in this scenario shall the Stock account will get a hit????
    2. I have maintained Price Control "V" in Material Master.However, I have maintained a Standard Price by mistake.In that case shall SAP ignores the MAP & takes Standard Price into account & post PRD??
    Regards
    Soumick 

    Hi,
    Before checking Planned Delivery costs accounting documents in MIRO posting and MIRO cancellation document, 1st check how Planned Delivery costs designed for your procurement process.
    Use t.code:ME23N, check your Purchase order
    Option-1:
    Is Planned Delivery costs added to inventory account and at the same time Planned Delivery costs posted to Separate Planned Delivery costs G/L account.
    OR
    Option-2:
    Is Planned Delivery costs posted to Planned Delivery costs G/L account ONLY
    OR
    Option-3:
    Is Planned Delivery costs added to inventory account ONLY.
    Based the above one setting, system  will post goods receipt and invoice posting document with corresponding accounting entries. Also cancellation of invoice posting document refer to these setting.But account posting depends on price control available in material master.
    NOTE:
    Standard price procedure (price control “S”):The system carries out all stock postings at a price defined in the material master. Variances in price are posted to price difference accounts.
    Moving average price (price control “V”): The system valuates goods receipts with the purchase order price and goods issues with the current moving average price.Differences in price between the purchase order price and the invoice are posted directly to the relevant stock account if there is sufficient stock coverage.
    Regards,
    Biju K

Maybe you are looking for

  • Report purchase price from Sales order to delivery.

    Please, is there anyone knows a solution for a resumption of the purchase price was register in a libne of sales order when we created by the DI API corresponding delivery ? Edited by: Rui Pereira on Dec 23, 2008 3:08 PM

  • Function help :

    I need a function that has to find out if a pk already has been assigned in another table as an foreign key. I've written this: function check ( id1 in number return varchar2 is cursor c ( b number ) is select id from a, b where a.pk1= b and b.fk_id

  • Storing data in arrays and using Stirng methods

    Hi There! Could any one help me in developing a kind of "PhoneBook" in java? Coding for the following program is required in java(jdk1.2). The problem is to program a PhoneBook in the following way when the program executes A list of following option

  • Crashing if I open a document, but not if I use the 'File' menu?

    I've got InDesign CS5 on Windows 7. If I open InDesign and use File > Open, I can launch my projects without trouble. If I go to the file in Windows Explorer and double-click it, InDesign launches, but hangs without opening the document and I have to

  • Auto Batch Number FMS